P09 520 23 106_JACC Enclosure Project Final Full Set 08_10_2023.pdf

PDF 33 MB Posted

Attached to
Renovate Interior Space JACC Federal contract opportunity
Solicitation number
520-23-106
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document summarizes a federal solicitation to renovate interior space at a Joint Ambulatory Care Center. The solicitation number is 520-23-106 and was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16. It seeks offers to complete interior renovations including upgrades to finishes, fixtures, casework and mechanical/electrical systems. The solicitation was released on August 10, 2023 and responses are due by September 15, 2023. Award is expected to be made by October 31, 2023 to a small business contractor. The work must be completed within 180 calendar days of the award date.

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Interior Space JACC, newest first.
File Type Posted
36C25623R0109 0003.pdf PDF
00 01 10 - Table of Contents - Redacted.docx DOCX document
36C25623R0109 RFI Responses.docx DOCX document
VOL 1 BINDER.pdf PDF
VHA ICRA 2023-1.0_Final Template_0.docx DOCX document
01 00 00 - General Requirements rev2.docx DOCX document
VOL 2 BINDER.pdf PDF
VOL 3 BINDER.pdf PDF
S04 Site Visit Sign in Sheet 520-23-106 8.24.23.pdf PDF
36C25623R0109 0002.pdf PDF
36C25623R0109 0001.pdf PDF
P03 - Brand Name JA JACC CO Signed - R1_Redacted.pdf PDF
36C25623R0109 EXHIBIT A.docx DOCX document
36C25623R0109 EXHIBIT D.docx DOCX document
Specs 4 14 2023.pdf PDF
36C25623R0109 EXHIBIT B.docx DOCX document
36C25623R0109 EXHIBIT C.docx DOCX document
WD FL20230203 Mod 1 dtd 01.13.2023.txt TXT text file
Final SOW Renovate interior spaces.pdf PDF
36C25623R0109 EXHIBIT E.docx DOCX document
36C25623R0109 EXHIBIT F.docx DOCX document
ICRA Contacting Only.pdf PDF
36C25623R0109 Final.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPLICABLE BUILDING CODES AND CONSTRUCTION STANDARDS

• ALL BUILDING DESIGN AND CONSTRUCTION STANDARDS AS OUTLINED IN THE VA

TECHNICAL INFORMATION LIBRARY (https://www.cfm.va.gov/til/).

• 2021 NFPA 101 LIFE SAFETY CODE.

• 2018 INTERNATIONAL BUILDING CODE (IBC).

• 2018 INTERNATIONAL MECHANICAL CODE (IPC).

• OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.

• VA SEISMIC DESIGN REQUIREMENTS, H-18-8.

• 2017 NATIONAL ELECTRICAL CODE (NEC).

• 2018 INTERNATIONAL PLUMBING CODE (IPC).

• ASME CODE FOR PRESSURE PIPING.

• ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING VA

SUPPLEMENT, BARRIER FREE DESIGN GUIDE (PG-18-13)

• BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE, AMERICAN

CONCRETE INSTITUTE AND COMMENTARY (ACI 318).

• MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE FACTOR DESIGN

SPECIFICATIONS FOR STRUCTURAL STEEL BUILDINGS, AMERICAN INSTITUTE OF

STEEL CONSTRUCTION (AISC).

• ENERGY POLICY ACT OF 2005 (EPACT).

• DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL,

COMMERCIAL AND MULTI-FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-

RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435.

• FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS:

MEMORANDUM OF UNDERSTANDING (MOU).

• EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL ENVIRONMENTAL, ENERGY,

AND TRANSPORTATION MANAGEMENT.

• THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE GENERAL

REQUIREMENTS SECTION 01 00 00 AND 01 35 26 OF THE VA MASTER CONSTRUCTION

SPECIFICATION.

• VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY – ASHRAE STANDARD

62.1-2016; MEDICAL SPACES - ASHRAE 170-2013, NON-MEDICAL SPACES ASHRAE

62.1-2016.

• SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE STANDARD 15–2013.

• VA FIRE PROTECTION DESIGN GUIDE, 8TH EDITION (2021).

***SPECIAL NOTE***

THESE DRAWINGS SUPPLEMENT THE WRITTEN SCOPE OF WORK AND SPECIFICATIONS

SUPPLIED WITH THE TASK ORDER SOLICITATION. THE DRAWINGS ARE PROVIDED TO

GRAPHICALLY CLARIFY THE OVERALL INTENT OF THE IMPROVEMENTS NEEDED TO THE

VARIOUS SPACES WITHIN THE CLINIC. IT IS IMPORTANT FOR THE BIDDER TO

UNDERSTAND THAT NOT ALL WORK REQUIRED TO COMPLETE THE MODIFICATIONS

ARE CLEARLY SHOWN IN THE DRAWINGS OR SPECIFICALLY OUTLINED IN THE SCOPE

OF WORK NARRATIVE. HOWEVER, THE SCOPE OF WORK NARRATIVE IN

CONJUNCTION WITH THE DRAWINGS AND SPECIFICATIONS PROVIDE SUFFICIENT

INFORMATION FOR THE GENERAL CONTRACTOR TO PROPERLY BID AND COMPLETE

THE WORK. THE CONTRACTOR SHALL ANTICIPATE AND PERFORM ANY ADDITIONAL

WORK AS WOULD BE TYPICAL FOR THESE TYPES OF INTERIOR IMPROVEMENTS AND

BID THE WORK ACCORDINGLY. CONTRACTOR SHALL REQUEST CLARIFICATIONS TO

THE SCOPE PRIOR TO BIDDING. IF A REQUEST FOR INFORMATION/CLARIFICATION IS

NOT SUBMITTED PRIOR TO BIDDING, IT IS ASSUMED THE GENERAL CONTRACTOR

FULLY UNDERSTANDS THE INTENT OF THE WORK REQUIRED AND HAS BID

ACCORDINGLY.

ONLY 'NON-TYPICAL' OR 'MAJOR' UNFORESEEN CONDITIONS ENCOUNTERED THAT ARE

NOT INDICATED OR ANTICIPATED WILL BE CONSIDERED OUT OF SCOPE AND WARRANT

A CHANGE OF SCOPE AMENDMENT TO THE CONTRACT.

GENERAL NEW CONSTRUCTION (PROJECT) NOTES

A. IT IS THE GENERAL CONTRACTOR'S RESPONSIBILITY TO COORDINATE ALL REQUIRED WORK BETWEEN ALL CONSTRUCTION TRADES: ARCHITECTURAL, STRUCTURAL, MECHANICAL, PLUMBING, AND ELECTRICAL. ALL WORK SHALL BE COMPLETED TO MEET OR EXCEED ALL APPLICABLE BUILDING CODES AND CONSTRUCTION STANDARDS.

ANY DISCREPANCIES OR CLARIFICATION NEEDED SHALL BE DIRECTED TO THE VA COR PRIOR TO CONSTRUCTION

OR INSTALLATION.

B. CONTRACTOR SHALL FOLLOW ALL MANUFACTURER REQUIREMENTS, INSTRUCTIONS, AND RECOMMENDATIONS FOR INSTALLATION AND WARRANTY OF ALL MATERIALS USED IN THIS PROJECT. MANUFACTURER WARRANTIES SHALL BE ISSUED WHERE WARRANTIES ARE AVAILABLE. ALL PROJECT WORK SHALL BE USE MANUFACTURER APPROVED AND COMPATIBLE MATERIALS AND METHODS, INCLUDING ADHESIVES, SEALANTS, SOLVENTS, ETC.

C. CONTRACTOR SHALL SEND IN ALL SUBMITTALS TO VA COR PRIOR TO COMMENCEMENT OF THE WORK. WORK STARTED WITHOUT REVIEWED SUBMITTALS AND SHOP DRAWINGS SHALL BE DONE AT THE CONTRACTOR'S OWN RISK. ALL SUCH WORK IS SUBJECT TO REJECTION AND THE CONTRACTOR BEARS ALL LIABILITY FOR ALL COSTS AND DELAYS THAT RESULT. CONTRACTOR SHALL NOT BE ENTITLED COMPENSATION AS A RESULT OF INCORRECT OR UNACCEPTABLE WORK EXECUTED WITH REVIEWED AND APPROVED SHOP DRAWINGS RETURNED FROM THE VA COR. CONTRACTOR SHALL MAKE ALL SUBMITTALS AVAILABLE TO THE VA COR IN A TIMELY MANNER AND SHALL ALLOW REASONABLE TIME FOR THE VA COR TO REVIEW AND RETURN TO THE CONTRACTOR.

D. ALL SERVICE INTERRUPTIONS TO THE EXISTING FACILITY (IN NECESSARY) MUST BE SCHEDULED AT LEAST 3 WEEKS IN ADVANCE AND KEPT TO A MINIMUM. COORDINATE ALL DISRUPTIVE WORK AND OUTAGES WITH VA COR.

E. IN THE EVENT OF AN EMERGENCY, THE CONTRACTOR SHALL STOP WORK IN THE AFFECTED AREA, REMOVE ALL EQUIPMENT, TOOLS, MATERIALS, AND OTHER ITEMS THAT ACT AS A BARRIER TO EGRESS FROM THE BUILDING.

F. FIRE PROTECTION / ALARM - ALL FIRE PROTECTION WORK SHALL MEET ALL REQUIREMENTS OF THE VA FIRE PROTECTION DESIGN MANUAL. ALL FIRE ALARM PROVISIONS SHALL BE IN ACCORDANCE WITH NFPA 101. ANY FIRE ALARM SYSTEM MODIFICATIONS REQUIRED IN AN AREA BEING REMODELED SHALL BE COMPLETED BY A CERTIFIED FIRE ALARM MAINTENANCE CONTRACTOR AS APPROVED BY VA COR. ALL MODIFICATIONS/ADDITIONS SHALL BE FULLY TESTED AND CERTIFIED BY APPROVED THIRD PARTY FIRE ALARM INSPECTOR PRIOR TO ACCEPTANCE. REQUIRED FIRE PROTECTION SYSTEMS SHALL REMAIN OPERATIONAL FOR OCCUPIED AREAS FOR THE DURATION OF THE PROJECT. ANY MODIFICATION TO EXISTING FIRE PROTECTION SYSTEM SHALL BE

DESIGNED BY A PROFESSIONAL FIRE-SAFETY ENGINEER AND BE APPROVED BY VA COR.

G. FIRE RATED WALLS - CONTRACTOR TO VALIDATE ALL AND VERIFY ALL NECESSARY FIRE RATED AND/OR SMOKE WALLS AND ASSEMBLIES INDICATED ON PLANS IN THE WORK AREA(S). PROVIDE ALL REQUIRED PENETRATION DETAILING FOR PIPING, DUCTWORK, OR OTHER UTILITIES THAT MUST TRAVERSE FIRE/SMOKE WALLS.

