Attachment 13 - Implementation Project Schedule.pdf
PDF 541 KB Posted
- Attached to
- Logistics Modernization Integration Support (LMIS) for Defense Logistics Agency (DLA) Distribution Federal contract opportunity
- Solicitation number
- SP3300-20-R-5002
- Issued by
- Defense Logistics Agency Distribution
About this file
This project schedule outlines the implementation of the Logistics Modernization Integration Support (LMIS) contract for Defense Logistics Agency (DLA) Distribution. The multi-phase project involves modernizing DLA's distribution facilities through automation and conveyance system upgrades from June 2018 through June 2024.
Key aspects include replacing receiving, sorting, storage and retrieval systems; installing new conveyors, AGVs, racking and controls; integrating software; and reconfiguring facility layouts. Phase 1 upgrades the receiving dock from March 2021 through August 2021. Phase 2 installs parcel systems and expands receiving from July 2021 through March 2022. Phase 3 involves new sorting equipment through January 2022. Phase 4 automates distribution bay storage from June 2019 through June 2024. Final implementation and tie-ins are scheduled for weekends in 2022 through 2024 to minimize disruption. The incumbent contractor will complete engineering, manufacturing, installation, testing and go-live activities.
View the file
Other files for this federal contract opportunity
Show all 50
Logistics Modernization Integration Support (LMIS) for Defense Logistics Agency (DLA) Distribution has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This document is a copy of the project schedule for the EDC Modernization Delivery Order for Pool 1, Enterprise Facility Modernization. The DLA task durations in this document should be considered as fixed. However, the facilities and equipment task durations should be updated by each offeror to reflect their approach to the project. The project schedule matches the sequence nomenclature in the RFP functional and technical specification and in the Drawings.
ID Task Mode
Task Name Duration Start Finish % Compl
Actual Start Actual Finish
Predecessors Resource Names
1 LMIS Program IDIQ 1536 days? Fri 6/8/18 Sun 6/16/24 4% Fri 6/8/18 NA
2 Pre‐Solicitation Phase 365 days? Fri 6/8/18 Fri 11/1/19 71% Fri 6/8/18 NA
17 Solicitation, Eval, and Award Phase 214 days Mon 11/4/19 Tue 9/8/20 0% NA NA
26 Task Orders Award & Performance Phase 722 days? Thu 9/20/18 Tue 7/20/21 7% Thu 9/20/18 NA
27 EDC Modernization Task Order 722 days? Thu 9/20/18 Tue 7/20/21 7% Thu 9/20/18 NA
28 Pre‐Solicitation Phase 281 days? Thu 9/20/18 Fri 10/18/19 36% Thu 9/20/18 NA
34 Solicitation, Eval, and Award Phase 212 days? Mon 11/4/19 Thu 9/3/20 0% NA NA
45 Award & Performance Phase 219 days? Fri 9/4/20 Tue 7/20/21 0% NA NA
141 Engineering 120 days Thu 10/29/20 Wed 4/21/21 0% NA NA
142 Conveyor System Engineering 85 days Thu 10/29/20 Wed 3/3/21 0% NA NA
143 Mechanical Engineering 60 days Thu 10/29/20 Wed 1/27/21 0% NA NA
144 ME Phase 1 & 2 40 days Thu 10/29/20 Mon 12/28/20 0% NA NA 47
145 ME Phase 3 40 days Thu 11/12/20 Wed 1/13/21 0% NA NA 47,144FF+10 days
146 ME Phase 4 40 days Fri 11/27/20 Wed 1/27/21 0% NA NA 47,145FF+10 days
