Attachment 1 - Questions and Answers.pdf
PDF 116 KB Posted
- Solicitation number
- SP7000-24-Q-0004
- Issued by
-
Defense Logistics Agency
About this file
This document is a set of Questions and Answers related to solicitation SP7000-24-Q-0004 for the up to 60-month lease of 72 multi-functional devices (MFDs) and associated accessories/services for the Navy Nuclear Power Command (NNPTC)/Navy Nuclear Power Unit (NNPTU). The questions cover topics such as the sponsorship of the facility clearance level requirement and the possibility of extending the phase-in period. The solicitation is being issued by the Defense Logistics Agency (DLA) as a Request for Quotation (RFQ) on a Lowest Priced Technically Acceptable (LPTA) basis. The performance period is estimated to be from June 1, 2024 to May 31, 2029, with multiple option periods. The solicitation provides details on submission requirements, evaluation criteria, and applicable clauses/provisions.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEFENSE LOGISTICS AGENCY
DLA CONTRACTING SERVICES OFFICE
5404 J AVENUE, BUILDING 404
NEW CUMBERLAND, PENNSYLVANIA 17070-5059
Questions and Answers
SP7000-24-Q-0004
1. Would the DLA or the customer sponsor the winning vendor for the Facility Clearance Level (FCL) requirement?
Answer: Yes
2. Would the DLA or the customer consider extending the phase-in period to a minimum of 120 days to allow the awardee more time to meet the Facility Clearance Level (FCL) requirement?
Answer: The 90-day phase-in period is unable to be shifted due to the customers immediate need to meet mission requirements.