Soldiers Barrack Roof Prebid meeting minutes Jan 4 2022.pdf
PDF 128 KB Posted
- Solicitation number
- RFQ 171 230000000102 6
- Issued by
- Luce County, Mcbride Village, Michigan
About this file
This document is a pre-bid meeting minutes record for the Soldiers Barrack Roof project at Fort Mackinac, managed by Mackinac State Historic Parks. The project involves roof replacement work at the historic soldiers' barracks structure located on Mackinac Island. A pre-bid meeting was conducted on January 4, 2023, at 1:00 PM, with a site walk-through performed at the conclusion of the meeting. Bids are due by January 18, 2023, at 2:00 PM, with bid security required at the time of submission. The project scope includes roof replacement and removal of existing shingles, with vendors responsible for procuring and arranging for dumpster services. Equipment access to the site is restricted by a gate width limitation of 7 feet 10 inches, which vendors must account for in their planning and material movement logistics.
Key considerations for bidders include that vendors may use their own equipment to transport shingles from the project site to the dumpster located in the park service yard, subject to the gate width restriction. The agency clarified that no asbestos assessment has been performed on the existing roof, and bidders should review Article 2 of the bid documents regarding hazardous materials and environmental requirements. The agency committed to expediting approval of any repair work discovered during roof removal to minimize project delays. The bid documents include a schedule of alternates on page 4, allowing vendors to propose alternative materials. The agency indicated it would consider contractor input regarding specifications such as stainless steel versus galvanized nails and the inclusion of a breather system, though these items do not represent changes to the project documents unless subsequently formalized through an addendum.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
751/22340.AGY
Fort Mackinac Soldier’s Barrack Roof
Pre-bid Meeting Minutes
January 4, 2023
A. Meeting began at 1:00 PM
B. Followed agenda
1) Bidder responsible for familiarity with all documents and requirements.
2) Date and time of bid opening: January 18th, 2023, 2:00pm
3) Bid security due by bid opening.
4) Reviewed scope of work and forms to be submitted as well as projects dates and contact information.
5) Reviewed special conditions for use of vehicles on Mackinac Island.
6) Reviewed vendor responsibility for procuring dumpster and arranging for it to be emptied.
C. Questions
1) Question: Bidder raised concerns that method of moving shingles from project site to vendor provided dumpster. Concerns that the state park would not be able to keep up with the rate of shingle removal from the building if the park was hauling it out by dray. Asked if vendor could use own equipment to move shingles to dumpster in park service yard.
Answer: Yes—vendor can use own equipment to move shingles from project site to dumpster. Equipment will be limited by width of gate into Fort Mackinac – 7’ 10”.
2) Question: Has asbestos assessment been performed.
Answer: No—Reviewed Article 2 Hazardous Materials/Environmental Request.
3) Question: Bidder raised concerns on agency turnaround on approval of repair work needed but not discovered until existing roof is removed and having a long delay as approval is waited to perform repairs.
Answer: In the interest of both the contractor and the agency to complete the project, the approval would be expediated to the maximum extent possible.
4) Question: Can product materials be listed as alternates on the bid document?
Answer: There is a schedule of alternates listed on page 4 of bid documents.
5) Question: Bidder asked about stainless steel vs. galvanized nails?
Answer: Agency will take into consideration.
6) Question: Why is a breather not being required.
Answer: Mackinac State Historic Parks has generally not required the use of a breather. Agency will take into consideration.
D. Reiterated that nothing stated in the prebid meeting will change project documents unless subsequent addendum is issued.
E. Performed site walk through.
F. Meeting ended at 1:45pm.