147 Controls Engineering 45 days Tue 12/29/20 Wed 3/3/21 0% NA NA
148 ECE Phase 1 & 2 25 days Tue 12/29/20 Wed 2/3/21 0% NA NA 144
149 ECE Phase 3 25 days Thu 1/14/21 Wed 2/17/21 0% NA NA 145
150 ECE Phase 4 25 days Thu 1/28/21 Wed 3/3/21 0% NA NA 146
151 Pallet Conveyor Engineering (Phase 5) 60 days Thu 10/29/20 Wed 1/27/21 0% NA NA
154 Storage and Retrevial Engineering 90 days Thu 10/29/20 Wed 3/10/21 0% NA NA
155 Receiving Buffer System Engineering (Phase 2) 60 days Thu 10/29/20 Wed 1/27/21 0% NA NA 47
156 DB Area Storage and Retrevial System Engineering (Phase 4) 90 days Thu 10/29/20 Wed 3/10/21 0% NA NA 47
157 AGV Engineering 90 days Thu 10/29/20 Wed 3/10/21 0% NA NA
158 Mechanical Engineering (Phase 5) 90 days Thu 10/29/20 Wed 3/10/21 0% NA NA 47
159 Controls Engineering (Phase 5) 90 days Thu 10/29/20 Wed 3/10/21 0% NA NA 158FF
160 Facilities Engineering‐ all facility modifications 120 days Thu 10/29/20 Wed 4/21/21 0% NA NA
161 Preliminary Design 90 days Thu 10/29/20 Wed 3/10/21 0% NA NA 47
162 Government Review 10 days Thu 3/11/21 Wed 3/24/21 0% NA NA 161
163 Final Design 10 days Thu 3/25/21 Wed 4/7/21 0% NA NA 162
164 Government Approval 10 days Thu 4/8/21 Wed 4/21/21 0% NA NA 163
165 Permitting (If Applicable) 20 days Thu 4/22/21 Wed 5/19/21 0% NA NA
168 Manufacturing 170 days Tue 12/29/20 Mon 8/30/21 0% NA NA
169 Conveyor Manufacturing 80 days Tue 12/29/20 Wed 4/21/21 0% NA NA
175 Controls Manufacturing 55 days Thu 1/28/21 Wed 4/14/21 0% NA NA
181 Receiving Buffer System Manufacturing 120 days Thu 1/28/21 Mon 7/19/21 0% NA NA
184 DB Storage and Retrevial Manufacturing 120 days Thu 3/11/21 Mon 8/30/21 0% NA NA
187 AGV Manufacturing 90 days Thu 3/11/21 Mon 7/19/21 0% NA NA
189 Shipping (Freight) 172 days Tue 1/26/21 Tue 9/28/21 0% NA NA
190 Conveyor Shipping (Freight) 67 days Tue 1/26/21 Wed 4/28/21 0% NA NA
191 Phase 1 Conveyor Freight 5 days Thu 3/11/21 Wed 3/17/21 0% NA NA
193 Phase 2 Conveyor Freight 5 days Thu 3/11/21 Wed 3/17/21 0% NA NA
195 Phase 3 Conveyor Freight 5 days Thu 4/8/21 Wed 4/14/21 0% NA NA
197 Phase 4 Conveyor Freight 5 days Thu 4/8/21 Wed 4/14/21 0% NA NA
199 Phase 5 Pallet Conveyor and AGV Freight 67 days Tue 1/26/21 Wed 4/28/21 0% NA NA
202 Controls Shipping (Freight) 30 days Thu 3/11/21 Wed 4/21/21 0% NA NA
203 Phase 1 Controls Freight 5 days Thu 4/15/21 Wed 4/21/21 0% NA NA 176
204 Phase 2 Controls Freight 5 days Thu 4/15/21 Wed 4/21/21 0% NA NA 177
205 Phase 3 Controls Freight 5 days Thu 4/15/21 Wed 4/21/21 0% NA NA 178
206 Phase 4 Controls Freight 5 days Thu 4/15/21 Wed 4/21/21 0% NA NA 179
207 Phase 5 Controls Freight 5 days Thu 3/11/21 Wed 3/17/21 0% NA NA 180
208 Receiving Buffer System Shipping (Freight) 60 days Thu 5/20/21 Mon 8/16/21 0% NA NA
211 DB Storage and Retrevial Shipping (Freight) 45 days Tue 7/27/21 Tue 9/28/21 0% NA NA
214 Conveyor Implementation Transition Plan 1280 days? Mon 6/3/19 Sun 6/16/24 0% NA NA
215 Phase 1 Receiving Conveyor 114 days Thu 3/18/21 Fri 8/27/21 0% NA NA
216 Phase 1.01 Receiving Dock & Process Mezzanine 105 days Thu 3/18/21 Mon 8/16/21 0% NA NA
217 Installation Pre‐Work 95 days Thu 4/1/21 Mon 8/16/21 0% NA NA
218 DLA Installation Pre‐Work 15 days Thu 4/1/21 Thu 4/22/21 0% NA NA
