DK Heart Butte Dam Safety Modification
Solicitation number
140R6026R0004
Issued by

About this file

Summary: Heart Butte Dam Safety of Dams Modification Solicitation

This is a Request for Proposal (RFP) solicitation for comprehensive civil, geotechnical, and structural construction activities to enhance the long-term safety, stability, and performance of Heart Butte Dam located approximately 80 miles west of Bismarck, North Dakota. The Bureau of Reclamation intends to award a firm fixed price contract under Part 15 of the Federal Acquisition Regulation, with an estimated project magnitude exceeding $10 million and a period of performance from December 31, 2026 to April 30, 2030. The NAICS code is 237990 (Other Heavy and Civil Engineering Construction) with a small business size standard of $45 million. Sealed offers are due by May 29, 2026, with a 180-day acceptance period for the government. A mandatory site visit is scheduled for April 28, 2026 at 12:00 Mountain Standard Time, requiring attendees to provide safety boots, hard hats, and safety vests.

The work includes clearing and grubbing, cofferdam and temporary channel crossing construction, removal and control of groundwater through a comprehensive dewatering system with deep wells and observation wells, demolition and repair of the spillway/outlet works conduit, jet grouting operations for cutoff walls and treatment zones, backfill grouting, chemical grout repair, embankment construction with multiple soil zones, filter installation, riprap placement, and restoration and revegetation activities. Contractors must register in the System for Award Management (SAM) prior to submission and use the Invoice Processing Platform (IPP) for payment requests. Key compliance requirements include adherence to Reclamation Safety and Health Standards, environmental protection standards, water pollution control, protection of historical and archaeological resources, and federal contracting regulations. The solicitation includes detailed specifications organized into divisions covering general requirements, existing conditions, concrete work, metals, earthwork, utilities, and geological investigations, with extensive submittal requirements for construction plans, quality control programs, safety documentation, and equipment specifications.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior Bureau of Reclamation

March 2026

Heart Butte Dam Safety of Dams Modification

Heart Butte Unit, North Dakota Pick-Sloan Missouri Basin Program

Solicitation No. 140R6026R0004

Heart Butte Dam Safety of Dams Modification Solicitation No. 140R6026R0004

Forward - 2

HEART BUTTE DAM

SAFETY OF DAMS MODIFICATION

HEART BUTTE UNIT, NORTH DAKOTA

PICK-SLOAN MISSOURI BASIN REGION

FOREWORD

The Heart Butte Dam Safety of Dams Modification (HBDSDM) is located approximately 80 miles west of Bismark, North Dakota in Grant County.

The HBDSDM Work consists of a comprehensive suite of civil, geotechnical, and structural construction activities designed to enhance the long-term safety, stability, and performance of the Heart Butte dam infrastructure as described in this solicitation.

SITE VISIT: A SITE VISIT WILL BE HELD ON APRIL 28, 2026 AT 12:00

MOUNTAIN STANDARD TIME. ATTENDEES ARE TO PROVIDE AND WEAR

SAFETY BOOTS, HARD HATS, AND SAFETY VESTS. SEE 52.236-27 SITE VISIT

(CONSTRUCTION) ALT I FOR MORE SITE VISIT INFORMATION.

FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S

PUBLICATION "RECLAMATION SAFETY AND HEALTH STANDARDS"

INCLUDING REVISIONS AT http://www.usbr.gov/safety/rshs/index.html WHICH IS

APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT WBR

1452.223-81 SAFETY AND HEALTH.

NORTH AMERICAN INDUSTRIAL CLASSIFICATION SYSTEM (NAICS) CODE:

The NAICS Code for this project is 237990 Other Heavy and Civil Engineering Constructi on which has a small business size standard of $45 million.

MAGNITUDE OF PROJECT:

In accordance with FAR 36.204, the estimated magnitude of this proposed construction project is more than $10,000,000.

TYPE OF CONTRACT:

In accordance with Part 15 of the Federal Acquisition Regulation (FAR), the Bureau of Reclamation intends to award a firm fixed price contract for this effort.

PERIOD OF PERFORMANCE:

The period of performance for this requirement is anticipated to from December 31, 2026 to April 30, 2030. The contractor who receives the award will be required to commence work within 10 days of receiving a signed Notice to Proceed from the Contracting Officer. The expected period of performance is inclusive of receipt and acceptance of all submittals by the Bureau of Reclamation, final on-site cleanup by the contractor, and completion of invoicing.

http://www.usbr.gov/safety/rshs/index.html

Safety of Dams Modification Solicitation No. 140R6026R0004

Forward - 2

SITE VISIT:

See Section L, FAR 52.236-27 Alt I, of this solicitation.

METHOD OF SUBMISSION OF PROPOSALS:

See Section L of this Solicitation.

POINT OF CONTACT:

All questions and correspondence concerning this solicitation should be submitted via email to Contracting Officer Mitchell Frost at the following email address: mitchell_frost@ios.doi.gov.

SYSTEM FOR AWARD MANAGEMENT (SAM):

Any contractor interested in doing business with the F ederal Government is required to register in the System for Award Management (SAM) database at https://sam.gov, prior to submitting a proposal. SAM is a federal owned and operated free website. The contractor's Unique Entity ID (UEI) and banking information are required for registration. Contractors may obtain information on registration and annual confirmation requirements at the SAM website at https://sam.gov.

INVOICE PROCESSING PLATFORM (IPP):

Payment requests for the anticipated contract are r equired to be submitted electronically through the U.S.

Department of Treasury's Invoice Processing Platform (IPP) system. The IPP website is https:// www.ipp.gov. The contractor must use the IPP website to register access and submit requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP production helpdesk via e-mail at IPPCustomerSupport@fiscal.treasury.gov or by telephone at (866) 973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor can submit a waiver request in writing to the Contractor Officer with its proposal. Note:

Waivers will be on a case-by-case basis and not automatically granted as determined by the Contract Officer.

mailto:mfrost@usbr.gov https://sam.gov/ https://sam.gov/ http://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov

PART I

The Schedule

SECTION A

Solicitation, Offer, and Award

(Standard Form 1442)

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140R6026R0004

Bureau of Reclamation Missouri Basin Regional Office 2021 4th Avenue North Billings MT 59101

R60

Mitchell Frost 0000000000

05/29/2026

10 10

1 3

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

Bureau of Reclamation Missouri Basin Regional Office 2021 4th Avenue North Billings MT 59101

R60

Travis Stephens

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140R6026R0004

Delivery: 04/30/2030

Period of Performance: 12/31/2026 to

04/30/2030

00010 1 LSHeart Butte Dam, Safety of Dams Modification

Product/Service Code: Z2PZ

Product/Service Description: REPAIR OR

ALTERATION

OF OTHER NON-BUILDING FACILITIES

SECTION B

The Schedule

Safety of Dams Modification

Price Schedule B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

HEART BUTTE DAM SAFETY OF DAMS MODIFICATION

PICK-SLOAN MISSOURI BASIN PROGRAM, NORTH DAKOTA

PRICE SCHEDULES

B.1 PRICE SCHEDULES

(a) Offers will be considered for award on the following Price Schedules, but no offer will be considered for award on only a part of the Price Schedules.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) The Government will award the Price Schedule. Price Schedules A through G are optional price schedules that the Government is not required to exercise.

(d) Quantities in the Price Schedules are estimated quantities for comparison of offers only.

See applicable contract clause(s) in Section H for discussion of variation in the estimated quantity of unit-priced items.

(e) See the contract clause at WBR 1452.232-81 Alt I, Payment for Mobilization and Preparatory Work, for CLIN 1-1.

(f) Definitions:

(1) CLIN - Contract Line Item Number.

Price Schedule B - 2

PRICE SCHEDULE

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

1-1 WBR

1452.232- 81 Alt I

Mobilization and Preparatory Work

For the lump sum of $

1-2 01 52 20 Temporary Housing 30 months $ $

1-3 01 55 20 Traffic Control For the lump sum of $

1-4 01 78 30 Final As-built Drawings 10% of Total Price Schedule

1-5 02 07 10 Fishing Platform and Access Ramp Removal, Design and Construction

For the lump sum of $

1-6 02 07 10 Sidewalk Removal, Design and Construction

For the lump sum of $

1-7 03 15 12 6-inch PVC Waterstops 38 lin ft $ $

1-8 03 20 00 Concrete Reinforcing 10,200 lbs $ $

1-9 03 30 00 Cast-In-Place Concrete 92 yd3 $ $

1-10 03 64 00 Backfill Grouting For the lump sum of $

1-11 03 81 10 Saw Cutting Existing Concrete 77 lin ft $ $

1-12 03 81 10 Concrete Removal, Hydro-demolition, 12-Inch Calibration Settings

61 yd3 $ $

1-13 03 81 17 Grouted Holes 1,030 EA $ $

1-14 03 81 17 Chemical Grout For the lump sum of $

1-15 05 50 00 Miscellaneous Metalwork For the lump sum of $

1-16 05 50 00 Conduit Shoring System For the lump sum of $

1-17 08 33 20 Roll-up Door For the lump sum of $

1-18 31 02 10 Dust Abatement For the lump sum of $

1-19 31 03 20 Cofferdam Construction For the lump sum of $

1-20 31 03 20 Temporary Channel Crossing For the lump sum of $

1-21 31 03 33 Contractor Designed Unwatering System

For the lump sum of $

Price Schedule B - 3

PRICE SCHEDULE

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

1-22 31 03 33 Temporary Observation Wells Installation/Removal

480 lin ft $ $

1-23 31 03 33 Supplementary Temporary Observation Wells Materials

175 lin ft $ $

1-24 31 03 33 Deep Wells Installation/Removal 2,100 lin ft $ $

1-25 31 03 33 Deep Wells Operation 16 months $ $

1-26 31 03 33 Supplementary Deep Wells Materials

660 lin ft $ $

1-27 31 09 10 Abandoning and Removing Existing Instrumentation

For the lump sum of $

1-28 31 09 12 New Embankment Measurement Points

For the lump sum of $

1-29 31 09 12 Temporary Embankment Measurement Points and Monitoring During Construction

For the lump sum of $

1-30 31 09 20 New Slotted-Pipe Piezometers For the lump sum of $

1-31 31 09 30 Inspection Well Instrumentation For the lump sum of $

1-32 31 09 30 Prefabricated Weir Boxes For the lump sum of $

1-33 31 11 00 Clearing and Grubbing For the lump sum of $

1-34 31 14 10 Stripping 18.0 acres $ $

1-35 31 23 16 General Excavation 20,000 yd3 $ $

1-36 31 23 16 Excavation for Spillway Channel Remediation

2,000 yd3 $ $

1-37 31 23 16 Contractor Designed Soil Reinforcement Zone

For the lump sum of $

1-38 31 23 18 Deep Filter Trench Shoring and Excavation

550 yd3 $ $

1-39 31 23 70 Controlled Low Strength Material 52 yd3 $ $

1-40 31 24 12 Zone 3, Filter Sand Material 9,100 yd3 $ $

1-41 31 24 13 Zone 4, Gravel Drain Material 2,200 yd3 $ $

Price Schedule B - 4

PRICE SCHEDULE

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

1-42 31 24 14 Zone 5, Stability Berm Fill 32,000 yd3 $ $

1-43 31 24 15 Zone 6, Reinforced Backfill Material

2,900 yd3 $ $

1-44 31 32 32 Geotextile 1,650 yd2 $ $

1-45 31 32 36 Jet Grouting Test Sections For the lump sum of $

1-46 31 32 36 Final Jet Grouting Treatment For the lump sum of $

1-47 31 37 01 Stability Berm Access Road Riprap

730 yd2 $ $

1-48 31 37 01 Spillway Channel Riprap 780 yd2 $ $

1-49 31 37 02 Riprap Bedding 1,500 yd2 $ $

1-50 31 37 10 Remove and Stockpile Existing Rockfill

1,100 yd3 $ $

1-51 31 37 10 Rockfill Slope Protection 2,800 yd2 $ $

1-52 32 15 10 Gravel Surfacing 2,400 yd2 $ $

1-53 32 31 10 Chain Link Fence 350 lin ft $ $

1-54 32 32 24 Mechanically Stabilized Earth Walls

5,400 ft2 $ $

1-55 32 91 10 Topsoil 17.5 acres $ $

1-56 32 91 60 Topsoil Erosion Control Matting 5.3 acres $ $

1-57 32 92 20 Restoration and Revegetation 17.5 acres $ $

1-58 33 46 36 12-Inch Diameter HDPE Pipe Test Section and Camera

For the lump sum of $

1-59 33 46 36 12-Inch Diameter Perforated HDPE Pipe 1,100 lin ft $ $

1-60 33 46 36 12-Inch Diameter Nonperforated HDPE Pipe 440 lin ft $ $

1-61 33 46 36 18-Inch Diameter Nonperforated HDPE Pipe 250 lin ft $ $

1-62 33 46 36 Drain Cleanouts 14 EA $ $

Price Schedule B - 5

TOTAL FOR PRICE SCHEDULE $_________________

OPTIONAL PRICE SCHEDULE A – HIGHWAY REPAVING

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

2-1 01 55 00 Highway Repaving For the lump sum of $

TOTAL FOR OPTIONAL PRICE SCHEDULE A $_________________

OPTIONAL PRICE SCHEDULE B – SUPPLEMENTARY BACKFILL GROUTING

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

3-1 03 64 00 Supplementary Backfill Grout Hole Drilling

60 lin ft $ $

3-2 03 64 00 Supplementary Backfill Grouting Operations

200 ft3

TOTAL FOR OPTIONAL PRICE SCHEDULE B $_________________

OPTIONAL PRICE SCHEDULE C – CARE OF RESERVOIR RELEASES DURING

CONSTRUCTION

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

4-1 31 03 10 Care of Reservoir Releases During Construction, Ongoing Jet Grouting within Conduit

For the lump sum of $

4-2 31 03 10 Care of Reservoir Releases During Construction, Ongoing Backfill Grouting

For the lump sum of $

4-3 31 03 10 Care of Reservoir Releases During Construction, Ongoing Conduit Demolition and Repair

For the lump sum of $

4-4 31 03 10 Care of Reservoir Releases During Construction, Ongoing Spillway Channel Remediation

For the lump sum of $

TOTAL FOR OPTIONAL PRICE SCHEDULE C $_________________

Price Schedule B - 6

OPTIONAL PRICE SCHEDULE D – PHASE I DEWATERING

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

5-1 31 03 33 Phase I - Supplementary Temporary Observation Wells Installation/Removal

44 lin ft $ $

5-2 31 03 33 Phase I - Supplementary Deep Wells Installation/Removal

92 lin ft $ $

5-3 31 03 33 Phase I - Supplementary Deep Wells Operation

8 months $ $

TOTAL FOR OPTIONAL PRICE SCHEDULE D $_________________

OPTIONAL PRICE SCHEDULE E – PHASE II DEWATERING

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

6-1 31 03 33 Phase II - Supplementary Temporary Observation Wells Installation/Removal

44 lin ft $ $

6-2 31 03 33 Phase II - Supplementary Deep Wells Installation/Removal

91 lin ft $ $

6-3 31 03 33 Phase II - Supplementary Deep Wells Operation

3 months $ $

TOTAL FOR OPTIONAL PRICE SCHEDULE E $_________________

OPTIONAL PRICE SCHEDULE F – PHASE III DEWATERING

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

7-1 31 03 33 Phase III - Supplementary Temporary Observation Wells Installation/Removal

44 lin ft $ $

7-2 31 03 33 Phase III - Supplementary Deep Wells Installation/Removal

270 lin ft $ $

7-3 31 03 33 Phase III - Supplementary Deep Wells Operation

4 months $ $

Price Schedule

B - 7

TOTAL FOR OPTIONAL PRICE SCHEDULE F $_________________

OPTIONAL PRICE SCHEDULE G – PHASE IV DEWATERING

CLI

N

Section Supplies or Services Quantity and Unit

Unit Price

Amount

8-1 31 03 33 Phase IV - Supplementary Temporary Observation Wells Installation/Removal

44 lin ft $ $

8-2 31 03 33 Phase IV - Supplementary Deep Wells Installation/Removal

200 lin ft $ $

8-3 31 03 33 Phase IV - Supplementary Deep Wells Operation

8 months $ $

TOTAL FOR OPTIONAL PRICE SCHEDULE G $_________________

END OF SUPPLIES OR SERVICES AND PRICES/COSTS

Price Schedule B - 8

This page intentionally left blank.

SECTION C

Description / Specifications

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 20 Reservoir Operations 01 31 19 Project Management and Coordination 01 31 35 Onsite Video System 01 32 10 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 35 50 Site Security 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 46 25 Third Party Quality Control Inspections 01 51 00 Temporary Utilities 01 52 10 Government Field Office 01 52 20 Temporary Housing 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Spillway Conduit and Stilling Basin 01 56 12 Protection of Existing Infrastructure 01 56 20 Existing Fences 01 57 20 Environmental Protection 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 - EXISTING CONDITIONS

02 07 10 Fishing Platform, Access Ramp, and Sidewalks

DIVISION 03 - CONCRETE

03 11 10 Concrete Forming

03 15 12 PVC Waterstop 03 20 00 Concrete Reinforcing 03 20 30 Post-Installed Adhesive Anchors 03 30 00 Cast-In-Place Concrete 03 64 00 Backfill Grouting 03 81 10 Concrete Demolition and Removal 03 81 17 Chemical Grout Repair

DIVISION 05 - METALS

05 50 00 Metal Fabrications

DIVISION 08 - OPENINGS

08 33 20 Roll-Up Door

DIVISION 31 - EARTHWORK

31 02 10 Dust Abatement 31 03 10 Care of Reservoir Releases During Construction 31 03 20 Cofferdam Construction and Temporary Channel Crossing 31 03 33 Removal and Control of Water 31 09 10 Abandoning and Removing Existing Instrumentation 31 09 12 New and Temporary Embankment Measurement Points 31 09 20 New Piezometers 31 09 30 Seepage Measurement Instrumentation 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 02 Compacting Earth Materials 31 23 16 Excavation 31 23 18 Excavation of Deep Filter Trench and Shoring 31 23 19 Use of Borrow Area 31 23 39 Disposal of Excavated Materials 31 23 70 Controlled Low Strength Material 31 24 10 Embankment, General 31 24 12 Zone 3 - Filter Sand Material 31 24 13 Zone 4 - Gravel Drain Material 31 24 14 Zone 5 - Stability Berm Fill 31 24 15 Zone 6 - Reinforced Backfill Material 31 32 32 Geotextile 31 32 36 Jet Grouting 31 37 01 Riprap 31 37 02 Riprap Bedding 31 37 10 Rockfill Slope Protection

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 15 10 Gravel Surfacing 32 31 10 Chain Link Fence 32 32 24 Mechanically Stabilized Earth Walls 32 91 10 Topsoil 32 91 60 Topsoil Erosion Control Matting 32 92 20 Restoration and Revegetation

DIVISION 33 - UTILITIES

33 46 36 HDPE Pipe Drains

DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors 51 00 05 DOI Security Forms 51 00 10 Climatological Data 51 00 20 Historic Reservoir Elevations 51 00 30 Historic Unwatering for Stilling Basin Inspections 51 00 35 Well Profile Analysis 51 00 40 Evaluation of Potential Filter Sand and Gravel Drain Sources 51 00 45 Friable Particle Count Method 51 00 50 Instrumentation Data 51 00 55 Spillway and Outlet Works Discharge and Tailwater Elevation Data 51 00 80 USBR Guidelines for Earthwork Construction Control Testing of Gravelly Soils 51 00 85 Lake Tschida Water Test Results 51 00 90 Environmental Assessment 51 00 95 Photographs

DIVISION 52 - DRAWINGS

52 00 00 Drawings

DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS

53 10 00 Geologic Investigations 53 20 00 Records of Geologic and Subsurface Investigations

END OF CONTENTS

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located approximately 72 miles southwest of Bismarck, North Dakota in Grant County.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Clearing, grubbing, and stripping of the work area and borrow areas.

B. Abandoning and removing existing piezometers and seepage monitoring points.

C. Installing and operating dewatering and unwatering systems to support stable excavation slopes, embankment and filter construction, jet grouting and foundation backfill grouting operations. Installation of a cofferdam and river crossing to aid the dewatering efforts and temporary river crossing to gain access across the Heart River channel for required work.

D. Installing temporary embankment measurement points for monitoring and identifying potential areas of instability during excavation.

E. Design and construction of a soil reinforcement zone along the right side of the spillway chute access road to widen the work area.

F. Jet grouting test sections along the right side of the spillway chute to inform the design, geometry, operations, and schedule for production jet grouting.

G. Jet grouting to install cutoff walls along the sides of the spillway/outlet works conduit and along the right side of the spillway chute.

H. Jet grouting to install the treatment zone underneath the spillway/outlet works conduit.

I. Design and construction of a temporary conduit shoring system and demolition of a section of the spillway/outlet works conduit floor and side walls, repairing the steel reinforcements and replacing concrete to restore the outlet works conduit.

J. Backfill grouting of potential voids beneath the spillway/outlet works conduit from the interior of the conduit.

K. Drillings and installing chemical grout at existing joints and cracks within the spillway/outlet works conduit.

L. Excavating existing dam embankment, foundation and spillway/outlet works discharge channel at the end of the stilling basin.

Summary of Work

01 11 00 - 2

M. Furnishing and installing new sand filter layer in the spillway discharge channel at the end of stilling basin and covering with riprap bedding and riprap layers to restore the original geometry of the spillway discharge channel.

N. Constructing new deep sand filter trench using a Contractor designed shoring system to support the vertical trench wall for placing and compacting sand filter material within the trench.

O. Furnishing and installing new filter sand and gravel drain seepage blanket downstream of the dam.

P. Constructing cast-in-place concrete toe drain inspection well.

Q. Furnishing and installing perforated and non-perforated high-density polyethylene (HDPE) toe drain pipes and cleanouts.

R. Excavating, screening, and delivering borrow material for embankment stability berm fill.

S. Constructing new stability berm fill and constructing the mechanically stabilized earth (MSE) wall along the right side of the stability berm.

T. Furnishing and installing flumes and weir boxes.

U. Placing riprap bedding and riprap along the toe of the stability berm below the access road.

V. Placing rockfill slope protection on lower face and sides of the stability berm above the access road.

W. Constructing new embankment measurement points and piezometers.

X. Restoring all ground disturbance within construction use area and restoring gravel access roads.

Y. Furnishing and installing roll-up door on spillway/outlet works conduit headwall.

Z. Removal, design, and construction of a new fishing platform and access ramp adjacent to the left spillway chute wall.

AA. Removal, design, and construction of new sidewalks.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

01 11 00 - 3

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.04 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 53:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

01 11 00 - 4

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and

Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Site Use Plan:

1. For each Contractor use location on Government land, identify location and describe extent of impact. Potential uses include but are not limited to the following:

a. Buildings and service areas including offices, laydown areas, temporary housing, and fuel and oil storage areas.

b. Site power and other utilities.

c. Parking areas, equipment staging, jet grout plant, temporary roads, construction-water access, and haul routes.

d. Material stockpiling and staging areas.

e. Areas for processing, storing, and disposing of waste materials from construction operations.

2. Provide initial and post construction digital recordings of Lake Tschida

Campground special use area, if used for temporary housing.

a. Provide a copy of use agreement with the campground manager, if used for temporary housing.

http://www.usbr.gov/mussels/prevention

Use of Site 01 14 10 - 2

3. Describe methods for removing temporary structures and facilities, cleaning, and rehabilitating site after completion of construction activities.

1.04 PROJECT CONDITIONS

A. Government land required for construction facilities is shown on the Drawings.

B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be allowed within the constraints shown on the Drawings.

D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

E. Lake Tschida Campground special use area as shown on the Drawings is available for temporary housing during construction.

1. Use of Lake Tschida Campground shall be coordinated with the campground manager.

2. Do not use the special use area for stockpiling, staging, or as a laydown area.

F. Existing paved and unpaved roads made available for Contractor use are shown on drawings. Refer to Drawings for roads that are not available for Contractor use.

G. Housing trailers to be set up on Government land for construction personnel.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Before bringing onsite, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.

3. The COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment onsite.

01 14 10 - 3

3.02 RESTORATION

A. Existing roads used by the Contractor shall be repaired to pre-construction condition.

1. Cleaning of existing paved roads shall include passes with a street sweeper, power washing the road surface, brooming, or any other means necessary along the Heart Butte Dam crest and 100 feet beyond site entrances.

2. Repair of existing roads shall be in accordance with Section 01 55 00 – Vehicular Access and Parking.

B. Restore temporary construction roads not required to remain in place to original contours and make impassable to vehicular traffic when no longer required.

C. Except as specified below, after completion of work, scarify and regrade Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

D. Seed disturbed areas of Government land used for construction purposes and not required for completed installation in accordance with Section 32 92 20 – Restoration and Revegetation.

01 14 10 - 4

Work Restrictions

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS

PART 1 GENERAL

MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 WORK RESTRICTIONS

A. Lake Tschida Downstream Campground as shown on the Drawings will remain closed throughout construction operations. The campground and facilities may be used during construction in coordination with the campground manager according to 01 14 10 – Use of Site.

B. Public shall be allowed access to Heart Butte Reservoir and its recreation areas throughout construction. Public access below the dam and within all work areas is closed to the public throughout construction operations.

C. If the dam crest road is used as part of the construction haul route, the maximum weight of the fully loaded construction vehicles traveling on the dam crest road shall be restricted according to North Dakota Department of Transportation’s (NDDOT) rating and requirements for State Highway 49. Refer to Section 01 55 00 – Vehicular Access and Parking.

D. The Contractor shall maintain public use of roadways throughout the area not within the road-closure limits and access to and from the reservoir and appurtenant facilities during construction.

E. Road Closures:

1. If needed, limit temporary road closures to between 9:00 am to 4:00 pm and each shall not exceed 30 minutes.

F. Minimum volumes of Zone 3 - Filter Sand Material shall be placed in stockpiles on site before beginning deep filter trench excavation and spillway channel excavation.

Minimum volumes of Zone 3 are as follows:

1. Before beginning deep filter trench excavation:

a. Zone 3: 550 cy

2. Before beginning spillway channel excavation:

a. Zone 3: 440 cy

G. Allowable Work Hours: 24 hours a day, Monday through Saturday.

Work Restrictions 01 14 12 - 2

H. The Contractor-designed soil reinforcement zone shall be constructed prior to construction of jet grouting treatment zone.

I. Construction of jet grouting treatment zone shall proceed after jet grouting test sections and Test Sections Report are completed and the Final Jet Grouting Treatment Plan is approved by the Government.

J. The jet grouting treatment zone on both sides of the conduit between spillway station 11+96 and 12+48 shall be constructed prior to drilling and installing the Phase I dewatering wells. Drilling the Phase I dewatering wells shall begin at least 7 days after the jet grouting treatment zone are completed.

K. Complete backfill grouting operations in the first construction season after operational releases are complete and prior to initiating jet grouting operations. The Government will perform normal reservoir operations during the first construction season and make outlet works releases until approximately the end of October. The Government is expected to stop outlet works releases on October 31st of the first construction season to allow the Contractor to proceed with the backfill grouting operation inside the conduit. The Contractor shall complete the backfill grouting operation by December 30th of the first construction season.

1. The jet grouting test sections and jet grouting treatment zone along the right side of the spillway chute between jet grouting treatment control points 902 and 904 (see Drawing 203-D-60019) are excluded from this restriction.

L. The construction schedule of jet grouting treatment zone installation inside the conduit shall be approved by COR after the jet grouting test sections are completed and deemed acceptable. Installation of the jet grouting treatment zone beneath the conduit shall be ready to proceed on August 1st of the second construction season and shall meet the following criteria:

1. The Government has completed reservoir draw down to the reduced pool elevation.

2. Approved, Contractor-designed unwatering system including unwatering of the spillway stilling basin shall be installed following reservoir drawdown and conclusion of outlet works releases.

3. Phase I dewatering wells shall be installed and groundwater level lowered to a minimum El. 1995 in the footprint of jet grouting treatment zone beneath the conduit. Refer to Section 31 03 33 – Removal and Control of Water for requirements.

M. Jet grouting treatment zone beneath the conduit shall be installed, verified, and approved by November 1st in the second construction season.

N. The Contractor-designed temporary conduit shoring system shall be installed before demolition of the conduit floor and side walls occurs. The temporary conduit shoring system shall be designed to sustain 600 cubic feet per second (cfs) of discharge flow in

01 14 12 - 3 the conduit. Refer to Section 03 11 10 – Concrete Forming and Section 05 50 00 – Metal Fabrications.

O. After the jet grouting treatment zone beneath the conduit is installed and approved, conduit demolition and repair shall begin on November 1st and shall be completed by January 15th when the probability for uncontrolled spillway releases is at lowest level according to the historical inflow data (work may be released earlier than November 1st dependent upon interior jet grouting completion). Operation of the approved, Contractor-designed unwatering system including unwatering of the spillway stilling basin shall continue during conduit demolition and repair.

P. The Government will monitor the reservoir level and inflow conditions during construction activities within the conduit or spillway channel. If reservoir water level rises and uncontrolled spillway release becomes likely, the Contracting Officer will inform the Contractor at least 10 days before the expected spillway release. Refer to Section 31 03 10 – Care of Reservoir Releases during Construction.

Q. Excavation and installation of Zone 3 - Filter Sand Material, riprap bedding and riprap in the spillway discharge channel at the end of the stilling basin shall be performed after reservoir draw down is complete in either the second or the third construction season. At the same time, the stilling basin shall be completely unwatered. Refer to Section 01 14 20 – Reservoir Operations and Section 31 03 33 – Removal and Control of Water.

R. The spillway channel excavation and remediation shall not begin until jet grouting operations outside the conduit are complete and the jet grouting treatment zone achieves the specified compressive strength.

S. Place compacted fill to a minimum depth of 5 feet above top of the conduit before allowing any construction equipment and vehicle travel across the top of the conduit.

Refer to Section 01 56 10 – Protection of Existing Spillway Conduit and Stilling Basin for requirements.

T. After installation of the jet grouting treatment zone beneath the conduit is completed, construction equipment and vehicle travel over the conduit is not permitted until the conduit repair has been completed and concrete achieves the specified compressive strength.

U. The deep filter trench excavation and shoring shall not begin until all jet grouting operations are completed and accepted.

V. Phase III dewatering system and approved, Contractor-designed unwatering system including unwatering of the spillway stilling basin shall be installed prior to beginning deep filter trench excavation. Groundwater levels shall be monitored prior to beginning deep filter trench excavation. Refer to Section 31 03 33 – Removal and Control of Water and Section 31 23 18 – Excavation of Deep Filter Trench and Shoring for requirements.

W. Construction of the blanket filter and drainage system shall not begin until deep filter trench excavation and backfill is complete.

01 14 12 - 4

X. Phase IV dewatering system and approved, Contractor-designed unwatering system including unwatering of the spillway stilling basin shall be installed prior to beginning excavation for the blanket filter and shallow filter trench within the relic river channel area. Groundwater levels shall be monitored prior to beginning excavation for the blanket filter and shallow filter trench. Refer to Section 31 03 33 – Removal and Control of Water for requirements.

Y. Place a minimum five feet (unless shown otherwise on Drawings) of fill over the completed blanket filter and drainage system by the end of the third construction season, not including sacrificial earthfill material for winter shutdown.

Z. Chemical grout repair shall be completed by the end of the third construction season.

AA. The trees on the property of the Lake Tschida campground shall be protected during construction.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Reservoir Operations

01 14 20 - 1

SECTION 01 14 20

RESERVOIR OPERATIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 RESERVOIR OPERATIONS DURING CONSTRUCTION

A. Heart Butte Reservoir is owned, operated and maintained by the Bureau of Reclamation.

B. The Government will perform normal reservoir operations during the first construction season and continue discharge from spillway and outlet works conduit until the end of October of the first season. Temporary channel crossing across the Heart River, if used, shall allow releases to safely pass over or beneath the crossing. Refer to Section 31 03 20

– Cofferdam Construction and Temporary Channel Crossing.

C. For construction activities adjacent to the spillway stilling basin, discharge channel and within the spillway/outlet works conduit, based on the agreed upon schedule for the work, the Government will draw down the reservoir to a reduced pool level by August 1st in the second construction season and restrict outlet works releases until the following spring.

D. In the third construction season, the Government will draw down the reservoir to a reduced pool level by July 1st and restrict outlet works releases until the following spring.

E. After the third construction season is completed, the Government will resume normal reservoir operations.

F. Outlet works releases after August 1st of the second construction season and after July 1st of the third construction season may be required to control unexpected large inflows to prevent uncontrolled spillway release during construction. Refer to Sections 01 14 12 – Work Restrictions and 31 03 10 – Care of Reservoir Releases During Construction.

G. Based on the historical reservoir inflow data and operation records, no uncontrolled spillway releases are expected from November 1st to December 15th, and low likelihood of uncontrolled spillway releases from December 15th to January 15th.

H. Historic Heart Butte Reservoir elevation data are provided in Section 51 00 20 – Historic Reservoir Elevations for informational purposes only.

Reservoir Operations

01 14 20 - 2

I. For instant, daily, monthly, and annual Heart Butte Reservoir operations data, refer to https://www.usbr.gov/gp/hydromet/index.html (station Code LTR, Lake Tschida Reservoir).

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used https://www.usbr.gov/gp/hydromet/index.html

Project Management and Coordination

01 31 19 - 1

SECTION 01 31 19

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at www.usbr.gov/safety

1.03 SUBMITTALS

A. Submit in accordance with Section 01 33 00 – Submittals:

B. RSN 01 31 19-1, Weekly Coordination Meeting Agenda:

1. Agenda.

2. 12-week look-ahead schedule covering the following as applicable:

a. Construction review items and tasks.

3. Work completed to date.

C. RSN 01 31 19-2, Weekly Coordination Meeting Minutes:

1. Meeting minutes from weekly coordination meeting to include the following:

a. Include date, time, and list of attendees.

b. Summary of topics discussed.

c. List of action items including the following:

1) Description of action item.

2) Responsible party.

3) Date to be completed.

PART 2 PRODUCTS

http://www.usbr.gov/safety

Project Management and Coordination

01 31 19 - 2

PART 3 EXECUTION

3.01 PROJECT COORDINATION

A. The Contractor and Government shall hold weekly project coordination meetings to review ongoing construction activities and coordinate upcoming construction activities.

B. The following meetings are considered significant, but do not relieve Contractor from responsibility of attending other meetings required by specifications. Preconstruction Conference is separate meeting requirement from meetings listed in this section:

1. Weekly Coordination Meetings:

a. Attendees as required:

1) Contractor’s Project Manager, Project Engineer, Superintendent, and Quality Control Supervisor, and any pertinent subcontractors.

2) Government’s COR, Project Manager, Project Engineer, safety personnel, and other required Reclamation staff.

b. Purpose:

1) Review drawings, data, and technical requirements of specifications. Schedule, Progress, and Coordination:

a) Review safety, progress made, schedule, project issues, submittals, Request for Information (RFI), and resolution necessary to meet specifications requirements.

b) Contractor Quality Control results and procedures including status of planning meetings for definable features of work under Section 01 46 00 – Quality Procedures.

c) Review dates that activities were started and completed, remaining duration, and percent complete.

d) Review submittals register, submittals currently in review and approval, and meeting submittals due dates or delivery time frames.

e) Provide 12-week look-ahead schedule at least 3 federal working days before start of meeting.

f) Review as-built drawings.

g) Provide meeting minutes from the previous weekly meeting.

Onsite Video System

01 31 35 - 1

SECTION 01 31 35

ONSITE VIDEO SYSTEM

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in the prices offered in the Price Schedule for other items of work.

a. Includes installation of a minimum four cameras, maintenance, data storage and transmittal, removal, and training.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (Reclamation)

1. RCD 05-01 Information Management, available at https://www.usbr.gov/recman/DandS.html

1.03 SUBMITTALS

A. Submit in accordance with Section 01 33 00 - Submittals.

B. RSN 01 31 35-1, Onsite Video System:

1. System provider experience, number of systems operating, references.

2. Installation plan:

a. Including:

1) Location.

