This is Construction Addendum No. 2 issued by the Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division for the Fort Mackinac Soldiers Barracks Roof Project (File Number 751/22340.AGY). The addendum provides clarifications and modifications to the original Request for Proposal. Project Director Myron Johnson issued this addendum on January 6, 2022, with a proposal due date of January 18, 2023. The project scope involves roofing installation work, specifically addressing specifications for cedar shingles and ice and water membrane installation across the roof areas.
The addendum clarifies two key specifications: First, bidders must disregard references to "shakes" and instead focus on cedar shingle specifications requiring installation of Number 1 grade, 100% heartwood, 100% clear, and 100% edge grain "Blue Label" 18-inch Western red cedar shingles at 5-inch exposure, with Number 2 or 3 grade shingles acceptable for starter courses. Second, the ice and water protection requirements specify installation of "Winterguard" or equivalent ice and water membrane over all roof areas, with eaves requiring two courses of 36-inch wide membrane featuring minimum 3.5-inch side laps and 6-inch end laps. No pricing information, set-asides, incumbent details, or funding sources are detailed in this addendum document.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 2/22)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION ADDENDUM NO. 2
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.
Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
01/06/2022
PROJECT NAME
Fort Mackinac Soldiers Barracks Roof Project
FILE NUMBER
751/22340.AGY
PROJECT DIRECTOR
Myron Johnson
PROPOSAL DUE DATE:
1/18/2023
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
A. “Clarification—Bidders advised to disregard the term “shakes” in bullet point 9 of scope.
Specifications for cedar shingles are stated in bullet point 10: “Vendor shall install new Number 1 grade, 100% heartwood, 100% clear, and 100% edge grain “Blue Label” 18”, Western red cedar shingles at recommended 5 ½ inch exposure. Number 2 or 3 grade shingles are acceptable for starter courses.”
B. Emailed question: “Ice and water over the entire roof?”
Answer: Bidders to be guided by bullet point 8 under project scope: “Vendor shall install
“Winterguard” (or equivalent) ice and water membrane over all roof areas. For eaves, two course of
36” wide I & W with minimum 3.5” side laps and 6-inch end laps.”
APPROVED BY:
PROJECT DIRECTOR DATE