220 MHE Facilities Installation 80 days Thu 4/22/21 Mon 8/16/21 0% NA NA
221 Install Sprinklers/Alarms Receiving Buffer Maintenance Structure 15 days Mon 7/12/21 Fri 7/30/21 0% NA NA 230
222 Install Lighting Under Receiving Buffer Maintenance Structure 3 days Mon 8/2/21 Wed 8/4/21 0% NA NA 221
223 Remove furniture, Deconstruct Offices and Breakrooms on Mezzanine 25 days Thu 4/22/21 Thu 5/27/21 0% NA NA 228FF,164
224 Build 1st floor Breakroom/restroom; Convert mezz office to breakroom 55 days Fri 5/28/21 Mon 8/16/21 0% NA NA 223
225 HVAC and electrical modifications 30 days Fri 5/28/21 Mon 7/12/21 0% NA NA 228FF,223
226 Automation Installation 90 days Thu 3/18/21 Mon 7/26/21 0% NA NA
227 Mechanical Installation 90 days Thu 3/18/21 Mon 7/26/21 0% NA NA
228 Demo Conveyor Dock Area (Mission) 2 days Thu 3/18/21 Fri 3/19/21 0% NA NA 192
229 Install Conveyor Dock Area (Mission) 5 days Mon 3/22/21 Fri 3/26/21 0% NA NA 228
230 Install Receiving Buffer Maintenance Platform 14 days Fri 6/18/21 Fri 7/9/21 0% NA NA 210
231 Install Conveyor on Process Mezzanine 10 days Tue 7/13/21 Mon 7/26/21 0% NA NA 230FF,192,225
232 Electrical Installation 65 days Thu 4/22/21 Mon 7/26/21 0% NA NA
233 Electrical Install Dock Area 5 days Thu 4/22/21 Wed 4/28/21 0% NA NA 229FF,203
234 Electrical Install Process Mezzanine 4 days Wed 7/21/21 Mon 7/26/21 0% NA NA 231FF,203
235 Phase 1.02 (Weekend Tie‐in) Receiving Dock and Parcel Receiving Mezzanine Area 4.5 days Sat 8/21/21 Sun 8/22/21 0% NA NA
236 Receiving Dock Conveyor Tie‐in 4.5 days Sat 8/21/21 Sun 8/22/21 0% NA NA
242 Returns Outbound Conveyor Tie‐in 4.5 days Sat 8/21/21 Sun 8/22/21 0% NA NA
248 Receiving Sorter Inbound Tie‐in 3 days Sat 8/21/21 Sun 8/22/21 0% NA NA
254 Receiving Sorter Recirc Tie‐in 4.5 days Sat 8/21/21 Sun 8/22/21 0% NA NA
260 Phase 1.03 (Post Tie‐in Demo) 5 days Mon 8/23/21 Fri 8/27/21 0% NA NA
261 Mechanical Demo 5 days Mon 8/23/21 Fri 8/27/21 0% NA NA 235
262 Electrical Demo 5 days Mon 8/23/21 Fri 8/27/21 0% NA NA 261FF
263 Controls Demo 5 days Mon 8/23/21 Fri 8/27/21 0% NA NA 262FF
264 Phase 1 Complete 0 days Fri 8/27/21 Fri 8/27/21 0% NA NA 260
265 Phase 2 Parcel Receipt, Pack Workstations and Receiving Buffer 728 days? Mon 6/3/19 Sun 4/17/22 0% NA NA
266 Installation Pre‐Work 576 days? Mon 6/3/19 Thu 9/9/21 0% NA NA
267 DLA Installation Pre‐Work 576 days Mon 6/3/19 Thu 9/9/21 0% NA NA
276 DLA J6 Pre‐Work 75 days? Thu 11/12/20 Wed 3/3/21 0% NA NA
289 DLA J61 Mezzanine & Receiving Cybersecurity Support 94 days? Thu 3/4/21 Fri 7/16/21 0% NA NA
314 Phase 2.01 Receiving, Receiving Buffer, Process Mezzanine Conveyor 120 days? Mon 7/12/21 Wed 12/29/21 0% NA NA
315 CCP Parcel Receiving Dock conveyor 53 days Mon 7/12/21 Thu 9/23/21 0% NA NA
316 DLA Parcel Receipt to Transport Tote Workstation Implementation (Temporary Station) 18 days Mon 7/12/21 Wed 8/4/21 0% NA NA
317 Install New Work Station Terminals and Printers 5 days Mon 7/12/21 Fri 7/16/21 0% NA NA 313FF
318 Install & Configure Software on VLAN, VMs, and HMI Terminals 5 days Mon 7/12/21 Fri 7/16/21 0% NA NA 317FF Contractor
319 Write & Provide Test Scripts 4 days Mon 7/19/21 Thu 7/22/21 0% NA NA 318
320 Testing Readiness Review (TRR) 2 days Fri 7/23/21 Mon 7/26/21 0% NA NA 319
