Scope of Work and Specifications Revised per Addendum 2-KA2601 Scope of Work and Specifications Revised per Addendum 2.pdf
PDF 158 KB Posted
- Solicitation number
- B27000570
- Issued by
- Kauai County, Hawaii
About this file
This Scope of Work and Specifications document, revised per Addendum No. 2 dated October 30, 2026, outlines repair requirements for the marginal wharf at Kikiaola Small Boat Harbor in Kekaha, Kauai, Hawaii, following damage from Hurricane Lowell. The project is managed by the State of Hawaii Department of Land and Natural Resources Division of Boating and Ocean Recreation (DOBOR). A mandatory site inspection and assessment by prospective contractors prior to the bid opening date is a hard eligibility requirement; bids from contractors who have not completed the site visit will not be accepted. Site visit arrangements must be coordinated with Kauai District Manager Jeremiah Aguilera at (808) 652-3660, (808) 241-3115, or jeremiah.g.aguilera@hawaii.gov. The project completion timeline is 90 consecutive calendar days from notice to proceed, with liquidated damages assessed at $100 per calendar day for delays. The estimated construction cost is $1 million, and award is anticipated within 90 days of bid opening.
The scope of work includes complete demolition and removal of the existing wooden superstructure (beams, decking, steel pipe pile attachments, and hardware), site preparation of steel pipe piles and concrete abutments, and installation of new marginal wharf components using marine-grade lumber with Chemonite ACZA pressure treatment, 316 stainless steel hardware, and cast aluminum cleats (Schoellhorn-Albrecht S1224-15 or approved equivalent). The contractor must dispose of all construction waste at the nearest County landfill with documentation provided. The contract includes five line items: mobilization/demobilization (not to exceed 10% of items 2-4), best management practices installation and maintenance, demolition and waste removal, marginal wharf repair, and a $100,000 allowance for Engineer-directed additional work. The contractor must hold a State Class "A" General Engineering license, furnish performance and payment bonds equal to 100 percent of contract price, maintain $1 million per occurrence general liability insurance and $1 million combined single limit auto liability insurance, and comply with prevailing wage requirements. Price preferences of 10% for recycled products and 5% for bidders registered with the State Department of Labor and Industrial Relations for apprenticeable trades apply. DOBOR will obtain the required U.S. Army Corps of Engineers permit; no other permits are required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S-1
Job No. KA26-01 Kikiaola Small Boat Harbor
Hurricane Lowell Marginal Wharf Repair Kekaha, Kauai, Hawaii
Revised per Addendum No. 2 dated October 30, 2026
Scope of Work and Specifications
Site Inspection and Assessment:
Prior to bidding, the contractor shall visit the site for inspection and assessment to understand the existing conditions and full scope of work required to complete repairs. Confirmation of the completed site inspection and assessment prior to the bid opening date shall be noted on the bid proposal form. Additional work items may be necessary to complete the repairs that may not be shown on the plans; however, the contractor is responsible to account for all existing site conditions and their impact on the repair scope of work. Site visit arrangements shall be made by calling the DOBOR Kauai District Manager, Jeremiah Aguilera, at (808) 652- 3660 or (808) 241-3115 or via email at jeremiah.g.aguilera@hawaii.gov. Bids received from contractors who have not completed a site visit prior to the bid opening date will not be accepted.
Demolition, Removal, and Disposal:
The contractor shall fully remove the entire marginal wharf wooden superstructure including, but not limited to, beams, decking, steel pipe pile attachments/brackets, and hardware. Any bolts or extruding objects, metals, etc.
attached to the pipe piles and/or concrete abutments shall be cut flush to the concrete or pile. Cut bolts or metals at the concrete abutments shall be painted with corrosion resistant paint. The contractor shall also remove and dispose of the damaged section of concrete revetment cap and adjacent delaminated asphalt.
After demolition is complete, the only components of the marginal wharf that to remain should be the steel pipe piles and concrete abutments.
All construction waste shall be properly removed, hauled, and disposed of at the nearest County landfill or other appropriate disposal site for construction waste. The contractor shall provide documents showing that all concrete waste was disposed of at the nearest County landfill or other appropriate disposal site for construction waste including landfill receipts or other documents.
Site Preparation:
The contractor shall prepare the steel pipe piles as necessary to accommodate the new marginal wharf attachment brackets. The existing concrete abutments shall be cleared of all debris and prepared for attachment of the new marginal wharf superstructure. The contractor shall provide adequately sized bearing plates on each pipe pile to properly support the new wharf superstructure. Bearing plates shall be provided with the contractor’s submittals/shop drawings for approval by the Engineer.
Repair:
The contractor shall follow the repair plans attached to this solicitation with additional annotations noted in red and blue. The contractor may follow the connection bracket detail show on the repair plans if feasible, otherwise the contractor shall design their own angles, brackets, hardware, etc. to provide connection of the new wharf superstructure to the existing pipe piles. Submittal/shop drawings shall be provided for review and approval by the Engineer. All hardware including bolts, washers, lag screws, etc. shall be 316 stainless steel.
All beams and decking shall be constructed of marine-grade lumber with Chemonite ACZA pressure treated wood or approved equal. All cleats shall be 15” cast aluminum, 2-hole cleats, Number S1224-15 by Schoellhorn-Albrecht or approved equal.
mailto:jeremiah.g.aguilera@hawaii.gov
Job No. KA26-01 Kikiaola SBH Hurricane Lowell Marginal Wharf Repair Scope of Work and Specifications – Revised per Addendum No. 2 dated October 30, 2026
Permits:
DOBOR will apply for and obtain the required U.S. Army Corps of Engineers (USACE) permit. No other permits are required for this project. DOBOR is exempt from County SMA and building permits. Construction work shall commence immediately upon receipt of the USACE permit.