SOW - 653-21-102 Seismic Retrofit B3 R4.4.24.docx
DOCX document 28 KB Posted
- Solicitation number
- 36C26024R0060
About this file
This document is a Statement of Work (SOW) for the Seismic Retrofit and Renovation of Building 3 at the Roseburg VAMC campus, Project Number 653-21-102. The project includes a full seismic retrofit and renovation of the 13,250 square foot administration building, as well as the addition of an elevator and stair tower. Key details include:
The project scope encompasses demolition, new construction, interior alterations, seismic retrofit, and exterior improvements. The building will be unoccupied during construction, which is expected to take 720 days after the Notice to Proceed. The contractor will be required to attend weekly project meetings and coordinate closely with VA staff. This SOW is related to Federal Contract Opportunity 84623b738d244ac0811c9e73f874cdb5, Solicitation Number 36C26024R0060, for the renovation of Building 3 at the Roseburg VAMC, which is being procured by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 20.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Seismic Retrofit and Renovation of Building 3 Project Number 653-21-102
1.0 DESCRIPTION OF WORK
The project is in Building 3 which houses administration offices on the Roseburg VAMC campus. This project includes a full seismic retrofit and renovation of the 13,250 square foot (GSF) building and the addition of an elevator and stair tower. The Contractor will provide all labor, materials and equipment for the demolition and construction services needed to complete this project. All work will meet SOW, drawings, and specification requirements as well as any applicable manufacturer’s recommended installation procedures.
The renovation includes the following, as well as all work in the specifications and drawings:
· Demolition
· New construction
· Interior alterations
· Seismic retrofit
· Exterior grading/drainage
· Exterior improvements
The above list is intended to serve as a starting point for construction and does not represent the only information in determining the project scope.
1.0.1 The building will be unoccupied throughout the construction process.
1.0.2 A high level of coordination with VA staff will be required. Regularly scheduled project meetings will be required to facilitate this communication.
1.1 Project Management
1.1.1 Project meetings will be held on a weekly basis or more frequently if needed.
1.1.2 The contractor will plan and coordinate the project meetings including agenda and taking of meeting minutes to be emailed out to all attendees.
1.1.3 VA meeting room facilities may be utilized for project meetings. The Contractor will coordinate with Facilities Management Service (Building 10) for use of VA facilities.
1.1.4 Work complete: 90 days for Limited Notice to Proceed for submittals and 720 days for Notice to Proceed for construction.