321 System Testing & Troubleshooting 5 days Tue 7/27/21 Mon 8/2/21 0% NA NA 320
322 Operational Readiness Review (ORR) 2 days Tue 8/3/21 Wed 8/4/21 0% NA NA 321 Contractor,Installation Support,J62B P
323 Mechanical Installation 10 days Mon 8/30/21 Mon 9/13/21 0% NA NA 194,264
3/10/21
5/19/21
3/17/21 3/17/21
8/27/21
Contractor
Contractor,Installation Support,J62B PMO,J64 NTS & TFS,OT Acquisition BPA
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
2019 2020 2021 2022 2023 2024
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Project: LMIS SOW Implementa Date: Mon 11/18/19
Task Name Duration Start Finish % Compl
Actual Start Actual Finish
Predecessors Resource Names
324 Electrical Installation 7 days Wed 9/8/21 Thu 9/16/21 0% NA NA 323FF+3 days,204
325 Debug/ Test/ Commission 5 days Fri 9/17/21 Thu 9/23/21 0% NA NA 324,321FF
326 Ready for Go‐Live 0 days Thu 9/23/21 Thu 9/23/21 0% NA NA 325
327 Parcel Receipt Workstations and Conveyor 65 days? Mon 8/30/21 Mon 11/29/21 0% NA NA
328 DLA Parcel Receipt Workstations and Mission Non‐conveyable Decant workstations Implementation 24 days? Tue 10/19/21 Fri 11/19/21 0% NA NA
335 Mechanical Installation 40 days Mon 8/30/21 Mon 10/25/21 0% NA NA 194,264
336 Electrical Installation 25 days Tue 10/5/21 Mon 11/8/21 0% NA NA 335FF+10 days,204
337 Debug/ Test/ Commission 15 days Tue 11/9/21 Mon 11/29/21 0% NA NA 336,333FF
338 Ready for Go‐Live 0 days Mon 11/29/21 Mon 11/29/21 0% NA NA 337
339 Receiving Buffer Conveyor 47 days Mon 8/30/21 Wed 11/3/21 0% NA NA
340 Mechanical Installation 30 days Mon 8/30/21 Mon 10/11/21 0% NA NA 194,264
341 Electrical Installation 20 days Thu 9/23/21 Wed 10/20/21 0% NA NA 340FF+7 days,204
342 Debug/ Test/ Commission 10 days Thu 10/21/21 Wed 11/3/21 0% NA NA 341
343 Ready for Go‐Live 0 days Wed 11/3/21 Wed 11/3/21 0% NA NA 342
344 Routing Sorter, Empty Carton Conveyor, Mission Non‐Conveyable Decant and Inbound Returns Conveyor 85 days? Mon 8/30/21 Wed 12/29/21 0% NA NA
345 DLA Mission Non‐conveyable Decant workstations Implementation 39 days? Tue 10/19/21 Fri 12/10/21 0% NA NA
346 Install New Work Station Terminals and Printers 15 days Tue 10/19/21 Mon 11/8/21 0% NA NA 353FF
347 Install & Configure Software on VLAN, VMs, and HMI Terminals 10 days? Tue 10/26/21 Mon 11/8/21 0% NA NA 346FF Contractor
348 Write & Provide Test Scripts 5 days? Tue 11/9/21 Mon 11/15/21 0% NA NA 347
349 Testing Readiness Review (TRR) 2 days? Tue 11/16/21 Wed 11/17/21 0% NA NA 348
350 System Testing & Troubleshooting 15 days? Thu 11/18/21 Wed 12/8/21 0% NA NA 349
351 Operational Readiness Review (ORR) 2 days Thu 12/9/21 Fri 12/10/21 0% NA NA 350 Contractor,Installation Support,J62B P
352 Mechanical Installation 40 days Mon 8/30/21 Mon 10/25/21 0% NA NA 194,264
353 Electrical Installation 25 days Tue 10/5/21 Mon 11/8/21 0% NA NA 352FF+10 days,204
354 Compactor 60 days Tue 10/5/21 Wed 12/29/21 0% NA NA
355 Replace Facility enclosure for compactors 60 days 0% NA NA
356 Install New Compactor 10 days Tue 10/5/21 Tue 10/19/21 0% NA NA 357SF
357 Install Compactor Chute 5 days Tue 10/19/21 Mon 10/25/21 0% NA NA 352FF
358 Debug/ Test/ Commission 15 days Thu 11/18/21 Wed 12/8/21 0% NA NA 353,350FF