FIRE/SMOKE WALLS SHALL BE CONSTRUCTED FULL HEIGHT TO DECK WITH U.L. CERTIFIED WALL ASSEMBLY AND AS APPROVED BY VA COR. WALLS SHALL BE FULLY CAULKED TOP AND BOTTOM WITH APPROVED FIRE- CAULKING MATERIAL. COORDINATE PENETRATIONS WITH MECHANICAL, ELECTRICAL, AND PLUMBING

REQUIREMENTS.

H. CONNECTIONS OF ALL NEW ARCHITECTURAL BRACING, MECHANICAL, PLUMBING, AND ELECTRICAL SYSTEMS TO THE EXISTING BUILDING STRUCTURE SHALL BE DESIGNED BY THE CONTRACTOR AND SUBMITTED TO THE VA COR FOR REVIEW AND APPROVAL PRIOR TO INSTALLATION. THE EXISTING STRUCTURE SHALL NOT BE COMPROMISED IN ANY WAY AS A RESULT OF CONSTRUCTION OF ANY PART OF THIS PROJECT. ANY DAMAGE TO EXISTING BUILDING STRUCTURE OR SYSTEMS SHALL BE REPAIRED IMMEDIATELY AT CONTRACTOR'S EXPENSE IN

A MANNER AS APPROVED BY VA COR.

I. REUSE EXISTING (UNDAMAGED OR STAINED) CEILING GRID AND TILES AS ABLE.

J. REUSE EXISTING LIGHT FIXTURES AS ABLE. REWORK CEILING LAYOUT AS SHOWN.

K. REUSE EXISTING HVAC SUPPLY AND EXHAUST GRILLES/DIFFUSERS AS ABLE.

L. FIELD VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BIDDING AND DURING CONSTRUCTION. REPORT ANY DISCREPANCIES OR CLARIFICATIONS NEEDED TO THE VA COR PRIOR TO PERFORMING ANY WORK. ANY

MODIFICATIONS NEEDED SHALL BE AS APPROVED BY VA CO.

M. ANY FLOOR, WALL, OR CEILING, CUTTING OR FILLING THAT IS REQUIRED TO COMPLETE THIS PROJECT SHALL BE

PATCHED, PAINTED, AND RETURNED TO MATCH EXISTING CONDITIONS AND FINISHES.

T. ANY CUTTING OR WELDING WILL REQUIRE DAILY HOT WORK PERMIT TO BE OBTAINED BY/COORDINATED WITH VA COR.

SUBMIT CERTIFICATIONS AS REQUIRED BY THE SPECIFICATIONS.

U. 'TYPICAL' DOOR FRAME CLEARANCE TO ADJACENT PERPENDICULAR WALLS IS TYPICALLY 4". VERIFY WITH VA COR IF

CLARIFICATION IS NEEDED.

V. TEMPORARY BRACING OR SHORING MAY BE NECESSARY AND SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.

W. CONTRACTOR SHALL PATCH AND REPAIR ALL OPENINGS, VOIDS, OR PENETRATIONS RESULTING FROM THE INSTALLATION OF EQUIPMENT, PIPING, DUCTWORK, ETC. ALL WALLS, FLOORS, AND/OR ROOF ASSEMBLY INTEGRITIES

SHALL BE MAINTAINED.

X. GYPSUM BOARD AND STUD FRAMING REQUIRED TO BE REMOVED FOR PLACEMENT/INSTALLATION OF NEW PLUMBING, WIRING, CONDUIT, RECEPTACLES, FIXTURES, EQUIPMENT, AND OR SYSTEMS, SHALL BE REPLACED AND FINISHED TO

MATCH EXISTING ADJACENT IN ALL RESPECTS, INCLUSIVE OF WALL RATING AND FINISH.

Y. PAINTING WORK SHALL INCLUDE ALL TAPING, SURFACE PREPARATION, CLEANING, DE-RUSTING, PRIMING AND FINISHING AS REQUIRED BY STANDARD PRACTICE. SCOPE OF PAINTING ALSO INCLUDES CLEANUP AND REMOVAL OF OVER-SPRAY, DRIPS AND SPLATTERS. EXCEPT AS NOTED OTHERWISE, CONTRACTOR SHALL PAINT ALL INTERIOR EXPOSED WALL AND ADJACENT AFFECTED BUILDING SURFACES TO ENSURE A COMPLETE AND LIKE-NEW (COMPLETE)

APPEARANCE.

Z. COVER AND PROTECT DOORS, FRAMES, AND WALLS AS NECESSARY TO PREVENT PAINT BRUSH OR ROLLER OVER-

SPRAY, PAINT DROPS, DAMAGE OR SOILING OF ANY KIND AS A RESULT OF CONSTRUCTION.

AA. REQUIRED CONCRETE EMBEDMENT (CONDUITS, PIPES, SLEEVES, ETC.) OF ANY MATERIAL NOT HARMFUL TO CONCRETE SHALL BE PERMITTED WITH APPROVAL OF THE VA COR, PROVIDED THEY ARE NOT CONSIDERED TO

STRUCTURALLY REPLACE THE DISPLACED CONCRETE.

BB. CONTRACTOR SHALL PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS BETWEEN DISSIMILAR

METALS.

CC. WHERE JOB CONDITIONS REQUIRE CHANGE FROM THE DRAWINGS THAT DOES NOT CHANGE THE SCOPE OR NATURE OF THE WORK REQUIRED, THE CONTRACTOR SHALL MAKE SUCH CHANGES WITHOUT ADDITIONAL COST TO THE VA.

NO CHANGE IN SCOPE MAY BE MADE WITHOUT WRITTEN PERMISSION FROM THE CONTRACTING OFFICER.

DD. ALL VA BUILDINGS AND PROPERTIES ARE NON-SMOKING FACILITIES. NO SMOKING OR TOBACCO USE OF ANY KIND WILL BE ALLOWED AT ANY TIME THROUGHOUT THE PROJECT. CONTRACTOR SHALL ADHERE TO VA POLICY AND

REGULATION CONCERNING TOBACCO USE.

EE. UPON COMPLETION OF THE WORK, CONTRACTOR SHALL LEAVE THE ENTIRE PROJECT SITE IN A CLEAN, NEW, FINISHED AND USABLE CONDITION WITH ALL DISTURBED AREAS COVERED WITH MATERIALS AS OUTLINED IN THE

SCOPE THE SCOPE OF WORK.

N. RESTORE / REPAIR ADJACENT FINISHES AT ALL LOCATIONS BETWEEN EXISTING AND NEW WORK AS REQUIRED FOR

SEAMLESS/LIKE NEW TRANSITIONS.

O. GENERAL CONTRACTOR SHALL COORDINATE ALL REQUIRED MECHANICAL AND ELECTRICAL DUCT SIZES AS NEEDED FOR MOST EFFICIENT AND LOGICAL CONNECTIONS TO EXISTING INFRASTRUCTURE AND AS APPROVED BY VA COR.

P. ALL REQUIRED MEANS OF EGRESS FROM ALL BUILDING LOCATIONS SHALL BE MAINTAINED THROUGHOUT THE

CONSTRUCTION PROCESS.

Q. WALL OUTLETS, SWITCHES, RELOCATED OR NEW THERMOSTATS, ETC. SHALL BE INSTALLED LEVEL AND PLUMB.

R. THE WORK INDICATED IN THE DRAWINGS AND NOTES DESCRIBES THE GENERAL SCOPE OF WORK ONLY AND IS NOT INTENDED TO BE INCLUSIVE OF ALL WORK NECESSARY AND REQUIRED TO FULLY COMPLETE SCOPE. ANY QUESTIONS OR CLARIFICATIONS NEEDED TO FULLY UNDERSTAND AND EXECUTE THE WORK SHALL BE SUBMITTED IN WRITING TO

THE VA COR PRIOR TO PERFORMING THE WORK.

S. COORDINATE ALL SITE OPERATIONS WITH THE VA COR, INCLUDING STAGING AREAS, MATERIAL STORAGE, ACCESS TO

WORK, NOISY OPERATIONS, OR INTERRUPTION OF UTILITIES.

AC. ACOUSTICAL

A/C AIR CONDITIONING

A.T. ACOUSTICAL TILE

A.F.F. ABOVE FINISHED FLOOR

ADJ. ADJUSTABLE

ALT. ALTERNATE

& AND

APPROX. APPROXIMATE

ARCH. ARCHITECTURAL

A.D. AREA DRAIN

ASPH. ASPHALT

@ AT

∠ ANGLE

BM. BEAM

B.M. BENCH MARK

BIT. BITUMINOUS

BLK. BLOCKING

BD. BOARD

B.O.C. BOTTOM OF CURB

BOT. BOTTOM

BLDG. BUILDING

B.U. or B/U BUILT UP

CPT. CARPET

C.B. CATCH BASIN

C.O. CLEAN OUT

CLG. CEILING

CEM. CEMENT

℄ or CL. CENTERLINE

C.T. CERAMIC TILE

CH. CHANNEL

COL. COLUMN

CONC. CONCRETE

C.M.U. CONCRETE MASONRY UNIT

CONT. CONTINUOUS

C.J. CONTROL JOINT

CONF. CONFERENCE

DP. DAMPROOFING

DET. DETAIL

DIA. DIAMETER

DIM. DIMENSION

DS. DOWNSPOUT

DWGS. DRAWINGS

E.R.D. EMERGENCY ROOF DRAIN

E. ELEVATOR

EA. EACH

ELEC. ELECTRICAL

E.I.F.S. EXTERIOR INSULATION AND FINISH

SYSTEM

ELEV. or EL. ELEVATION E.J. or EXP JT. EXPANSION JOINT

EQ. EQUAL

EQUIP EQUIPMENT

EXP. EXPANSION

EXST. EXISTING

EXT. EXTERIOR

FIN. FINISH

FIN. FL. FINISHED FLOOR

F.H.C. FIRE HOSE CABINET

F.H. FIRE HYDRANT

F.E. FIRE EXTINGUISHER

F.E.C. FIRE EXTINGUISHER CABINET

FL. FLOOR

F.D. FLOOR DRAIN

FTG. FOOTING

FURR FURRING

FIN. FINISH

FIN. FL. FINISHED FLOOR

F.H.C. FIRE HOSE CABINET

F.H. FIRE HYDRANT

F.E. FIRE EXTINGUISHER

F.E.C. FIRE EXTINGUISHER CABINET

FL. FLOOR

F.D. FLOOR DRAIN

FTG. FOOTING

FURR FURRING

HCP. or H/C HANDICAPPED

HDW. HARDWARE

HGT. or HT. HEIGHT

H.C. HOLLOW CORE

H.M. HOLLOW METAL

HORIZ. HORIZONTAL

H.B. HOSE BIBB

I.D. INSIDE DIAMETER (DIMENSION)

