SF30SP60026R0399P0002.pdf

PDF 1 MB Posted

Attached to
Amendment 0002 Preventative maintenance and repairs to Building 5730 Lackland Air Force Base, San Antonio, Texas
Solicitation number
SP060026R0399
Issued by

About this file

This is Amendment 0002 to Solicitation SP060026R0399 issued by DLA Energy Aerospace to modify the original solicitation. The amendment is issued by DLA Energy Aerospace Energy-DLAE-M located at Building 5730, 1525 Wurtsmith Street, JBSA Lackland, TX 78236, with an effective date of SP0600. The modification number is 0002, and the requisition/purchase request number is SP0600.

The amendment incorporates two new attachments by reference: Attachment H – Comprehensive Maintenance Plan R1 and Attachment I – Questions and Answers. Attachment I contains industry questions and answers regarding the solicitation, with all questions and answers noted as complete at the time of this amendment issuance. Contractors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation, either by completing items 8 and 15 and returning one copy of the amendment, acknowledging receipt on each copy of their offer submitted, or by separate letter or telegram with specific reference to the solicitation and amendment numbers. Failure to acknowledge receipt by the deadline may result in rejection of the offer.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DLA ENERGY AEROSPACE ENRGY-DLAE-M

BLDG 5730

1525 WURTSMITH STREET

JBSA LACKLAND TX 78236

SP060026R0399

SP0600

x x

CONTINUATION SHEET PAGE 2 OF 2 PAGES REFERENCE NO. OF DOCUMENT BEING CONTINUED:

SP060026R0399 - 0002

Amendment 0002 is issued to make the following changes to solicitation SP060026R0399:

(1) The following documents are hereby incorporated by reference and added as an attachment to the solicitation:

Attachment H

Attachment I

– Comprehensive Maintenance Plan R1

– Questions and Answers

(2) Questions and Answers from Industry are provided in Attachment I. At this time all Questions and Answers are complete.

Please read document carefully.

CONTINUED ON NEXT PAGE

Preventive Maintenance Checklist:

Asset Type: Air Handler

Description: AIR HANDLING UNIT (DIRECT DRIVE)

Frequency: Quarterly 1Estimated Time (hours):A17QUCode:

(T)ools, (S)afety Equipment and (M)aterials

Mechanics tool set.1

Vacuum and cleaning materials.2

Safety Guidelines

Schedule shutdown with operating personnel.1

De-energize, lock out and tag electrical circuit(s).2

Review and follow manufacturer OM instructions.3

Record equipment damage or deficiencies.4

Follow safety procedures for handling refrigerants (DX units only).5

Record results in the equipment history log.6

Maintenance Procedures

Check/clean/adjust grills, dampers, vanes, linkages are required.

Check temperatures and pressures.

Check for unusual noise/vibration.

Inspect for leaks.

Check condition of extended lubrication lines when present.

Restore to service.

Clean up work area and remove trash.

PM Checklist Page 1 of 1Printed Thursday, October 26, 2023 A17QU

SAMPLE

Asset Type: AIR HANDLER

Description: AIR HANDLING UNIT

Frequency: AN 8Estimated Time (hours):AH01ANCode:

(T) Mechanics tool set1

(T) Tachometer2

(S) Safety glasses or goggles3

(S) Gloves4

(M) Cleaning products (use appropriate PPE)5

(M) Lubricants6

(T) Grease gun7

(T) Clamp-on ammeter8

(T) Fin comb9

(T) Self sealing, quick disconnect refrigerant hose fittings10

(T) Portable vacuum cleaner11

(T) Pressure washer12

(M) Coil cleaning solution13

(T) Electronic leak detector14

(S) Lockout/tagout kit15

(T) Refrigerant recovery machine16

(M) Replacement filter17

(M) Spare belt18

(M) Refrigerant19

(M) Corrosion removal materials, primer and paint20

(M) Algae tablets or Clorox bleach21

(T) Refrigerant vacuum pump.22

(T) Empty refrigerant gas cylinder, adequately sized.23

(M) Tube of leak lock.24

(T) Refrigeration tubing split box end wrenches.25

(T) New schrader valve access pot caps, with seals.26

(T) New schrader valve stems, with insert tool and lock off tool.27

Individual(s) performing maintenance must be certified in EPA approved refrigerant recovery procedures, and comply with the latest provisions of the United States Clean Air Act and Environmental Protection Agency regulations as they apply to protection of stratospheric ozone and the disposal of lead based paint residue.

Schedule outage of equipment with effected personnel.2

Review manufacturer's operation and maintenance instructions.3

De-energize, lockout, and tag circuit. CAUTION - Check that circuits are dead before proceeding with any work. Re-ascertain that you have identified and located the correct electrical circuit breaker, and any other source of power, i.e.: control power.