359 Ready For Go‐Live 0 days Fri 12/10/21 Fri 12/10/21 0% NA NA 358,351
360 Phase 2.02 (Weekend Tie‐in) 20 days? Mon 11/22/21 Sat 12/18/21 0% NA NA
386 Phase 2.03 (Post Weekend Tie‐in Phase 2.02) 15 days Mon 12/20/21 Thu 1/13/22 0% NA NA
390 Phase 2.04 Parcel Receiving Dock and Centralized Pack Area 84 days? Mon 12/13/21Wed 4/13/22 0% NA NA
417 Phase 2.05 DB Recirculation Conveyor (Weekend Tie‐in) 0 days Sat 4/16/22 Sun 4/17/22 0% NA NA
423 Phase 2.06 Mission Parcel Receiving Dock Area (Weekend Tie‐in) 0 days Sat 1/29/22 Sun 1/30/22 0% NA NA
429 Phase 2.07 Phase 2.07 CFS Parcel Receiving Dock (Weekend Tie‐in) 0 days Sat 2/5/22 Sun 2/6/22 0% NA NA
435 Receiving Buffer Storage and Retrevial System 142 days? Tue 9/7/21 Tue 3/29/22 0% NA NA
447 Phase 2 Complete 0 days Tue 3/29/22 Tue 3/29/22 0% NA NA 435
448 Phase 3 New CFS Sorter, AWOS Routing Sorter 662 days? Mon 6/3/19 Thu 1/13/22 0% NA NA
576 Phase 4 New DB Automated Storage System and GtP Pick & Stow Workstations 1280 days? Mon 6/3/19 Sun 6/16/24 0% NA NA
577 DLA J6 Pre‐Work 85 days? Thu 10/29/20 Wed 3/3/21 0% NA NA
590 DLA J61 DB High Bay Cybersecurity Support 99 days? Thu 3/4/21 Fri 7/23/21 0% NA NA
616 Phase 4.01 Prework DB Conveyor Demo Ailes 17 Through 32 361 days Mon 6/3/19 Fri 10/30/20 0% NA NA
617 DLA Installation Pre‐Work 361 days Mon 6/3/19 Fri 10/30/20 0% NA NA
618 Empty DB Shelves Aisles 32‐17 361 days Mon 6/3/19 Fri 10/30/20 0% NA NA
619 Pick & Relocate F‐Pops & G‐Pops(82000 NSN,s) 189 days Mon 6/3/19 Fri 2/28/20 0% NA NA
620 Rewarehouse Inventory DB Aisle 32‐17 (16 Aisles) to Aisles 1 through 16 172 days Mon 3/2/20 Fri 10/30/20 0% NA NA 619
621 Aisles 17 through 32 DB Rack Empty 0 days Fri 10/30/20 Fri 10/30/20 0% NA NA 620 622 MHE (Facilities) Aisles 32‐27 40 days Tue 10/8/19 Tue 12/3/19 0% NA NA
623 Remove Ceiling Sprinklers (Above Rack) Aisles 32‐22 20 days Tue 10/8/19 Mon 11/4/19 0% NA NA 618SS+90 days
624 Install Ceiling Sprinklers (Above Rack) Aisles 32‐22 30 days Tue 10/22/19 Tue 12/3/19 0% NA NA 623SS+10 days
625 Remove/ Relocate/Install Lighting (Ceiling) Aisles 32‐22 20 days Tue 10/8/19 Mon 11/4/19 0% NA NA 618SS+90 days
626 Phase 4.01 DB Conveyor Demolition Aisles 32‐17 27 days Tue 8/24/21 Thu 9/30/21 0% NA NA
627 Mechanical Demo 25 days Tue 8/24/21 Tue 9/28/21 0% NA NA 620
628 Remove Metal Shelf Bins 12 days Tue 8/24/21 Thu 9/9/21 0% NA NA 625,213
629 Remove In/Out Conveyor Spurs 5 days Fri 9/10/21 Thu 9/16/21 0% NA NA 625,628
630 Remove Front Catwalks 8 days Fri 9/17/21 Tue 9/28/21 0% NA NA 629
631 Electrical Demo 10 days Wed 9/15/21 Tue 9/28/21 0% NA NA 627FF
632 Controls Demo 10 days Fri 9/17/21 Thu 9/30/21 0% NA NA 631FF+2 days
633 Phase 4.02 DB Main Conveyor Line Inbound/Outbound Replacement (Weekend) 0 days Sat 10/2/21 Sun 10/3/21 0% NA NA
634 Mechanical Demo & Install 3 days Sat 10/2/21 Sun 10/3/21 0% NA NA 632,198
635 Electrical Demo & Install 2 days Sat 10/2/21 Sun 10/3/21 0% NA NA 634FF+1 day,206
636 Controls Demo & Install 1 day Sun 10/3/21 Sun 10/3/21 0% NA NA 635FF
637 Debug/ Test/ Commission 1 day Sun 10/3/21 Sun 10/3/21 0% NA NA 636
638 DB Main Conveyor Line InBound/ Outbound Replacement Tie‐in Go‐Live 0 days Sun 10/3/21 Sun 10/3/21 0% NA NA 637
639 Phase 4.03 Installation of DB and DK area 158 days? Mon 8/30/21 Wed 4/13/22 0% NA NA
