Attachment 36 - AMHE DIDs (DI-DLAMGMT-00012 Project Management Plan).pdf

PDF 98 KB Posted

Attached to
Logistics Modernization Integration Support (LMIS) for Defense Logistics Agency (DLA) Distribution Federal contract opportunity
Solicitation number
SP3300-20-R-5002
Issued by
Defense Logistics Agency Distribution

About this file

This document contains a Data Item Description (DID) for a Project Management Plan (PMP) related to the Logistics Modernization Integration Support (LMIS) for Defense Logistics Agency (DLA) Distribution solicitation. The DID provides instructions for contractors to prepare and submit a PMP that demonstrates their technical and managerial approach for meeting the requirements in the statement of work. The PMP must include details on the contractor's organization structure, anticipated personnel qualifications, use of government facilities and equipment, and approach for integrating, implementing and managing the program. It must also include performance plans, metrics, risk identification, and impacts to the integrated master schedule. Revisions to the PMP must be submitted with a summary of all changes.

View the file

Other files for this federal contract opportunity

Other files attached to Logistics Modernization Integration Support (LMIS) for Defense Logistics Agency (DLA) Distribution, newest first.
File Type Posted
LMIS RFP SP3300-20-R-5002 Amendment 0009.pdf PDF
LMIS RFP Questions and Responses Version 3.xlsx XLSX spreadsheet
RFP SP3300-20-5002 Rev. 3 (02.28.20) Tracked Changes.docx DOCX document
RFP SP3300-20-5002 Rev. 2 (02.19.20).pdf PDF
LMIS RFP SP3300-20-R-5002 Amendment 0006.pdf PDF
Attachment 20 - Service Contract Act Wage Determination.pdf PDF
Attachment 15 - EDC Modernization CDRLs & DIDs Cross Reference.xlsx XLSX spreadsheet
LMIS RFP Questions and Responses Version 2.xlsx XLSX spreadsheet
Attachment 37 - AMHE Compliance Checklist.xlsx XLSX spreadsheet
Attachment 39 - Service Contract Act Wage Determination.pdf PDF
Attachment 7 - Schedule Page (Pool 1) Rev. 1.xlsx XLSX spreadsheet
LMIS RFP SP3300-20-R-5002 Amendment 0005.pdf PDF
Attachment 43 - TE 1.4 CIRS Tutorial.pdf PDF
Attachment 44 - TE 1.5 Contractor Investigative Request Sep 2016.pdf PDF
LMIS RFP Questions and Responses.xlsx XLSX spreadsheet
RFP SP3300-20-5002 Rev. 1 (01.21.20).pdf PDF
Attachment 45 - TE 1.6 DD2875 SAAR Aug 2009.pdf PDF
Attachment 32 - Pool 2 Continuation of Supplies Services Instructions Rev. 1 (01.17.20).pdf PDF
Attachment 42 - TE 1.3 CIRS Manual.pdf PDF
LMIS Pre-Proposal Conference Questions & Answers.pdf PDF
LMIS Pre-Proposal Conference Agenda.pdf PDF
RFP SP3300-20-R-5002 Amendment 0001.pdf PDF
Attachment 13 - Implementation Project Schedule.pdf PDF
Attachment 32 - Pool 2 Continuation of Supplies Services Instructions.pdf PDF
Attachment 2 - Past Performance Questionnaire.docx DOCX document
Attachment 6 - CDRLs (CDRL A002 - Small Business Participation Biannual Progress Report).pdf PDF
Attachment 1 - Basic IDIQ PWS.pdf PDF
Attachment 3 - Subcontracting Plan Template -Includes Elements 1-15.docx DOCX document
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00008 GFE & GFP Report Requirements).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00013 Certificate of Compliance).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMISC-00002 Commercial Manual).pdf PDF
Attachment 8 - Pool 1 Continuation of Supplies Services Instructions.pdf PDF
Attachment 34 - AMHE Drawings (NCDP2_17_01_01_01A_DE_R-.DWG).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMISC-00003 Warranty Information and Technical Representatives List).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMISC-00004 Training Baseline (TB) and Training Materials).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00006 Network Infrastructure and Comm Protocols, Ports, Services).pdf PDF
RFP SP3300-20-5002.pdf PDF
Attachment 31 - Pool 2 Schedule.xlsx XLSX spreadsheet
Attachment 35 - LMIS IDIQ -AMHE and Systems sample TO CDRL DD Form 1423.pdf PDF
Attachment 4 - TE 1.1 Contractor Personnel Security - UPDATE 26FEB2018.pdf PDF
Attachment 5 - TE 1.2 CAC Procedures.pdf PDF
Attachment 34 - AMHE Drawings (NCDP2_17_01_01_01A_EL_R-.DWG).pdf PDF
Attachment 34 - AMHE Drawings (AMHE Drawings).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00003 Testing and Verification Plan).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00002 Software, Firmware, and Coding Inventory Requirements).pdf PDF
Attachment 34 -AMHE Drawings (NCDP2_17_01_01_01A_PR_R-.DWG).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00014 In-Progress Review (IPR) and Report Requirements).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMISC-00005 Power Requirements).pdf PDF
Attachment 36 - AMHE DIDs (DI-DLAMGMT-00005 DoD Architecture Framework Documentation).pdf PDF
Attachment 33 - AMHE SOW.pdf PDF
Show all 50

Logistics Modernization Integration Support (LMIS) for Defense Logistics Agency (DLA) Distribution has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Form Approved OMB No. 0704-0188

Page ___ of ___ Pages

PREVIOUS EDITION MAY BE USED.DD FORM 1664, AUG 96 (EG)

DATA ITEM DESCRIPTION

1. TITLE 2. IDENTIFICATION NUMBER

3. DESCRIPTION/PURPOSE

4. APPROVAL DATE

(YYYYMMDD)

5. OFFICE OF PRIMARY RESPONSIBILITY (OPR) 6a. DTIC APPLICABLE 6b. GIDEP APPLICABLE

7. APPLICATION/INTERRELATIONSHIP

8. APPROVAL LIMITATION 9a. APPLICABLE FORMS 9b. AMSC NUMBER

10. PREPARATION INSTRUCTIONS

11. DISTRIBUTION STATEMENT

Distribution Statement A: Approved for public release; distribution is unlimited.