Follow site safety procedures and your supervisor's instructions.5

PM Checklist Page 1 of 3Printed Thursday, October 26, 2023 AH01AN

Refrigerant must not be intentionally vented to the atmosphere. Recover, reclaim, and recycle refrigerant. Maintain a log stating quantity and type of refrigerant added or removed. Disposal of refrigerant and refrigerant oils must be performed in accordance with published regulations and directives.

Record and report to your supervisor any equipment damage or deficiencies found while performing this task.

All tests shall conform to the manufacturer's test procedures and standard values. Insure all equipment is properly grounded, to no more than 5 ohms resistance.

Inspect filter. If necessary, perform the following maintenance.

Remove old filters.

Vacuum filter section of air handler.

Inspect frame, clamp, etc. for signs of wear or damage. Repair if necessary

Install new filters or clean old filters if they are a reusable type. Insure direction of airflow corresponds with the airflow arrow on the air filter, and that they are sized properly to cover the openings.

Inspect fan blades and other moving parts for dirt accumulation, damage, or excessive wear. Clean and repair as necessary.

Check fan RPMs against design specifications.

Inspect dampers for dirt accumulation, clean as necessary. Inspect seals, repair or replace as necessary.

Inspect damper actuators for proper operation. Adjust linkage if out of alignment.

Lubricate mechanical connections on dampers (use lubricant sparingly).

If equipped, drain and clean humidifier pan or pad. Replace pad if necessary. Remove corrosion and

Perform motor maintenance.

Inspect ventilation ports for dirt accumulation or foreign objects.

Clean exterior of motor surface.

Check motor alignment. Inspect bearings for excessive wear.

Lubricate bearings according to manufacturer's recommendations.

Inspect belt alignment, condition, and tension. Adjust or replace as necessary.

Remove filler and drain plugs (use zerk fittings if installed).

Free drain hole of any hard grease or other blockage.

Add grease as required. Use high quality lithium based grease unless otherwise noted .

Check motor windings for soil/foreign object accumulation. Blow out, vacuum or clean as necessary.

Inspect motor and compressor hold down bolts, and grounding straps for tightness.

Perform unit maintenance.

Thoroughly clean interior and exterior of machine and inspect for damage.

Clean drain pan and lines and note excessive corrosion. Treat rusted areas with rust inhibitor.

CAUTION: Insure that rust inhibitor does not introduce volatile organic compounds or contaminants to drain pan. Thoroughly rinse drain pan after treatment.

PM Checklist Page 2 of 3Printed Thursday, October 26, 2023 AH01AN

On direct expansion units, use a halogen leak detector or similar device to inspect all refrigerant lines, fittings, and valves for leaks. Correct any leaks.

Check refrigerant level, add as necessary.

Inspect condition of cooling and reheat coils. If required, use fin comb to straighten fins.

Clean coils. Use detergent or coil cleaning solution if heavily soiled. CAUTION: Use appropriate PPE when handling cleaning products.

Drain and clean humidifier pad or pan, if equipped. Replace pad if necessary. Remove corrosion as required.

With power OFF, tighten, inspect all electrical connections for tightness, wiring for damaged insulation, etc. 11 Inspect and adjust vibration isolators.

Run Air Handler. Observe action of controls, relays, switches, etc. Insure that :

Humistat activates humidifier.

Re-heat coils operate properly.

Discharge air temperature is set properly.

Assure that Pre heat controls and safety cutout controls are within operating guidelines.

Double check evaporator coil operation using the pressure - temperature relationship chart & suggested superheat scale.

Inspect and adjust vibration isolators.

Remove tags, perform operational tests, and return to service.

PM Checklist Page 3 of 3Printed Thursday, October 26, 2023 AH01AN

Frequency: QU 2Estimated Time (hours):AH01QUCode:

(T) Tachometer2

(S) Safety glasses or goggles3

(S) Gloves4

(M) Cleaning products (use appropriate PPE)5

(M) Lubricants6

(T) Grease gun7

(T) Clamp-on ammeter8

(T) Fin comb9

(T) Self sealing, quick disconnect refrigerant hose fittings10

(T) Portable vacuum cleaner11

(T) Pressure washer12

(M) Coil cleaning solution13

(T) Electronic leak detector14

(S) Lockout/tagout kit15

(T) Refrigerant recovery machine16

(M) Replacement filter17

(M) Spare belt18

(M) Refrigerant19

(M) Corrosion removal materials, primer and paint20

(M) Algae tablets or Clorox bleach21

(T) Refrigerant vacuum pump.22

(T) Empty refrigerant gas cylinder, adequately sized.23

(M) Tube of leak lock.24

(T) Refrigeration tubing split box end wrenches.25

(T) New schrader valve access pot caps, with seals.26

(T) New schrader valve stems, with insert tool and lock off tool.27

Individual(s) performing maintenance must be certified in EPA approved refrigerant recovery procedures, and comply with the latest provisions of the United States Clean Air Act and Environmental Protection Agency regulations as they apply to protection of stratospheric ozone and the disposal of lead based paint residue.