640 Rack and Structure Installation Aisles 32‐27 95 days Fri 9/17/21 Wed 2/2/22 0% NA NA
641 Install New DB Storage Rack 20 days Fri 9/17/21 Thu 10/14/21 0% NA NA 625,632SS
642 Install Maintenance Platforms and Structures 15 days Fri 10/15/21 Thu 11/4/21 0% NA NA 641
643 Install new In‐Rack Sprinklers/alarms 60 days Fri 11/5/21 Wed 2/2/22 0% NA NA 642
644 Install New Maintenance Platform Lighting 10 days Fri 11/5/21 Thu 11/18/21 0% NA NA 642
645 New DB Storage Rack Ready For Automation Installation 0 days Wed 2/2/22 Wed 2/2/22 0% NA NA 644,643
646 Automation Installation 158 days? Mon 8/30/21 Wed 4/13/22 0% NA NA
679 New DB Storage and retrevial System Go‐Live 0 days Wed 4/13/22 Wed 4/13/22 0% NA NA 666,672,659,678
680 Phase 4.04 Installation of DB Area Aisles 22 through 26 210 days Thu 2/3/22 Mon 11/28/22 0% NA NA
681 Rack and Structure Installation Aisles 26‐22 210 days Thu 2/3/22 Mon 11/28/22 0% NA NA
682 Install New DB Storage Rack 20 days Thu 2/3/22 Wed 3/2/22 0% NA NA 645
683 Install Maintenance Platforms and Structures 15 days Thu 3/3/22 Wed 3/23/22 0% NA NA 682
684 Install new In‐Rack Sprinklers/alarms 60 days Thu 3/24/22 Thu 6/16/22 0% NA NA 683
685 Install New Maintenance Platform Lighting 10 days Fri 6/17/22 Thu 6/30/22 0% NA NA 684
686 New DB Storage Rack Ready For Automation Installation 0 days Thu 6/30/22 Thu 6/30/22 0% NA NA 685,684
687 DB Storage and Retrevial/ Conveyor Area Aisles 26‐22 105 days Fri 7/1/22 Mon 11/28/22 0% NA NA
688 Mechanical Install 60 days Fri 7/1/22 Mon 9/26/22 0% NA NA 686
689 Electrical Install 45 days Mon 8/15/22 Mon 10/17/22 0% NA NA 688FF+15 days
690 Controls Install 20 days Tue 10/4/22 Mon 10/31/22 0% NA NA 689FF+10 days
691 Debug/ Test/ Commission 20 days Tue 11/1/22 Mon 11/28/22 0% NA NA 690
692 DB Storage and Retrevial/ Conveyor Area Aisles (26‐22) Go‐Live 0 days Mon 11/28/22 Mon 11/28/22 0% NA NA 691
693 DLA Installation Pre‐Work 65 days Thu 4/14/22 Fri 7/15/22 0% NA NA
694 Rewarehouse Inventory from Aisle 16‐11 DB to DB Through Decant and Stow ‐ 6 Aisles 65 days Thu 4/14/22 Fri 7/15/22 0% NA NA 679
695 MHE (Facilities) Aisles 21‐11 40 days Mon 7/18/22 Mon 9/12/22 0% NA NA
696 Remove Ceiling Sprinklers (Above Rack) Aisles 21‐11 20 days Mon 7/18/22 Fri 8/12/22 0% NA NA 694
697 Install Ceiling Sprinklers (Above Rack) Aisles 21‐11 30 days Mon 8/1/22 Mon 9/12/22 0% NA NA 696SS+10 days
698 Remove/Relocate/Install Lighting (Ceiling) Aisles 21‐11 20 days Mon 7/18/22 Fri 8/12/22 0% NA NA 694
699 Phase 4.05 DB Conveyor Demo Aisles 11 through 16 23 days Mon 7/18/22 Wed 8/17/22 0% NA NA
700 Remove Metal Shelf‐Bins 8 days Mon 7/18/22 Wed 7/27/22 0% NA NA 694
701 Mechanical Demo 5 days Thu 7/28/22 Wed 8/3/22 0% NA NA 700
702 Electrical Demo 5 days Thu 8/4/22 Wed 8/10/22 0% NA NA 701
9/23/21
11/29/21
11/3/21
Contractor
Contractor,Installation Support,J62B PMO,J64 NTS & TFS,OT Acquisition BPA
12/10/21
4/17/22 1/30/22 2/6/22
3/29/22
10/30/20
10/3/21
10/3/21
2/2/22
4/13/22
6/30/22
11/28/22
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
2019 2020 2021 2022 2023 2024
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Task Name Duration Start Finish % Compl
Actual Start Actual Finish