INSUL. INSULATION

INT. INTERIOR

INV. INVERT

JAN. JANITOR

J.B. JOIST BEARING

JT. JOINT

LAM. LAMINATE

LAM. LAMINATE

L.A.T. LAY-IN-ACOUSTICAL TILE

LT. WT. LIGHT WEIGHT

MTL. METAL

M.H. MOP HANGER

M.H. MANHOLE

M.O. MASONRY OPENING

MAX. MAXIMUM

MECH. MECHANICAL

MEMB. MEMBRANE

MISC. MISCELLANEOUS

M.R.GYP.BD. MOISTURE RESISTANT GYPSUM BOARD

MTD. MOUNTED

NOM. NOMINAL

N.I.C. NOT IN CONTRACT

NO. or # NUMBER

N.T.S. NOT TO SCALE

O.C. ON CENTER

OPNG. OPENING

OH. OVERHEAD

OPP. OPPOSITE

O.D. OUTSIDE DIAMETER (DIMENSION)

PTD. PAINTED

PR. PAIR

PTN. PARTITION

PVMT. PAVEMENT

PLAS. PLASTER

PL. PLATE

POL. POLISHED

LBS. POUNDS

P.I.P. POURED-IN-PLACE

PRE-FAB. PRE-FABRICATED

PC. CONC. PRECAST CONCRETE

P.T.D. PAPER TOWEL DISPENSER

P. LAM. PLASTIC LAMINATE

PWD. PLYWOOD

P.L. PROPERTY LINE

RAD. RADIUS

REF. REFERENCE

R.C.P. REINFORCED CONCRETE PIPE

REINF. REINFORCEMENT

REQ. REQUIRED

RESIL. RESILIENT

R. RISER

R.D. ROOF DRAIN

RM. ROOM

RD. ROUND

R.B. RUBBER BASE

S.N.D. SANITARY NAPKIN DISPENSER

SLT. SEALANT

SEC. SECURITY

SEC. GL. SECURITY GLASS

S.H.M. SECURITY HOLLOW METAL

SER. S. SERVICE SINK

SCHD. SCHEDULED

SHT. SHEET

S.V. SHEET VINYL

SIM. SIMILAR

S.D. SOAP DISPENSER

S.C. SOLID CORE

SPEC. SPECIFICATION

SQ. SQUARE

SQ. FT. SQUARE FEET

STD. STANDARD

S.ST. STAINLESS STEEL

STL. STEEL

STOR. STORAGE

ST.DR. STORM DRAIN

STRUCT. STRUCTURAL

SUSP. SUSPENDED

SYM. SYMMETRICAL

TELE. TELEPHONE

T'HOLD THRESHOLD

TLT. TOILET

T.P.H. TOILET PAPER HOLDER

T.O.C. TOP OF CURB

T.O.S. TOP OF STEEL

T.B. TOWEL BAR

T. TREAD

TRT'D TREATED

TYP. TYPICAL

T.O.W. TOP OF WALL

U.N.O. UNLESS OTHERWISE NOTED

V.B. VINYL BASE

V.C.T. VINYL COMPOSITION TILE

V.W.C. VINYL WALL COVERING

VERT. VERTICAL

VEST. VESTIBULE

V.T.R. VENT THRU ROOF

W.H. WATER HEATER

W.P. WATER PROOF

W.W.M. WELDED WIRE MESH

W.GL. WIRE GLASS

W.C. WATER CLOSET

W/ WITH

W/O WITHOUT

WSCT. WAINSCOT

WT. WEIGHT

WD. WOOD

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

U.S. Department of Veterans Affairs

PENSACOLA VA CLINIC

790 VETERANS WAY, PENSACOLA, FL 32507

520-23-106

RENOVATE VARIOUS INTERIOR SPACES TO IMPROVE PRIMARY

CARE AND OTHER SPECIALTY SERVICES, JACC

G0104-12-2023 RCC RCC/LB

Construction Documents

PENSACOLA BAY

292 - GULF BEACH HWY

I-110HW

Y 29

HWY 98

PROJECT LOCATION

HW

Y 90

PAR

KIN

G

PARKING

PARKING

PARKING

RETENTION

RETENTION

RETENTION

VE

TE

R

AN

S W

AY

US HIGHWAY 98

LOADING DOCK

MECHANICAL YARD2

SOUTH ENTRANCE3

NORTH ENTRANCE4

VEHICLE INSPECTION LANE5

CONTRACTOR STAGING AREA6

SHEET INDEX

Sheet Number Sheet Name

G01 Coversheet A01 First Floor Improvement Locations A02 Second Floor Improvement Locations A03 First Floor - Demolition A04 Second Floor - Demolition A05 First Floor - Architectural A06 Second Floor - Architectural

FP01 Fire Protection Notes FP02 First Floor Fire Protection FP03 Second Floor Fire Protection M01 First Floor - HVAC - Bravo M02 First Floor - HVAC - Charlie/Radiology M03 Second Floor - HVAC - EMPU M04 Second Floor - HVAC - Eye Clinic/India/Juliet M05 HVAC Schedules E01 First Floor - Electrical E02 Second Floor - Electrical

N

VICINITY MAP

NTS

CAMPUS REFERENCE MAP

NTS

N

COMMON ABBREVIATIONS

LOCATION MAP

NTS

N

US HWY 98

S

ST

A

VE

W NAVY BLVD

S FAIRFIELD DR

CHIEF'S

WAY

PROJECT LOCATION

Revisions: Date:

520-23-106 zz

RENOVATE VARIOUS INTERIOR SPACES TO

IMPROVE PRIMARY CARE AND OTHER

SPECIALTY SERVICES, JACC

PENSACOLA VA CLINIC

790 VETERANS WAY

PENSACOLA, FL 32507

COVER SHEET - SHEET INDEX - LOCATION MAPS

GENERAL PROJECT NOTES

VA CAPITAL ASSET MANAGEMENT

TEAM RM

CONS.

TEAM RM

CONS.

OFFICE

OFFICE

OFFICE

OFFICE

A05

A05

A05

A03

A03

A03

DEMO

NEW

DEMO

NEW

DEMO

NEW

POLICE

CANTEEN

ENGINEERING

LOGISTICS

EMS

PHARMACY

DIAGNOSTIC MEDICINE

ORTHOPEDICS

PHYSICAL THERAPY

PROSTHETICS

NAVY

PRIMARY CARE

PRIMARY CARE

MEDICAL ADMIN

PUBLIC AFFAIRS

LOADING

DOCK

MAIN ENTRANCE

REAR ENTRANCE

PRIMARY CARE

EC

H

O

FO

XT

R

O T

G O

LF

HO

TE

L

AL

PH

A

BR

AV

O

CH

AR

LI

E

DE

LT

A

11 12

CLOSET

PROJECT PHASING

a. THIS PROJECT SHALL BE COMPLETED IN PHASES TO ENSURE LEAST AMOUNT OF

DISRUPTION TO VETERANS AND STAFF AND TO ENSURE LIFE SAFETY REQUIREMENTS

REMAIN WITHIN REQUIRED LIMITS THROUGHOUT THE ENTIRE CONSTRUCTION

PROCESS.

b. TWO PHASES ARE RECOMMENDED FOR THE WORK:

a. PHASE 1 TO INCLUDE:

• FIRST FLOOR - BRAVO AREA (PRIMARY CARE)

• SECOND FLOOR - LIMA AREA (EYE CLINIC)

• SECOND FLOOR - INDIA (VACCINE CLINIC)

• SECOND FLOOR - OSCAR (SURGERY TEAM ROOM 2D164-2D165)

b. PHASE 2 TO INCLUDE:

• FIRST FLOOR - CHARLIE AREA (PRIMARY CARE)

• SECOND FLOOR - OSCAR (SURGERY TEAM ROOM 2F101-2F102)

• SECOND FLOOR - JULIET - NEW OFFICE SPACE ADJACENT TO 2C167.

• SECOND FLOOR - INDIA - NEW CONSULT SPACE

c. AT CONTRACTOR'S DISCRETION:

• FIRST FLOOR - FOXTROT - NEW APC CLOSET

O ffi ce of

Fac ilit ie s

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

BUILDING / LOCATION INFORMATION: DRAWING TITLE:

BUILDING NUMBER:

CAMPUS:

ADDRESS:

FLOOR # (IF APPLICABLE):

ROOM # / SUITE DESCRIPTION:

SHEET NUMBER:

ADDITIONAL DRAWING INFORMATION:

SHEET OF

Project Title:

520-23-106

RENOVATE VARIOUS INTERIOR SPACES TO IMPROVE

PRIMARY CARE AND OTHER SPECIALTY SERVICES, JACC

Veterans Affairs - Engineering

Drawings Prepared By:

Drawing Date:

GULF COAST VETERANS HEALTH CARE SYSTEM

400 VETERANS AVENUE, BILOXI, MS 39531

zz

FIRST FLOOR

VARIOUS

Pensacola VA Clinic

790 Veterans Way, Pensacola, FL 32507

OVERALL IMPROVEMENT FLOOR PLANS

FIRST FLOOR

04-12-2023

A01 A01 6

1" = 20'-0" First Floor Improvement Locations

N

EXISTING PIC 01 - FIRST FLOOR EXISTING PIC 02 - FIRST FLOOR

EXISTING PIC 03 - FIRST FLOOR EXISTING PIC 04 - FIRST FLOOR

EXISTING PIC 05 - FIRST FLOOR EXISTING PIC 06 - FIRST FLOOR

EXISTING PIC 07 - FIRST FLOOR EXISTING PIC 08 - FIRST FLOOR

EXISTING PIC 09 - FIRST FLOOR EXISTING PIC 10 - FIRST FLOOR

EXISTING PIC 11 - FIRST FLOOR EXISTING PIC 12 - FIRST FLOOR

PHASE 1

PHASE 2

PHASE 1 OR 2

A06

A06

A06

A06

A04

A04

A04

A04

DEMO

NEW

DEMO

NEW

DEMO

NEW

DEMO

NEW

A04

A06

DEMO NEW

EYE CLINIC

AUDIOLOGY

DENTAL

OUTPATIENT SURGERY

OUTPATIENT

MENTAL HEALTH

SPECIALTY

CARE

SPECIALTY

CARE

SPECIALTY

CARE

CLINIC ADMIN

LI

M

A M

IK

E

N O

VE

M

B

ER

O

SC

AR

IN

D

IA

JU

LI

ET

K

IL

O

OFF

VACCINE CLINIC

CONS

TEAM

RM

TEAM

RM

MAS

EXPANSION

PROJECT PHASING

a.

b.

THIS PROJECT SHALL BE COMPLETED IN PHASES TO ENSURE LEAST AMOUNT OF

DISRUPTION TO VETERANS AND STAFF AND TO ENSURE LIFE SAFETY REQUIREMENTS

REMAIN WITHIN REQUIRED LIMITS THROUGHOUT THE ENTIRE CONSTRUCTION

PROCESS.