Schedule outage of equipment with effected personnel.2

Review manufacturer's operation and maintenance instructions.3

De-energize, lockout, and tag circuit. CAUTION - Check that circuits are dead before proceeding with any work. Re-ascertain that you have identified and located the correct electrical circuit breaker, and any other source of power, ie: control power.

Follow site safety procedures and your supervisor's instructions.5

PM Checklist Page 1 of 3Printed Thursday, October 26, 2023 AH01QU

Refrigerant must not be intentionally vented to the atmosphere. Recover, reclaim, and recycle refrigerant. Maintain a log stating quantity and type of refrigerant added or removed. Disposal of refrigerant and refrigerant oils must be performed in accordance with published regulations and directives.

Record and report to your supervisor any equipment damage or deficiencies found while performing this task.

All tests shall conform to the manufacturer's test procedures and standard values. Insure all equipment is properly grounded, to no more than 5 ohms resistance.

Inspect filter. If necessary, perform the following maintenance.

Remove old filters.

Vacuum filter section of air handler.

Inspect frame, clamp, etc. for signs of wear or damage. Repair if necessary

Install new filters or clean old filters if they are a reusable type. Insure direction of airflow corresponds with the airflow arrow on the air filter, and that they are sized properly to cover the openings.

Inspect fan blades and other moving parts for dirt accumulation, damage, or excessive wear. Clean and

Check fan RPMs against design specifications.

Inspect dampers for dirt accumulation, clean as necessary. Inspect seals, repair or replace as necessary.

Inspect damper actuators for proper operation. Adjust linkage if out of alignment.

Lubricate mechanical connections on dampers (use lubricant sparingly).

If equipped, drain and clean humidifier pan or pad. Replace pad if necessary. Remove corrosion and

Perform motor maintenance.

Inspect ventilation ports for dirt accumulation or foreign objects.

Clean exterior of motor surface.

Check motor alignment. Inspect bearings for excessive wear.

Lubricate bearings according to manufacturer's recommendations.

Inspect belt alignment, condition, and tension. Adjust or replace as necessary.

Remove filler and drain plugs (use zerk fittings if installed).

Free drain hole of any hard grease or other blockage.

Add grease as required. Use high quality lithium based grease unless otherwise noted .

Check motor windings for soil/foreign object accumulation. Blow out, vacuum or clean as necessary.

Inspect motor and compressor hold down bolts, and grounding straps for tightness.

Perform unit maintenance.

Thoroughly clean interior and exterior of machine and inspect for damage.

Clean drain pan and lines and note excessive corrosion. Treat rusted areas with rust inhibitor.

CAUTION: Insure that rust inhibitor does not introduce volatile organic compounds or contaminants to drain pan. Thoroughly rinse drain pan after treatment.

PM Checklist Page 2 of 3Printed Thursday, October 26, 2023 AH01QU

On direct expansion units, use a halogen leak detector or similar device to inspect all refrigerant lines, fittings, and valves for leaks. Correct any leaks.

Check refrigerant level, add as necessary.

Inspect condition of cooling and reheat coils. If required, use fin comb to straighten fins.

Clean coils. Use detergent or coil cleaning solution if heavily soiled. CAUTION: Use appropriate PPE when handling cleaning products.

Drain and clean humidifier pad or pan, if equipped. Replace pad if necessary. Remove corrosion as required.

With power OFF, tighten, inspect all electrical connections for tightness, wiring for damaged insulation, etc. 11 Inspect and adjust vibration isolators.

Run Air Handler. Observe action of controls, relays, switches, etc. Insure that:

Humistat activates humidifier.

Re-heat coils operate properly.

Discharge air temperature is set properly.

Assure that Pre heat controls and safety cutout controls are within operating guidelines.

Double check evaporator coil operation using the pressure - temperature relationship chart & suggested superheat scale.

Inspect and adjust vibration isolators.

Remove tags, perform operational tests, and return to service.

PM Checklist Page 3 of 3Printed Thursday, October 26, 2023 AH01QU

Asset Type:

Description: Heat recovery unit annual preventive maintenance.

Frequency: 2Estimated Time (hours):AH05ANCode:

(T) Mechanics tool set.1

(T) Grease gun and oiler.2

(M) Biocide.3

(T) Pressure washer.4

(T) Vacuum.5

(T) Fin comb.6

(T) Cleaning tools and materials.7

(T) PPE8

(T) Ladder (if necessary).9

(T) Electrician's tool set.10

(T) Cleaning equipment and materials.11

(M) Lubricants.12

(M) Lamps.13

(T) Filter replacement.14

1. Schedule shutdown with operating personnel, as needed.1

2. Review manufacturer's instructions.2

3. De-energize, lock out and tag electrical circuit(s).3

4. Comply with the latest provisions of the Clean Air Act and Environmental Protections Agency (EPA) regulations.

5. Don't vent refrigerants. Refrigerants must be recovered.5

6. Refrigerants and oils to be removed for disposal must be analyzed for hazardous waste and handling accordingly.

7. Follow all safety procedures for handling refrigerants and all labels on refrigerant containers.7

Quarterly procedures:

Check differential pressure and clean or change filters if limit will be excessed before next quarterly check.