Predecessors Resource Names
703 Controls Demo 5 days Thu 8/11/22 Wed 8/17/22 0% NA NA 702
704 Phase 4.06 Installation of DB Area Aisles 21 through 17 205 days Fri 7/1/22 Fri 4/21/23 0% NA NA
705 Rack and Structure Installation Aisles 21‐17 205 days Fri 7/1/22 Fri 4/21/23 0% NA NA
706 Install New DB Storage Rack 20 days Fri 7/1/22 Fri 7/29/22 0% NA NA 686
707 Install Maintenance Platforms and Structures 15 days Mon 8/1/22 Fri 8/19/22 0% NA NA 706
708 Install new In‐Rack Sprinklers/alarms 60 days Mon 8/15/22 Mon 11/7/22 0% NA NA 707SS+10 days
709 Install New Maintenance Platform Lighting 10 days Tue 11/8/22 Mon 11/21/22 0% NA NA 708
710 New DB Storage Rack Ready For Automation Installation Aisles 21‐17 0 days Mon 11/21/22 Mon 11/21/22 0% NA NA 709
711 DB Storage and Retrevial/ Conveyor Area Aisles 21‐17 105 days Tue 11/22/22 Fri 4/21/23 0% NA NA
712 Mechanical Install 60 days Tue 11/22/22 Fri 2/17/23 0% NA NA 710
713 Electrical Install 45 days Mon 1/9/23 Fri 3/10/23 0% NA NA 712FF+15 days
714 Controls Install 20 days Mon 2/27/23 Fri 3/24/23 0% NA NA 713FF+10 days
715 Debug/ Test/ Commission 20 days Mon 3/27/23 Fri 4/21/23 0% NA NA 714
716 DB Storage and Retrevial/ Conveyor Area Aisles (21‐17) Go‐Live 0 days Fri 4/21/23 Fri 4/21/23 0% NA NA 715
717 50% New DB Storage and Retrevial System Active (100% 2019 Capacity with F an G POPs removed) 0 days Fri 4/21/23 Fri 4/21/23 0% NA NA 716
718 Phase 4.07 DLA Installation Pre‐Work 108 days Mon 4/24/23 Tue 9/26/23 0% NA NA
719 Rewarehouse Inventory from Aisle 10 to 1 DB to DB Through Decant and Stow ‐ 10 Aisles 108 days Mon 4/24/23 Tue 9/26/23 0% NA NA 717
720 Phase 4.07 MHE (Facilities) Aisles 10‐1 118 days Mon 5/8/23 Tue 10/24/23 0% NA NA
721 Remove Ceiling Sprinklers (Above Rack) Aisles 10‐1 20 days Tue 8/29/23 Tue 9/26/23 0% NA NA 719FF
722 Install Ceiling Sprinklers (Above Rack) Aisles 10‐1 30 days Wed 9/13/23 Tue 10/24/23 0% NA NA 721SS+10 days
723 Remove/Relocate/Install Lighting (Ceiling) Aisles 10‐1 20 days Mon 5/8/23 Mon 6/5/23 0% NA NA 719SS+10 days
724 Phase 4.07 Installation of DB Area Aisles 16 through 11 200 days Tue 11/22/22 Thu 9/7/23 0% NA NA
725 Rack and Structure Installation Aisles 16‐11 200 days Tue 11/22/22 Thu 9/7/23 0% NA NA
726 Install New DB Storage Rack 20 days Tue 11/22/22 Mon 12/19/22 0% NA NA 710
727 Install Maintenance Platforms and Structures 15 days Tue 12/20/22 Fri 1/13/23 0% NA NA 726
728 Install new In‐Rack Sprinklers/alarms 60 days Thu 12/29/22 Fri 3/24/23 0% NA NA 727SS+5 days
729 Install New Maintenance Platform Lighting 10 days Mon 3/27/23 Fri 4/7/23 0% NA NA 728
730 New DB Storage Rack Ready For Automation Installation Aisles 16‐11 0 days Fri 4/7/23 Fri 4/7/23 0% NA NA 729
731 DB Storage and Retrevial/ Conveyor Area Aisles 16‐11 105 days Mon 4/10/23 Thu 9/7/23 0% NA NA
732 Mechanical Install 60 days Mon 4/10/23 Wed 7/5/23 0% NA NA 730
733 Electrical Install 45 days Mon 5/22/23 Wed 7/26/23 0% NA NA 732FF+15 days
734 Controls Install 20 days Thu 7/13/23 Wed 8/9/23 0% NA NA 733FF+10 days
735 Debug/ Test/ Commission 20 days Thu 8/10/23 Thu 9/7/23 0% NA NA 734
736 DB Storage and Retrevial/ Conveyor Area Aisles (16‐11) Ready for Go‐Live 0 days Thu 9/7/23 Thu 9/7/23 0% NA NA 735