TWO PHASES ARE RECOMMENDED FOR THE WORK:

a. PHASE 1 TO INCLUDE:

• FIRST FLOOR - BRAVO AREA (PRIMARY CARE)

• SECOND FLOOR - LIMA AREA (EYE CLINIC)

• SECOND FLOOR - INDIA (VACCINE CLINIC)

• SECOND FLOOR - OSCAR (SURGERY TEAM ROOM 2D164-2D165)

b. PHASE 2 TO INCLUDE:

• FIRST FLOOR - CHARLIE AREA (PRIMARY CARE)

• SECOND FLOOR - OSCAR (SURGERY TEAM ROOM 2F101-2F102)

• SECOND FLOOR - JULIET - NEW OFFICE SPACE ADJACENT TO 2C167.

• SECOND FLOOR - INDIA - NEW CONSULT SPACE

c. AT CONTRACTOR'S DISCRETION:

• FIRST FLOOR - FOXTROT - NEW APC CLOSET

O ffi ce of

Fac ilit ie s

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

BUILDING / LOCATION INFORMATION: DRAWING TITLE:

BUILDING NUMBER:

CAMPUS:

ADDRESS:

FLOOR # (IF APPLICABLE):

ROOM # / SUITE DESCRIPTION:

SHEET NUMBER:

ADDITIONAL DRAWING INFORMATION:

SHEET OF

Project Title:

520-23-106

RENOVATE VARIOUS INTERIOR SPACES TO IMPROVE

PRIMARY CARE AND OTHER SPECIALTY SERVICES, JACC

Veterans Affairs - Engineering

Drawings Prepared By:

Drawing Date:

GULF COAST VETERANS HEALTH CARE SYSTEM

400 VETERANS AVENUE, BILOXI, MS 39531

zz

SECOND FLOOR

VARIOUS

Pensacola VA Clinic

790 Veterans Way, Pensacola, FL 32507

OVERALL IMPROVEMENT FLOOR PLANS

SECOND FLOOR

04-12-2023

A02 A02 6

1" = 20'-0" Second Floor Improvement Locations

N

EXISTING PIC 01 - SECOND FLOOR EXISTING PIC 02 - SECOND FLOOR EXISTING PIC 03 - SECOND FLOOR

EXISTING PIC 04 - SECOND FLOOR EXISTING PIC 05 - SECOND FLOOR EXISTING PIC 06 - SECOND FLOOR

EXISTING PIC 07 - SECOND FLOOR EXISTING PIC 08 - SECOND FLOOR EXISTING PIC 09 - SECOND FLOOR

EXISTING PIC 10 - SECOND FLOOR EXISTING PIC 11 - SECOND FLOOR

EXISTING PIC 12 - SECOND FLOOR EXISTING PIC 13 - SECOND FLOOR

EXISTING PIC 14 - SECOND FLOOR EXISTING PIC 15 - SECOND FLOOR

VACCINE CLINIC

PHASE 1

PHASE 2

OFFICE

PHASE 2

PHASE 1

PHASE 2

PHASE 1

EXAM

ROOM

1C202

EXAM

ROOM

1C204

TOILET

1C206

TOILET

1C207

OFFICE

1C208

TOILET

1C209

TOILET

1C210

LOBBY

1G103

LOBBY /

WAITING

ROOM

1C211

CORRIDOR

C1-31

EXAM

ROOM

1C205

CORRIDOR

C1-28

EXAM

ROOM

1C203

EXAM

ROOM

1C178

VITALS

1C177

CORRIDOR

C1-27

C&P Storage 1C176

CORRIDOR

C1-24

EXAM

ROOM

1C179

EXAM

ROOM

1C167

VITALS

1C169

NURSING

TRIAGE

1C171

CORRIDOR

C1-23

EXAM

ROOM

1C168

NURSING

TRIAGE

1C170

NURSING

GROUP

CONSULT

1C172

ELECTRICAL

1C173

STAIRWELL

1STR4

LOBBY /

WAITING

ROOM

1C174

MAS

RECEPTION

1C175

1, 2

13' - 0" 11' - 4"

3'

8'

0" 5'

0"

8'

0"

6' - 1"

2' - 0"

8' - 6" 7' - 8"

NOTES:

1. ICRA - TYPE C / GROUP 3 / CLASS III

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

6 6

A*

CONSTRUCT ICRA BARRIER AS

REQUIRED TO ADD TEMP. ACCESS

DOOR AND WALL. COORDINATE WITH

VA COR.

PROTECT EXISTING

MILLWORK AND FURR-DOWN

ABOVE TO BE RETURNED TO

USE AT CONCLUSION OF

CONSTRUCTION

DEMOLISH EXISTING WALL. PATCH

AND PAINT TO MAKE SUITABLE FOR

STAFF TO PASS INTO MAS AREA

DURING CONSTRUCTION.

REWORK CEILING GRID AND TILES

AS REQUIRED. WALL TO BE

RECONSTRUCTED IN SAME PLACE.

CLOSE, LOCK AND SEAL DOOR DURING

CONSTRUCTION - NO THROUGH ACCESS

4' - 0"

3' - 1"

CONSTRUCT ICRA BARRIER AS

REQUIRED TO ADD TEMP. ACCESS

DOOR AND WALL. COORDINATE WITH

VA COR.

1, 2

3 3

EXISTING LAY-IN CEILING TO

REMAIN ADJACENT TO DEMO'D.

REWORK EXISTING TO REMAIN TO

DIE INTO NEW WALL

EXISTING LAY-IN CEILING TO

REMAIN ADJACENT TO DEMO'D.

REWORK EXISTING TO REMAIN

TO DIE INTO NEW WALL

13' - 0" 11' - 4"

8'

0"

6' - 1"

2' - 0"

8' - 1" 8' - 1"

3'

0"

0"

A*

PROTECT EXISTING

MILLWORK AND FURR-DOWN

ABOVE TO BE RETURNED TO

USE AT CONCLUSION OF

CONSTRUCTION

CONSTRUCT ICRA BARRIER AS

REQUIRED TO ADD TEMP. ACCESS

DOOR AND WALL. COORDINATE WITH

VA COR.

DEMOLISH EXISTING WALL. PATCH

AND PAINT TO MAKE SUITABLE FOR

STAFF TO PASS INTO MAS AREA

DURING CONSTRUCTION. REWORK

CEILING GRID AND TILES AS

REQUIRED. WALL TO BE

RECONSTRUCTED IN SAME PLACE.

EMPLOYEE

HEALTH

1C133

CORRIDOR

C1-19

LOBBY /

WAITING

ROOM

1C134

CORRIDOR

C1-16

VITALS

1C132

VITALS

1C130

CORRIDOR

C1-12

OFFICE

1C105

NURSING

OFFICE

1C103

LOBBY /

WAITING

ROOM

1C100

MAS

RECEPTION

1C131

4 6 6

6 6

1, 2

1, 2

8' - 4"

2' - 3"

13' - 1"

2' - 10"

4'

6"

9' - 10"

NOTES:

1. ICRA - TYPE C / GROUP 3 / CLASS III

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

A*

STOP TEMP WALL JUST WITHIN ICRA-

ENCLOSURE - FULLY SEAL ALL

AROUND -

COORDINATE EXACT LOCATION WITH

VA COR.

1' - 6" 1' - 8"

CONSTRUCT ICRA BARRIER AS

REQUIRED TO ADD TEMP. ACCESS

DOOR AND WALL. COORDINATE WITH

VA COR.

1, 2

3 3

3 3

EXISTING LAY-IN CEILING TO REMAIN

ADJACENT TO DEMO'D. REWORK EXISTING

TO REMAIN TO DIE INTO NEW WALL

EXISTING LAY-IN CEILING TO REMAIN

ADJACENT TO DEMO'D. REWORK EXISTING

TO REMAIN TO DIE INTO NEW WALL

4'

0"

A*

STOP TEMP WALL JUST WITHIN ICRA-

ENCLOSURE - FULLY SEAL ALL

AROUND -

COORDINATE EXACT LOCATION WITH

VA COR.CONSTRUCT ICRA BARRIER AS

REQUIRED TO ADD TEMP. ACCESS

DOOR AND WALL. COORDINATE WITH

VA COR.

TOILET

1D141

LOCKERS

1D137

TOILET

1D140

CORRIDOR

C1-77

X-RAY

1D125

BLOOD

DRAW 4

1D109D

BLOOD

DRAW 3

1D109C

BLOOD

DRAW 2

1D109B

DRESSING

ROOM

1D132 1, 2

13' - 7"

5'

6"

NOTES:

1. ICRA - TYPE C / GROUP 3 / CLASS III

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

A*

1, 2 5'

6"

13' - 7"

A*

GENERAL DEMOLITION NOTES

A. ALL WORK SHALL ADHERE TO OSHA, MDEQ, AND VA SAFETY GUIDELINES

AND REQUIREMENTS FOR APPLICABLE WORK IN PROGRESS.

B. ALL DEMOLITION AND CONSTRUCTION WORK WILL TAKE PLACE OUTSIDE

OF NORMAL HOSPITAL OPERATING HOURS AND ON WEEKENDS. THE

WORK SCHEDULE WILL BE COORDINATED AND AGREED UPON BY THE

COR PRIOR TO BEGINNING THE WORK AND SHOULD BE SIGNED OFF

ACCORDINGLY.

C. SMOKE DETECTORS AND FIRE ALARM DEVICES IN THE WORK AREA SHALL

REMAIN AND BE PROTECTED. RECONNECTION OF ALL FIRE ALARM

DEVICES, IF REQUIRED, SHALL BE COORDINATED WITH THE OWNER'S

EXISTING FIRE ALARM SYSTEM AND FIRE SAFETY OFFICER.

D. CONTRACTOR SHALL COORDINATE ALL DEMOLITION WORK BETWEEN ALL

DISCIPLINES. CONTRACTOR SHALL DISPOSE OF ALL ITEMS PER

SPECIFICATIONS. VA COR MAY REQUEST SOME ITEMS BE SALVAGED.

ANY SUCH ITEMS WILL BE IDENTIFIED DURING THE PRE-CONSTRUCTION

WALK-THROUGH.

E. THROUGHOUT CONSTRUCTION, THE CONTRACTOR IS RESPONSIBLE FOR

PROTECTING ALL EXISTING MATERIALS & UTILITIES WITHIN THE

CONSTRUCTION AREA. ANY DAMAGE TO EXISTING BUILDING

STRUCTURAL, MATERIALS, OR UTILITIES CAUSED BY CONSTRUCTION

ACTIVITY SHALL BE REPAIRED OR REPLACED AT THE CONTRACTOR'S

EXPENSE AND APPROVED BY THE VA COR.

F. EXISTING SPRINKLER HEADS, IN AREAS WHERE CEILINGS ARE BEING

TEMPORARILY OR PERMANENTLY REMOVED, SHALL BE TURNED UPWARD

WITH LENGTHS AND HEADS ADJUSTED TO FULLY PROTECT THE AREAS

PER NFPA. IN AREAS WHERE NEW CEILINGS ARE BEING INSTALLED,

SPRINKLER HEADS SHALL BE TURNED DOWN AND INSTALLED IN THE

CENTER OF THE CEILING TILES WITH LENGTHS AND HEADS ADJUSTED TO

FULLY PROTECT THE AREAS.

