This document is a request for Standard Form 330 submissions from architecture and engineering firms for design services. The Department of Veterans Affairs intends to award a firm-fixed-price contract for design of Electronic Health Record Modernization infrastructure upgrades at the St. Louis VA Medical Center Jefferson Barracks Division. The scope of work includes electrical, communication, and security infrastructure improvements across multiple buildings. The period of performance for design completion is 184 calendar days from notice of award. The construction budget limitation is $20 million. Firms must submit an SF 330 by May 4, 2021. A two-phase evaluation process will select a minimum of three firms for written responses. The top-ranked firm from this second phase will receive the solicitation and participate in negotiations. The contract is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses.
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A/E CONTRACT SUPPLEMENT B
PROJECT NUMBER 657-21-701JB
EHRM – Infrastructure Upgrades – St. Louis, MO (Jefferson Barracks Division)
SUPPLEMENT B (For Schematics, Design Development, Construction Documents, Construction Cost Estimate and Construction Period Services)
DESIGN TIMEFRAME: A/E shall deliver final construction documents No Later Than (NLT) 184 calendar days after Notice of Award.
CONSTRUCTION BUDGET/DESIGN LIMITATION: $20,000,000. A/E shall refer to the Design Within
Funding Limitations section of this document.
B1 SCHEDULE OF SERVICES:
I. INTRODUCTION:
The mission of the Veterans Affairs Saint Louis Health Care System (VASTLHCS) is to provide the highest quality health care to our nation’s veterans. In order to accomplish this mission, VASTLHCS’ Facility Engineering Service (FES) intends to partner with an A/E Firm on a project to make EHRM Infrastructure Upgrades at the Jefferson Barracks (JB) Division, St. Louis, MO 63125. The renovation will upgrade the facilities electric and IT to allow for the new Electronic Health Record Modernization (EHRM) system.
The A/E Firm must provide Basic Professional Services as delineated in the Scope of Work. As part of the Basic Professional Services, FES expects the following primary A/E disciplines to be included: Supervisor, VPIH, Architectural, Mechanical, Electrical, and Plumbing (Including Fire Protection).
II. SCOPE OF CONSTRUCTION PROJECT:
1. The scope of this project includes but not limited to the following infrastructure improvements:
a. Electrical (electrical panel upgrade, power (normal, emergency)), Bonding, UPS, Building
Management System interfaces, assess for new and upgrades to existing HVAC.
b. Reconfiguration, expansion and renovation of existing space (demo, new construction, finishes), renovation of existing Data Center (piping, exterior wall, interior wall for water proofing).
c. Communication infrastructure (new Data outlets, patch panels, upgrade to Cat 6A cable) in buildings as necessary, physical security upgrades, assess and upgrade fiber infrastructure backbone campus wide within buildings and between buildings, install diversified path to datacenter for WAN, and hazardous material abatement.
d. Project Building locations include: Buildings 1, 2, 3, 3T, 18, 23, 24, 25, 51, 51T, 52, 53, 53T, 55, 56, 57, 58, 59, 60, 60T, 75 and site.
III. SCOPE OF WORK FOR A/E:
1. Design Development:
a. The A/E shall make investigations necessary to thoroughly evaluate the area. All designs shall be in accordance with A/E Submission Instructions for Minor and NRM Construction Program, Program Guide PG-18-15, Volume C.
b. Upon completion of initial field survey and assessment, provide a comprehensive report of existing conditions and findings to VASTLHCS’ Facility Engineering Service. Report will include initial cost estimate for all work included in the EHRM – Infrastructure Upgrades – Jefferson Barracks Division project. This report will be considered the Design Narrative as referenced in ”B5 DESIGN REVIEW AND COMPLETION SCHEDULE” below.
2. Construction Document:
a. After the VAMC approves the A/E's design development, the A/E shall prepare construction documents necessary to accomplish the approved design development.
b. As part of the 100% design submission, the A/E shall provide a written synopsis describing the overall scope of the construction project as well as any pertinent information about the project that would assist potential bidders in preparing a comprehensive bid package. This synopsis is intended to be a general description of the project not to exceed two written pages in length.
c. The final design documents from a resultant contract will be subject to review and approval (by signature) of all members of an Integrated Project Team (IPT) consisting of medical center personnel. These individuals will be identified by the COR at the first design review meeting.
3. Solicitation Support Services: The A/E shall perform construction period services as detailed later in this scope of work. Construction Period Services will be included as Option Items to be exercised after completion of the design, in accordance with the Contract.
4. Functional Product:
a. It is important to emphasize that the A/E shall perform design development and detailed design work, and prepare detailed construction documents, keeping in mind that the end result is a completely functional and fully operational system.
b. VPIH Survey: The A/E Firm will complete a survey, to include testing, identifying any and all asbestos, lead, and mold containing materials within the project area. This project will remove all lead, asbestos, and mold in areas being renovated.
c. All spaces within the scope of work must be designed according to applicable codes, standards, and the TIL.
d. The A/E shall submit a basis of design narrative (15%) and design plans (35%, 65%, 95%, 100% Contract Docs for Bidding, and Release for Construction Set) specifications, submittals schedule, estimates and other documentation in accordance with the “B4 DESIGN DELIVERABLES” section of this Supplement B. The construction work will be performed under a separate Firm-Fixed-Price contract awarded by the VA. As a result, the Construction Documents must conform to the estimated Total Construction Cost Price, not including any contingencies, and convey the entire construction work completely and clearly, such that any bidder can produce an accurate bid without surveying the work site.