When changing filters, clean filter compartment, coils, housing, room, area as required.

Lubricate Blower Bearings.

Clean condensate drain pan. Ensure condensate drains are clear. Service condensate pumps.

Check summer/winter switch in proper position.

Remove tags and restore to service.

Clean up work area and remove trash.

Annual procedures:

PM Checklist Page 1 of 2Printed Thursday, October 26, 2023 AH05AN

Description: Heat recovery unit annual preventive maintenance.

Frequency: 2Estimated Time (hours):AH05ANCode:

FAN

Tag out unit.

Check fan blades for dust buildup and clean if necessary.

Check fan blades and moving parts for cracks and excessive wear.

Check mounting bolts, set screws, etc for security.

Check dampers for dirt accumulations, clean as necessary. Check belt, repair or replace as necessary.

Check damper actuators and linkage for proper operation. Adjust linkage on dampers if out of alignment.

Lubricate mechanical connections of dampers sparingly.

Clean coils by brushing, blowing, vacuuming or pressure washing.

Check coils for leaking and adjust tightness of fittings when required.

Check for refrigerant leaks on all lines, valves, fittings, coils, etc. If leaks cannot be stopped or corrected, report leak status to supervisor.

Use fin comb to straighten coil fins.

Clean heat exchanger.

Flush and clean condensate pans and drains, remove all rust, prepare metal and paint where required. Treat condensate pans with an EPA approved biocide.

Check belts for wear and cracks, adjust tension or alignment and replace belts when necessary.

Check couplings for alignment, tightness and wear.

Vacuum interior of unit.

Lubricate fan shaft bearings while unit is running. Do not over lubricate. Remove old or excess lubricant.

Check and repair damaged insulation.

Check soundness of unit's structures and clean.

Remove tags, perform operational test and return unit to service.

MOTOR

Tag out unit.

Clean exterior of motor surfaces of soil accumulation.

Clean motor ventilation ports.

Lubricate motor bearings.

Check hold down bolts and grounding straps for tightness.

Clean motor starter and check connections for tightness.

Check motor starter and controls for proper operation.

Re-lamp as necessary.

Remove tags, perform operational test and return unit to service.

PM Checklist Page 2 of 2Printed Thursday, October 26, 2023 AH05AN

Description: Heat recovery unit quarterly preventive maintenance.

Frequency: 1Estimated Time (hours):AH05QUCode:

(T) Mechanics tool set.1

(M) Filter replacement.2

(T) Lubricant and grease gun.3

(T) Vacuum and cleaning materials.4

(T) Ladder (if necessary).5

(S) PPE6

1. Schedule shutdown with operating personnel, as needed.1

2. Review manufacturer's instructions.2

3. De-energize, lock out and tag electrical circuit(s).3

4. Comply with the latest provisions of the Clean Air Act and Environmental Protections Agency (EPA) regulations.

5. Don't vent refrigerants. Refrigerants must be recovered.5

6. Refrigerants and oils to be removed for disposal must be analyzed for hazardous waste and handling accordingly.

7. Follow any safety procedures for handling refrigerants and all labels on refrigerant containers.7

Quarterly procedures:

Check differential pressure and clean or change filters if limit will be exceeded before next quarterly check.

When changing filters, clean filters compartment, coils, housing, room, area as required.

Lubricate Blower Bearings.

Clean condensate drain pan. Ensure condensate drains are clear. Service condensate pumps.

Check summer/winter switch in proper position.

Remove tags and restore to service.

Clean up work area and rempve trash.

PM Checklist Page 1 of 1Printed Thursday, October 26, 2023 AH05QU

Asset Type: A/C, Split-System Unit

Description: AC SPLIT SYSTEM, CONDENSER & EVAPORATOR

Frequency: Annual 2Estimated Time (hours):AS02ANCode:

(T) Megger.1

(M) Biocide strips.2

(M) Filter replacement.3

(T) Vacuum.4

(T) Fin comb.5

(T) Coil cleaner.6

(T) Oiler.7

(T) Clamp-on amp meter.8

Mechanic's tool set, refrigeration system tools.9

Refrigerant manifold gage set.10

Refrigerant leak tester.11

Cleaning tools and materials, pressure washer, vacuum, fin comb,12

Rust removal materials, primer, paint.13

Lubricants, belts.14

Personal protection equipment for handling refrigerants.15

Ladder.16

Schedule work with operating personnel.1

Follow site safety rules for lockout and tagout.2

Be very careful when climbing roof access ladders.3

Review and follow the manufacturer’s instructions.4

Follow safety and environmental rules for refrigerants.5

Don't vent refrigerants. Refrigerants must be recovered.6

Submit a work order if refrigerants need to be added.7

Report any problems you find.8

Record the results in the maintenance log.9

Lock and tag out unit.