G. TEMPORARY BRACING OR SHORING MAY BE NECESSARY, AND SHALL BE

THE RESPONSIBILITY OF THE CONTRACTOR.

H. CONTRACTOR SHALL PATCH AND REPAIR ALL OPENINGS, VOIDS OR

PENETRATIONS LEFT BY THE INSTALLATION OR CONSTRUCTION OF

EQUIPMENT, PIPING, DUCTS, ETC. TO MAINTAIN THE INTEGRITY OF THE

WALL, FLOOR, AND/OR ROOF ASSEMBLY.

I. USE OF ANY PLUMBING FIXTURE (SINK,TOILET, FLR. DRAIN, OR CATCH

BASIN, ETC.) FOR WASH-UP DISPOSAL OF THERE WASTE FROM, OR IS

SPENT STRICTLY LIQUIDS, PROHIBITED. PAINT P

J. CONTRACTOR SHALL PROTECT ALL BUILDING UTILITIES AND SYSTEMS

INCLUDING BUT NOT LIMITED TO EXISTING ELECTRICAL EQUIPMENT, FIRE

PROTECTION, PLUMBING FIXTURES, PIPING, DUCTING, MECHANICAL

EQUIPMENT, COMMUNICATION SYSTEMS (WIRELESS AND HARD WIRED)

AND ALARM SYSTEMS DURING DEMOLITION AND CONSTRUCTION. ANY

ITEMS OR SYSTEMS DAMAGED AS A RESULT OF THE PROJECT SHALL BE

THE RESPONSIBILITY OF THE CONTRACTOR TO REPAIR OR REPLACE AT

NO COST TO THE OWNER.

K. EACH AND EVERY INDIVIDUAL LOCATION OR ITEM NEEDED TO BE

DEMOLISHED OR MODIFIED MAY NOT BE REFLECTED OR DELINEATED IN

THE DRAWINGS. AMOUNTS AND QUANTITIES SHALL BE FIELD VERIFIED

AND CLARIFIED BY THE VA COR PRIOR TO DEMOLITION OR

CONSTRUCTION.

L. ANY EXISTING FLOOR DRAINS, CLEAN OUTS, AND THEIR ASSOCIATED

PIPING SYSTEMS SHALL BE COVERED DURING ALL DEMOLITION AND NEW

PROJECT WORK. COVER AND PIPING SYSTEMS SHALL BE COVERED

DURING ALL DEMOLITION AND NEW PROJECT WORK. COVER AND UN-

COVER AS REQUIRED TO PREVENT INFILTRATION OF DEMOLITION OR

CONSTRUCTION DEBRIS THROUGH EACH SHIFTS WORK DAILY

THROUGHOUT DURATION OF THE PROJECT. CONTRACTOR SHALL NOT

LEAVE FLOOR DRAINS COVERED AT THE END OF A DAYS SHIFT OR WHEN

NO WORK IS IN PROGRESS.

M. WALL MOUNTED FIRE EXTINGUISHERS SHALL REMAIN WITHIN 60" OF

ORIGINAL LOCATION THROUGHOUT ALL WORK IN THE PROJECT.

CONTRACTOR SHALL VERIFY WORKING ORDER AND CHARGE AT ALL

TIMES THROUGHOUT PROJECT WORK.

N. CONTRACTOR SHALL NOT STORE OR STAGE ANY MATERIALS,

DEMOLISHED OR NEW, IN EXISTING MAIN CORRIDORS, ADJACENT ROOMS,

OR ANY OTHER AREAS, INCLUDING TOOLS, EQUIPMENT, LADDERS, ETC.

UNLESS COORDINATED AND APPROVED BY THE VA COR.

O. ANY PIPING, DUCTWORK, SYSTEMS, ETC. TO BE PERMANENTLY

ABANDONED OVERHEAD, IN WALLS OR FLOOR SLABS, SHALL BE SEALED,

CAPPED, AND TESTED, BEFORE SEALING OR COVERING IN NEW WALLS OR

BACK-FILLED IN SLABS.

P. CARE MUST BE TAKEN WHEN REMOVING OR RELOCATING AND ALL

CONDUIT AND WIRING. THE CONTRACTOR SHALL VERIFY THE POWER

SOURCE HAS BEEN DISABLED PRIOR TO ELECTRICAL DEMOLITION OR

CONSTRUCTION. VA COR SHALL BE NOTIFIED IMMEDIATELY SHOULD AN

ELECTRICAL, MECHANICAL, DATA OR OTHER ISSUE ARISE.

Q. AT AREAS WHERE FLOORING IS DEMOLISHED, REMOVE SYSTEM IN ITS

ENTIRETY TO DECK. FULLY PREPARE CONCRETE SLAB FOR INSTALLATION

OF NEW FLOORING. ADHERE TO MANUFACTURER REQUIREMENTS AND

TOLERANCES FOR NEW INSTALLATION. IF REQUIRED, GRIND AND/OR

APPLY SELF-LEVELING COMPOUND TO ENSURE REQUIRED FLATNESS.

KEYNOTES - DEMOLITION

1. HATCHED AREA DENOTES APPROXIMATE EXTENT OF DEMOLITION

REQUIRED. COORDINATE FULL EXTENT OF DEMOLITION WITH NEW WORK.

2. FULLY REMOVE PARTITIONS, DOORS, CEILINGS, FLOORING, BASE,

FIXTURES, ASSOCIATED CONDUIT, ETC. WITHIN HATCHED AREA AND

PREPARE AREA FOR NEW WORK. DIRECT ANY CLARIFICATIONS NEEDED

TO VA COR.

3. DEMO PORTION OF GYPSUM BD. FURR-DOWN INCL. FIXTURES WITHIN. -

PORTION OF FURR-DOWN TO REMAIN - ENSURE FIXTURE IN THIS PORTION

REMAINS OPERATIONAL.

4. FULLY REMOVE ALL BASE AND WALL CABINETS.

5. DEMO AND REMOVE NURSE-CALL PANEL BOX. NEATLY BUNDLE AND

SECURE ASSOCIATED WIRING ABOVE CEILING FOR REMOVAL IN FUTURE

PROJECT.

6. DEMO MAS WORKSTATION MILLWORK COMPLETELY. TAKE CARE TO

ENSURE PORTION TO REMAIN CAN BE NEATLY TRIMMED TO NEW WALL

WITH LIKE-NEW APPEARANCE.

7. REMOVE WOOD DOOR AND H.M. FRAME. PREP OPENING FOR INFILL.

8. REMOVE PARTITION, WOOD DOOR, AND H.M. FRAME

9. PARTIAL DEMOLITION OF EXISTING COLUMN FURRING MAY BE REQUIRED.

FIELD VERIFY AND CONSULT WITH VA COR AS NEEDED.

10. REMOVE AND DISPOSE OF ALL RESTROOM FIXTURES. CAREFULLY CAP

EXISTING UTILITIES WITHIN WALL CAVITY FOR FUTURE USE. EXISTING SINK

TO REMAIN WHERE INDICATED ON PLAN.

11. REMOVE EXISTING H.M. DOOR AND FRAME. PREP OPENING TO RECEIVING

NEW OPPOSITE HAND H.M. FRAME AND WOOD DOOR.

12. DEMOLISH PORTION OF GYPSUM BOARD FURR-DOWN SHOWN DASHED.

13. TAKE CARE WHEN REMOVING PORTION OF WALL AT CEILING FURR-DOWN.

FURR-DOWN IS TO REMAIN AND BE INFILLED, PATCHED, FINISHED AND

PAINTED TO MATCH REST OF EXISTING FURR-DOWN FOR LIKE-NEW

APPEARANCE

15. REMOVE BASE AND UPPER CABINETS COMPLETELY. PREPARE AREA FOR

NEW FINISHES.

16. TAKE SPECIAL CARE WHEN DEMOLISHING PORTION OF EXISTING WALLS

ADJACENT TO FURR-DOWN. FURR-DOWN TO REMAIN AND BE EXPANDED

OVER TOP OF REWORKED CHECK-IN MILLWORK BELOW.

17. CUT OPENING AND INSTALL 3'-0" x 7'-0" TEMP H.M.F. WOOD DOOR FOR

STAFF USE DURING CONSTRUCTION. DEMOLISH TEMP DOOR AND FRAME

AND INFILL, PATCH, PAINT, REWORK BASE BOTH SIDES OF WALL AS

REQUIRED FOR NEW APPEARANCE.

18. DEMOLISH EXISTING MILLWORK RECEPTION DESK AND FURR-DOWN

ABOVE. LIGHTING AND CEILING GRID ABOVE TO BE REWORKED AS

REQUIRED.

19. REMOVE FLOATING WALL AND ADJACENT FURR-DOWN.

20. REWORK LOBBY LVT FLOORING WHERE WALL REMOVED FOR SEAMLESS

APPEARANCE.

21. REMOVE PORTION OF FURR-DOWN AND REWORK LOBBY-SIDE TO NEW

WALL.

22. REMOVE PARTIAL GRID AND TILES OF SUSPENDED CEILING. (CEILING GRID

TO BE REWORKED TO EXTEND OVER ENLARGED RECEPTION AREA).

23. REMOVE UPPER PORTION OF MILLWORK CABINETRY. EXISTING

RECEPTION WORKING SURFACE IS TO BE EXTENDED AS SHOWN ON

IMPROVEMENT PLAN.

24. DEMOLISH PNEUMATIC TUBE SYSTEM AND CHASE. PREP AREA FOR

INCLUSION INTO USABLE SPACE.

25. CONSTRUCT TEMPORARY WALL TO JUST BELOW CEILING WITH 3'0"x7'0"

ACCESS DOOR FOR MAS PERSONNEL TO USE DURING CONSTRUCTION.

GASKET T.O.W. TO CEILING. WALL AND DOOR SHOULD BE PAINTED FOR

PRESENTABLE APPEARANCE CONSTRUCTION. PROVIDE REQUIRED STAFF

ELECTRONIC ACCESS CONTROL KEYPAD. COORDINATE WITH VA COR.

UPON COMPLETION OF CONSTRUCTION AND REMOVAL OF ICRA BARRIERS,

ETC. THAT PROHIBIT STAFF FROM ACCESSING THEIR SPACE FROM

PRIMARY CARE, REMOVE TEMPORARY WALL/DOOR. REPAIR/REPLACE

FLOORING/BASE AS REQUIRED IN WAITING ROOM AS NECESSARY FOR

NEW APPEARANCE. WALL SHOULD BE REMOVED AND AREA RETURNED TO

USABLE CONDITION AFTER HOURS OR OVER A WEEKEND. COORDINATE

WITH VA COR.

14. TAKE SPECIAL CARE WHEN DEMOLISHING PORTION OF EXISTING CEILING

GRID AND TILES. EXISTING GRID AND TILES CAN BE REUSED AS ABLE

WHEN REWORKING CEILING TO NEW WALL LAYOUT. REPLACE GRID AND

TILES AS NEEDED TO ENSURE LIKE-NEW APPEARANCE.