737 Phase 4.08 Weekend Conveyor Replacement Aisles 16 through 1 0 days Sat 9/9/23 Mon 9/11/23 0% NA NA
738 Mechanical Demo & Install 3 days Sat 9/9/23 Sun 9/10/23 0% NA NA 736
739 Electrical Demo & Install 2 days Sat 9/9/23 Sun 9/10/23 0% NA NA 738FF+1 day
740 Controls Demo & Install 1 day Sun 9/10/23 Sun 9/10/23 0% NA NA 739FF+1 day
741 Debug/ Test/ Commission 1 day Sun 9/10/23 Mon 9/11/23 0% NA NA 740
742 Weekend Conveyor Replacement Aisles 16 through 1 Tie‐in Go‐Live 0 days Mon 9/11/23 Mon 9/11/23 0% NA NA 741
743 Phase 4.09 Demolition of existing DB Conveyor Aisles 10 through Aisle 1 23 days Wed 9/27/23 Fri 10/27/23 0% NA NA
744 Remove Metal Shelf‐Bins 8 days Wed 9/27/23 Fri 10/6/23 0% NA NA 719
745 Mechanical Demo 5 days Mon 10/9/23 Fri 10/13/23 0% NA NA 744
746 Electrical Demo 5 days Mon 10/16/23 Fri 10/20/23 0% NA NA 745
747 Controls Demo 5 days Mon 10/23/23 Fri 10/27/23 0% NA NA 746
748 Phase 4.10 New DB Conveyor and DB Shuttle System Aisles 10 through Aisles 1 160 days Mon 10/30/23 Tue 6/11/24 0% NA NA
749 Rack and Structure Installation Aisles 10‐1 160 days Mon 10/30/23 Tue 6/11/24 0% NA NA
750 Install New DB Storage Rack 20 days Mon 10/30/23 Fri 11/24/23 0% NA NA 747
751 Install Maintenance Platforms and Structures 15 days Mon 11/27/23 Fri 12/15/23 0% NA NA 750
752 Install new In‐Rack Sprinklers 10 days Mon 12/18/23 Tue 1/2/24 0% NA NA 751
753 Install New Maintenance Platform Lighting 10 days Wed 1/3/24 Tue 1/16/24 0% NA NA 752
754 New New DB Storage Rack Ready For Automation Installation Aisles 10‐1 0 days Tue 1/16/24 Tue 1/16/24 0% NA NA 753
755 DB Storage and Retrevial/ Conveyor Area Aisles 10‐1 105 days Wed 1/17/24 Tue 6/11/24 0% NA NA
756 Mechanical Install 60 days Wed 1/17/24 Tue 4/9/24 0% NA NA 754
757 Electrical Install 45 days Wed 2/28/24 Tue 4/30/24 0% NA NA 756FF+15 days
758 Controls Install 20 days Wed 4/17/24 Tue 5/14/24 0% NA NA 757FF+10 days
759 Debug/ Test/ Commission 20 days Wed 5/15/24 Tue 6/11/24 0% NA NA 758
760 DB Storage and Retrevial/ Conveyor Area Aisles (10‐1) Go‐Live 0 days Tue 6/11/24 Tue 6/11/24 0% NA NA 759
761 Phase 4.11 Final Weekend Tie‐in of DB Conveyor System 0 days Sat 6/15/24 Sun 6/16/24 0% NA NA
767 Phase 4 DB Area Complete 0 days Sun 6/16/24 Sun 6/16/24 0% NA NA 766
768 Phase 5 AGV System 818 days? Tue 2/2/21 Fri 4/19/24 0% NA NA
769 Phase 5.01 Receiving & Process Mezzanine Area 10 days Mon 8/30/21 Mon 9/13/21 0% NA NA
776 Phase 5.02 CFS Sorter Area 7 days Thu 4/15/21 Fri 4/23/21 0% NA NA
781 Phase 5.03 Main Aisle Between AWOS and CFS Area 42 days Tue 2/2/21 Wed 3/31/21 0% NA NA
788 Phase 5.04 Main Facility 375 days? Tue 3/30/21 Tue 9/20/22 0% NA NA
941 Phase 5.05 Shipping Dock 284 days? Tue 9/20/22 Wed 11/1/23 0% NA NA
1005 Phase 5.06 DR High Bay Storage 529 days? Wed 6/2/21 Wed 7/5/23 0% NA NA
1068 Phase 5.07 DB High Bay Storage 216 days Tue 1/3/23 Mon 11/6/23 0% NA NA
1086 Phase 5.08 DB High Bay Storage 333 days Tue 1/3/23 Fri 4/19/24 0% NA NA
1104 0 days Sun 6/16/24 Sun 6/16/24 0% NA NA 1102,767
11/21/22
4/21/23 4/21/23
4/7/23
9/7/23 9/11/23
9/11/23
1/16/24
6/11/24 6/16/24 6/16/24
6/16/24
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
2019 2020 2021 2022 2023 2024
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress