QA 14Jun2010.docx
DOCX document 22 KB Posted
- Attached to
- Privatization of the Water Utility Sytem
- Solicitation number
- SP060010R0808
- Issued by
-
Defense Logistics Agency Energy
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0014.pdf | ||
| 2013.3.15_Revised_SF33.pdf | ||
| Amendment_0013.pdf | ||
| Amendment_0012.pdf | ||
| Amendment_0011.pdf | ||
| SP0600-10-R-0808_Amd 0010.pdf | ||
| Exhibit JE1 Subcontracting Plan.pdf | ||
| Amendment 0009 - SF 30.pdf | ||
| Amendment 0008 - SF 30.pdf | ||
| Amendment 0007 - SF 30.pdf | ||
| QA 21 Jun 2010.docx | DOCX document | |
| Amendment 0006 - SF 30.docx | DOCX document | |
| Amendment 0005 - SF 30.pdf | ||
| Admendment 0004 - SF30.pdf | ||
| Amendment 0003 - SF 30.pdf | ||
| Amendment 0002.pdf | ||
| Mar 10 - Final Industry Brief template.ppt | PPT presentation | |
| Amendment 0001_04 Apr 10.pdf | ||
| FBO secur access instructions.pdf | ||
| PublicNoticeofpre-proposalconf.doc | DOC document | |
| SP06010R0808_RFP EPA Version 3 Template Final Feb 2010.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 Page 3 of 3
Dover Air Force Base
PROSPECTIVE OFFEROR/CONTRACTOR QUESTIONS &
GOVERNMENT ANSWERS
June 14, 2010
Questions and Answers for Dover Air Force Base, DE SP0600-10-R-0808:
Q1: Recommend the contractor be permitted to keep some equipment on base, such as a backhoe, trench box, and truck or two, plus some repair inventory, to avoid having to go through the commercial gate in the event of an emergency. The contractor would need a garage or other space to store this equipment and some inventory. What would be available on the base?
A1: The Government may provide a reasonably-sized tract of land on-base for the UP Contractor to establish facilities to meet the contract requirements. The Offeror shall provide a description of the physical facilities and compound area required to support the utility system, and include the estimated costs in their proposal. The Government will try to make this tract of land as permanent as possible; however, changing installation mission and future base development plans may require relocation of the UP Contractor's facilities to elsewhere on the installation in the future. If the UP Contractor is required to relocate their facilities in the future, the Government will provide an alternate on-base tract of land.