e. The A/E will also participate in the VASTLHCS Pre-Construction Risk Assessment to determine the requirements for Infection Control, Interim Life Safety Measures, occupational safety and health, patient safety, public safety, security controls for physical and logistical access, and environmental controls and limitations on vibrations, noise, and disruptions to operations and utilities. The results of these assessments will be included in documentation submitted by the A/E pursuant to, and inclusive of, the Construction Documents. The VASTLHCS Pre-Construction Risk Assessment document will be provided to the A/E. This document will need to be added to the specifications.
f. Prior to submittal of a response to this proposal the A/E shall meet with the Contracting
Officer’s Representative (COR) at the proposed project site to review the scope of services and the project goals. The COR will provide A/E with a copy of the latest Facilities Condition Assessment (FCA) applicable to this project.
g. Overall site plans will be provided as a Reference Drawing with Room Numbers showing the areas within the project boundary.
h. The C&A requirements do not apply, and that a Security Accreditation Package is not required.
5. Sustainability Requirements:
a. Design shall comply with the most current version of the VA Sustainable Design Manual at time of award found on the VA technical Information Library https://www.cfm.va.gov/til/sustain.asp
b. The following deviations are allowed: None
c. GUIDING PRINCIPLES CHECKLIST: AE shall complete and submit the appropriate Federal Energy Management Guiding Principles Checklist https://energy.gov/eere/femp/downloads/guiding-principles-checklists-new-construction-and-modernization-and-existing
IV. A/E FEE DETERMINATION:
The A/E is to present their fee proposal for evaluation and negotiation in the following format:
1. Submit completed Price Proposal on NCO 15 Form 10-6298 (SOW Attachment 32). The spreadsheet is to have the work broken out in hours by position, by discipline and by design phase. Include a list of the number of drawings required for each design phase broken out by drawing type per discipline. Include a summary of the foregoing with the number of hours required for each drawing type and each major task. The spreadsheet will be used to facilitate review and comprehension of work effort and document fee. Submit the electronic file of the spreadsheet upon request.
https://www.cfm.va.gov/til/sustain.asp https://energy.gov/eere/femp/downloads/guiding-principles-checklists-new-construction-and-modernization-and-existing https://energy.gov/eere/femp/downloads/guiding-principles-checklists-new-construction-and-modernization-and-existing
2. Include a letter of understanding with the price proposal that presents a detailed understanding of the Supplement B. The letter of understanding shall include an analysis of the fee included and excluded from 6% fee limitation as compared to the estimated Construction Budget.
3. Reproduction and delivery costs of Design Review Material and other direct costs, such as travel costs, are included in the costs for each design phase and are not reimbursable. The costs of Bidding reproduction, delivery and other direct costs in accordance with the “Milestone Submittal Requirements” are included in the CD Phase. Unused site visits will be deducted at the end of the contract.
4. Provide an outline of the Quality Assurance/Quality Control actions that your firm will take during the design process and construction period. Monthly QA/QC reports are required, including actions taken to maintain project quality, schedule and budget, and will be submitted with project invoices using the NCO 15 invoice format.
5. Correction of A/E’s Errors and Omissions, including required site visits to ascertain remedial action, is included in scope of services at no additional cost to the VA.
V. REPORTS, DRAWINGS, SPECIFICATIONS AND SCHEDULES:
1. Kick-Off Meeting:
a. An initial kickoff meeting will be held with the Contracting Officer and local staff. This meeting will take place within two weeks after Notice of Award. This meeting will be intended to provide an onsite familiarization with the project. The VA will provide workload data and any available As-Built drawings. Any available As-Built drawings, electronic or hard copy, and supporting documentation will be made available to the A/E at the Kick-Off meeting. Lead and Asbestos Hazardous Material Surveys within the project limits will be made available to the A/E. Please note that all As-Built Drawings and documents furnished by VA St. Louis are for informational purposes only, and it is the responsibility of the A/E firm and contractors to verify existing conditions to fulfill their contract obligations.
b. A/E Design Submissions shall comply with the VA A/E Design Submission Requirements as found in the VA Technical Information Library (TIL). The VA will provide comments and guidance following each design review session. All meetings shall be held at Building 57, Engineering Conference Room, 1 Jefferson Barracks Drive, MO.
2. Schematic Design:
a. The A/E firm shall conduct an onsite review of the existing locations of the various functions that will be relocated to and/or remodeled within the space to help understand the needs of the departments. They shall meet with the representatives of these departments to review and compare the VA design guides to the specific departmental needs. This will serve as an opportunity for the A/E to gain a further understanding of the direction the facility wants the project to go.
b. After meeting with the departments, the A/E shall prepare a minimum of three separate schematic layouts of the space for review. The A/E shall provide pros and cons for each option. The A/E shall present these options to the COR who will in turn present them to the departmental leads and senior leadership. The VA will select the preferred option for the design. Space layouts shall meet current VA Space Planning Criteria’s (7610 Building Design Guide) and be in compliance with the Uniform Federal Accessibility Standards (UFAS), and VA Barrier Free Design Guide (PG-18-13).
c. At the Schematic Design Review Meeting, the A/E should be prepared to discuss the scope of the project, provide examples of current VA standard room layouts, site drawings identifying the project area showing a basic schematic layout of the various functions, a timeline for design and a brief construction summary. The A/E shall record the minutes of the meeting to document the thoughts and concerns of the facility.
3. Design Development:
a. The A/E firm shall make investigations necessary to thoroughly evaluate the conditions of the existing space. There will be a systems redesign for this process bring the SPS space up to current design standards. Including but not limited to any energy efficiency improvements available for the application. All designs shall be in accordance with A/E Submission Instructions for Minor and NRM Construction Program, PG-18-15, Volume C (See SOW Attachment #1).
b. Mechanical, plumbing, electrical, and fire and safety systems must meet current codes and standards, including VA Standards. All new space and utilities will be designed to meet the Interagency Security Committee’s and other relevant physical security guidelines.
4. Construction Documents:
a. The A/E firm shall complete such further investigations to develop the accepted design development documents into working drawings and specifications for issuance through the competitive bid process.
b. The A/E firm shall provide a complete construction plan detailing all phases and sequencing of construction to minimize the impact on the facility.
c. In most instances, the VA Master Construction Specifications will be edited and incorporated in the project specifications. However, in those instances where corresponding VA Master Construction Specifications are not available, the A/E shall develop the specification for incorporation into the project specifications. It is required that the A/E design in accordance to VA guidelines as these guidelines supersede any other industry guidelines. It is important to note that all specification sections are to be thoroughly edited to maintain uniformity of formatting and structure. All spec writer notes must be remove.
d. Working drawings and specifications shall provide for construction within the National Fire Protection Association Code, VA Standards, and other applicable national codes.
e. The A/E firm shall provide a clause in the specifications indicating method by which a contractor will provide information to the firm to allow the firm to provide as-built drawings upon completion of construction.
f. A/E will also package documents in files no larger than 10 MEG or less.
5. As-Built Drawings:
a. All electronic files shall be sent to the VA and subject to review and approval by the VA. All electronic files sent to the VA shall be in packages no larger than 10 MB for internal distribution. BIM models may be sent separately via CD or an approved file sharing system and be as large as required. Submit one full size set on sheets of mylar. The A/E firm shall submit one (1) complete set of drawings provided on disc using AutoCAD Release 2019 or later version, and also .pdf format. Models should be provided in Revit 2019. The A/E shall follow the VA Standard CAD format for layering in accordance with the “B3 DESIGN
CRITERIA” section of this Supplement B.
b. Record As-Built Drawings shall show any and all As-Built conditions, and include, but not limited to, any changes to the 100% Construction Documents, RFI’s, Change Orders, modifications, latent conditions, equipment information, and contractor notes/comments.
c. The A/E firm shall submit said As-Built within 30 days of submitted red-line as-built drawings.
6. Reproduction of Drawings and Specifications:
a. The VA St. Louis Health Care System currently utilizes AutoCAD 2019 and Revit 2019. Submit all electronic drawings to support this format. All other supporting documents shall be prepared in MS Word and in accordance with the “B4 DESIGN DELIVERABLES” section of this Supplement B. If CAD technology (AutoCAD) is used, then all CAD files and supporting electronic files shall be submitted to the VA, including but not limited to external references, images, or other documents. All external references shall be linked via “No Path” or
“Relative Path” and it is preferred that images are inserted into the .dwg file. If BIM technology (Revit)is used, then all BIM models and corresponding BIM files shall be submitted to the VA. BIM files shall be linked via “No Path” or “Relative Path” and it is preferred that images are inserted into the file. BIM model names, workset names, and sheet names shall conform to the naming standards set forth in any supplied As-Built documents..
b. AutoCAD files and .pdf files shall be generated and submitted with each submittal and conform to TIL standards. The name of each electronic sheet (.pdf & .dwg) shall be the VA Project Number, sheet number, and sheet name. For example: 657-21-701JB_01-GI- 001_COVER. Comprehensive .pdf sets shall also be submitted and include the VA Project Number in the description. All drawings in the Release for Construction Set of Contract Documents and Record Drawings drawing sets shall be signed and sealed by the Architect and/or Engineer of record.
c. See the Milestone Submittal Requirements table in this document for requirements at each submittal unless noted otherwise. All electronic files sent to the VA shall be in packages no larger than 10 MB for internal distribution. BIM models may be sent separately via CD or an approved file sharing system and be as large as required.
d. One DVD/CD-ROM computer disk containing all reports, specifications, documents and drawings will be required for each milestone submission. All necessary reports, cost estimates and other documents shall be prepared in accordance with all applicable portions of the A/E Submission Instructions, Program Guide PG-08-15, and Volume C. The VA reserves the right to require immediate delivery of the A/E’s digital files to the VA at any time.
e. Specifications should be provided in both hardcopy and electronic form.
f. One half size set of drawings and one set of specs shall be sent to the Contracting Officer at the 95% and 100% construction document review periods.
g. At the 95% and 100% construction document review periods, the specifications should have all revisions incorporated providing a “clean” set of specifications for review and approval.
VI. PROMOTION OF FULL AND OPEN COMPETITION:
1. A/E agrees to prepare specifications that are not competitively restrictive or proprietary.
Specifications will be based on performance criteria when possible and will not use a product by a specific manufacturer, except as a basis of design.
2. If an occasion arises that use of a product by a specific manufacturer is necessary, the A/E will provide a justification including:
a. Why the particular manufacturer/product must be used or why a performance specification cannot be written (proprietary design, etc.).
b. The evaluation criteria of alternate manufacturer’s product that must be met to be considered equal. These evaluation criteria will be used to accept the alternate manufacturer’s product as equal to the specified product. These evaluation criteria shall be comprehensive to ensure an equal product is supplied meeting contract requirements.
c. In the event it is necessary to pre-qualify major components, the A/E will advise the Contracting Officer of such, so that the necessary action can be taken to establish a Qualified Products List.
d. In addition to requirements of these special provisions, a certification will be provided stating the specification solicitation is not restrictive; it has been written to provide full and open competition; and will list at least three manufacturers who can supply the specified major components or systems of the project.
VII. OI&T INFRASTRUCTURE STANDARD FOR TELECOMMUNICATIONS SPECS
1. The current version for this standard is version 3.0, dated August 21, 2020 (https://www.cfm.va.gov/til/dguide/OIT-InfrastrucStdTelecomSpaces.pdf). The design for this project at VA St. Louis Health Care System Jefferson Barracks Division, must meet the Campus Support Center (CSC) requirements of the Infrastructure Standard for Telecommunications Spaces.
2. The Infrastructure Standard for Telecommunications Spaces (The Standards) serves as the master reference document of criteria for Department of Veterans Affairs (VA) facility Information Technology (IT) support infrastructure. It defines the technical requirements necessary to maintain optimum reliability and efficiency within VA facilities and computing https://gcc01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cfm.va.gov%2Ftil%2Fdguide%2FOIT-InfrastrucStdTelecomSpaces.pdf&data=04%7C01%7C%7Ca9f3597357224afeda3b08d8b0ce369d%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C637453747004265160%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=upFd7zIaj4i1eWvP3laD4gKUUMLbOjV2dwgw7ZnVnNk%3D&reserved=0 centers. IT Support Infrastructure is defined as all passive telecommunications and information technology equipment and supporting physical space and equipment.
3. This standard is owned and maintained by Solution Delivery (SD) Data Center and Infrastructure Engineering and questions or concerns should be directed to the following email group: OIT ITOPS SD Data Center and Infrastructure Engineering.
4. Users must ensure their use of this technology/standard is consistent with VA policies and standards, including, but not limited to, VA Handbooks 6102 and 6500; VA Directives 6004, 6513, and 6517; and National Institute of Standards and Technology (NIST) standards, including Federal Information Processing Standards (FIPS). Users must ensure sensitive data is properly protected in compliance with all VA regulations. Prior to use of this technology, users should check with their supervisor, Information Security Officer (ISO), Facility Chief Information Officer (CIO), or local Office of Information and Technology (OI&T) representative to ensure that all actions are consistent with current VA policies and procedures prior to implementation.
VIII. MISCELLANEOUS:
1. The existing drawings for Jefferson Barracks Buildings included within the limits of this project will be provided to the A/E consultant For Reference Only. As-Built and Record Drawings have been found to not show the actual location, quantity, etc., of all building features and should only be used as a general guide. The A/E shall verify the existing drawings to the extent necessary for completion of construction. Files in *.dwg or*.rvt format will be provided to the A/E if those files are available for distribution.
2. The VA COR will assist the A/E when site inspection procedures impact the functioning of any of the building utility systems, services or health care operations. Spaces with controlled access will require a member of the VA staff to continuously escort the A/E Consultant whilst accessing the space. As a result, the A/E must coordinate with VA Engineering to identify where the A/E is intending to perform site visit surveys at least fourteen (14) days in advance of any site visit.
3. Some utility systems, services or health care operations are critical, and if a disruption is required, it must be executed outside of normal working hours. Normal working hours are Monday through Friday, 7:30 a.m. to 4:00 p.m. This schedule must be coordinated with the VA COR fourteen (21) days in advance.
4. The A/E is responsible for recording the minutes of all meetings with the VA. The format of the meeting minutes shall be subject to prior approval from the VA COR. The draft meeting minutes shall be distributed for review and comment within one working day following the meeting to the COR, who will in turn distribute the same to each invited VA-attendee as required. Meeting minutes are loaded to Submittal Exchange or equal web system. The VA shall have (2) working days upon receipt of the meeting draft documents to make any additional comments or corrections. The final meeting minutes shall be issued within (3) calendar days after the meeting to the VA CO and the COR.
5. Coordination of each submittal will be fully documented by the A/E. Using industry standard methods, the A/E will collect, document and resolve all comments and consolidate them into a usable format. The resolution of each comment requires the COR and commenter’s concurrence. For each design submittal, the A/E will conduct a comment review meeting where each comment received will be either:
a. Concurred as Written
b. Non-Concurred; Request Discussion
c. Requires Clarification
6. At the conclusion of the comment review meeting, the A/E will provide meeting minutes showing the status of each comment made. The resolution will be incorporated into the project documents (drawings, specifications, etc.) prior to the next submittal. Any comment resolutions not included in the project documents will be provided to the CO and COR with explanation as to why each was not included.
IX. DESIGN FUNDING LIMITATION:
1. In accordance with FAR 52.236-22, Design within Funding Limitation (APR 1984), the estimated
Total Construction Contract Price for this Project proceeding into CDs is not to exceed
Construction budget listed above not including any Project Contingencies, VA Furnished/
Installed Medical Equipment, VA Furnished/Installed FFE or Professional Service Fees. The A/E is responsible for designing the Project within the estimated total Construction Contract Price for the Design Development and Construction Document phases of this Project. If, at any time, the
A/E determines that the design’s construction cost (excluding contingencies) will exceed the
Total Construction Contract Price (TCCP) the A/E shall immediately inform the Contracting
Officer in writing. Such written notification shall include the reasons why the A/E believes the
TCCP will probably be exceeded and shall offer proposed solutions to reduce the project cost to be within the TCCP.
X. PROBABLE CONSTRUCTION COST ESTIMATE:
1. Cost estimates must be prepared IAW VA Manual for the Preparations of Cost Estimates, located on the TIL. They must provide sufficient detail to identify the cost of project systems and components as appropriate for the stage of development of the design in the SD, DD and CD Phases. Update construction cost data with each submittal review milestone. Costs presented shall be broken down sufficiently to allow for direct comparison cost with the contractor’s proposed cost.
2. VA Form 10-6238, Estimate Worksheet (SOW Attachment 33): This form serves two purposes:
a. To show the division of cost between labor and material for each cost item; and
b. To extend the level of detail of an estimate beyond square foot cost summaries.
The estimated costs shall include all labor, materials, mobilization, overhead, insurance, and applicable contractor markup. A/E may utilize their estimate worksheets if approved in advance by the VA.
3. Electronic copy of estimate shall be provided with each submittal. Estimate detail shall include a breakdown by Project specification division number for labor and material broken out by quantity and unit cost for each type of material or equipment, including equipment rentals.
General Division shall include costs associated with project duration. Include Summary of estimate by Division Number with each submittal.
4. Providing the estimates as "lump sum" or "allowance" figures in the Construction Documents will not be acceptable. For the Schematic estimate, a 15% total contingency allowance is allowable. For the Design Development estimate, a 10% total contingency allowance is allowable. Contingency allowances are not permitted in the final Construction Documents Estimate. Construction cost estimating shall correspond with the work shown in the drawings and be commensurate with the degree of detail shown in the drawings. Construction cost estimating shall also include all elements within the contractor’s bid; such as reasonable overhead and profit and fees across all tiers, insurance, taxes, bonds, hazardous abatement and any other such items. Costs will include itemization of the following:
a. Number of labor hours by trade (or crew1)
b. Labor dollars by trade (or crew1)
c. Material quantity
d. Material dollars
e. Equipment Rental and associated cost
f. Any other Direct cost not associated with work to be performed by a specific trade
1 When using a crew, instead of a trade, then use a crew code and include a schedule, or legend, of only the crew codes applied, showing each type of trade, each hourly rate, and each trade person quantity.
5. Some costs for General Conditions or General Requirements may also be required in the project estimate whenever these costs can be shown to be direct costs as opposed to indirect (overhead) costs. For example, if it is common practice for the Contractor to use a rented negative air HEPA machine and consumable plastic sheeting to comply with the Infection Control Risk Assessment (ICRA) requirements, then the associated costs would be direct material and labor costs. In addition, if the Construction Documents require the Contractor to perform fulltime on-site superintendence solely dedicated to the construction project, then these would be direct labor costs. Furthermore, whenever the Contractor is to provide on-site factory-authorized training to the VA staff, then the travel, lodging, meals and incidental costs would be direct costs. If the Construction Documents require the Contractor to perform housekeeping services, then the associated costs would be direct costs. If the Construction Documents call the Contractor to execute specific safety and OSHA activities, then the costs associated with these activities would be direct labor and material costs; however, OSHA activities performed by the Contractor by its staff at its home office and not specified in the Construction Documents, then such associated costs would be indirect costs and would not be included with the project estimate.
B2 INDUSTRIAL HYGIENE SERVICES:
I. INDUSTRIAL HYGIENIST TASKS:
For the work scope described in B1 SCHEDULE OF SERVICES above Hazardous materials (Asbestos, Lead, Mold, heavy metal and etc…) ARE included in this contract. Lead and Asbestos Hazardous Material Surveys within the project limits is attached to this SOW for consultant’s reference. Hazardous Materials site visits are to have 7 conferences and inspections.
1. Architect/Engineer Responsibilities:
a. Determine if asbestos, lead or mold is present. If found, design a method for abating/remediating all asbestos containing materials, lead containing materials and mold contaminated items impacting this project.
b. Determine location of asbestos, lead and/or mold contamination, and any water and moisture damage. Work with the I.H. to uncover and assess hidden areas.
c. For mold contamination, determine entry point of water infiltration
d. For asbestos and lead contamination, determine the extent of abatement required to eliminate all impacts to this project.
e. Review the I.H. Report.
f. Produce a written report compiling all necessary information.
II. VA PROFESSIONAL INDUSTRIAL HYGIENIST (VPIH):
The A/E will retain a specialist in VPIH services to provide sufficient oversight of the abatement process.
The following VPIH services will comply with federal, state and local laws and regulations:
1. Review of Contractor Provided Asbestos Abatement Plan: The VPIH is responsible for reviewing and approving the Contractor's Professional Industrial Hygienist (CPIH) work plans. Provide comments and recommendations to ensure VA personnel and/or patients are not exposed to asbestos fibers.
2. Provide Air Sampling: Provide air sampling of the construction site to verify that no asbestos fibers were released during the asbestos abatement activities. Field work and sampling activities shall be performed by trained personnel under the direction of a licensed Industrial Hygienist or Board Certified Microbial Consultant.
3. Provide Abatement Oversight: Provide oversight of the abatement contractor to ensure compliance with abatement laws and regulations.
4. Provide Final Clearance: Ensure the contractor has completed the abatement work required and provide final clearance that the abatement work is complete and there are no impacts to the Medical Center.
5. Provide Final Report: Provide a final report showing daily logs, sampling results and collected documents.
III. All work shall be in compliance with applicable laws, regulations and procedures published or issued by federal, state and local regulatory agencies for the abatement and control of hazardous materials.
B3 GOVERNMENT FURNISHED DESIGN CRITERIA:
I. The A/E shall design in accordance with the requirements of the following VA publications, which can be found in the VA Tech Info Library (TIL) at http://www.cfm.va.gov/TIL/ :
-VA Master Construction Specifications, Program Guide, PG-18-1;
http://www.cfm.va.gov/TIL/spec.asp
-VA Design and Construction Procedures, PG-18-3; http://www.cfm.va.gov/TIL/cPro.asp
-VA Standard Alert – SA-017 R01 OIT Infrastructure Standard for Telecommunication Spaces
-VA Infrastructure Standard for Telecommunications Spaces Version 3.0 August 21, 2020
-VA Standard Details, PG-18-4, Volumes 1, 3, 4, 5, 6 & 7; http://www.cfm.va.gov/TIL/sDetail.asp
-VA Equipment Guide List, PG-18-5; http://www.cfm.va.gov/TIL/equip.asp
-VA Design Manuals for the applicable disciplines, PG-18-10; http://www.cfm.va.gov/til/dManual.asp
-VA Design Guides for Graphics, PG-18-12; http://www.cfm.va.gov/til/dGuide.asp
-VA Barrier Free Design Guide, PG-18-13; http://www.cfm.va.gov/TIL/accessibility.asp
-VA Environmental Compliance Manual, PG-18-17; http://www.cfm.va.gov/til/spclRqmts.asp#EC
-VA Design Alerts and Quality Alerts; http://www.cfm.va.gov/til/alert.asp
-VA CAD Standards; http://www.cfm.va.gov/til/projReq.asp#cad
-VA Design Review Checklists; http://www.cfm.va.gov/til/projReq.asp#reviewCheck
-VA AE Design Submission Requirements; http://www.cfm.va.gov/til/aeDesSubReq.asp
-Office of Construction & Facilities Management Design Manual, Architectural Design Manual, http://www.cfm.va.gov/til/dManual/dmARhosp.pdf
-VA Medical Center Memorandums (“MCM”) (Request From COR)
II. Other design criteria may be required to meet specific requirements of the design work scope that are not listed above or are not available on the VA Office of Facilities web site. The A/E is responsible for obtaining and complying with all such criteria.
B4 DESIGN DELIVERABLES:
I. DISTRIBUTION OF A/E MATERIALS TO THE VA:
The A/E shall provide the means necessary to submit large electronic files to VA recipients. Files over 10 MB may not be transmitted through the VA email system. File transfer protocol websites (FTP) are prohibited for use by VA employees. Provide Submittal Exchange or equal web system. Service should be provided through construction period services and allow use by construction contractor.
1. Reproduction and delivery costs of Design Review Material in accordance with the “Milestone Submittal Requirements” are included in the costs for each design phase and are not reimbursable.
2. Bidding and Construction Material reproduction and delivery costs in accordance with the “Milestone Submittal Requirements” are included in the CD Phase and are not reimbursable.
3. The A/E shall provide a “Stand Alone Certification Memo” to the VA with the 65% Contract
Documents for Bidding. (see attached format).
http://www.cfm.va.gov/TIL/ http://www.cfm.va.gov/TIL/ http://www.cfm.va.gov/TIL/spec.asp http://www.cfm.va.gov/TIL/spec.asp http://www.cfm.va.gov/TIL/cPro.asp http://www.cfm.va.gov/TIL/cPro.asp http://www.cfm.va.gov/TIL/sDetail.asp http://www.cfm.va.gov/TIL/sDetail.asp http://www.cfm.va.gov/TIL/equip.asp http://www.cfm.va.gov/TIL/equip.asp http://www.cfm.va.gov/til/dManual.asp http://www.cfm.va.gov/til/dManual.asp http://www.cfm.va.gov/til/dManual.asp http://www.cfm.va.gov/til/dGuide.asp http://www.cfm.va.gov/til/dGuide.asp http://www.cfm.va.gov/TIL/accessibility.asp http://www.cfm.va.gov/TIL/accessibility.asp http://www.cfm.va.gov/til/spclRqmts.asp#EC http://www.cfm.va.gov/til/spclRqmts.asp#EC http://www.cfm.va.gov/til/alert.asp http://www.cfm.va.gov/til/alert.asp http://www.cfm.va.gov/til/projReq.asp#reviewCheck http://www.cfm.va.gov/til/projReq.asp#reviewCheck http://www.cfm.va.gov/til/aeDesSubReq.asp http://www.cfm.va.gov/til/dManual/dmARhosp.pdf
4. Record Documents (“As-Built”) shall be submitted to the VA immediately prior to final acceptance of the project by the VA. Record Documents shall conform to the VA standard requirements including originals and record specifications incorporating all of the actual finished conditions, project revisions/amendments and products. Record Document Material reproduction and delivery costs in accordance with the “Milestone Submittal Requirements” are included in the CPS Phase and are not reimbursable.
II. MILESTONE SUBMITTAL REQUIREMENTS (Refer to following page):
Note 1: “.orig” indicates digital file in the document’s original file format i.e. “.doc”, “.rvt”, “.dwg”, “xls”, etc.
Note 2: Letter size reports may contain 11” x 17” drawing or exhibit pages tri-folded to letter size as required.
Note 3: Letter size (8.5” x 11”) submittal documents less than or equal to 25 pages may be stapled, all other letter size documents shall be bound with a Cover Sheet containing the Project information, date and Table of Contents.
MILESTONE SUBMITTAL REQUIREMENTS
Number of Required Submittal Documents
Submittal Description Digital File Letter Drawings
.orig .pdf Half Size Full Size Mylar Design Narrative Submittal:
Condition Assessment 1 Cost Estimate 1 1
35% Schematic Design Submittal:
Reports & Calculations 1 Outline Specifications 1 1
Drawings 1 1 1 1 Existing Condition Record Drawings 1 1
65% Contract Document Submittal
Reports 1 1 Draft Specifications 1 1
Stand Alone Certification Memo 1 1
95% Contract Document Submittal
Reports 1 1
Specifications 1 1 Drawings 1 1 2 1
100% Contract Documents for Bidding
Final Cost Estimate 1 1 Reports & Calculations 1 1
Specifications 1 1 Drawings 1 1 2 1
Release for Construction Set (Incorporate all Solicitation Amendments):
Final Cost Estimate 1 1
Reports & Calculations 1 1 Specifications 1 1
Existing Condition Record Drawings 1 1 1 1
Record Document Submittal:
Final Project Construction Cost 1 1
Operation & Maintenance Manuals 1 1 2 Record Specifications 1 1 2
Record Drawings 1 1 2 1
B5 DESIGN REVIEW AND COMPLETION SCHEDULE:
I. The A/E shall perform Design work according to the schedule shown below. The A/E is also responsible for following specification Section 01 32 16.10 Architectural and Engineering CPM Schedules, which is located in SOW Attachment 4 - EHRM Design Schedule (CPM). If a due date on the timeline below falls on a Holiday or Weekend, the submittal shall be due the following business day. The remaining timeline will not be shifted to accommodate Holidays or Weekends.
Design Phase Phase Duration (Days1)
Calendar Days from
NOA
Notice of Award 0 0
Project Design “Kick-off” Meeting 1 1
Design Narrative 14 15
Design Narrative Discussion via Conference Call 7 22
35% Schematic Design Submittal and Asbestos, Lead and Mold testing reports.
31 53
35% Schematic Design Review Meeting 102 63
65 % Construction Documents 31 94
65% Joint Review 102 104
95% Construction Documents 30 134
95% Construction Documents 72 141
100% Contract Documents Issued for Bidding 24 165
100% Contract Document Submittal Review 72 172
Contract Documents Issued for Bidding: 12 184
Release for Construction Set of Contract Documents TBD3 Immediately following award of contract
Record Document Submittal: TBD3 Within 30 calendar days of receiving red lined drawings
Note 1: Number of Days is calendar days.
Note 2: Review Meetings occur on noted number of days after submittal of phase documents.
Note 3: “TBD” is To-be-Determined.
1. The Contracting Officer (CO) may schedule additional Design Reviews as necessary when it is determined by the CO that such reviews are required for satisfactory completion of A/E contract requirements. The A/E will be reimbursed for additional review meetings in accordance with the rate sheet, unless it is solely determined by the CO that such additional reviews were requested by the A/E, or were required due to the A/E’s failure to meet contract requirements.
2. The A/E is responsible for recording the minutes of all meetings. The format of the meeting minutes shall be subject to prior approval from the VA COR. The draft meeting minutes shall be distributed for review and comment within one working day following the meeting to the COR, who will in turn distribute the same to each invited VA-attendee as required. Notification by email to the COR that the draft documents are available on Submittal Exchange or equal web system, is the preferred method. The VA shall have (2) calendar days upon receipt of the meeting draft documents to make any additional comments or corrections. The final meeting minutes shall be issued within (3) calendar days after the meeting to the VA CO and the COR.
3. Milestone review minutes shall comply with the requirements for meeting minutes, except that two days shall be added to each response period. In addition, the submitted milestone review drawing mark-ups by the VA and any review meeting comments shall be described in a tabular form with the comment (listed by discipline), comment originator, partly responsible for responding to comment, and a column indicating whether comment was incorporated into design documents. If comment was not incorporated or only partially incorporated, provide an explanation for the action.
4. The interim and final documents (SD, DD and CD) from this contract will be subject to review and approval (by signature) of all members of an Integrated Project Team (“IPT”) consisting of Medical Center personnel. These individuals will be identified by the COR by the first design review meeting. The A/E shall prepare a title sheet for each submission and phase as appropriate to receive approval signatures from members of the IPT. The COR will provide A/E with a copy of the Memorandum identifying IPT members.
B6 SCHEMATIC REVIEW SUBMISSION (35% REVIEW):
I. SPECIFICATIONS:
1. Submit an index of all VA Master Construction Specification sections intended for use. Include a brief description of any A/E originated sections to be used.
2. A/E shall obtain the VA Master Construction Specifications and any other VA Technical Documents at http://www.va.gov/facmgt.
II. ARCHITECTURAL:
1. Submit as a minimum, a layout for each project. Include fixed equipment at a scale not less than
1/8” =1’ 0”. Submit ¼” – 1’ 0” scale floor plans of special rooms, to show layout and identification of equipment. Include elevation views and or renderings as necessary to allow end users to decide which concept they desire to be developed.
http://www.va.gov/facmgt
2. Show schematic sections, as needed, to define the building and/or equipment concepts. Include field verified locations of existing or remaining details.
3. Show roof and penthouse plans if required.
4. Show legends that as a minimum reflect all items denoted on drawing at this submission.
III. HEATING, VENTILATION, AND AIR CONDITIONING:
1. Submit, as a minimum, outline plan drawings showing HVAC replacement unit locations, sizes of connection lines to existing services, and any lines to be removed.
2. Provide a written description of the replacement HVAC unit considered for the project and how it will be connected to the existing system to justify final system selection.
IV. PLUMBING:
1. Submit, as a minimum, outline plan drawings showing main water line locations feeding the project boundary, compressor locations, sizes of main lines, including drains, points of connection to existing piping, all new piping and piping to be removed.
V. ASBESTOS, LEAD AND MOLD:
1. If any areas are identified as containing hazardous materials, show areas of suspected Asbestos
Containing Material (ACM), lead and mold abatement required. Show quantities that will require abatement for each. Lead may be lead paint, lead shower pans, lead lined walls, lead lined doors, etc.
VI. ELECTRICAL:
1. Submit, as a minimum, floor plan showing new and existing panel locations and sizes. Indicate point of connection to existing distribution centers.
VII. PHASING:
1. Submit, as a minimum, drawing number indicating a separate phasing drawing.
2. Provide a written description of each Phase.
VIII. COST ESTIMATES:
1. A/E shall submit a construction cost estimate simultaneously with the drawings for this project at each project submission.
2. This estimate shall show the cost of construction which would be expected to be reflected by the Construction Contractor’s bids, if the bids were submitted on the same date as the estimate.
The level of detail for this estimate shall be consistent with the degree of completeness of the drawings being submitted. Simply stated, this means that if a construction element is shown, it must be priced; if it is shown in detail, it must be priced in detail. For detailed elements, “lump sum” or “allowance” figures will not be acceptable.
B7 SOLICITATION SUPPORT SERVICES:
I. AE shall provide solicitation support services during the construction period’s solicitation phase.
1. Pre-bid site visit to include meeting and project walk around. This is the meeting where contractors are invited to the job site to visually inspect the construction site in order to accurately develop a construction bid package.
2. The AE shall be available during this entire site visit to assist the VA in answering any contractor questions. All questions shall be logged by the AE and will be submitted in writing by the contractor to the Contracting Officer. Responses may not be provided verbally onsite.
II. Answer any technical questions/requests for information (RFI) received from contractors over the duration of the solicitation, including questions asked during the site visit.
1. Questions from contractors may come at multiple times and cover several or a few questions over the course of the solicitation period. Technical question responses will be provided to the Contracting Officer who will distribute the information via amendment to the solicitation.
2. Answers to RFIs will be required from the AE within five (5) calendar days of the date the questions are sent to the AE from either the project COR or CO. An alternate response period may be submitted for review, however, unless approved by the CO and COR, the AE is required to comply with the five (5) calendar day requirement.
3. Throughout the solicitation period, the AE shall provide addenda as necessary if required to revise specs and drawings.
III. In response to any technical questions and/or addenda issued during the solicitation period, the AE shall provide any final revisions to the 100% FC CD as part of the construction contract. These documents shall be labeled Final Construction Documents.
B8 STRUCTURAL ECONOMIC ANALYSIS:
I. A structural economic analysis IS required with regard to this contract.
B9 STRUCTURAL/SEISMIC ANALYSIS:
I. A structural/seismic analysis IS required with regard to this contract.
B10 CONSTRUCTION PERIOD SERVICES:
I. A/E firm shall provide such construction period services to allow the VA to monitor the contract on a daily basis with adequate support from the A/E firm. The items of support shall include, but not be limited to:
1. Review of all technical submittals, shop drawings and other technical correspondence. All submittals and shop drawings shall be reviewed within two weeks of receipt.
2. The A/E will provide and maintain a Submittal Exchange or equal web system that will be accessible to the VA staff assigned to the project. This site shall be used throughout the duration of the project during both design and construction for meeting minutes and design reviews during the design phase and used by A/E, COR, Contracting Officer and construction contractor during construction phase to upload: submittal reviews, meeting minutes, construction daily logs, etc.
3. Provide advice and consultation on RFIs raised by the VA or the contractor on technical matters.
Provide additional design and sketches as necessary should issues arise with the constructability of the initial design. A/E shall respond to raised RFI’s within (7) calendar days after submission of RFI by VA or the contractor.
4. Provide cost estimates as necessary to assist in negotiating any changes to the contract.
II. Modification Requests:
a. Modification requests shall be submitted within seven (7) calendar days of submittal to the A/E.
This includes the review of the contractor’s change order/modification proposal for construction change orders, as well as the formulation of an IGCE for the modification, as requested. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.” All documents in any of the electronic formats listed above. Note - If major modification, VA will provide additional time and document format guidance.
III. VPIH oversight services estimated at 30 calendar days ARE required with regards to this contract.
B11 SITE VISITS:
I. A/E firm shall provide representatives to make periodic site visits during the construction to provide additional support to the VA in managing the contract.
II. Site visits during the Construction Period Services (CPS) as outlined in the original contract ARE required with regard to this contract. Site visits shall be at a fixed cost per site visit.
1. Pre-Bid Visit: Provide one (1), scheduled through the Contracting Officer.
2. General Site Visits during construction: Provide six (6).
3. Final inspections, at completion of project and/or at completion of any phase where the VA must accept work done by the contractor. A final punchlist shall be conducted by all design trades. The cumulative findings shall be combined into one final list and provided to the VA for issuance to the contractor: Provide five (5).
All site visits…