INFECTION CONTROL (ICRA) NOTES

Note: Rated ICRA Barriers not required for Fire Protection / Life Safety.

A. THE CONTRACTOR SHALL PROVIDE, COORDINATE, AND MAINTAIN ALL INFECTION

CONTROL / AIR QUALITY CONTROL MEASURES TO MEET THE ESTABLISHED CLASS

RATING AS REQUIRED BY THE INFECTION CONTROL OFFICER.

B. OBTAIN INFECTION CONTROL PERMIT BEFORE CONSTRUCTION BEGINS.

C. COORDINATE ALL DEMOLITION/CONSTRUCTION DEBRIS PATH OF TRAVEL AND

INTERIM LIFE SAFETY MEASURES WITH VA COR.

D. IMMEDIATELY REPLACE ANY DISPLACED CEILING TILES IN AREAS ACTIVELY USED BY

VETERANS OR STAFF FOR VISUAL INSPECTION.

E. AS ABLE, EXECUTE WORK BY METHODS TO MINIMIZE DUST GENERATED BY

CONSTRUCTION OPERATIONS. PROVIDE ACTIVE MEANS TO PREVENT AIR-BORNE

DUST FROM DISPERSING INTO ATMOSPHERE. I.E. WATER-MIST WORK SURFACES

TO CONTROL DUST WHILE CUTTING.

F. SEAL UNUSED DOORS WITH TAPE

G. WIPE SURFACES AND WET MOP WITH DISINFECTANT. VACUUM WORK WITH HEPA-

FILTERED VACUUMS.

H. CONSTRUCT ALL REQUIRED ICRA CONSTRUCTION BARRIERS PRIOR TO BEGINNING

WORK. CONSTRUCTION AREAS SHALL REMAIN ISOLATED FROM OTHER AREAS OF

THE MEDICAL CLINIC. ISOLATE HVAC SYSTEM WITHIN CONSTRUCTION AREA TO

PREVENT CONTAMINATION OF EXISTING DUCT SYSTEM. NO RETURN AIR OR

EXHAUST SHALL PASS INTO AREAS OUTSIDE OF THE CONSTRUCTION AREA. BLOCK

OFF AND SEAL ALL AIR VENTS. DO NOT REMOVE BARRIERS FROM WORK AREA

UNTIL COMPLETE PROJECT IS THOROUGHLY CLEANED BY ENVIRONMENTAL

MANAGEMENT SERVICES.

I. AFTER PROJECT INSPECTION AND ACCEPTANCE BY VA SAFETY, INFECTION

CONTROL, ENGINEERING AND COR, CONSTRUCTION BARRIERS CAN BE REMOVED.

PATCH OR REPAIR ANY DAMAGE FROM CONSTRUCTION BARRIER REMOVAL AND

REMOVE ISOLATION OF HVAC SYSTEM.

J. MAINTAIN NEGATIVE AIR PRESSURE IN CONSTRUCTION AREAS AT ALL TIMES FOR

THE DURATION OF CONSTRUCTION USING HEPA-FILTERED FILTRATION UNITS. SEAL

ALL HOLES, PUNCTURES, AND PENETRATIONS FROM PIPES AND CONDUITS

APPROPRIATELY AND IMMEDIATELY TO MAINTAIN DUST PROTECTION AND NEGATIVE

PRESSURE.

K. WORK AREA SHALL BE KEPT CLEAN AND ORDERLY. CONTAIN CONSTRUCTION

WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. COVER

TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING.

L. SIGNAGE SHALL BE USED TO REDIRECT ALL MEDICAL CENTER PERSONNEL,

PATIENTS, AND VISITORS SO THEY DO NOT PASS THROUGH THE CONSTRUCTION

AREA. PROVIDE SIGNS ON DOORS AND INTO CONSTRUCTION AREA THAT READS:

"CONSTRUCTION AREA - DO NOT ENTER".

M. TACKY MATS SHALL BE PLACED AT ALL DOORS INTO THE CONSTRUCTION AREA AND

SHALL BE MONITORED TO MAKE SURE THEY REMAIN EFFECTIVE.

N. CONTRACTOR AND SUBCONTRACTORS SHALL CONSULT VA COR AND INFECTION

CONTROL REPRESENTATIVE PRIOR TO ALL WORK TO BE PERFORMED IN AREAS

OUTSIDE OF CURRENT WORK AREAS.

O. ANY DUST TRACKED OUTSIDE OF CONSTRUCTION AREA SHALL BE CLEANED

IMMEDIATELY. MAINTAIN STAFFING AND EQUIPMENT NECESSARY FOR CLEANING

DUST/DEBRIS FROM FLOORS AND ADJACENT OCCUPIED AREAS AS REQUIRED

INCLUDING DUST MOPS, WET MOPS, BROOMS, BUCKETS, CLEAN WIPE RAGS, ETC.

P. AFTER COMPLETION OF THE WORK, CONSTRUCTION AREA SHALL BE FULLY

VACUUMED WITH HEPA FILTERED VACUUM AND WET MOPPED WITH DISINFECTANT.

CLASS III ICRA REQUIREMENTS INCLUDE:

Q. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS

ROOM SO THEY CAN BE VACUUMED USING A HEPA-FILTERED VACUUM CLEANER

BEFORE LEAVING WORK SITE OR THEY CAN WEAR CLOTH OR PAPER COVERALLS

THAT ARE REMOVED EACH TIME THEY LEAVE THE WORK SITE.

R. ALL PERSONNEL ENTERING THE WORK SITE ARE REQUIRED TO WEAR SHOE

COVERS.

CLASS IV ICRA REQUIREMENTS INCLUDE ALL OF ITEMS A-P ABOVE

PLUS THE FOLLOWING:

CONSTRUCTION ACTIVITY TYPE C:

ACTIVITY GENERATES MODERATE TO HIGH

LEVELS OF DUST, REQUIRES GREATER THAN 1

WORK SHIFT FOR COMPLETION.

IC RISK GROUP:

GROUP 3: MEDIUM / HIGH RISK

GROUP 4: HIGH RISK

ICRA LEGEND

SUGGESTED ICRA BOUNDARY LOCATION - FIELD VERIFY

EXACT LOCATION(S) IN FIELD WITH VA COR PRIOR TO

INSTALLATION.

A* CONSTRUCTION ACCESS

LOCATION - SEE PLAN -

PROVIDE TACKY MATS

BOTH INSIDE AND OUTSIDE

OF BARRIER

O ffi ce of

Fac ilit ie s

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

BUILDING / LOCATION INFORMATION: DRAWING TITLE:

BUILDING NUMBER:

CAMPUS:

ADDRESS:

FLOOR # (IF APPLICABLE):

ROOM # / SUITE DESCRIPTION:

SHEET NUMBER:

ADDITIONAL DRAWING INFORMATION:

SHEET OF

Project Title:

520-23-106

RENOVATE VARIOUS INTERIOR SPACES TO IMPROVE

PRIMARY CARE AND OTHER SPECIALTY SERVICES, JACC

Veterans Affairs - Engineering

Drawings Prepared By:

Drawing Date:

GULF COAST VETERANS HEALTH CARE SYSTEM

400 VETERANS AVENUE, BILOXI, MS 39531

zz

FIRST FLOOR

VARIOUS

Pensacola VA Clinic

790 Veterans Way, Pensacola, FL 32507

ENLARGED IMPROVEMENT PLANS - DEMOLITION / ICRA

FIRST FLOOR

04-12-2023

A03 A03 6

1/8" = 1'-0"1 First Floor - Enlarged Partial Plan - CHARLIE - Demolition

1/8" = 1'-0"2 First Floor - Enlarged Partial Plan - BRAVO - Demolition

1/8" = 1'-0"3 First Floor - Enlarged Partial Plans - Equipment Room - Demolition

NOTE: REFER TO SHEETS FP02 AND FP03 FOR SMOKE BARRIER

LOCATIONS AND DESIGNATIONS AND ENSURE PROPER

CONSTRUCTION OF NEW REQUIRED BARRIERS PER THE

REQUIREMENTS ON SHEET FP01.

MEDICATION

ROOM

2C173

LOBBY /

WAITING

ROOM

2C170

LOBBY /

WAITING

ROOM

2G100

LOBBY /

WAITING

ROOM

2G107

STAIR 4

2STR4

ELECTRICAL

2C169

SOILED

UTILITY

2C166

CORRIDOR

C2-26

WOMEN'S

HEALTH

OFFICE

2C165

GASTRO

EXAM

ROOM

2C133

SOILED

UTILITY

2C135

CORRIDOR

C2-22

NURSE

TEAM

ROOM

2C131

TOILET

2C130

TOILET

2C129

LOBBY /

WAITING

ROOM

2C128

RHEUMATOLOGY

PROVIDER

2C136

MEDICATION

ROOM

2C126

LOBBY /

WAITING

ROOM

2C127

SOCIAL

WORK

OFFICE

2C167

WOMEN'S

HEALTH

EXAM

ROOM

2C164

15' - 8" 17' - 6"

9'

6"

12' - 11"

6' - 8"

10' - 0" 11' - 5"

1,2

1,210 10

20' - 4"

7 7

REWORK LVT FLOORING

EXISTING SINK

TO REMAIN

NOTES:

1. ICRA - TYPE C / GROUP 3 / CLASS III

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

A*

CLOSE, LOCK AND

SEAL DOORS DURING

CONSTRUCTION - NO

THROUGH ACCESS

A*

OIT/COMM

2A137

CORRIDOR

C2-08

LOBBY /

WAITING

ROOM

2A136

LOBBY /

WAITING

ROOM

2G104

GROUP

ROOM/SHARED

MED

APPTS

2A135

LOBBY /

WAITING

ROOM

2C100

12' - 7"

NOTES:

1. ICRA - TYPE C / GROUP 3 / CLASS III

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

CLOSE, LOCK AND

SEAL DOOR DURING

CONSTRUCTION - NO

THROUGH ACCESS

A*

PREP/RECOVERY

2F112

STORAGE

2F112A

TOILET

2F115

ONCOLOGY

INFUSION

CLINIC

2F119

MEDICATION

ROOM

2D167

ONCOLOGY

INFUSION

CLINIC

2D169

CORRIDOR

C2-65

CORRIDOR

C2-66

CORRIDOR

C2-64

STORAGE

ALCOVE

2D163

CLEAN

UTILITY

2D162

SOILED

UTILITY

2D166

MINOR

PROCEEDURE

ROOM

2D142

SCRUB

C2-66A

MINOR

PROCEEDURE

ROOM

2D138

13' - 0"

1"

6'

4"

1, 2

NOTES:

1. ICRA - TYPE C / GROUP 4 / CLASS IV

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

A*

LOBBY /

WAITING

ROOM

2G103

LOBBY /

WAITING

ROOM

2B100

MULTIPURPOSE

ROOM

2B125

MAS

Reception

2B101

CORRIDOR

C2-82

EXAM /

TREATMENT

ROOM

2B123

DIALATION

WAITING

2B103

CORRIDOR

C2-83

10' - 3"

0"

NOTES:

1. ICRA - TYPE C / GROUP 3 / CLASS III

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

A*

A*

1, 2

1, 2

12 13

6' - 8"11

17' - 11"

9'

6" 3'

3"

12' - 11" 19' - 0"

1, 2

12' - 0"

4'

0"

A*

CLOSE, LOCK AND

SEAL DOORS DURING

CONSTRUCTION - NO

THROUGH ACCESS

A*

12' - 7"

" 1, 2

CLOSE, LOCK AND

SEAL DOOR DURING

CONSTRUCTION - NO

THROUGH ACCESS

A*

1, 2

121214

13' - 0"

A*

1, 2

A*

A*

GENERAL DEMOLITION NOTES

A. ALL WORK SHALL ADHERE TO OSHA, MDEQ, AND VA SAFETY GUIDELINES

AND REQUIREMENTS FOR APPLICABLE WORK IN PROGRESS.

