36C25623R0109 RFI Responses.docx

DOCX document 33 KB Posted

Attached to
Renovate Interior Space JACC Federal contract opportunity
Solicitation number
520-23-106
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document contains responses to requests for information regarding federal solicitation number 520-23-106 to renovate interior space at a Veterans Affairs medical center. Key details include:

As-built drawings of existing telecommunications and electrical systems were provided. Infection control risk assessments will be required on a case-by-case basis for work above ceilings outside the defined work area. Nurse call devices and cabling affected by demolition will need to be deactivated by the contractor or a subcontractor. The specification sections and table of contents were revised to clarify the scope of work. Each phase must be fully completed before the next phase can begin. Wall guards and handrails will be required continuously at corridor and atrium walls. Some fire sprinklers may need temporary relocation during construction. The contractor will be responsible for testing modified mechanical and plumbing systems. The superintendent can also serve as the site safety officer and quality control manager. All work must occur outside normal operating hours and on weekends to avoid disrupting hospital operations.

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Interior Space JACC, newest first.
File Type Posted
36C25623R0109 0003.pdf PDF
VOL 3 BINDER.pdf PDF
VHA ICRA 2023-1.0_Final Template_0.docx DOCX document
01 00 00 - General Requirements rev2.docx DOCX document
VOL 2 BINDER.pdf PDF
00 01 10 - Table of Contents - Redacted.docx DOCX document
VOL 1 BINDER.pdf PDF
S04 Site Visit Sign in Sheet 520-23-106 8.24.23.pdf PDF
36C25623R0109 0002.pdf PDF
36C25623R0109 0001.pdf PDF
36C25623R0109 EXHIBIT B.docx DOCX document
36C25623R0109 EXHIBIT C.docx DOCX document
WD FL20230203 Mod 1 dtd 01.13.2023.txt TXT text file
Final SOW Renovate interior spaces.pdf PDF
36C25623R0109 EXHIBIT A.docx DOCX document
36C25623R0109 EXHIBIT D.docx DOCX document
Specs 4 14 2023.pdf PDF
P09 520 23 106_JACC Enclosure Project Final Full Set 08_10_2023.pdf PDF
P03 - Brand Name JA JACC CO Signed - R1_Redacted.pdf PDF
36C25623R0109 EXHIBIT E.docx DOCX document
36C25623R0109 EXHIBIT F.docx DOCX document
ICRA Contacting Only.pdf PDF
36C25623R0109 Final.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR

OFFICIAL

USE

ONLY

Source

Selection

Sensitive

Information—See

FAR

2.101

3.104 Project No. 520-23-106 Renovate Interior Space JACC

36C25623R0109

Proposal RFI #1 –
Please provide Telecommunications (or electrical) as-builts to include the existing cable tray pathways, rack elevations in 2A137, 2B157, 2E106, 1A138, 1C194, 2D135, and data

(voice) single line drawings.

All as-builts attached in Volumes 1,2, and 3 attached. See electrical and systems in volume 3.

Proposal RFI #2 –
Sheet A03, ICRA Requirements item N, please confirm work above the ceiling outside the work area is allowed without containment tents providing the instructions stated during the meeting 8-24-23 are explicitly followed
i.e.open, perform work, close immediately, nothing left open or unattended, area kept clean of dust and debris.

ICRA outside the work area will be handled on a case-by-case basis with advising from VA Infection Control. See attached " VHA ICRA 2023-1.0_Final Template_0” This details exact ICRA requirements for each work task and work locations within the clinic. These ICRA requirements can be reduced as the construction activity is reduced.

The patient care activity areas are clarified below for each area of project phasing:

1. High Risk

a. 1st floor Bravo (Primary Care)

b. 2nd floor Lima area (Eye Clinic)

c. 2nd floor India (Vaccine clinic)

d. 1st floor Charlie (Primary Care)

e. 2nd floor Juliet (New Office Space adjacent to 2C167)

f. 2nd floor India (New Consult Space)

g. 1st floor Foxtrot (New APC Closet)

2. Highest Risk

a. 2nd floor Oscar (Surgery Team Room 2D164-2D166)

b. 2nd floor Oscar (Surgery team Room 2F101-2F102)

Proposal RFI #3 -
Demolition describes removing Nurse Call devices and cabling. Are these devices going to be deactivated in the Nurse Call system by the current Nurse Call technicians prior to the demolition phase?

No. Contractor to perform or subcontract deactivation of affected nurse call systems. System OEM is SimplexGrinnell (Johnson Controls).

Can the VA please revise the specifications’ table of contents and subsequent divisions to be specific to the work involved only in this Project? See attached redacted Table of Contents.

Please revise Specification 01 00 00 section 1.3 parts A - Q – it appears to be for a different project. Replace 01 00 00 General Requirements with the attached 01 00 00 General Requirements Rev2

To what extent will Phase 1 have to be completed before we can begin work on Phase 2?

Per specs General Requirements 01-00-00-4 “Each Phase shall be completed in its entirety, for all disciplines, from demolition to final punch-walk and acceptance by the VA, prior to the commencement of the subsequent Phase”

There is a corner guard, hand rail, and wall guard in the finish legend however they are not shown or called out in any of the notes. Will these be required? Please provide locations.

Yes, they will be required. Where existing hand rails and wall guards are made discontinuous by construction, these shall be made continuous around the envelope of the newly constructed spaces. This includes all corridor walls and atrium walls. Wall guards to be place on all outside corners.

Will temporary fire sprinklers have to be provided?

No.

Some fire sprinklers will be required to be temporarily relocated above the removed ceiling fire barriers during construction in accordance with SOW section “Fire protection during construction”, General Requirements Specs 01-00-00, and fire protection drawing sets.

What will the contractor be responsible for during commissioning?

No commissioning is required for this project. Specs table of contents has been amended to clarify. Contractor is responsible for T&B and testing of modified systems such as tube system in accordance with SOW. To confirm 21-08-00 Commissioning of Fire Suppression Systems.

Can the Superintendent also be the Prime Contractor’s Commissioning Manager during commissioning?

No commissioning is required by contract. Specs table of contents has been amended to clarify.

Can the Superintendent also be the site quality control manager?

Yes

Is a full time Site Safety Health Officer required for the full duration of the project?

Can the Superintendent also be the site safety health officer?

As is typical for most VA projects can the CQC plan be implemented by the onsite superintendent and administrated by the PM without additional staff (other than what is required for commissioning) as call for in 01 45 00.?

Will any of this work have to be performed after hours or weekends Per drawings “All demolition and construction work will take place outside of normal hospital operating hours and on weekends”