Check with operating or area staff for problems.

Clean dust and dirt from entire unit and all ventilation ports.

Wash coils with water hose. Only use a coil cleaning solution if nothing else will work.

Inspect system for any signs of rust. Remove rust, prime with rust inhibitor, paint to match original condition. Rust must be completely removed down to base metal.

Clean blowers, fans, motors, drip pans and drain piping.

Check and adjust vibration eliminators.

Grease shaft and motor bearings, if needed.

Adjust the belt tension and alignment, if needed.

PM Checklist Page 1 of 3Printed Thursday, October 26, 2023 AS02AN

Check electrical wiring and connections; tighten loose connections.

Clean area around equipment.

Check system for refrigeration leaks. If leaks are detected, submit a work order to correct the problems and recharge the system.

Remove locks and tags

Perform operational check and return to service.

Record suction and discharge pressures, sub-cooling and superheat.

EVAPORATOR PROCEDURE

GENERAL:

Cover all exposed surfaces below the evaporator.

Carefully remove access panels, covers, or ceiling tiles to gain access to the equipment.

CASING

CASING:

Clean the exterior and interior of the unit casing.

Remove rust and corrosion. Apply corrosion protection.

Carefully inspect all fasteners to ensure integrity and replace any which have rusted. Allreplacement components, parts, and materials should be of rust resistant manufacture.

Check belts and alignment, if applicable.

Inspect air side and condensate removal components:

Inspect and clean coils by vacuuming or brushing. Use coil cleaner if excessively dirty.

Use fin comb to straighten coil fins where necessary.

Inspect and clean washable filters if dirty. Recharge wire mesh filters with oil when applicable.

Inspect and replace disposable filters if dirty.

Drain and clean condensate pan. Check condensate lines for free flow.

Replace biocide strips.

Fix damaged or missing insulation on the cooling lines using "Armaflex" and/or no-drip tape.

Clean strainers.

Check controls, trap, freeze-stat, and control-stat for proper operation.

Service condensate pumps if equipped.

Clean and test motors and fans:

Check ventilation ports for soil accumulation, clean if necessary.

Clean fan blades and check for damage.

Check belts and alignment, if applicable.

Lubricate motor bearings where required. Check manufacturer's information for requirements.

Check motor windings for accumulation of soil. Vacuum if required.

Check electrical connections for tightness.

Return to service and perform an operational test.

Test in heating and cooling modes.

PM Checklist Page 2 of 3Printed Thursday, October 26, 2023 AS02AN

Check unit sensors and calibrate if required. Record calibration values.

Check unit for noise, vibration or condensate leakage.

Check for refrigeration leaks. Submit a work order to repair any leaks found.

Measure running current for all motors and check if is on line of the manufacturer datasheet.

PM Checklist Page 3 of 3Printed Thursday, October 26, 2023 AS02AN

Asset Type: A/C, SPLIT SYSTEM

Description: AC SPLIT SYSTEM, CONDENSER HEAT PUMP

Frequency: Quarterly 0.5Estimated Time (hours):AS02QUCode:

Mechanic's tool set, refrigeration system tools.1

Cleaning tools and materials, hose and water, fin comb.2

Rust removal materials, primer, paint.3

Lubricants, belts.4

Ladder.5

Be very careful when climbing roof access ladders.3

Submit a work order if refrigerants need to be added.5

Report any problems you find.6

Record the results in the maintenance log.7

Lock and tag out unit.

Check with operating or area staff for problems.

Clean dust and dirt from entire unit and all ventilation ports.

Wash coils with water hose. Only use a coil cleaning solution if nothing else will work.

Inspect system for any signs of rust. Remove rust, prime with rust inhibitor, paint to match original condition. Rust must be completely removed down to base metal.

Clean blowers, fans, motors, drip pans and drain piping.

Grease shaft and motor bearings, if needed.

Remove locks and tags

PM Checklist Page 1 of 1Printed Thursday, October 26, 2023 AS02QU

Asset Type: HVAC, Fan Coil Unit

Description: FAN COIL UNIT BELT DRIVE

Frequency: Annual 1Estimated Time (hours):FC04ANCode:

Mechanic's tool set.1

Meggar.2

Clamp-on amp meter.3

Cleaning materials and equipment.4

Oiler.5

Lubricants.6

Coil cleaner.7

Fin comb.8

Vacuum.9

Ladder.10

Filter replacement.11

Belts.12

Biocide strips.13

Check with operating or area personnel for deficiencies.3

Follow safety and environmental procedures for handling refrigerants (DX units only).5

Cover all exposed surfaces before moving ceiling tiles.7

Protect ceiling tiles and grids from damage and dirt.8

Casing:

Inspect and clean coils by vacuuming or brushing. Use coil cleaner if excessively dirty.

Inspect and clean washable filters if dirty. Recharge wire mesh filters with oil when applicable.

Inspect and replace disposable filters if dirty.

Repair damaged or missing insulation on the cooling lines.