2) Coverage of site work.

3) Onsite zoom capabilities.

4) Power supply.

5) Mounting pole, hardware, and details.

6) Bird landing deterrent

3. Documentation of system capabilities.

4. Manufacturer’s instructions for system use:

a. Instructions shall include a manual and online support describing the program use, examples of the specific functions.

b. Instructions shall include stepwise guidance documenting the interface screens and data retrieval procedures.

https://www.usbr.gov/recman/DandS.html

01 31 35 - 2

c. Demonstrating and discussing operations, ease of use, uploads, downloads, report creation, tracking, searching, editing.

d. Online training representative simultaneously to Contractor and Government staff involved on the project.

e. Program support directly from the manufacturer by email, phone, and website. Submit contact information.

C. RSN 01 31 35-2, Project Monitoring Permanent Record.

1. All project web cameras documentation of photographic documentation and video documentation.

1.04 QUALIFICATIONS

A. System Provider: At least 3 years successful performance in providing required services.

1.05 VIDEO SYSTEM DESIGN REQUIREMENTS

A. Camera systems shall provide remote jobsite monitoring, team collaboration, project documentation.

B. Users can remotely view live images and video of construction activities.

C. Photo documentation can be catalogued or shared among team members.

D. Any number of custom time-lapses can be scheduled and viewed anytime.

E. The system shall include 4G LTE cellular service to connect the cameras to the internet.

1. Signal is strongest east of the dam.

F. Continuously monitor the project site from 6:00 a.m. to 8:00 p.m. daily Monday through Sunday. Hours may be adjusted to meet Contractor’s working activities.

G. Allow the Government to view or download segments of this video footage from the web interface.

H. Camera’s data such as images and time-lapse videos shall be available for download directly within the web interface.

I. Access:

1. Web-Based:

a. Live and stored video are accessible by authorized individuals via an internet site.

b. Compatible with web browsers MS Internet Explorer, Apple Safari, Mozilla Firefox, and Google Chrome.

c. The web interface shall use SSL encryption for data security.

Onsite Video System 01 31 35 - 3

PART 2 PRODUCTS

2.01 GENERAL

A. Cameras shall be a commercial-off-the-shelf (COTS) product.

2.02 PAN TILT AND ZOOM (PTZ) CAMERAS

A. PTZ Camera, as manufactured by Truelook, Inc. (Website: www.TrueLook.com) Phone:

833-878-3566; or equal, having the following essential characteristics:

1. A robotic Pan-Tilt-Zoom (PTZ) camera shall allow any number of simultaneous users to remotely aim and zoom the camera.

2. PTZ camera shall capture up to 100-megapixel panoramic images.

3. PTZ camera shall be able to simultaneously time-lapse multiple different areas.

4. PTZ camera shall meet the following specifications:

a. Type: Heavy Duty.

b. Mount Type: Pendant.

c. Enclosed.

d. User controlled robotic panning (360°) and tilting

e. 10x optical zoom

f. 1920x1080 pixel HD resolution

g. 4.7-47mm focal length

h. Auto-focus including positioning and manual focus adjustment as required for all web cameras, optimization of camera setup for available bandwidth and lighting at the Internet connection source and camera location(s) and configuration of pre-sets and bounds for Pan-Tilt-Zoom web cameras.

i. Horizontal field of view of 61.8°

j. Max 20lbs weight

k. System dimensions of 14.9 x 11.7 x 13.2”

l. Operational conditions shall be -25° to 140°F.

m. Power supply: battery with solar battery backup system.

n. Connectivity: Capable of wired ethernet, wireless ethernet and cellular modem web camera connections. Web camera service to include delivery of cameras and all related equipment.

o. Wireless component, for wireless connection web cameras.

p. For cellular connection web cameras:

1) Modem; Modem bracket; Antenna.

http://www.truelook.com/

01 31 35 - 4

q. Additional/Optional equipment or components as required to complete installation and expressly agreed.

r. Provide additional equipment not specified in these specifications but necessary to make the system complete and operational.

PART 3 EXECUTION

3.01 IMPLEMENTATION

A. Maintain and manage video system and services. Data and stored information shall belong to the Contractor, who has sole responsibility for the system.

B. Coordinate location of the PTZ camera with COR so as not to impact Contractor’s construction activities.

1. Elevated/overhead vantage point is preferable.

C. Locate the cameras with approval by the COR:

1. Upstream part of the service spillway viewing the dam crest.

D. Finish installing PTZ cameras at least 5 days prior to beginning of construction.

E. All PTZ furnish cameras to the Government upon completion of work under this contract.

F. Static images captured and archived from each web camera’s live image stream at 15-minute intervals during onsite work. Integrated commenting and tagging of static images to allow for isolation of issues for report generation.

G. Time lapse videos created and archived from the images captured by each web camera’s live image stream beginning at the sixtieth (60th) day of active hosting for the web camera’s image stream. Update time lapse videos on a weekly basis.

H. Share access to system and data with the Government for contract purposes.

I. In accordance with Reclamation Directive and Standard RCD 05-01, information received, created, or compiled by Reclamation officials, employees, contractors, and other staff (employees) is the property of the Federal Government and shall be maintained in accordance with established standards.

1. The system data shall not be considered as…