B. ALL DEMOLITION AND CONSTRUCTION WORK WILL TAKE PLACE OUTSIDE

OF NORMAL HOSPITAL OPERATING HOURS AND ON WEEKENDS. THE

WORK SCHEDULE WILL BE COORDINATED AND AGREED UPON BY THE

COR PRIOR TO BEGINNING THE WORK AND SHOULD BE SIGNED OFF

ACCORDINGLY.

C. SMOKE DETECTORS AND FIRE ALARM DEVICES IN THE WORK AREA SHALL

REMAIN AND BE PROTECTED. RECONNECTION OF ALL FIRE ALARM

DEVICES, IF REQUIRED, SHALL BE COORDINATED WITH THE OWNER'S

EXISTING FIRE ALARM SYSTEM AND FIRE SAFETY OFFICER.

D. CONTRACTOR SHALL COORDINATE ALL DEMOLITION WORK BETWEEN ALL

DISCIPLINES. CONTRACTOR SHALL DISPOSE OF ALL ITEMS PER

SPECIFICATIONS. VA COR MAY REQUEST SOME ITEMS BE SALVAGED.

ANY SUCH ITEMS WILL BE IDENTIFIED DURING THE PRE-CONSTRUCTION

WALK-THROUGH.

E. THROUGHOUT CONSTRUCTION, THE CONTRACTOR IS RESPONSIBLE FOR

PROTECTING ALL EXISTING MATERIALS & UTILITIES WITHIN THE

CONSTRUCTION AREA. ANY DAMAGE TO EXISTING BUILDING

STRUCTURAL, MATERIALS, OR UTILITIES CAUSED BY CONSTRUCTION

ACTIVITY SHALL BE REPAIRED OR REPLACED AT THE CONTRACTOR'S

EXPENSE AND APPROVED BY THE VA COR.

F. EXISTING SPRINKLER HEADS, IN AREAS WHERE CEILINGS ARE BEING

TEMPORARILY OR PERMANENTLY REMOVED, SHALL BE TURNED UPWARD

WITH LENGTHS AND HEADS ADJUSTED TO FULLY PROTECT THE AREAS

PER NFPA. IN AREAS WHERE NEW CEILINGS ARE BEING INSTALLED,

SPRINKLER HEADS SHALL BE TURNED DOWN AND INSTALLED IN THE

CENTER OF THE CEILING TILES WITH LENGTHS AND HEADS ADJUSTED TO

FULLY PROTECT THE AREAS.

G. TEMPORARY BRACING OR SHORING MAY BE NECESSARY, AND SHALL BE

THE RESPONSIBILITY OF THE CONTRACTOR.

H. CONTRACTOR SHALL PATCH AND REPAIR ALL OPENINGS, VOIDS OR

PENETRATIONS LEFT BY THE INSTALLATION OR CONSTRUCTION OF

EQUIPMENT, PIPING, DUCTS, ETC. TO MAINTAIN THE INTEGRITY OF THE

WALL, FLOOR, AND/OR ROOF ASSEMBLY.

I. USE OF ANY PLUMBING FIXTURE (SINK,TOILET, FLR. DRAIN, OR CATCH

BASIN, ETC.) FOR WASH-UP DISPOSAL OF THERE WASTE FROM, OR IS

SPENT STRICTLY LIQUIDS, PROHIBITED. PAINT P

J. CONTRACTOR SHALL PROTECT ALL BUILDING UTILITIES AND SYSTEMS

INCLUDING BUT NOT LIMITED TO EXISTING ELECTRICAL EQUIPMENT, FIRE

PROTECTION, PLUMBING FIXTURES, PIPING, DUCTING, MECHANICAL

EQUIPMENT, COMMUNICATION SYSTEMS (WIRELESS AND HARD WIRED)

AND ALARM SYSTEMS DURING DEMOLITION AND CONSTRUCTION. ANY

ITEMS OR SYSTEMS DAMAGED AS A RESULT OF THE PROJECT SHALL BE

THE RESPONSIBILITY OF THE CONTRACTOR TO REPAIR OR REPLACE AT

NO COST TO THE OWNER.

K. EACH AND EVERY INDIVIDUAL LOCATION OR ITEM NEEDED TO BE

DEMOLISHED OR MODIFIED MAY NOT BE REFLECTED OR DELINEATED IN

THE DRAWINGS. AMOUNTS AND QUANTITIES SHALL BE FIELD VERIFIED

AND CLARIFIED BY THE VA COR PRIOR TO DEMOLITION OR

CONSTRUCTION.

L. ANY EXISTING FLOOR DRAINS, CLEAN OUTS, AND THEIR ASSOCIATED

PIPING SYSTEMS SHALL BE COVERED DURING ALL DEMOLITION AND NEW

PROJECT WORK. COVER AND PIPING SYSTEMS SHALL BE COVERED

DURING ALL DEMOLITION AND NEW PROJECT WORK. COVER AND UN-

COVER AS REQUIRED TO PREVENT INFILTRATION OF DEMOLITION OR

CONSTRUCTION DEBRIS THROUGH EACH SHIFTS WORK DAILY

THROUGHOUT DURATION OF THE PROJECT. CONTRACTOR SHALL NOT

LEAVE FLOOR DRAINS COVERED AT THE END OF A DAYS SHIFT OR WHEN

NO WORK IS IN PROGRESS.

M. WALL MOUNTED FIRE EXTINGUISHERS SHALL REMAIN WITHIN 60" OF

ORIGINAL LOCATION THROUGHOUT ALL WORK IN THE PROJECT.

CONTRACTOR SHALL VERIFY WORKING ORDER AND CHARGE AT ALL

TIMES THROUGHOUT PROJECT WORK.

N. CONTRACTOR SHALL NOT STORE OR STAGE ANY MATERIALS,

DEMOLISHED OR NEW, IN EXISTING MAIN CORRIDORS, ADJACENT ROOMS,

OR ANY OTHER AREAS, INCLUDING TOOLS, EQUIPMENT, LADDERS, ETC.

UNLESS COORDINATED AND APPROVED BY THE VA COR.

O. ANY PIPING, DUCTWORK, SYSTEMS, ETC. TO BE PERMANENTLY

ABANDONED OVERHEAD, IN WALLS OR FLOOR SLABS, SHALL BE SEALED,

CAPPED, AND TESTED, BEFORE SEALING OR COVERING IN NEW WALLS OR

BACK-FILLED IN SLABS.

P. CARE MUST BE TAKEN WHEN REMOVING OR RELOCATING AND ALL

CONDUIT AND WIRING. THE CONTRACTOR SHALL VERIFY THE POWER

SOURCE HAS BEEN DISABLED PRIOR TO ELECTRICAL DEMOLITION OR

CONSTRUCTION. VA COR SHALL BE NOTIFIED IMMEDIATELY SHOULD AN

ELECTRICAL, MECHANICAL, DATA OR OTHER ISSUE ARISE.

Q. AT AREAS WHERE FLOORING IS DEMOLISHED, REMOVE SYSTEM IN ITS

ENTIRETY TO DECK. FULLY PREPARE CONCRETE SLAB FOR INSTALLATION

OF NEW FLOORING. ADHERE TO MANUFACTURER REQUIREMENTS AND

TOLERANCES FOR NEW INSTALLATION. IF REQUIRED, GRIND AND/OR

APPLY SELF-LEVELING COMPOUND TO ENSURE REQUIRED FLATNESS.

KEYNOTES - DEMOLITION

1. HATCHED AREA DENOTES APPROXIMATE EXTENT OF DEMOLITION

REQUIRED. COORDINATE FULL EXTENT OF DEMOLITION WITH NEW WORK.

2. FULLY REMOVE PARTITIONS, DOORS, CEILINGS, FLOORING, BASE,

FIXTURES, ASSOCIATED CONDUIT, ETC. WITHIN HATCHED AREA AND

PREPARE AREA FOR NEW WORK. DIRECT ANY CLARIFICATIONS NEEDED

TO VA COR.

3. DEMO PORTION OF GYPSUM BD. FURR-DOWN INCL. FIXTURES WITHIN. -

PORTION OF FURR-DOWN TO REMAIN - ENSURE FIXTURE IN THIS PORTION

REMAINS OPERATIONAL.

4. FULLY REMOVE ALL BASE AND WALL CABINETS.

5. DEMO AND REMOVE NURSE-CALL PANEL BOX. NEATLY BUNDLE AND

SECURE ASSOCIATED WIRING ABOVE CEILING FOR REMOVAL IN FUTURE

PROJECT.

6. DEMO MAS WORKSTATION MILLWORK COMPLETELY. TAKE CARE TO

ENSURE PORTION TO REMAIN CAN BE NEATLY TRIMMED TO NEW WALL

WITH LIKE-NEW APPEARANCE.

7. REMOVE WOOD DOOR AND H.M. FRAME. PREP OPENING FOR INFILL.

8. REMOVE PARTITION, WOOD DOOR, AND H.M. FRAME

9. PARTIAL DEMOLITION OF EXISTING COLUMN FURRING MAY BE REQUIRED.

FIELD VERIFY AND CONSULT WITH VA COR AS NEEDED.

10. REMOVE AND DISPOSE OF ALL RESTROOM FIXTURES. CAREFULLY CAP

EXISTING UTILITIES WITHIN WALL CAVITY FOR FUTURE USE. EXISTING SINK

TO REMAIN WHERE INDICATED ON PLAN.

11. REMOVE EXISTING H.M. DOOR AND FRAME. PREP OPENING TO RECEIVING

NEW OPPOSITE HAND H.M. FRAME AND WOOD DOOR.