Cycle hot water and chill water valves two times.

Service condensate pumps if equipped.

Check and adjust the fan and belt:

PM Checklist Page 1 of 2Printed Friday, October 27, 2023 FC04AN

Frequency: Annual 1Estimated Time (hours):FC04ANCode:

Check and adjust the fan and belt:

Lubricate fan shaft bearings (if not sealed) according to the manufacturer's instructions.

Check V-belt condition and tension. Adjust if needed, or replace.

Check sheaves for excessive wear. Submit a work order for replacement if necessary.

Clean fan blades and interior unit surfaces to remove soil.

Check tightness of all mounting bolts.

Clean and test motors:

Check ventilation ports for soil accumulation, clean if necessary.

Meggar motors 5 horsepower or greater.

Check unit sensors and calibrate if required. Record calibration values.

Check unit for noise, vibration or leakage.

Measure running current for all motors 5 horsepower or greater.

PM Checklist Page 2 of 2Printed Friday, October 27, 2023 FC04AN

Frequency: Quarterly 0.5Estimated Time (hours):FC04QUCode:

Cleaning materials and equipment.2

Oiler.3

Filter replacement.4

Vacuum.5

Belts.6

Ladder.7

Biocide strips.8

Check unit for noise and vibration.

Inspect and clean washable filters if dirty. Recharge wire mesh filters with oil when applicable

Inspect and replace disposable filters when dirty.

Check V-belt condition and tension. Adjust if needed, or replace.

Damp wipe exterior surfaces.

Clean surrounding floor area, and remove any dirt and debris from work area.

PM Checklist Page 1 of 1Printed Friday, October 27, 2023 FC04QU

Description: FAN COIL UNIT DIRECT DRIVE

Frequency: Annual 2.5Estimated Time (hours):FC05ANCode:

Meggar.2

Clamp-on amp meter.3

Cleaning materials and equipment.4

Oiler.5

Lubricants.6

Coil cleaner.7

Fin comb.8

Vacuum.9

Ladder.10

Filter replacement.11

Quarterly Procedure

Check unit for noise and vibration

Inspect and clean washable filters

Damp wipe exterior surfaces

Clean surraunding floor area, and remove any dirt and debris from work area

Check and clean the drain system of the unit and check for proper operation

Check the unit for all proper function

Annual Procedure

Casing:

Inspect and clean coils by vacuuming and brushing. Use coil cleaner in compliance with the manufacturer instructions.

Replace the filters fabric (this does not apply to the plastic filters)

PM Checklist Page 1 of 2Printed Friday, October 27, 2023 FC05AN

Frequency: Annual 2.5Estimated Time (hours):FC05ANCode:

Repair damaged or missing insulation on the cooling lines.

Cycle hot water and chill water valves two times.

Service condensate pumps :

Clean and wash with right products

Clean and test motors and fans:

Clean air grills

Clean fan blades and check for damage.

Check the thermostats for proper operation

Check unit for noise, vibration or leakage.

PM Checklist Page 2 of 2Printed Friday, October 27, 2023 FC05AN

Frequency: Quarterly 0.5Estimated Time (hours):FC05QUCode:

Cleaning materials and equipment.2

Oiler.3

Filter replacement.4

Vacuum.5

Ladder.6

Check unit for noise and vibration.

Inspect and clean washable filters.

Damp wipe exterior surfaces.

Clean surrounding floor area, and remove any dirt and debris from work area.

Check and clean the drain system of the unit and check for proper operation

Check the unit for all proper function

PM Checklist Page 1 of 1Printed Thursday, October 26, 2023 FC05QU

Asset Type: Fan, Other

Description: FAN, LESS THAN 7.5 HP

Frequency: Annual 1Estimated Time (hours):FN34ANCode:

Tachometer.2

Cleaning equipment and materials.3

Vacuum.4

Motor grease and grease gun (Polyrex-EM).5

Pillow block bearing grease. (Refer to pillow block bearing’s manufacturer for appropriate grease type. Otherwise, NLGI No. 2 general purpose grease may be used.)

Check with operating personnel for deficiencies.2

Follow the site safety rules and your supervisor’s instructions.3

Obtain and review manufacturer's instructions.4

Report any problems you find.5

Record the results in the equipment history log.6

Fan:

For normally de-energized units or high/low temperature start units, simulate a start signal and verify that the unit works.

Lock and tag out the unit.

Thoroughly clean the unit.

Check fan blades for dust buildup, and clean if necessary.

Check fan blades and moving parts for excessive wear. Clean as needed.

Check fan RPM, and compare RPM to design specifications.

Check bearing collar set screws on fan shaft to make sure they are tight.

Check fan wheel for bent or damaged vanes.

Vacuum the interior of unit if accessible. Clean the exterior.

If applicable - Check belts for wear. Adjust tension or alignment, and replace belts when necessary.

Multiple belt drives should be replaced with matched sets.

Lubricate fan bearings.

Check structural members, vibration eliminators and flexible connections.

Check that hold down bolts are secure.

Test fan operation.

Remove all trash and clean the area around the fan.

Motors:

Check ventilation ports for soil accumulation, and clean if necessary.

Evaluate motor and lubricate bearings if necessary.

PM Checklist Page 1 of 2Printed Thursday, October 26, 2023 FN34AN

Description: FAN, LESS THAN 7.5 HP

Frequency: Annual 1Estimated Time (hours):FN34ANCode:

Check controller for proper operation. Check electrical connections for tightness. Relamp as necessary.

Remove locks and tags. Return the unit to service. Check for unusual noise or vibration. Check for evidence of overheating. Make sure the unit actually works.

PM Checklist Page 2 of 2Printed Thursday, October 26, 2023 FN34AN

Description: FAN, BELT DRIVEN LESS THAN 7.5 HP

Frequency: Semi-Annual 0.5Estimated Time (hours):FN34SACode:

Grease gun.2

Pillow block bearing grease. (Refer to pillow block bearing’s manufacturer for appropriate grease type. Otherwise, NLGI No. 2 general purpose grease may be used.)

Lubricate fan shaft bearings while the unit is running. Add grease slowly until slight bleeding occurs from the seals. Do not over lubricate. Remove old or excess lubricant.

PM Checklist Page 1 of 1Printed Friday, October 27, 2023 FN34SA

Asset Type: FAN, SUPPLY

Description: FAN, BELT DRIVEN LESS THAN 7.5 HP

Frequency: Quarterly 2Estimated Time (hours):FNS34QUCode:

(M) Filter replacement2

(T) Lubricant and grease gun3

(T) Vacuum and cleaning materials4

(T) Ladder (if necessary)5

PROCEDURES: (QUARTERLY)

Replace filters if present

PM Checklist Page 1 of 1Printed Friday, December 1, 2023 FNS34QU

A17QU

ACLCH12AN

ACLCH12MO

ACLCH21AN

ACLCH21MO

ACLCH21SA

AH01AN

AH01QU

AH05AN

AH05QU

AH16AN

AH17QU

AS02AN

AS02QU

BO01AN

BO01MO

BO01SA

BO02AN

BO02MO

BO02SA

BP84AN

BP84SA

CH14AN

CH14MO

CH14SA

CH20AN

CH20QU

CHAC02MO

CHAC02QU

CHAC02SA

CHAC03AN

CT09AN

CT09MO

CT09QU

CT09SA

F39SA

FC04AN

FC04QU

FC05AN

FC05QU

FN34AN

FN34SA

FNS34QU

S-07 AN

WH05QU

Questions and Answers

1. To ensure accurate pricing and a complete understanding of the HVAC systems covered under this requirement, will the Government allow interested offerors to attend a site visit at Building 5730? Site Visit was scheduled for May 6, 2026, and May 13, 2026, per Amendment 0001.

2. Can the Government provide a complete HVAC equipment list, including unit type, manufacturer, model number, serial number, tonnage/capacity, voltage/phase, refrigerant type, location, age/year of manufacture, and current operational status? See Excel document “BLDG 5730 HVAC Equipment Schedule M-601 R2”. Tonnage/capacity, voltage/phase, age/year manufacturer are located on data plates, attached. Refrigerant is R410A.

3. If a complete equipment list is not currently available, will offerors be permitted to inspect and document unit information during a scheduled site visit so pricing can be based on verified equipment data? Site Visit was scheduled for May 6, 2026, and May 13, 2026, per Amendment 0001.

4. Can the Government provide current photos of the HVAC equipment, access points, mechanical rooms, rooftop/ground locations, controls, condensate drains, and any hard-to-access equipment areas? Photos will not be provided due to site visit scheduled May 6, 2026, and May 13, 2026, per Amendment 0001.

5. Are there any known existing deficiencies, failed components, refrigerant leaks, control issues, airflow issues, drainage issues, or equipment currently not operating as designed? HVAC system is fully operational with no failed components. Deficiencies include: Dedicated offline Facility Explorer control software may be outdated but is operational. 3 cold spots in the building require heating coils to be on 24/7 even during the summer. DOAS unit may not have been installed as designed for optimal energy efficiency but is operational.

6. Please clarify the required tasks for each quarterly preventative maintenance visit, including whether coil cleaning, filter replacement, belt inspection/replacement, capacitor testing, refrigerant checks, drain treatment, electrical checks, thermostat/control checks, and written service reports are required. These quarterly PM visits are based off MFR recommendations and commercial industry standards. There are 3 quarterly visits and 1 annual visit per year. See attached “Comprehensive Maintenance Plan R1” checklists as a sample guide for annual and quarterly PMs.

7. Will filters be Government-furnished or contractor-furnished? If contractor-furnished, please provide filter sizes, quantities, MERV rating requirements, and replacement frequency. Filter list provided with Amendment 0001.

8. Should belts, drain tablets, coil cleaner, contact cleaner, minor hardware, and other PM consumables be included in the quarterly PM price, or billed separately when needed? CLIN 0003 is provided to price out PM consumables.

9. For on-demand repairs, should repair parts be included in fixed pricing, or billed separately upon Government approval? If separately, is there an allowed material markup or required markup limit? CLIN 0003 is provided to price out parts which are included in a quote for repairs.

10. What response time is required for urgent, emergency, after-hours, weekend, holiday, or mission-critical HVAC service calls? As stated in the SOO repairs shall be tended to the following day no later than 8:00 am once a Contract Specialist issues a task order. Should the order be placed on a Friday or holiday, response time to the site will be the next available working day.

11. Please define normal working hours for this contract. Are PM services required during normal duty hours only, or may work be performed after hours to minimize disruption? As stated in the SOO normal working hours are Monday through Friday 7:00 AM -3:00 PM except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. All work is to be performed during these time frames in order to provide COR coverage.

12. Since pricing is requested in 30-minute increments, should offerors provide separate rates for regular time, after-hours, weekend, holiday, and emergency demand service? Contractors should provide pricing as they see fit to provide proper information for the Government to make a sound decision.

13. Will the Government allow a minimum service charge for demand calls, such as a one-hour or two-hour minimum, even though billing increments are requested in 30-minute intervals? The Government will allow a reasonable minimum service charge as provided by the Contractor upon arrival and investigation of situation.

14. What base access requirements apply to contractor personnel, vehicles, and subcontractors? Contractors will be required to provide a list of the personnel who will access the base as needed. All personnel may be subject to an NCIC background check.

15. Will Government personnel provide escorts to mechanical areas, rooftops, controlled spaces, or secure areas, or must contractor personnel obtain unescorted access? Government personnel (COR or appointees) will be available during the performance of the service.

16. Is the HVAC system connected to a building automation system or DDC controls? If so, what manufacturer/platform is used, and will the contractor be expected to troubleshoot controls? The DDC control system is not connected to the Lackland BACNET system and is dedicated and not online. WiFi or wireless connection capabilities are unknown. Facility Explorer 2018 3rd party licensed software outdated but operational. Yes troubleshooting controls is part of annual PM.

17. Can the Government identify refrigerant types used in the covered equipment, including whether any units use R-22 or other phased-down refrigerants? There is no indication that R-22 is used. MFR Data plates attached show R410A used for DOAS and split system for COMM room. No refrigerant is listed on outside unit data plates for the 2 air handlers.

18. If equipment requires major repair or replacement beyond normal PM, will that work be handled through separate approval, separate purchase order, or a contract line item? The Solicitation provides a CLIN which will be available for repairs. Repairs will be quoted and a separate task order will be issued against this CLIN as listed in the Solicitation.

19. Are any HVAC units currently under manufacturer, installer, or extended warranty? HVAC units are outside all warranties; therefore, a Blanket Purchase Agreement is being solicited at this time.

20. Can the Government provide prior service records, PM reports, repair history, asset condition reports, or known recurring issues for the covered HVAC equipment? Yes, for DLA direct contracted and self-help work but limited for Lackland Base Civil Engineer (BCE) records.

21. What documentation must be submitted after each PM or repair visit? As stated in the SOO attached to the Solicitation a Work Certificate will be provided to the COR no later than five (5) workdays after the performance of the repair and three (3) days after the preventative maintenance is completed.

22. Please clarify the evaluation method for award, including whether award will be based on lowest price technically acceptable, best value, past performance, technical approach, or another method. Awards will be issued based on the lowest price technically acceptable methodology.

23. Are subcontractors permitted for specialized work such as refrigeration, controls, lift support, or electrical work, provided the prime contractor remains responsible for contract performance? Subcontractors are permitted but will remain under the Contractor’s responsibility. All personnel assigned to Subcontractors will be required to successfully gain base access.

24. Are lifts, ladders, roof hatches, fall protection anchor points, or other access equipment available on site, or must the contractor provide all access equipment? Government issued tools will not be accessible by the Contractor. Contractors will provide their own equipment and safety apparatuses.

25. Please confirm the total number of HVAC units covered by the contract and whether the requirement includes only Building 5730 or any additional associated spaces/equipment. Here are 4 HVAC system units labeled: “CU-3/DOAS-1”, “SSCU-1” for the COMM room 117, “CU-2/AHU-2”, and “CU-1/AHU-1”. All are dedicated to building 5730 only. HVAC systems include VAV boxes throughout.

26. Please clarify NAICS code for Solicitation SP060026R0399. Proper NAICS code for Solicitation SP060026R0399 is 561210.

27. Approximately how many repair orders were issued annually under prior service arrangements for Building 5730? If historical data is unavailable, can the Government provide an estimated annual repair order volume for pricing purposes? This is a new requirement, and no prior repair orders have been established. It is difficult to project repair order volume. Pricing requested in the Solicitation per the Worksheet should be pricing for hourly rates for repairs by technician.