This document is an Earthwork Specifications section that provides detailed requirements for excavation, backfilling, and compaction work related to a federal construction project. Key details include:
The document covers classification of excavation materials, specification of satisfactory and unsatisfactory materials, definitions of degrees of compaction, requirements for off-site soils, and procedures for dewatering, grading, backfilling, and compaction. It also outlines testing and inspection requirements, as well as disposition of surplus materials. This specification would be referenced as part of a larger solicitation for the repair of eroded portions of a drainage channel and retention pond at an Air Force facility.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section Page 1
EARTHWORK SPECIFICATIONS
08/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO T 180 (2017) Standard Method of Test for Moisture-
Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2017) Installation of Ductile-Iron Mains and
Their Appurtenances
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
AWPA C2 (2003) Lumber, Timber, Bridge Ties and Mine
Ties - Preservative Treatment by Pressure Processes
AWPA P5 (2015) Standard for Waterborne Preservatives
ASTM INTERNATIONAL (ASTM)
ASTM A139/A139M (2016) Standard Specification for Electric-
Fusion (ARC)-Welded Steel Pipe (NPS 4 and over)
ASTM A252 (2010) Standard Specification for Welded and
Seamless Steel Pipe Piles
ASTM C136/C136M (2014) Standard Test Method for Sieve
Analysis of Fine and Coarse Aggregates
ASTM C33/C33M (2018) Standard Specification for Concrete
Aggregates
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No.
200) Sieve in Soils by Washing
Section Page 2
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for
Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2434 (1968; R 2006) Permeability of Granular Soils
(Constant Head)
ASTM D2487 (2017) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D422 (1963; R 2007; E 2014; E 2014) Particle-Size
Analysis of Soils
ASTM D4318 (2017; E 2018) Standard Test Methods for
Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D6938 (2017a) Standard Test Method for In-Place
Density and Water Content of Soil and Soil- Aggregate by Nuclear Methods (Shallow Depth)
ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction
Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft. (600 kN-m/cu. m.))
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 600/4-79/020 (1983) Methods for Chemical Analysis of Water and Wastes
EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test
Methods for Evaluating Solid Waste:
Physical/Chemical Methods
1.2 DEFINITIONS
1.2.1 Satisfactory Materials
Satisfactory materials comprise any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP. Satisfactory materials for grading comprise stones less than 8 inches, except for fill material for pavements and railroads which comprise stones less than 3 inches in any dimension.
1.2.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as satisfactory which contains root and other organic
Section Page 3 matter or frozen material. Notify the Contracting Officer when encountering any contaminated materials.
1.2.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136/C136M, ASTM D422, and ASTM D1140.
1.2.4 Degree of Compaction
Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with AASHTO T 180 and corrected with AASHTO T 224. To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of Paragraph 7.2 in
AASHTO T 180.
1.2.5 Hard/Unyielding Materials
Hard/Unyielding materials comprise of weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 6 inch in any dimension. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.2.6 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
1.2.7 Unstable Material
Unstable materials are too wet to properly support appurtenant structure.
1.2.8 Select Granular Material
1.2.8.1 General Requirements
Select granular material consist of materials classified as GW GP, SW, SP, by ASTM D2487 where indicated. The liquid limit of such material must not exceed 35 percent when tested in accordance with ASTM D4318. The plasticity index must not be greater than 12 percent when tested in accordance with
Section Page 4
ASTM D4318, and not more than 35 percent by weight may be finer than No. 200 sieve when tested in accordance with ASTM D1140. Provide a minimum coefficient of permeability of 0.002 feet per minute when tested in accordance with ASTM D2434.
1.2.9 Initial Backfill Material
Initial backfill consists of select granular material or satisfactory materials approved by the government.
1.2.10 Expansive Soils
Expansive soils are defined as soils that have a plasticity index equal to or greater than 35 when tested in accordance with ASTM D4318.
1.2.11 Nonfrost Susceptible (NFS) Material
Nonfrost susceptible material are a uniformly graded washed sand with a maximum particle size of 6 inch and less than 5 percent passing the No. 200 size sieve, and with not more than 3 percent by weight finer than 0.02 mm grain size.
1.3 SYSTEM DESCRIPTION
Subsurface soil boring logs are . The subsoil investigation report and samples of materials taken from subsurface investigations may be examined.
These data represent the best subsurface information available; however, variations may exist in the subsurface between boring locations.