12. DEMOLISH PORTION OF GYPSUM BOARD FURR-DOWN SHOWN DASHED.

13. TAKE CARE WHEN REMOVING PORTION OF WALL AT CEILING FURR-DOWN.

FURR-DOWN IS TO REMAIN AND BE INFILLED, PATCHED, FINISHED AND

PAINTED TO MATCH REST OF EXISTING FURR-DOWN FOR LIKE-NEW

APPEARANCE

15. REMOVE BASE AND UPPER CABINETS COMPLETELY. PREPARE AREA FOR

NEW FINISHES.

16. TAKE SPECIAL CARE WHEN DEMOLISHING PORTION OF EXISTING WALLS

ADJACENT TO FURR-DOWN. FURR-DOWN TO REMAIN AND BE EXPANDED

OVER TOP OF REWORKED CHECK-IN MILLWORK BELOW.

17. CUT OPENING AND INSTALL 3'-0" x 7'-0" TEMP H.M.F. WOOD DOOR FOR

STAFF USE DURING CONSTRUCTION. DEMOLISH TEMP DOOR AND FRAME

AND INFILL, PATCH, PAINT, REWORK BASE BOTH SIDES OF WALL AS

REQUIRED FOR NEW APPEARANCE.

18. DEMOLISH EXISTING MILLWORK RECEPTION DESK AND FURR-DOWN

ABOVE. LIGHTING AND CEILING GRID ABOVE TO BE REWORKED AS

REQUIRED.

19. REMOVE FLOATING WALL AND ADJACENT FURR-DOWN.

20. REWORK LOBBY LVT FLOORING WHERE WALL REMOVED FOR SEAMLESS

APPEARANCE.

21. REMOVE PORTION OF FURR-DOWN AND REWORK LOBBY-SIDE TO NEW

WALL.

22. REMOVE PARTIAL GRID AND TILES OF SUSPENDED CEILING. (CEILING GRID

TO BE REWORKED TO EXTEND OVER ENLARGED RECEPTION AREA).

23. REMOVE UPPER PORTION OF MILLWORK CABINETRY. EXISTING

RECEPTION WORKING SURFACE IS TO BE EXTENDED AS SHOWN ON

IMPROVEMENT PLAN.

24. DEMOLISH PNEUMATIC TUBE SYSTEM AND CHASE. PREP AREA FOR

INCLUSION INTO USABLE SPACE.

25. CONSTRUCT TEMPORARY WALL TO JUST BELOW CEILING WITH 3'0"x7'0"

ACCESS DOOR FOR MAS PERSONNEL TO USE DURING CONSTRUCTION.

GASKET T.O.W. TO CEILING. WALL AND DOOR SHOULD BE PAINTED FOR

PRESENTABLE APPEARANCE CONSTRUCTION. PROVIDE REQUIRED STAFF

ELECTRONIC ACCESS CONTROL KEYPAD. COORDINATE WITH VA COR.

UPON COMPLETION OF CONSTRUCTION AND REMOVAL OF ICRA BARRIERS,

ETC. THAT PROHIBIT STAFF FROM ACCESSING THEIR SPACE FROM

PRIMARY CARE, REMOVE TEMPORARY WALL/DOOR. REPAIR/REPLACE

FLOORING/BASE AS REQUIRED IN WAITING ROOM AS NECESSARY FOR

NEW APPEARANCE. WALL SHOULD BE REMOVED AND AREA RETURNED TO

USABLE CONDITION AFTER HOURS OR OVER A WEEKEND. COORDINATE

WITH VA COR.

14. TAKE SPECIAL CARE WHEN DEMOLISHING PORTION OF EXISTING CEILING

GRID AND TILES. EXISTING GRID AND TILES CAN BE REUSED AS ABLE

WHEN REWORKING CEILING TO NEW WALL LAYOUT. REPLACE GRID AND

TILES AS NEEDED TO ENSURE LIKE-NEW APPEARANCE.

1, 2

11' - 3"

Corr.

C2-62

Corr.

C2-60

TLT.

2F101

TLT.

2F102

A*

1, 2

1, 2

11' - 3"

NOTES:

1. ICRA - TYPE C / GROUP 4 / CLASS IV

2. DIMENSIONS ARE APPROX. AND MUST BE

FIELD VERIFIED IN ALL CASES.

A*

INFECTION CONTROL (ICRA) NOTES

Note: Rated ICRA Barriers not required for Fire Protection / Life Safety.

A. THE CONTRACTOR SHALL PROVIDE, COORDINATE, AND MAINTAIN ALL INFECTION

CONTROL / AIR QUALITY CONTROL MEASURES TO MEET THE ESTABLISHED CLASS

RATING AS REQUIRED BY THE INFECTION CONTROL OFFICER.

B. OBTAIN INFECTION CONTROL PERMIT BEFORE CONSTRUCTION BEGINS.

C. COORDINATE ALL DEMOLITION/CONSTRUCTION DEBRIS PATH OF TRAVEL AND

INTERIM LIFE SAFETY MEASURES WITH VA COR.

D. IMMEDIATELY REPLACE ANY DISPLACED CEILING TILES IN AREAS ACTIVELY USED BY

VETERANS OR STAFF FOR VISUAL INSPECTION.

E. AS ABLE, EXECUTE WORK BY METHODS TO MINIMIZE DUST GENERATED BY

CONSTRUCTION OPERATIONS. PROVIDE ACTIVE MEANS TO PREVENT AIR-BORNE

DUST FROM DISPERSING INTO ATMOSPHERE. I.E. WATER-MIST WORK SURFACES

TO CONTROL DUST WHILE CUTTING.

F. SEAL UNUSED DOORS WITH TAPE

G. WIPE SURFACES AND WET MOP WITH DISINFECTANT. VACUUM WORK WITH HEPA-

FILTERED VACUUMS.

H. CONSTRUCT ALL REQUIRED ICRA CONSTRUCTION BARRIERS PRIOR TO BEGINNING

WORK. CONSTRUCTION AREAS SHALL REMAIN ISOLATED FROM OTHER AREAS OF

THE MEDICAL CLINIC. ISOLATE HVAC SYSTEM WITHIN CONSTRUCTION AREA TO

PREVENT CONTAMINATION OF EXISTING DUCT SYSTEM. NO RETURN AIR OR

EXHAUST SHALL PASS INTO AREAS OUTSIDE OF THE CONSTRUCTION AREA. BLOCK

OFF AND SEAL ALL AIR VENTS. DO NOT REMOVE BARRIERS FROM WORK AREA

UNTIL COMPLETE PROJECT IS THOROUGHLY CLEANED BY ENVIRONMENTAL

MANAGEMENT SERVICES.

I. AFTER PROJECT INSPECTION AND ACCEPTANCE BY VA SAFETY, INFECTION

CONTROL, ENGINEERING AND COR, CONSTRUCTION BARRIERS CAN BE REMOVED.

PATCH OR REPAIR ANY DAMAGE FROM CONSTRUCTION BARRIER REMOVAL AND

REMOVE ISOLATION OF HVAC SYSTEM.

J. MAINTAIN NEGATIVE AIR PRESSURE IN CONSTRUCTION AREAS AT ALL TIMES FOR

THE DURATION OF CONSTRUCTION USING HEPA-FILTERED FILTRATION UNITS. SEAL

ALL HOLES, PUNCTURES, AND PENETRATIONS FROM PIPES AND CONDUITS

APPROPRIATELY AND IMMEDIATELY TO MAINTAIN DUST PROTECTION AND NEGATIVE

PRESSURE.

K. WORK AREA SHALL BE KEPT CLEAN AND ORDERLY. CONTAIN CONSTRUCTION

WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. COVER

TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING.

L. SIGNAGE SHALL BE USED TO REDIRECT ALL MEDICAL CENTER PERSONNEL,

PATIENTS, AND VISITORS SO THEY DO NOT PASS THROUGH THE CONSTRUCTION

AREA. PROVIDE SIGNS ON DOORS AND INTO CONSTRUCTION AREA THAT READS:

"CONSTRUCTION AREA - DO NOT ENTER".

M. TACKY MATS SHALL BE PLACED AT ALL DOORS INTO THE CONSTRUCTION AREA AND

SHALL BE MONITORED TO MAKE SURE THEY REMAIN EFFECTIVE.

N. CONTRACTOR AND SUBCONTRACTORS SHALL CONSULT VA COR AND INFECTION

CONTROL REPRESENTATIVE PRIOR TO ALL WORK TO BE PERFORMED IN AREAS

OUTSIDE OF CURRENT WORK AREAS.

O. ANY DUST TRACKED OUTSIDE OF CONSTRUCTION AREA SHALL BE CLEANED

IMMEDIATELY. MAINTAIN STAFFING AND EQUIPMENT NECESSARY FOR CLEANING

DUST/DEBRIS FROM FLOORS AND ADJACENT OCCUPIED AREAS AS REQUIRED

INCLUDING DUST MOPS, WET MOPS, BROOMS, BUCKETS, CLEAN WIPE RAGS, ETC.

P. AFTER COMPLETION OF THE WORK, CONSTRUCTION AREA SHALL BE FULLY

VACUUMED WITH HEPA FILTERED VACUUM AND WET MOPPED WITH DISINFECTANT.

CLASS III ICRA REQUIREMENTS INCLUDE:

Q. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS

ROOM SO THEY CAN BE VACUUMED USING A HEPA-FILTERED VACUUM CLEANER

BEFORE LEAVING WORK SITE OR THEY CAN WEAR CLOTH OR PAPER COVERALLS

THAT ARE REMOVED EACH TIME THEY LEAVE THE WORK SITE.

R. ALL PERSONNEL ENTERING THE WORK SITE ARE REQUIRED TO WEAR SHOE

COVERS.

CLASS IV ICRA REQUIREMENTS INCLUDE ALL OF ITEMS A-P ABOVE

PLUS THE FOLLOWING:

CONSTRUCTION ACTIVITY TYPE C:

ACTIVITY GENERATES MODERATE TO HIGH

LEVELS OF DUST, REQUIRES GREATER THAN 1

WORK SHIFT FOR COMPLETION.

IC RISK GROUP:

GROUP 3: MEDIUM / HIGH RISK

GROUP 4: HIGH RISK

ICRA LEGEND

SUGGESTED ICRA BOUNDARY LOCATION - FIELD VERIFY

EXACT LOCATION(S) IN FIELD WITH VA COR PRIOR TO

INSTALLATION.

A* CONSTRUCTION ACCESS

LOCATION - SEE PLAN -

PROVIDE TACKY MATS

BOTH INSIDE AND OUTSIDE

OF BARRIER

O ffi ce of

Fac ilit ie s

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

BUILDING / LOCATION INFORMATION: DRAWING TITLE:

BUILDING NUMBER:

CAMPUS:

ADDRESS:

FLOOR # (IF APPLICABLE):

ROOM # / SUITE DESCRIPTION:

SHEET NUMBER:

ADDITIONAL DRAWING INFORMATION:

SHEET OF

Drawing Prepared By:

ENGINEERING - ACTIVATIONS OFFICE

SPACE COMMITTEE

CAPITAL ASSET MANAGEMENT…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .