Ft Bragg Installation Design Guide (Condensed) Aug 2026.pdf

PDF 2 MB Posted

Attached to
Contractor-owned, Contractor-operated (COCO) bulk retail services at two locations on Fort Bragg, NC.
Solicitation number
SPE60326R0526
Issued by

About this file

This is an Installation Design Guide (IDG) for Contractor-Owned, Contractor-Operated (COCO) fuel facilities at Fort Bragg, NC, specifically condensed for DLA Energy-funded projects with a 29-year facility lifespan. The guide establishes design and construction policies for contractor-owned fuel storage and distribution infrastructure that will integrate with existing government utilities and systems while maintaining visual compatibility with surrounding structures.

Design requirements specify that commercial design specifications (NFPA 30 and 30A) apply rather than UFC military construction standards, with contractor responsibility for structural integrity, environmental compliance, and all North Carolina state permits. The guide mandates a four-stage government review process: 35% concept review by DLA Energy (facility footprint, utilities, setbacks, traffic flow), 65% intermediate review by DPW and state agencies (utility and environmental integration), 95% Fire Marshall review (emergency systems), and 100% final permit verification by DPW. Key operational standards address traffic control and workzone safety per NCDOT specifications, storm drainage systems designed for 10-year storm events in non-airfield areas with sealed reinforced concrete piping and precast/cast-in-place concrete manholes, fire suppression systems requiring licensed Fire Protection Engineer design and seismic Site Class C compliance, and exterior finishes using specified Federal Standard colors (primarily FS-24084 Dark Bronze, FS-20059 Mission Brown, FS-23617 Beige). Additional requirements include 20% of materials sourced within 500 miles, all construction and demolition waste directed to off-installation certified landfills with monthly waste reporting, ADA-compliant parking and accessibility standards, sealed concrete pavement minimum 7 inches thick for roadways per UFC 3-250-01, and comprehensive landscape establishment including turf seeding, irrigation systems, and plant maintenance for 365-day establishment periods. The contractor bears full responsibility for design coordination, utility protection, environmental permitting, quality assurance, and project closeout compliance.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONDENSED INSTALLATION DESIGN GUIDE

For

DLA ENERGY-FUNDED

CONTRACTOR-OWNED, CONTRACTOR-OPERATED (COCO)

FUEL FACILITIES

AT

FORT BRAGG, NC

1. General: The information in this guide is comprised of a collection of Fort Bragg design and construction policies consolidated by DLA Energy to serve as the Installation Design Guide (IDG) until a more formal and presentable version is developed. It contains information to assist offerors in developing design and cost proposals for Contractor-owned, Contractor-operated fuel facility services at Fort Bragg, NC. Not all guidance in the IDG will apply to these facilities as described in the paragraph below.

2. IDG Applicability and Limitations: Most of the IDG and Governmental standards found in Unified Facility Criteria (UFC) directives do not apply to the structural design of these facilities due to the temporary (29 years) nature of these contractor-owned, contractor-maintained, contractor-operated fuel facilities, but this paragraph will help differentiate.

A. Design: This is neither Military Construction (MILCON), nor government-owned or government-maintained infrastructure; therefore, the UFC structural design specifications do not apply unless specifically included in the contract. Commercial Design specifications will be used for the fuel facility (such as NFPA 30 and 30A) and associated infrastructure, except for those infrastructure components or systems that must integrate, connect, or interface with base infrastructure, utilities, systems, or equipment. That infrastructure or component will be compatible, allowing tie-in and function with the existing government infrastructure as necessary. Structural exterior appearances and landscaping will match the surrounding government structures in accordance with the IDG to blend visually.

B. Oversite: Various Permitting Offices will have regulatory oversite authority as required for their permit.

Department of Public Works (DPW) will provide construction permits and associated project oversite to ensure compliance with regulatory and permit directives, Installation regulatory/policy, and contract requirements.

C. Review: Elements of government review/approval are reduced but not eliminated. Plans will be provided to the DPW as required for permits, utility integration, stormwater, erosion control, and project oversite.

Government review and approval of the Contractor’s design submittals (35%, 65%, 95%, 100%) is solely for verification of compliance with the Ground Lease, Base Master Plan, Safety, and Environmental standards.

Government approval does not relieve the Contractor of its sole responsibility for design accuracy, structural/mechanical integrity, environmental compliance, or the procurement of mandatory State of North Carolina permits.

35% Concept: – DLA Energy contract requirements, facility footprint, site obstructions/restrictions, setback distances, traffic flow, utility connection concept; performed by DLA Energy during proposal evaluation prior to award.

65% Intermediate Review: – Utility and Environmental: locks in how the contractor's private facility will interact with the government's infrastructure when the base's sanitary sewer, water, network, and power grids connect to the facility. Stormwater design, retention basins and OWS appropriate size. Connection for street access. This review is done by DPW and/or State agencies after post-award when coordinating utility hookups and acquiring permits.

95% Pre-final Review: Fire Marshall – Review of emergency shut-off and notification systems and connectivity to base emergency services.

100% Final: Permit check – DPW verifies all permits are secured and issues Construction Authorization.

All reviews are being expedited due to the time limitations in this project. The Contractor must notify the Contracting Officer of any delay.

3. Sustainability and Maintainability: Materials and products shall be provided in accordance with ASHRAE 90.1, ASHRAE 189.1. Select materials and products that require less maintenance and reduce life cycle costs, require minimal energy to extract and process into the finished building components, that reduce energy consumption for the building, that can be cleaned and maintained easily with non-toxic or low-VOC substances, that resist the growth of biological contaminants, that are readily recyclable and maximize recycled content, that can be reused after serving the original purpose, and that reduce water consumption. Twenty percent of the provided products and materials shall be produced within a 500-mile radius of the project.

4. Solid Waste Disposal: The Fort Bragg Lamont Construction and Demolition (C&D) Landfill is closed and will not accept any C&D Waste or Asbestos Waste. The Municipal Solid Waste (MSW) Transfer Station at the Lamont Landfill Facility is closed and will not accept MSW at the facility.

• All contractors shall use a State Certified C&D Landfill or Subtitle “D” Landfill located off the Installation for disposal of C&D waste, asbestos waste and MSW.

• The contractor is responsible for maintaining data on all waste disposed (C&D and MSW) and all materials recycled off Fort Bragg.

• The Department of the Army (DA) and the North Carolina Department of Environmental Quality (NC DEQ) require monthly and annual reporting of all materials (waste and recyclables) managed by Fort Bragg.

• The Fort Bragg Environmental Compliance Branch, Solid Waste/Recycling Office is responsible for compiling data into monthly Directorate Reports to be consolidated into reports for the DA and the NC DEQ.

• A provided form from the Solid Waste/Recycling Office or a contractor form shall be filled out for all wastes or recyclables that are hauled off the installation with the type of waste or recycled material, the weight of the waste/material (tons or pounds) and the certified facility the waste or recyclables were delivered. This information is required to be sent to the Fort Bragg Solid Waste/Recycling Office by the second Friday of each month. Email to Shawn Hardy at shawn.c.hardy.civ@army.mil

A. Policy Update: Effective June 1, 2026, the Lamont Landfill Recycling Area will no longer accept concrete, brick, or block for any contracts awarded after June 1, 2026.

B. Concrete Recycling: Contractors must transport all recyclable concrete, brick, and block to an off-installation recycling facility. The contractor is responsible for coordinating with the facility to ensure all specific acceptance requirements are met. Additionally, all materials must be tested and certified free of asbestos and lead-based paint (LBP) prior to delivery.

C. Disposal Requirements: Any materials containing asbestos or LBP must be disposed of by the contractor at a State-certified C&D landfill or a Subtitle D landfill located off the installation.

D. The Lamont Landfill Recycling Area will accept recyclable items.

• Trees, Limbs: Shall be cut to 6 feet or less in length. No stumps will be accepted.

• If the tree has a large diameter (for example 3 ft. Dia.) it shall be cut to lengths of 3 feet or less.

• Shall be minimal amount of dirt in load. Will accept ground wood chips. No trash in load

• Pallets: Serviceable and non-serviceable pallets.

• Scrap Steel: No items requiring demilitarized accepted. No items with liquids in them.

• Scrap Aluminum: No items requiring demilitarized accepted. No items with liquids in them.

• Cardboard to be recycled: Cardboard can be taken to the Fort Bragg Recycling Center at BLDG 3-

1240, Rock Merritt Ave and Reilly Road or to the Lamont Landfill Cardboard Dumpster. Shall be clean of trash, plastics, Styrofoam, wood, metal, etc.

• Wire: Small amounts can be brought to the Fort Bragg Recycling Center at BLDG 3-1240. Large amounts of wire can be taken to Lamont Landfill Wire Pile.

• Copper: Small amounts can be brought to the Fort Bragg Recycling Center at BLDG 3-1240. Large amounts of wire can be taken to Lamont Landfill Copper Pile

E. State Law and Fort Bragg regulations require covering of loads of waste or recyclables to prevent litter.

F. All waste or recyclable material loads are subject to have their contents inspected while present on Fort Bragg.

Questions for Lamont Landfill can be answered by Landfill Manager Dan Messier at daniel.j.messier.civ@army.mil

(910)396-6873 or (910)309-7741.

Contact the Solid Waste/Recycling Program at 908-5881 or 396-2295 for additional guidance.

Note: All recyclable materials generated from a construction or demolition job are property of the government unless the contract specifies the contractor can retain the materials. Recyclable materials include items such as HVAC units (Freon removed), air handlers, piping, metal beams, motors, valves, copper wire, etc. These items shall be transported to the DPW Recycling Center (Butner Rd. and Rock Merritt Ave) or the Recycling Area at the Lamont Landfill Facility.

5. Enclosures:

Enclosure 1 – Traffic Control and Work Zone Safety Enclosure 2 – Storm Drainage Utilities Enclosure 3 – Fire Suppression Enclosure 4 – Finishes Enclosure 5 – Clearing and Grubbing Enclosure 6 – Seeding Specifications Enclosure 7 – Soil Stabilization Enclosure 8 – Landscape Establishment

Enclosure 9 – Sodding Enclosure 10 – Concrete, Sidewalks, and Gutters Enclosure 11 – Plumbing Enclosure 12 – Electrical Enclosure 13 – Engine Generators Enclosure 14 – Telecommunications Enclosure 15 – Paintings and Coating Enclosure 16 – Signage

ENCLOSURE 1

FORT BRAGG TRAFFIC CONTROL AND WORKZONE SAFETY POLICY

The Contractor shall maintain traffic during construction and provide, install, and maintain all traffic control devices in accordance with these project guidelines, the Project Special Provisions, North Carolina Department of Transportation Standard Drawings, the current edition of NCDOT Standard Specifications for Roads and Structures, and the current edition of the Manual of Uniform Traffic Control Devices (MUTCD).

The Contractor shall utilize complete and proper traffic controls and traffic control devices during all operations. All traffic control and traffic control devices required for any operation shall be functional and in place prior to the commencement of that operation. Signs for temporary operations shall be removed during periods of inactivity. The Contractor is required to leave the project in a manner that will be safe to the traveling public and which will not impede motorists.

Traffic movements through lane closures on roads with two-way traffic shall be controlled by flaggers stationed at each end of the work zone. In situations where sight distance is limited, the Contractor shall provide additional means of controlling traffic, including, but not limited to, two-way radios, pilot vehicles, or additional flaggers. Flaggers shall be competent personnel, adequately trained in flagging procedures, and furnished with proper safety devices and equipment, including, but not limited to, safety vests and stop/slow paddles.

All personnel when working in traffic areas or areas in close proximity to traffic shall wear an approved safety vest, or shirt or jacket which meets the color requirements of the Manuel of Uniform Traffic Control Devices (MUTCD).

The Contractor shall comply with all applicable Federal, State, and local laws, ordinances, and regulations governing safety, health, and sanitation, and shall provide all safeguards, safety devices, and protective equipment, and shall take any other needed actions, on his own responsibility that are reasonably necessary to protect the life and health of employees on the job and the safety of the public, and to protect property in connection with the performance of the work covered by the contract.

Work on any roadway, parking lot or exposed traffic movement area may require a traffic control plan. The plan shall incorporate the applicable MUTCD and NCDOT standards and sealed by a professional Traffic Engineer licensed in the state of North Carolina. A deviation from this directive, requiring a sealed traffic control plan can be made based on emergency, safety and roadway conditions by the Fort Bragg - DPW Civil and or Traffic Engineer.

The Fort Bragg Civil and or Traffic Engineers at DPW require a ten day (working days) notice to begin work for security and inter-agency approvals. Exceptions to the schedule may be granted for emergency situations. An approved traffic control plan by DPW but not submitted for an approved work start date may be considered null and void after sixty calendar days of the plan approval date if no action is taken to initiate the work.

The Contractor shall provide written notice to the Fort Bragg Civil and or Traffic Engineer at the start and projected completion date to this work. Any deviation for this schedule shall be approved by the Fort Bragg Civil and or Traffic Engineer.

Open cuts on asphalt roadways will require full depth patching with applicable base, full depth patching with Asphalt Concrete Surface Course type SF9.5A in 2-inch lifts if applicable, the same day. The work shall also comply with NCDOT Standard roadway repair and patching policies and techniques.

No material storage shall be allowed along the shoulders of the roadway, parking lots or areas with active traffic during non-working hours. Equipment shall be parked away from active traffic areas and shall be properly barricaded to prevent equipment obstruction within the clear recovery area. The Contractor shall comply with all OSHA requirements and provide a competent person on site to supervise all phases of this type of work.

The Contractor shall comply with all federal, state, and Fort Bragg environmental regulations and shall obtain all necessary federal, state, and Fort Bragg environmental permits, including but not limited to, those related to sediment control, storm water, wetland, streams, endangered species, and historical sites.

The Fort Bragg Directorate of Public Works shall be notified prior to beginning work that affects permanent traffic control devices. The Contractor shall be responsible to relocate, modify, repair, or replace traffic signals and component equipment, traffic signs and pavement markings in compliance with NCDOT current equipment and standards where applicable. The Contractor may be required to install temporary traffic signals, pavement markings, raised pavement markers and signing to accomplish the work. These tasks shall be noted in the approved traffic control plan.

It shall be the responsibility of the Contractor to determine the location of the other utilities within the work zone area.

This shall also include the location of the water, sewer, and drainage systems. The Contractor shall be responsible for notifying other utility owners and providing protection and safeguards to prevent damage or interruptions to existing facilities and to maintain accessibility to the existing utilities. The Contractor shall be responsible for the repair or replacement of these utilities because of his work. All pipe repair work shall be in compliance with the NCDOT Standard Drawings and specifications, current edition.

Excavated area adjacent to pavement or active traffic areas having more than a 2-inch drop shall be shaped up at a 6:1 or flatter slope and designated by appropriate delineation during periods of inactivity, including, but not limited to, night and weekend hours.

Pre-cast concrete manholes, catch basins, or drainage structures shall be the type pre-approved by NCDOT. Manhole rings and covers, valve covers and storm drainage grates and frames shall be of the traffic bearing type approved by

NCDOT.

All work performed under this policy shall be contracted to an NCDOT licensed or certified contractor (Bonded in the state of North Carolina)

6.3.4 (Parking)

All parking lot designs shall be in compliance with all ADA (American Disabilities ACT) policies. The parking design can vary from perpendicular to angular depending on the geometrics. The project shall specify the use of Thermoplastic (Extruded material) or heated in place Thermoplastic material. Products used shall be in compliance with NCDOT standard specifications and on the NCDOT approved Qualified Product List (QPL) for asphalt surfaces. Polyurea material shall be used on concrete surfaces per NCDOT specification and on the approved QPL (Qualified Products List). A Pavement marking contractor assigned this type work shall be certified by NCDOT to do this type work.

6.3.4.1 (ADA Accessible Parking Space: Standard Details)

All parking lots shall be accessible to persons with disabilities in accordance with requirements of the ADA Accessibility Guidelines (ADAAG) and the Uniform Accessibility Standards (UFAS).

ADA Accessible Parking Space Specifications

1. Fort Bragg Standard shall be used:

a. Car Parking Space is minimum 9’ wide with a minimum 9’ wide access aisle.

b. Van parking Space is minimum 9’ wide with a minimum 9’ wide access aisle.

2. The International Symbol for Accessibility (ISA) shall be used to indicate the parking space

3. Parking spaces shall be marked to define the width and shall have an adjacent access aisle.

Access Aisle Specifications

1. Use of full parking space for access aisle minimizes cost of restriping and increases long-term flexibility.

2. Access aisle shall adjoin an accessible route.

3. Two parking spaces shall be permitted to share a common access aisle.

4. Access aisle shall be a minimum 9’ wide.

5. Access aisle shall extend for the entire length of the parking space(s) they serve.

6. Access aisle shall be marked to discourage parking in them.

7. For van accessible parking: access aisle shall be located on the passenger side of van.

Minimum Number of Accessible Parking Spaces: One space for a facility with less than 25 spaces.

6.3.4.2 (ADA Accessible Curb Ramp Details)

Curb Ramps

1. Provides an accessible route that people with disabilities can use to safely transition from a roadway to a curbed sidewalk and vice versa.

2. Maximum ramp slope: 8.33% (12:1)

3. Cross slope: 2.00%

4. Curb ramps require a (4’-0”) minimum landing with a maximum cross slope and longitudinal slope of 2% where pedestrians may be turning.

5. Slope should drain to curb

Sidewalks

1. Sidewalks should be a minimum width of 5’

2. Sidewalks should be set back a minimum 6’ from the adjacent road

6.3.4.3 (ADA Accessible Parking Space Sign Details)

ADA Accessible Sign Guidance

1. Accessible spaces shall be identified by signs using the International Symbol of Accessibility (ISA).

2. The sign shall be installed at the front of the parking space.

3. The sign must also state “van accessible” for such spaces. (This designation is informative and does not restrict use of such spaces to van users only).

4. Sign shall include maximum fine amount of $250, with the statute number (GS 20-37.6) located on the sign.

5. The van accessible and fine amount signage can be included on the main designation sign or provided on a separate sign.

ADA Accessible Sign Placement Guidance

1. The bottom of the sign must be placed a minimum 60” above the parking surface so that the entire sign is visible over the hood of the vehicle.

2. Signs can be on posts, or where feasible, on walls or suspended from ceilings (an 80” minimum headroom clearance is required at signs suspended above circulation paths.

6.3.9 (Traffic Signals, Roadway Marking and Signage)

6.3.9.1 (Traffic Signals)

All traffic signal designs for Fort Bragg, North Carolina shall be prepared by a Professional Traffic Engineer (PE) licensed and bonded to work in the State of North Carolina, to perform this type of work. The signal design engineering firm shall have the capability to conduct immediate –on call inspections (at the government’s request) during the different installation phases performed by the traffic signal installation contractor. The signal design engineer shall maintain and inspection performance log for the government to require corrective actions by the signal installation contractor if applicable.

All traffic signal work (New and Maintenance) shall be performed by an approved traffic signal contractor by NCDOT and work installed and inspected by a certified IMSA Level 2 Traffic Signal Technician in the state of North Carolina.

These technicians shall be bonded either individually or thru their company to certify compliant work performance associated with all policies and standards. The contractor assumes responsibility for the operation of the traffic signal at the point when he engages any portion of work that affects the function of the signal equipment and exposed traffic.

The contractor shall notify the responsible governmental agent of his intent to begin work. The contractor is responsible to respond to emergency or maintenance calls within a two-hour call-response period during construction and or the warranty period. Unless dictated by the DPW Civil or Traffic Engineer all traffic signal work is warranted for a period of one year beyond the final inspection approval date.

All signal equipment to be used shall comply with the NCDOT Project Special Provisions (version 06.6) and Intelligent Transportation Systems. The plans shall specify that all equipment used shall be listed on the current NCDOT approved QPL (Qualified Products List). The plans shall specify the use of a 2070L type signal controller listed on the NCDOT QPL or current approved type. No deviation from this policy shall occur unless approved by the Fort Bragg Civil or Traffic Engineer. The design shall comply with all policies and guidelines relative to the design listed in the following manuals:

1. Manual of Uniform Traffic Control (MUTCD)

2. FHWA – Railroad- Highway Grade Crossing Handbook and the Unified Facilities Criteria (UFC) Railroad

Track Maintenance & Safety Standards.

3. North Carolina Department of Transportation (NCDOT) Signals and Geometric Design Manual.

4. North Carolina Department of Transportation (NCDOT) Roadway Standard Drawings (The ITE and ASTM standards).

5. North Carolina Department of Transportation (NCDOT)

Roadway Design Manual Section 1 and 2.

6. North Carolina Department of Transportation (NCDOT)

Highway Guidelines Consultants.

7. Signal and Geometrics Section Design Manual 11.

8. Traffic Signal Operations and Maintenance Practices Report.

9. Project Special Provisions for Traffic Signals (version 06.6).

10. National Electric Safety Code

The Fort Bragg Installation Civil Engineer shall have the final approval of the design.

6.3.9.2 (Pavement Marking Materials)

All pavement marking shall be designed in compliance with MUTCD and the current NCDOT standard drawing s and specifications. The project shall specific Thermoplastic (Extruded) material or heated in place Thermoplastic material in compliance with NCDOT standard specifications. The product must be on the NCDOT QPL list for asphalt surface courses. Polyurea material shall be used on concrete bridge or roadways per NCDOT standard specifications and on the NCDOT approved QPL.

NCDOT, QPL, Temporary and Permanent pavement marking tape may be specified by the Fort Bragg Engineer on roadway and or parking lot projects.

6.3.9.3 (Pavement Marking Time Limitations)

The contractor shall comply with the NCDOT TIME LIMITIATIONS for placement and replacement of pavement markings.

6.3.9.4 (Pavement Markers)

All pavement markers shall be in conformance with MUTCD and the current NCDOT standard drawings and specifications, unless otherwise changed by the Installation Civil Engineer and or Traffic Engineer. The project shall specify the use of “snow plowable” pavement markers of a type approved on the NCDOT QPL.

The Fort Bragg Installation Civil Engineer and or Traffic Engineer shall have the final approval of the design. All Pavement marking-markers type work shall have a contractor certified and licensed by the NCDOT to perform this type work.

6.3.9.5 (Installation Requirements)

The installation of this material and associated work shall comply with either the MUTCD or NCDOT design policies or practices. All work shall be contracted to a licensed or certified NCDOT contractor (bonded in the state of North Carolina). If applicable, the contractor may be required to provide a traffic control plan signed and sealed by a licensed Professional Traffic Engineer in the State of North Carolina at the discretion of the Fort Bragg Installation Civil Engineer shall have the final approval of the design.

6.3.9.6 (Signing)

All roadway signing used on Fort Bragg shall comply with MUTCD and current NCDOT standards drawings and specifications. All material must be on the NCDOT approved QPL (Qualified Products List). All work shall be contracted to a licensed or certified NCDOT contractor (bonded in the state of North Carolina)

1. Regulatory, Warning and Guide Signs: All regulatory and guide signs shall be fabricated with Type III “high intensity” sheeting. All warning signs, except for school zones, bicycle, pedestrian, and highway-rail grade crossing warning signs shall be fabricated with Type III “high intensity” sheeting. The color of the sheeting shall be as specified in the MUTCD.

2. School Zone, Bicycle Pedestrian and Highway Rail Grade Crossing Warning Signs: It is standard practice of

NCDOT to install and maintain all school zone, bicycle, pedestrian, and highway-rail grade crossing warning signs using Type IX “high intensity” sheeting.

All school zones, bicycle, and pedestrian warning signs shall be “high intensity” fluorescent yellow-green. All highway-rail crossing advance warning signs shall be “high intensity” fluorescent yellow.

3. Temporary Traffic Control Work Zone Warning Signs: It is standard practice of the NCDOT, and for all agencies that work by contract for the NCDOT, to install and maintain all traffic control work zone warning signs both stationary and portable work zones signs using TYPE VII, VIII, or IX “high intensity” fluorescent orange sheeting.

A portable roll up sign (without adhesive backing) shall have the retro-reflective value of Type VII, VIII, or IX “high intensity” fluorescent orange sheeting. Again, the Fort Bragg Civil and or Traffic Engineer shall require a traffic control plan prepared and sealed by a Professional Traffic Engineer licensed in the State of North Carolina to perform this design.

The Fort Bragg Installation Civil Engineer and or Traffic Engineer shall have the final approval of the design.

6.3.9.6.1 (Ground Mounted Sign Installation)

All ground mounted signposts shall be driven to a 95% compaction rate, or 4’, whichever is greater.

The bottom of the sign shall be a minimum of 5’ above the ground and minimum 7’ from the edge of roadway pavement.

All signposts and backs of signs shall be painted federal standard color 595B dark brown 20059. All signs shall be in accordance with MUTCD standards and shall be high intensity grade B sheeting or greater, approved by NCDOT and listed on NCDOT QPL.

Typical Sign Layout

6.3.9.6.2 (Facility Sign Installation)

All facility signs shall be Type B, as per Fort Bragg Installation Design Guide, Chapter 10, Section 10.5. Sign shall be 36” x 60” brown metal panel (Fed STD 595B - #20059) with white, 3/4” inch border and white reflective upper- and lower-case letters. Mount on two pressure treated 4” x 4” wooden posts.

All ground mounted facility signposts shall be driven to a 95% compaction rate, or 4’, whichever is greater.

Fort Bragg Typical Type B Facility Sign Layout

6.3.9.6.3 (Ground Mounted Sign Supports)

The engineer or contract surveyor shall establish the proper offset, longitudinal location; foundation elevation and S-dimension of each ground mounted sign supports.

Vegetation shall be cleared in front of signs where necessary to achieve proper sight distance to the sign. The sight distance area includes the triangular region of land extending from the edge of the travel lane, 800 feet in advance of the sign to 4 feet beyond the furthest edge of the sign from the travel lane.

Breakaway Sign Supports

Breakaway signs shall be punched, cut or welded before galvanizing and each component part shall be galvanized in accordance with ASTM A123 before assembly.

Breakaway sign supports shall be provided that are uniformly straight to within 1/8-inch tolerance for pieces less than 20 feet in length and 1/4-inch tolerance for pieces over 20 feet in length.

The hinge point shall be bolted in the breakaway sign supports to ensure true alignment of the 2 sections.

Wood Sign Supports

Use wood posts that conform to Sections 1082-2 and 1082-3 of the NCDOT Standard Specifications for Roads and Structures.

All wood supports larger than 4 inches x 4 inches that have not been drilled shall be mounted behind a guardrail.

For wood posts, drill the bottom hole 4” above the ground and the top hole 18” above the ground. Holes shall be drilled perpendicular to the direction of travel. Dual supports must be a minimum of 7’ apart.

Galvanized steel backing plates and mounting bolts shall be used. Stiffeners shall be adjusted to avoid conflicts with supports. Holes shall be drilled in the center of the supports.

Typical Breakaway Sign Support

Hinge Connection

6.3.9.6.4 (Bollard Installation)

All bollards used on Fort Bragg shall comply with current NCDOT standard drawings and specifications. All material must be on the NCDOT approved QPL (Qualified Products List). All work shall be contracted to a licensed or certified NCDOT contractor (bonded in the state of North Carolina).

All bollards used on Fort Bragg shall be concrete filled and painted Federal standard dark brown (Fed STD 595B - #20059).

Top of bollard shall be precast or cast in place, not hand formed.

At the grade line, an expansion joint shall be provided when placed in rigid pavement.

Architectural drawings shall be referred to for location of bollards at doors and building corners.

Typical Bollard to Typical Bollard Footing Connection

6.3.9.7 (Asphalt)

Asphalt will not be used in this facility.

6.3.9.8 (Curb)

Curb shall be installed to standard per NCDOT current Standard Specification for Roads and Structures. Fort Bragg will use the 2’-6” curb design as shown in Figure 4.

All material must be on the NCDOT approved QPL (Qualified Products List). All work shall be contracted to a licensed or certified NCDOT contractor (bonded in the state of North Carolina).

Figure 4

6.3.9.9 (Minimum Specifications for Concrete Pavement for Roadways and Parking Areas)

When placing concrete pavement for roadways, refer the current, Division 7 of the NCDOT Construction Manual for Concrete Pavements, NCDOT Design Guide for Concrete Local Roads & Streets, NCDOT Roadway Design Manual, NCDOT Standard Specifications for Roads and Structures, UFC 3-250-01, 2016 and UFC 3-250-04. Use only materials on the NCDOT Qualified Product List (QPL) and all concrete plants used shall conform to section 700-2 of the NCDOT Construction Manual.

Rigid pavements for roads must be plain (non-reinforced) concrete of minimum 7” in thickness, except for those conditions listed in UFC 3-250-01, 2016 Chapter 14 or unless otherwise approved by the Government Civil Engineer.

Plain concrete pavements also include Roller-compacted concrete pavements (RCCP). In accordance to the UFC, non-reinforced pavement design requires a minimum of 0.05 percent steel in odd-shaped slabs and mismatched joints. Plain concrete pavement design must be in accordance to UFC 3-250-01, 2016 Chapter 13.

Appendix F of UFC 3-250-01, 2016 should be used to determine the thickness of concrete for primary roads, secondary roads and vehicle parking areas, based on the minimum gross vehicle weight. For minimum concrete thickness, refer to Figure F-12 of UFC 3-250-01, 2016 for primary roads and refer to Figure F-15 of UFC 3-250-01, 2016 for secondary Roads and parking areas. If the design includes vehicles not covered in Appendix F, Pavement-Transportation Computer Assisted Structural Engineering (PCASE) must be used. For areas used for aircraft loading, higher thickness may be used.

Soil classification for rigid pavement design should be in accordance to Chapter 10 of UFC 3-250-01, 2016.

The Technician at the concrete batching plant or central mixing plant is responsible for ensuring that all concrete materials comply with the Specifications, for their proper handling, and for ensuring that the materials are weighed into batches of the proper size. The Technician is also responsible for performing tests on cement (for air content) and making the test beams used for determining the compressive strength of the concrete. Compliance specifications are in accordance to section 700-2 of the Construction Manual.

The Plant (Batch) and Roadway Technician, should accomplish as a minimum, concrete sampling and testing indicated by the NCDOT Minimum Sampling Guide. The Plant (Batch) Technician is required to keep records pertaining to materials received, daily operations, and test results of materials tested.

The Standard Specifications requires the Contractor to run moisture tests on the aggregates each morning before paving operations begin, with a minimum of 2 tests per day, and as often thereafter as necessary to control the consistency of the concrete.

Specifications used by the Contractor for equipment or methods which will produce acceptable work require inspection and approval by the Engineer prior to the beginning of work. The Engineer should contact the Pavement Construction Section of the Construction Unit to request assistance prior to this inspection and approval.

The Contractor is required to submit a Process Control Plan for approval before placing concrete pavement and is typically submitted 3-6 months before the paving operations are scheduled to begin.

In cold weather, the Contractor must protect the concrete from freezing and maintain curing conditions to ensure adequate strength development. When paving in hot weather, concrete must be placed in a timely manner and curing applied as soon as possible. The pavement is to be protected during a rainstorm and the surface finish restored after a rainstorm and fully recorded in the project diary.

All work shall be contracted to a licensed or certified NCDOT contractor (bonded in the state of North Carolina).

Standard Typical details are shown below in Figures 1-9, but all pavement details are to be sealed by a Civil Engineer licensed in the state of North Carolina and approved by Fort Bragg Traffic Engineering.

Figure 1: General Concrete Pavement Figure 2: Plain Concrete Pavement Cross-Section (US Army Corps of Engineers) (UFC 3-250-01, 2016 Figure C16-1A)

Figure 3: Reinforced Concrete Pavement Detail

(US Army Corps of Engineers)

7” m in

7”

See Figures 3&5

Figure 4: Reinforced Concrete Pavement Detail with Aggregate and Compacted Subgrade

(US Army Corps of Engineers)

Figure 5: Plain Concrete Slab and Contraction Joint for Plain Concrete Pavements Detail

Figure 6: Portland Cement Concrete Pavement to Existing Asphalt Detail

7” min

Figure 7: Expansion Joints for Concrete Pavements Detail

Figure 8: Typical Layout of Joints at Intersection

(UFC 3-250-01, 2016 Figure C16-2)

Figure 9: Pavement Joint Detal Example (NCDOT Design for Concrete Local Roads & Streets – Figure 5)

ENCLOSURE 2

FORT BRAGG STORM DRAINAGE UTILITIES

Verify capacity of existing infrastructure, and whether it is sized sufficiently to handle new construction.

Include provisions to maintain utilities when executing new work. Think about constructability and coordination of demo with installation of new. Goal is not to leave an occupant/customer without service (gas, water, heat, sewer, etc.).

Trenching through roadways shall be avoided to the maximum extent possible. Whenever possible utilities shall be pressure-pumped below roadways.

Include in contract requirements stating that the contractor is responsible for IMMEDIATE repair of existing project site utility lines broken during construction. Repairs shall be made to the satisfaction of the appropriate government entity.

OMA projects shall include in the contract phone numbers for each utility that contractor is to use in case of an emergency.

Materials Standard for Strom Water Piping and Manholes Utilities

Purpose: To establish the minimum material requirements for piping and manholes in cantonment and training areas to ensure durability, safety, and environmental protection.

Scope: This standard applies to all storm water piping and manhole installations in cantonment and training areas.

Piping Materials

• Cantonment Areas: Sealed reinforced concrete piping shall be used for all piping installations in cantonment areas. Sealed concrete piping shall meet the requirements of UFGS-33-40-00 of UFC 3-210-10 [insert relevant standard or specification, e.g. ASTM C76].

• Green Belt and Training Areas: Sealed reinforced concrete piping shall be used for all piping installations in the green belt and training areas due to the presence of controlled burning activities. Sealed concrete piping shall meet the requirements of UFGS-33-40-00 of UFC 3-210-10 [insert relevant standard or specification, e.g.

ASTM C76].

• Airfields: The use of plastic pipe is not approved for use under any type of airfield pavement. Airfield storm water design shall meet UFC 3-201-01 and UFC 3-260-01. [insert relevant standard or specification, e.g.

ASTM C76].

Manhole Materials

• Manhole Construction: All manholes shall be constructed of precast or cast-in-place concrete to minimize storm water leakage and sinkhole formation.

• Precast Reinforced Concrete Manholes: Precast concrete manholes shall meet the requirements of UFGS-33-

40-00 and ASTM C478/C478M [insert relevant standard or specification, e.g. ASTM C913].

• Cast-in-Place Reinforced Concrete Manholes: Cast-in-place reinforced concrete manholes shall meet the requirements of UFGS 03 30 00, UFGS-33-40-00 [insert relevant standard or specification, e.g. ACI 318].

General Requirements

• All piping and manhole materials shall be resistant to corrosion and degradation from environmental factors.

• All joints and connections shall be designed and constructed to prevent leakage and ensure a watertight seal.

• All piping lines installed underground shall be marked with magnetic tape.

• All piping and manhole installations shall be tested and inspected to ensure compliance with this standard and relevant regulations.

Variance Availability

• The Director of Public Works (DPW) or designated representative may grant variances to this standard on a case-by-case basis, subject to review and approval.

• Variances may be considered for exceptional circumstances, such as:

o Unforeseen site conditions that render compliance with this standard impractical or impossible.

o The use of alternative materials or designs that provide equivalent or superior performance to those specified in this standard.

o Emergency repairs or replacements that require immediate action.

• Requests for variances shall be submitted in writing to the DPW representative, and shall include:

o A detailed description of the proposed variance and the reasons for requesting it.

o Supporting documentation, such as engineering calculations, material specifications, and test data.

o A plan for ensuring compliance with relevant regulations and standards.

• The DPW representative shall review and respond to variance requests in a timely manner and may require additional information or clarification as needed.

References: UFC 3-201-01, UFGS-33-40-00, UFC 3-260-01, UFGS 03 30 00, and UFC 3-210-10

Policy

It is the policy of Fort Liberty that storm drainage systems in non-airfield areas convey the 10-yr. storm event, storm drainage systems in airfield areas convey the 5-yr. storm event, and that post-construction peak runoff rates do not exceed pre-construction peak runoff rates in new construction areas. Pre-construction rates are defined herein as the peak rate of runoff that would be produced by the design storm events from the area prior to the currently proposed construction.

No deviation from or waiver of this policy will be allowed without approval of DPW Engineering Design Branch and Environmental Storm Water Program Manager.

DESIGN CRITERIA:

The following standards are site specific for Fort Liberty and are designed to work in conjunction with all UFC and Army Technical Manuals.

Hydrology Fort Liberty has selected the NRCS Unit Hydrograph Method or NRCS TR-55 as the standard for calculating runoff.

Basic data required for these methods are: drainage area rainfall frequency, runoff factor, and time of concentration.

Details of the methodology can be found in the SCS National Engineering Handbook, Section 4 and TR-55 NRCS Manual for Urban Hydrology for Small Watersheds. The use of alternate hydrograph methods to compute runoff must be approved by the DPW Engineering Design Branch.

Design Storm Events Storm drainage systems in non-airfield areas shall by designed to convey the 10-yr, 24-hr Type II storm event and storm drainage systems in airfield areas shall be designed to convey the 5-yr, 24-hr Type II storm event. In depth discussion of these criteria can be found in: Paragraph 3 Section b of TM 5-820-1, and Chapter 2 Section 2-2 of TM 5- 820-4. Pre- construction and post-construction peak runoff rates shall be evaluated for the 5-yr, 10-yr, and 100-yr storm events to verify that construction does not increase peak runoff rates. The following table includes the rainfall data that shall be used to determine storm drainage system capacities and peak runoff rates:

Precipitation Frequency Estimates (inches)

ARI*

(years) min min min min min min hr hr hr hr

2 0.51 0.81 1.03 1.42 1.78 2.10 2.23 2.66 3.14 3.70 5 0.59 0.95 1.21 1.72 2.20 2.63 2.80 3.35 3.97 4.68 10 0.65 1.05 1.33 1.93 2.52 3.03 3.26 3.90 4.65 5.45 100 0,83 1.33 1.68 2.57 3.54 4.41 4.90 5.92 7.20 8.24

*These precipitation frequency estimates are based on frequency analysis of partial duration series. ARI is the Average Recurrence Interval. NOAA Atlas 14, Volume 2, Version 3.

Complete rainfall records can be found at https://hdsc.nws.noaa.gov/ https://hdsc.nws.noaa.gov/

Construction Site Run-off.

All projects with land disturbing activity on Fort Liberty, regardless of size requires an Erosion Control Plan (ECP). All ECP’s must be submitted to the DPW Water Management Section (WMS) for review and approval prior to beginning the construction activity. Construction projects can be halted if an ECP is not approved for the site by the WMS or if the construction site does not comply with the approved ECP. Projects greater than one acre require an Erosion Control Permit. Erosion and sediment control measures must meet minimum design criteria as established by NCDEQ Division of Energy, Mineral and Land Resources (DEMLR). All required erosion and sediment control approvals/permits must be obtained from the appropriate review authority. Approved plans must be Stamped and signed by WMS. After approval by WMS, the plan must be submitted to Fayetteville Regional Office of DEMLR for approval. Upon approval, a Certificate of Approval is issued and must be kept on site along with the approved stamped plan.

In addition to the ECP permit projects that disturb 1 or more acres are subject to the NPDES General Permit for Construction Activities (NCG0l0000), which is administered by NCDEQ on behalf of the EPA. Upon approval of the ESC plan, Fort Liberty DPW WMS will submit a Notice of Intent (e-NOI) to obtain a Certificate of Coverage (COC).

A COC must be obtained prior to commencement of land disturbing activities.

Post-Construction Stormwater Management.

Fort Liberty Directorate of Public Works will administer this program through the Environmental Division, Water Management Section. Fort Liberty implements a two-fold Post-Construction Stormwater Management Program in accordance with the NPDES MS4 and Urbanizing Areas: Post-Construction Requirements (15A NCAC 02H .1017) and Section 438 of the Energy Independence Security Act of 2007 (EISA) Public Law 110-140.

The following applies to all projects:

(a) Comply with DAIM-OD MEMORANDUM: 2017 Implementing Guidance, Army Stormwater Management Using Low Impact Development Construction projects at Fort Liberty with a footprint of 5,000 square feet or greater shall use site planning, design, construction, and maintenance strategies for the property to maintain or restore, to the maximum extent technically feasible, the pre-development hydrology of the property with regard to the temperature, rate, volume, and duration of flow. These calculations are for use in designing post-construction, permanent Stormwater Control Measures (SCM’s) to meet the requirements of EISA07.

(b) Comply with 15A NCAC 02H .1017 NPDES MS4 and Urbanizing Areas: Post-Construction Requirements. Any project that disturbs greater than or equal to one acre, including projects less than one acre that are part of a larger common plan of development that discharge into the MS4 is subject to post-construction control requirements of 15A NCAC 02H .1017. All permanent stormwater control measures utilized to meet the requirements must be designed by an appropriately licensed professional (typically a North Carolina licensed Professional Engineer) and must comply with current NCDEQ Minimum Design Criteria (MDC) and methodologies.

(c) Comply with 15A NCAC 02H .1002 Definitions.

(d) Comply with 15A NCAC 02H .1003 Requirements That Apply to All Projects.

(e) Comply with 15A NCAC 02H .1050 MDC for all Stormwater Control Measures.

(f) Comply with UFC 3-210-10 Low Impact Development. This UFC provides technical criteria, technical requirements, and references for the planning and design of applicable DoD projects to comply with stormwater requirements under Section 438 of EISA and the Deputy Under Secretary of Defense DoD policy on implementation of stormwater requirements under EISA section 438.

(g) Comply with UFGS 33-40-00 Stormwater Utilities.

(h) Comply with UFC 3-201-01 Civil Engineering.

(i) Comply with 15A NCAC 02B .0216 Water Supply Watershed III (WS-III) if the project is located within designated water supply watershed.

(j) Comply with 15A NCAC 02B .0216 Water Supply Watershed IV (WS-IV) if the project is located within designated water supply watershed.

(k) Comply with 15A NCAC 02H .1021 High Quality Waters (HQW) in Non-Coastal Counties if the project is located within one mile of and draining to water classified as HQW.

“Comply with means to comply with the most recent version”.

Plans for stormwater mitigation must be submitted and approved by WMS prior to the Contracting Officer issuing a Notice to Proceed (NTP).

REQUIRED STORM DEPTH.

For high density projects designed to achieve runoff treatment, the required storm depth shall be 1 inch. Applicants shall have the option to design projects to achieve "runoff volume match" in lieu of "runoff treatment" as those terms are defined in Rule 15A NCAC 02H .1002.

For projects subject to ESIA requirements the required storm depth shall be of the 95th percentile Storm of 1.8 inches.

FORT LIBERTY APPROVED STORMWATER CONTROL MEASURES (SCM’s) Grassed Bioretention with under drains & Internal Water Storage (IWS) Underground Infiltration with full maintenance access consideration Permeable Surfaces Swales No Sand Filters unless all options have been exhausted!

OPERATION AND MAINTENANCE PLANS.

Stormwater Control Measures (SCM’s) constructed by Fort Liberty that are considered Real Property Assets of Fort Liberty will be inspected and maintained in accordance with Fort Liberty’s Stormwater Control Measure Inspection and Maintenance Manual.

Private development on Fort Liberty with regulated SCMs must comply with 15A NCAC 02H .1050 (11, 12) and shall have terms governing long term SCM operation and maintenance requirements included in the ground lease. In all cases, the Tenant must provide WMS with an Operation & Maintenance Plan for approval prior to beginning construction; and an As-Built Plan and Certification for each SCM upon completion of construction. For privately maintained SCM devices, the Tenant shall submit an annual operation and maintenance certification form (see Appendix F). This annual certification shall cover the fiscal year (October 1 September 30) and must be submitted prior to October 31 of each year to: WMS.

SCM As-Built Plans and Certification Each regulated SCM device must be certified by an appropriate professional certifying it has been constructed and will function as designed and approved. Professional licensing boards determine who is qualified to perform specific types of work. SCM As-Builts and Certifications are typically completed by a Professional Engineer licensed in the state of North Carolina.

Certification requires periodic inspection of each device by the certifying professional during construction. The As- Built Plan details the as-constructed configuration of the SCM. A Certification is required to confirm that the installed SCM is generally in compliance with the approved design and in good working order.

PROJECTS IN AREAS DRAINING TO WATER SUPPLY WATERSHEDS WS-III OR WS-IV.

Plot location of project in NCDEQ water supply watershed interactive map. If project falls within WS-III Comply with 15A NCAC 02B .0216 Water Supply Watershed III (WS-III). If project falls within WS-IV Comply with 15A NCAC 02B .0216 Water Supply Watershed IV (WS-IV).

VEGETATED SETBACKS.

Vegetated setbacks from perennial waterbodies, perennial streams, and intermittent streams shall be required in accordance with Rule 15A NCAC 02H .1003 and shall be at least 30 feet in width. Vegetated setbacks from such waters shall be required if the water is shown on either the most recent version of the soil survey map prepared by the Natural Resources Conservation Service of the United States Department of Agriculture which is herein incorporated by reference, including subsequent amendments and editions, and may be accessed at no cost at http://www.nrcs.usda.gov/wps/portal/nrcs/main/soils/survey/ or the most recent version of the 1:24,000 scale (7.5 minute) quadrangle topographic maps prepared by the United States Geologic Survey (USGS) which is herein incorporated by reference, including subsequent amendments and editions, and may be accessed at no cost at http://www.usgs.gov/pubprod/.