1.3.1 Classification of Excavation
No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation.
1.3.1.1 Common Excavation
Include common excavation with the satisfactory removal and disposal of all materials not classified as rock excavation.
1.3.1.2 Rock Excavation
Submit notification of encountering rock in the project. Include rock excavation with blasting, excavating, grading, disposing of material classified as rock, and the satisfactory removal and disposal of boulders 1/2 cubic yard or more in volume; solid rock; rock material that is in ledges, bedded deposits, and unstratified masses, which cannot be removed without systematic drilling and blasting; firmly cemented conglomerate deposits possessing the characteristics of solid rock impossible to remove without systematic drilling and blasting; and hard materials (see Definitions). Include the removal of any concrete or masonry structures, except pavements, exceeding 1/2 cubic yard in volume that may be encountered in the work in this classification. If at any time during excavation, the Contractor encounters material that may be classified as rock excavation, uncover such material and notify the Contracting Officer. Do not proceed with the excavation of this material until the Contracting Officer has classified the materials as common excavation or rock excavation and has taken cross sections as required. Failure on the part of the Contractor to
Section Page 5 uncover such material, notify the Contracting Officer, and allow ample time for classification and cross sectioning of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the Contracting Officer for the areas of work in which such deposits occur.
1.3.2 Blasting
Blasting will not be permitted.
1.3.3 Dewatering Work Plan
Submit procedures for accomplishing dewatering work to Contracting Officer and EPA.
1.4 SUBMITTALS
Government approval may be required on any of the following items. Items requiring submittals will be listed on the Submittal Register. Provide copies of all submittals per the requirements in Section 01 33 00, Submittal Procedures, or as listed on the Submittal Register.
SD-01 Preconstruction Submittals - Bid
SD-06 Test Reports
Within 24 hours of conclusion of physical tests, submit 2 copies of test results, including charts, graphs, or photos and results of calibration tests.
PART 2 PRODUCTS
2.1 REQUIREMENTS FOR OFFSITE SOILS
Test offsite soils brought in for use as backfill for Total Petroleum Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure (TCLP) including ignitability, corrosivity and reactivity. Backfill shall contain a maximum of 100 parts per million (ppm) of total petroleum hydrocarbons (TPH) and a maximum of 10 ppm of the sum of Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5030/8020. Perform TCLP in accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing for TPH, BTEX and TCLP from a composite sample of material from the borrow site, with at least one test from each borrow site. Do not bring material onsite until tests have been approved by the Contracting Officer.
2.3.3 Rock
Provide rock fragments sufficiently durable to ensure permanence in the structure and the environment in which it is to be used. Use rock fragments free from cracks, seams, and other defects that would increase the risk of
Section Page 6 deterioration from natural causes. Provide fragments sized so that no individual fragment exceeds a weight of 150 pounds and that no more than 10 percent of the mixture, by weight, consists of fragments weighing 2 pounds or less each. Provide rock with a minimum specific gravity of 2.50. Do not permit the inclusion of more than trace 1 percent quantities of dirt, sand, clay, and rock fines.
PART 3 EXECUTION
3.1 GENERAL EXCAVATION
Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times. Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from other approved areas selected by the Contractor as specified.
3.1.1 Ditches, Gutters, and Channel Changes
Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown on the drawings. Do not excavate ditches and gutters below grades shown. Backfill the excessive open ditch or gutter excavation with satisfactory, thoroughly compacted, material or with suitable stone or cobble to grades shown.
Dispose excavated material as shown or as directed, except in no case allow material be deposited a maximum 4 feet from edge of a ditch. Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work.
3.1.2 Drainage Structures
Make excavations to the lines, grades, and elevations shown, or as directed.
Clean rock or other hard foundation material of loose debris and cut to a firm, level, stepped, or serrated surface. Remove loose disintegrated rock and thin strata. Do not disturb the bottom of the excavation when concrete or masonry is to be placed in an excavated area.
3.1.3 Drainage
Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry. If needed, construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity
Section Page 7 and provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed.
3.1.4 Dewatering
Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Take control measures by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, maintain the water level continuously, at least 2 feet below the working level. Operate dewatering system continuously until construction work below existing water levels is complete. Submit performance records weekly. Measure and record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system. Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.
3.1.5.1 Bottom Preparation
Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each trench wall and to allow for proper drainage.
3.1.5.2 Removal of Unyielding Material
Where unyielding material is encountered in the bottom of the trench, remove such material 6 inch below the required grade and replaced with suitable materials as provided in paragraph BACKFILLING AND COMPACTION.
3.1.5.3 Removal of Unstable Material
Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND COMPACTION. When removal of unstable material is required due to the Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government.
3.1.5.4 Excavation for Appurtenances
Provide excavation for manholes, catch-basins, inlets, or similar structures sufficient to leave at least 24 inches clear between the outer structure surfaces and the face of the excavation or support members. Clean rock or loose debris and cut to a firm surface either level, stepped, or serrated, as shown or as directed. Remove loose disintegrated rock and thin strata.
Specify removal of unstable material
3.1.6 Underground Utilities
Section Page 8
The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
3.2 OPENING AND DRAINAGE OF EXCAVATION
Notify the Contracting Officer sufficiently in advance of the opening of any excavation or borrow pit to permit elevations and measurements of the undisturbed ground surface to be taken. Except as otherwise permitted, excavation areas providing adequate drainage. Transport overburden and other spoil material to designated spoil areas or otherwise dispose of as directed. Ensure that excavation of any area, or dumping of spoil material results in minimum detrimental effects on natural environmental conditions.
3.4 GRADING AREAS
Where indicated, divide work into grading areas within which satisfactory excavated material will be placed in embankments, fills, and required backfills. Do not haul satisfactory material excavated in one grading area to another grading area except when so directed in writing. Place and grade stockpiles of satisfactory and wasted materials as specified. Keep stockpiles in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal by rubber-tired equipment, the ground surface at stockpile locations; separately stockpile excavated satisfactory and unsatisfactory materials. Protect stockpiles of satisfactory materials from contamination which may destroy the quality and fitness of the stockpiled material. If the Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, remove and replace such material with satisfactory material from approved sources.
3.6 GROUND SURFACE PREPARATION
3.6.1 General Requirements
Remove and replace unsatisfactory material with satisfactory materials, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inches before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compact it as specified for the adjacent fill.
3.6.2 Frozen Material
Do not place material on surfaces that are muddy, frozen, or contain frost.
Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-
Section Page 9 wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary to plus or minus 2 percent of optimum moisture.
3.7 UTILIZATION OF EXCAVATED MATERIALS
Dispose unsatisfactory materials removing from excavations into designated waste disposal or spoil areas. Use satisfactory material removed from excavations, insofar as practicable, in the construction of fills, embankments, subgrades, shoulders, bedding (as backfill), and for similar purposes. Submit procedure and location for disposal of unused satisfactory material. Do not waste any satisfactory excavated material without specific written authorization. Dispose of satisfactory material, authorized to be wasted, in designated areas approved for surplus material storage or designated waste areas as directed. Clear and grub newly designated waste areas on Government-controlled land before disposal of waste material thereon. Stockpile and use coarse rock from excavations for constructing slopes or embankments adjacent to streams, or sides and bottoms of channels and for protecting against erosion. Do not dispose excavated material to obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way.
3.8 BURIED TAPE AND DETECTION WIRE
3.8.1 Buried Warning and Identification Tape
Refer to Owner requirements regarding buried warning and identification tape.
3.9 BACKFILLING AND COMPACTION
Place backfill adjacent to any and all types of structures, and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, to prevent wedging action or eccentric loading upon or against the structure. Prepare ground surface on which backfill is to be placed and provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.9.1 Trench Backfill
Backfill trenches to the grade shown. Do not backfill the trench until all specified tests are performed.
3.9.1.1 Replacement of Unyielding Material
Replace unyielding material removed from the bottom of the trench with select granular material or initial backfill material.
3.9.1.2 Replacement of Unstable Material
Replace unstable material removed from the bottom of the trench or excavation with select granular material placed in layers not exceeding 6 inches loose thickness.
Section Page 10
3.9.1.3.1 Class I
Angular, 0.25 to 1.5 inch, graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells.
3.9.1.3.2 Class II
Coarse sands and gravels with maximum particle size of 1.5 inch, including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included in this class as specified in ASTM D2487.
3.9.1.3.3 Sand
Clean, coarse-grained sand classified in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL, gradation SP by ASTM D2487 for beddingandbackfill as indicated.
3.9.1.3.4 Gravel and Crushed Stone
Clean, coarsely graded natural gravel, crushed stone or a combination thereof in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL, gradation having a classification of GWGP in accordance with ASTM D2487 for beddingandbackfillas indicated. Do not exceed maximum particle size of 3inches.
3.9.1.4 Final Backfill
Fill the remainder of the trench, except for special materials for roadways, railroads and airfields, with satisfactory material. Place backfill material and compact as follows:
3.9.1.4.1 Roadways, Railroads, and Airfields
Place backfill up to the required elevation as specified. Do not permit water flooding or jetting methods of compaction.
3.9.1.4.2 Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas
Deposit backfill in layers of a maximum of 12 inches loose thickness, and compact it to 85 percent maximum density for cohesive soils and 90 percent maximum density for cohesionless soils. Apply this requirement to all other areas not specifically designated above.
3.9.2 Backfill for Appurtenances
After a manhole, catchbasin, inlet, or similar structure has been constructed and the concrete has been allowed to cure for 14 days, place backfill in such a manner that the structure is not be damaged by the shock of falling earth. Deposit the backfill material, compact it as specified for final backfill, and bring up the backfill evenly on all sides of the structure to prevent eccentric loading and excessive stress.
3.10 SPECIAL REQUIREMENTS
file://tdka-fs-nas-02p/21ces-ce/CEN/05.%20CENM/CENM%20-%20Internal%20Share/MACC%202020/4%20Specifications/Word/31%2023%2000.00%2020.doc file://tdka-fs-nas-02p/21ces-ce/CEN/05.%20CENM/CENM%20-%20Internal%20Share/MACC%202020/4%20Specifications/Word/31%2023%2000.00%2020.doc file://tdka-fs-nas-02p/21ces-ce/CEN/05.%20CENM/CENM%20-%20Internal%20Share/MACC%202020/4%20Specifications/Word/31%2023%2000.00%2020.doc
Section Page 11
Special requirements for both excavation and backfill relating to the specific utilities are as follows:
Refer to Owner requirements regarding excavation and backfill for utilities.
3.11 SUBGRADE PREPARATION
3.11.1 Proof Rolling
Finish proof rolling on an exposed subgrade free of surface water (wet conditions resulting from rainfall) which would promote degradation of an otherwise acceptable subgrade. After stripping, proof roll the existing subgrade with six passes of a 15 ton, pneumatic-tired roller. Operate the roller in a systematic manner to ensure the number of passes over all areas, and at speeds between 2-1/2 to 3-1/2 mph. When proof rolling, provide one-half of the passes made with the roller in a direction perpendicular to the other passes. Notify the Contracting Officer a minimum of 3 days prior to proof rolling. Perform proof rolling in the presence of the Contracting Officer. Undercut rutting or pumping of material as directed by the Contracting Officerto a depth of 12 inch and replace with fill and backfillor select material.
3.11.2 Construction
Shape subgrade to line, grade, and cross section, and compact as specified.
Include plowing, disking, and any moistening or aerating required to obtain specified compaction for this operation. Remove soft or otherwise unsatisfactory material and replace with satisfactory excavated material or other approved material as directed. Excavate rock encountered in the cut section to a depth of 6 inches below finished grade for the subgrade. Bring up low areas resulting from removal of unsatisfactory material or excavation of rock to required grade with satisfactory materials, and shape the entire subgrade to line, grade, and cross section and compact as specified. After rolling, the surface of the subgrade for roadways shall not show deviations greater than 1/2 inch when tested with a 12-foot straightedge applied both parallel and at right angles to the centerline of the area.After rolling, do not show deviations for the surface of the subgrade for airfields greater than 1/4 inch when tested with a 12 foot straightedge applied both parallel and at right angles to the centerline of the area. Do not vary the elevation of the finish subgrade more than 0.05 foot from the established grade and cross section.
3.11.3 Compaction
Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Except for paved areas and railroads, compact each layer of the embankment to at least 95 percent of laboratory maximum density.
3.11.3.1 Subgrade for Railroads
Compact subgrade for railroads to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials.
3.11.3.2 Subgrade for Pavements
Section Page 12
Compact subgrade for pavements to at least 95 percentage laboratory maximum density for the depth below the surface of the pavement shown. When more than one soil classification is present in the subgrade, thoroughly blend, reshape, and compact the top 12 inch of subgrade.
3.11.3.3 Subgrade for Shoulders
Compact subgrade for shoulders to at least 95 percentage laboratory maximum density for the full depth of the shoulder.
3.11.3.4 Subgrade for Airfield Pavements
Compact top 24 inches below finished pavement or top 12 inches of subgrades, whichever is greater, to 100percent of ASTM D1557; compact fill and backfill material to 100percent of ASTM D1557.
3.12 SHOULDER CONSTRUCTION
Construct shoulders of satisfactory excavated material or as otherwise shown or specified. Submit advanced notice on shoulder construction for rigid pavements. Construct shoulders immediately after adjacent paving is complete. In the case of rigid pavements, do not construct shoulders until permission of the Contracting Officer has been obtained. Compact the entire shoulder area to at least the percentage of maximum density as specified in paragraph SUBGRADE PREPARATION above, for specific ranges of depth below the surface of the shoulder. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Finish shoulder construction in proper sequence in such a manner that adjacent ditches will be drained effectively and that no damage of any kind is done to the adjacent completed pavement. Align the completed shoulders true to grade and shaped to drain in conformity with the cross section shown.
3.13 FINISHING
Finish the surface of excavations, embankments, and subgrades to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within
0.1 foot of the grades and elevations indicated except that the degree of finish for subgrades specified in paragraph SUBGRADE PREPARATION. Finish gutters and ditches in a manner that will result in effective drainage.
Finish the surface of areas to be turfed from settlement or washing to a smoothness suitable for the application of turfing materials. Repair graded, topsoiled, or backfilled areas prior to acceptance of the work, and re-established grades to the required elevations and slopes.
3.13.1 Subgrade and Embankments
During construction, keep embankments and excavations shaped and drained.
Maintain ditches and drains along subgrade to drain effectively at all times. Do not disturb the finished subgrade by traffic or other operation.
Protect and maintain the finished subgrade in a satisfactory condition until ballast, subbase, base, or pavement is placed. Do not permit the storage or stockpiling of materials on the finished subgrade. Do not lay subbase, base course, ballast, or pavement until the subgrade has been checked and approved, and in no case place subbase, base, surfacing, pavement, or ballast on a muddy, spongy, or frozen subgrade.
Section Page 13
3.13.3 Grading Around Structures
Construct areas within 5 feet outside of each structure line true-to-grade, shape to drain, and maintain free of trash and debris until final inspection has been completed and the work has been accepted.
3.14 TESTING
Perform testing by a Corps validated commercial testing laboratory or the Contractor's validated testing facility. Submit qualifications of the Corps validated commercial testing laboratory or the Contractor's validated testing facilities. If the Contractor elects to establish testing facilities, do not permit work requiring testing until the Contractor's facilities have been inspected, Corps validated and approved by the Contracting Officer.
a. Determine field in-place density in accordance with ASTM D1556/D1556M.
b. Check the calibration curves furnished with the moisture gauges along with density calibration checks as described in ASTM D6938; check the calibration of both the density and moisture gauges at the beginning of a job on each different type of material encountered and at intervals as directed by the Contracting Officer.
c. Perform tests on recompacted areas to determine conformance with specification requirements. Appoint a registered professional civil engineer to certify inspections and test results. These certifications shall state that the tests and observations were performed by or under the direct supervision of the engineer and that the results are representative of the materials or conditions being certified by the tests. The following number of tests, if performed at the appropriate time, will be the minimum acceptable for each type operation.
3.14.1 Fill and Backfill Material Gradation
Perform compaction tests per the geotechnical representative requirements.
3.14.2 In-Place Densities
In-Place density tests shall be in accordance with the geotechnical representative recommendations.
3.14.3 Check Tests on In-Place Densities
Perform in place density tests per the geotechnical representative recommendations.
3.14.4 Moisture Contents
In the stockpile, excavation, or borrow areas, perform a minimum of two tests per day per type of material or source of material being placed during stable weather conditions. During unstable weather, perform tests as dictated by local conditions and approved by the Contracting Officer.
Section Page 14
3.14.5 Optimum Moisture and Laboratory Maximum Density
Perform moisture content tests per the geotechnical representative recommendations.
3.14.6 Tolerance Tests for Subgrades
Perform continuous checks on the degree of finish specified in paragraph SUBGRADE PREPARATION during construction of the subgrades.
3.14.7 Displacement of Sewers
After other required tests have been performed and the trench backfill compacted to the finished grade surface, inspect the outflow pipe to determine whether significant displacement or excessive soil displacement has occurred. Conduct this inspection in the presence of the Contracting Officer. Inspect pipe sizes larger than 36 inches, while inspecting smaller diameter pipe by shining a light or laser between manholes or manhole locations, or by the use of television cameras passed through the pipe. If, in the judgment of the Contracting Officer, the interior of the pipe shows poor alignment or excessive displaced soil is clogging the pipe or other defects that would cause improper functioning of the system, replace or repair the defects as directed at no additional cost to the Government.
3.15 DISPOSITION OF SURPLUS MATERIAL
Remove surplus material or other soil material not required or suitable for filling or backfilling, and brush, refuse, stumps, roots, and timber from Government property and delivered to a licensed/permitted facility or to a location approved by the Contracting Officer.
-- End of Section --
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Satisfactory Materials |
| 1.2.2 Unsatisfactory Materials |
| 1.2.3 Cohesionless and Cohesive Materials |
| 1.2.4 Degree of Compaction |
| 1.2.5 Hard/Unyielding Materials |
| 1.2.6 Rock |
| 1.2.7 Unstable Material |
| 1.2.8 Select Granular Material |
| 1.2.8.1 General Requirements |
| 1.2.9 Initial Backfill Material |
| 1.2.10 Expansive Soils |
| 1.2.11 Nonfrost Susceptible (NFS) Material |
| 1.3 SYSTEM DESCRIPTION |
| 1.3.1 Classification of Excavation |
| 1.3.1.1 Common Excavation |
| 1.3.1.2 Rock Excavation |
| 1.3.2 Blasting |
| Blasting will not be permitted. |
| 1.3.3 Dewatering Work Plan |
1.4 SUBMITTALS
| PART 2 PRODUCTS |
| 2.1 REQUIREMENTS FOR OFFSITE SOILS |
| 2.3.3 Rock |
| PART 3 EXECUTION |
| 3.1 GENERAL EXCAVATION |
| 3.1.1 Ditches, Gutters, and Channel Changes |
| 3.1.2 Drainage Structures |
| 3.1.3 Drainage |
| 3.1.4 Dewatering |
| 3.1.5.1 Bottom Preparation |
| 3.1.5.2 Removal of Unyielding Material |
| 3.1.5.3 Removal of Unstable Material |
| 3.1.5.4 Excavation for Appurtenances |
3.1.6 Underground Utilities
| 3.2 OPENING AND DRAINAGE OF EXCAVATION |
| 3.4 GRADING AREAS |
| 3.6 GROUND SURFACE PREPARATION |
| 3.6.1 General Requirements |
| 3.6.2 Frozen Material |
| 3.7 UTILIZATION OF EXCAVATED MATERIALS |
| 3.8 BURIED TAPE AND DETECTION WIRE |
| 3.8.1 Buried Warning and Identification Tape |
| 3.9 BACKFILLING AND COMPACTION |
| 3.9.1 Trench Backfill |
| 3.9.1.1 Replacement of Unyielding Material |
| 3.9.1.2 Replacement of Unstable Material |
| 3.9.1.3.1 Class I |
| 3.9.1.3.2 Class II |
| 3.9.1.3.3 Sand |
| 3.9.1.3.4 Gravel and Crushed Stone |
| 3.9.1.4 Final Backfill |
| 3.9.1.4.1 Roadways, Railroads, and Airfields |
| 3.9.1.4.2 Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas |
3.9.2 Backfill for Appurtenances
| 3.10 SPECIAL REQUIREMENTS |
| 3.11 SUBGRADE PREPARATION |
| 3.11.1 Proof Rolling |
| 3.11.2 Construction |
| 3.11.3 Compaction |
| 3.11.3.1 Subgrade for Railroads |
| 3.11.3.2 Subgrade for Pavements |
| 3.11.3.3 Subgrade for Shoulders |
| 3.11.3.4 Subgrade for Airfield Pavements |
| 3.12 SHOULDER CONSTRUCTION |
| 3.13 FINISHING |
| 3.13.1 Subgrade and Embankments |
| 3.13.3 Grading Around Structures |
| 3.14 TESTING |
| 3.14.1 Fill and Backfill Material Gradation |
| 3.14.2 In-Place Densities |
| 3.14.3 Check Tests on In-Place Densities |
| 3.14.4 Moisture Contents |
| 3.14.5 Optimum Moisture and Laboratory Maximum Density |
| 3.14.6 Tolerance Tests for Subgrades |
| 3.14.7 Displacement of Sewers |
3.15 DISPOSITION OF SURPLUS MATERIAL