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS.

Form Approved OMB No. 0704-0188

Page ___ of ___ Pages

PREVIOUS EDITION MAY BE USED.DD FORM 1664, AUG 96 (EG)

DATA ITEM DESCRIPTION

1. TITLE 2. IDENTIFICATION NUMBER

3. DESCRIPTION/PURPOSE

4. APPROVAL DATE

(YYYYMMDD)

5. OFFICE OF PRIMARY RESPONSIBILITY (OPR) 6a. DTIC APPLICABLE 6b. GIDEP APPLICABLE

7. APPLICATION/INTERRELATIONSHIP

8. APPROVAL LIMITATION 9a. APPLICABLE FORMS 9b. AMSC NUMBER

10. PREPARATION INSTRUCTIONS

11. DISTRIBUTION STATEMENT

Distribution Statement A: Approved for public release; distribution is unlimited.

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS.

DI-LMIS-00002 Program Management Plan
Untitled

DD Form 1664 (BLANK)

1 TITLE: Project Management Plan (PMP)
2 IDENTIFICATION NUMBER: DI-DLAMGMT-00012
3 DESCRIPTIONPURPOSE: 3.1 The PMP is a document that provides a complete and appropriate description of the technical and management approaches the Contractor will utilize to perform the efforts described within the Statement of Work (SOW) or Performance Work Statement (PWS). The PMP supports the Contractor's Work Breakdown Structure (WBS) and will be used by the Government to determine if the Contractor has a creditable understanding of the requirements identified in the SOW or PWS with the technical and managerial capabilities to meet those requirements. The PMP also assists with providing the Government with critical information on the Contractor's organization, practices, and techniques.
4 APPROVAL DATE YYYYMMDD: N/A
5 OFFICE OF PRIMARY RESPONSIBILITY OPR: DLA Information Operations - J62B
6a DTIC APPLICABLE: N/A
6b GIDEP APPLICABLE: N/A
7 APPLICATIONINTERRELATIONSHIP: 7.1 This Data Item Description (DID) is applicable to all contractor performance and work actions necessary to comply with requirements described within the contract.

7.2 This DID may be applied to programs or projects during Material Solution Analysis (MSA), Technology Maturation & Risk Reduction (TMRR), Engineering & Manufacturing Development (EMD), Production & Deployment (P&D), and Operations & Support (O&S) phases of the Defense Acquisition Life Cycle.

8 APPROVAL LIMITATION: N/A
9a APPLICABLE FORMS: N/A
9b AMSC NUMBER: N/A
10 PREPARATION INSTRUCTIONS: 10.1 Format: The PMP must be in the Contractor's design unless otherwise specified on the Contract Data Requirements List (CDRL / DD Form 1423). Unless stated otherwise on the CDRL, the deliverable to the Government must be provided in digital format and viewable using the latest version of Microsoft Office or Adobe software products as applicable.

10.2 Content: The PMP must include a table of contents; page numbering; a full description of the Contractor's technical approach; a description of how the program and project(s) will be integrated, implemented, and managed; plans for performance; metrics and standards appropriate or applicable to underlying task(s); identification of any risks or problem areas (perceived or presumed) that would be expected to satisfy the requirements; and key aspects of relationship of the PMP that will impact critical path elements on the Integrated Master Schedule (IMS). Additionally, the PMP must provide the following specific content:

10.2.a Organization Structure and Anticipated Personnel Qualifications: The PMP must include chart(s) showing the structure of the Contractor's program organization by title and name with the program office and support contractors; a Contractor functional organizational chart demonstrating the relationship of the program functions to the functional organizations with lines of authority and communications; plans that outline the total number of proposed staff and respective task area(s) or task(s) assigned (including supervisory and/or lead personnel that will be supplemented/added in worst possible scenario(s)); specific information (experience, qualifications, background, etc) for all expected key personnel to be assigned; details on Contractor personnel required to be on-site during contract performance; and information on subcontractors, vendors, suppliers (firm names, addresses, and telephone numbers) to be used with a brief description of the work to be performed and/or materials/equipment expected to be furnished by each.

(Continued)

PAGE NUMBER 1: 1
PAGE NUMBER 2: 2
1010 PREPARATION INSTRUCTIONS: 10.2.b Government Equipment and Facilities: The PMP must include details and depicting major requirements for Government Furnished Equipment (GFE) (including dates and duration that the GFE will be required) for Contractor performance.

10.3 Revisions: Unless otherwise indicated by revision and date, the PMP submitted by the Contractor to the Government as cited within this DID will be considered the most up to date iteration. Revisions to the PMP must be provided by the Contractor with an accompanying summary that clearly identifies to the Government all changes at the time of submission.

PAGE NUMBER 11: 2