This solicitation seeks proposals to replace the roof on Building 54 Bay 5 at the Defense Logistics Agency Distribution facility in New Cumberland, Pennsylvania. Offerors must provide all labor, materials and equipment to remove the existing roof system and asbestos-containing materials, then install the proposed new roof system using vapor barrier, insulation, cover board and .060 EPDM reinforced membrane. The deck will also be replaced in specified areas. The period of performance is 90 calendar days from notice to proceed. Work hours are weekly from 7:00am to 3:30pm excluding holidays. This small business set-aside has a total estimated value between $500,000 and $1,000,000, and requires registration in the System for Award Management database. The successful offeror will be the lowest priced responsive and responsible bidder.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SP3300-20-B-0001 Bid Abstract.pdf | ||
| SP3300-20-B-0001 - Amendment 0004.pdf | ||
| Dwg G-001 Rev 1.pdf | ||
| Building 54 Bay 5 Roof Pictures.pdf | ||
| Section 01 14 00 Work Restrictions Rev 1.pdf | ||
| SP3300-20-B-0001 - Amendment 0002.pdf | ||
| Site visit attendance sheet.pdf | ||
| SP3300-20-B-0001 - Amendment 0001.pdf | ||
| Solicitation.pdf | ||
| Attach 6 - SF-25 - Performance Bond.pdf | ||
| Attach 5 - SF-25A - Payment Bond.pdf | ||
| Attach 3 - Submittal Registers.pdf | ||
| Attach 8 - Bidders Schedule.pdf | ||
| Attach 4 - Wage Determination.pdf | ||
| Attach 7 - Bid Bond.pdf | ||
| Attach 2 - Drawings.pdf | ||
| Attach 1 - Specifications.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
SP3300
SEE CONTINUATION PAGE(S)
DLA Distribution Acquisition Operations, J-7 Mifflin Avenue, Bldg 430 New Cumberland, PA 17070
POC: James Heslop
(P) 717-770-3112 james.heslop@dla.mil
SP3300-20-B-0001
1 2
05/20/2020
04/09/2020
SP3300-20-B-0001
AMENDMENT 0003
Amendment 0003 is hereby incorporated into solicitation SP3300-20-B-0001.
Amendment 0003 is being issued to answer vendor questions.
Question 1 - In the keynote section of the drawings, number 5 states to "adjust hot pipe". What are the specific contractor's requirements in terms of the interior? Is there a masonry wall, etc.?
Answer to Question 1 – The referenced existing steel pipe is a hot steam relief vent. The existing vent currently extends through the existing roof, elbows and extends overtop the existing firewall and releases steam/moisture into Bay 4. The intent of Keynote 5 is to remove the extension pipe and elbow so flashing can be installed overtop existing hot pipe coming through the existing roof and then reinstall the existing elbow and extension pipe venting it onto the Bay 5 side. No work should be required in the building to perform the above adjustment.
Question 2 - Is it possible to revisit the abatement hours of work?
Answer to Question 2 – No, assigned demolition (including asbestos abatement) and disposal hours cannot not be changed due to mission requirements. These were clarified in Amendment 0002.
Question 3 - Will Quad rails and safety nets going be required for a single-story structure?
Answer to Question 3 – Refer to drawing G-001 - Safety and Health Requirement Note 1. It is the contractor’s responsibility to be familiar with these requirements and the requirements will be enforced as part of the project.
Question 4 - Are we install the new system in this way. Install a vapor barrier. Then install red rosin paper. Install 3" of insulation. Mechanically attached. 5/8" Cover board adhered. Adhere a .060 reinforced EPDM.
Answer to Question 4 - Refer to drawing A-101 – Proposed Roof Systems: Main Roof and Dock Roof. The proposed systems are clearly annotated to what is required and the order of installation. Specification Section 07 22 00 Paragraph 3.3 covers how Insulation is to be installed. Cover board is to be 5/8” thick per Proposed Roof System note on Drawing A-101.
Question 5 - Is a hard copy of the Bid-Bond Required?
Answer to Question 5 - The bid bond does not need submitted as hardcopy for this solicitation since the bid submission is being done electronically. Vendors should submit an electronic copy of their bid bond with their bid submission.
All other terms and conditions remain unchanged.
END OF AMENDMENT 0003