S02 - Solicitation - 36C25921R0082.docx
DOCX document 254 KB Posted
- Solicitation number
- 36C25921R0082
About this file
This solicitation is for installation of partitions at check-in desks at the Rocky Mountain Regional Veterans Affairs Medical Center in Aurora, Colorado. The contractor shall provide all labor, materials, and equipment to demolish existing desks and casework and install new desks and partitions based on provided drawings and specifications. The work includes electrical, data, and button installation and must restore surrounding spaces. The performance period is 240 calendar days from notice to proceed. Proposals are due by February 11, 2022 and must include past performance information and pricing on the SF1442 form. The work is set aside for verified service-disabled veteran-owned small businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 08 - Drawings for RFI 2 project 554-20-103.pdf | ||
| 36C25921R0082 0008.docx | DOCX document | |
| 36C25921R0082 0007.docx | DOCX document | |
| 36C25921R0082 0006.docx | DOCX document | |
| 36C25921R0082 0005.docx | DOCX document | |
| 36C25921R0082 0004.docx | DOCX document | |
| Amendment 03 - 36C25921R0082 0003.docx | DOCX document | |
| Amendment 02 - 36C25921R0082 0002.docx | DOCX document | |
| S04 - 2022-01-28-RFI_No_1-Project_554-20-103_Install_Partitions_at_Check-In_Desks-VEG-20-16.pdf | ||
| S04 - Site Visit Attendance.pdf | ||
| S06 - Amend 0001 - 36C25921R0082 0001.docx | DOCX document | |
| S02 - Drawings Part 4.pdf | ||
| S02 - Drawings Part 3.pdf | ||
| S02 - Drawings Part 2.pdf | ||
| S02 - Drawings Part 1.pdf | ||
| S02 - Specifications.pdf | ||
| S02 - ICRA.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25921R0082
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25921R0082
X
554-20-103 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 daniel.payne@va.gov
Daniel Payne 303-712-5827
The contractor shall furnish all labor, equipment, materials, and supervision to install partitions at check-in desks at Rocky Mountain Regional VAMC, 1700 N. Wheeling St, Aurora CO 80045.
Project magnitude: between $500,000 and $1,000,000. The NAICS code is 236220 - Small Business size standard is $39.5 M
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both ISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to close of solicitation.
All questions in relation to this solicitation must be submitted in writing via e-mail to daniel.payne@va.gov and received no later than January 26, 2022 at 1:00 P.M. Mountain Time (MT).
A site visit will be held on January 18, 2022 at 9:30 A.M. MT.
Please meet me in front of the Building K sign across from the coffee shop at the North Entrance.
Instructions, Conditions, and Notices to Offerors. All submitted proposals must be received in email by the closing date and time. This solicitation closes February 11, 2022 at 1:00 P.M. MT.
Proposals shall be submitted via e-mail in accordance with Part I/Section B, to be considered for this project.
Proposals received in any other format will result in the offeror's proposal not receiving further consideration.
A hard copy bid bond must be received at the address listed in block 7 prior to the closing date and time.
52.211-10
1:00 PM
MST
02-11-2022
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300
Financial Service Center PO Box 149971 Austin TX 78714-9971
Table of Contents
| A.3 Bid Schedule | 5 |
| A.4 Statement of Work | 6 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 12 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 19 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 19 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 19 |
| 2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) ALTERNATE I (MAY 2014) | 19 |
| 2.4 52.233-2 SERVICE OF PROTEST (SEP 2006) | 20 |
| 2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 21 |
| 2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 21 |
| 2.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 22 |
| 2.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 22 |
| REPRESENTATIONS AND CERTIFICATIONS | 23 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) | 23 |
| 3.2 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) | 26 |
| 3.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 28 |
| 3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 30 |
| 3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 32 |
| GENERAL CONDITIONS | 33 |
| 4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 33 |
| 4.2 52.219-14 LIMITATIONS ON SUBCONTRACTING (SEP 2021) | 34 |
| 4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021) | 35 |
| 4.4 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014) | 38 |
| 4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021) | 39 |
| 4.6 SUPPLEMENTAL INSURANCE REQUIREMENTS | 42 |
| 4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 43 |
| 4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 46 |
| 4.9 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 46 |
| 4.10 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 46 |
| 4.11 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 48 |
| 4.12 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION) | 49 |
| 4.13 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 50 |
| 4.14 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 50 |
| 4.15 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 51 |
| 4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 54 |
| 4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 55 |
| 4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 56 |
| 4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 56 |
| 4.20 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 56 |
| 4.21 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 57 |
| 4.22 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 59 |
| 4.23 Wage Determination | 59 |
| 4.24 List of Attachments | 64 |
A.3 Bid Schedule Bid Schedule The contractor shall furnish all labor, equipment, materials, and supervision to install partitions at check-in desks at Rocky Mountain Regional VAMC, 1700 N. Wheeling St, Aurora CO 80045.
The contractor shall include prices for all items listed in the pricing schedule and include all costs associated for work in the SOW, whether or not specifically listed in the pricing schedule. Work will be accomplished at the Rocky Mountain Regional VAMC, 1700 N. Wheeling St, Aurora CO 80045.
| CLIN |
| Description |
| Qty |
| Unit of issue |
Firm Fixed Price Lump Sum Total amount
| 0001 |
| Base Pricing |
(SEE SOW FOR DETAILS)
Provide all work as described by attached plans, specifications, and Wage Determinations for Veterans Administration project VA Project 554-20-103 Install Partitions at Check-In Desks at the Rocky Mountain Regional VAMC as described in the attached scope of work. Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 240 calendar days from receipt of notice to proceed.
| 1 |
| Job |
| $_________ |
Grand Total $_________________
A.4 Statement of Work Install Partitions at Check-In Desks Project Number 554-20-103 Rocky Mountain Regional Veterans Affairs Medical Center (RMRVAMC)
1.0 – OBJECTIVE:
The Department of Veteran’s Affairs has a requirement to improve patient privacy and traffic flow to and from the check-in desks by providing a system that will maximize the usability and privacy of the check-in desks in buildings A, E, & G at the Rocky Mountain Regional VA Medical Center located at 1700 N. Wheeling St, Aurora CO 80045.
2.0 – STATEMENT OF WORK
The contractor shall provide all labor, materials, and equipment to demolish and install new check-in desks at 15 locations throughout the VA hospital.
This work will require demolition of existing desks/casework and surrounding flooring and subsequent construction and installation of new desks/casework based on the design shown in the associated drawings and specs. The surrounding space must be restored to equal or better condition upon completion of the work including but not limited to dry wall, paint, and flooring. This work will require electrical and data/low voltage to be removed from the existing desk and reinstalled in the new desk as well as code yellow buttons.
The contractor will be required to set up ICRA level 3 containment around each desk/work area for the duration of the work. The containment should not impede the ability for patients and staff to travel through the waiting space.
The contractor should plan on storing all materials and tools offsite until the time of work as there is no provided storage space on VA property.
3.0 GENERAL:
Contractor and/or Sub-contractors shall attend a pre-bid walkthrough of the work before submitting a bid. The date and time of this walkthrough will be determined by the Contracting Officer’s Representative (COR). Contractor and/or subcontractors shall be responsible for making any clarification requests that arise at the pre-bid walkthrough directed to the VAMC’s COR prior to the bidding of work. VA reserves the right to reject a bid from a contractor who did not attend the pre-bid walkthrough.
The Department of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations 29, Part 1926. This includes the requirement that the contractor have a “Competent Person” on the job at all times (must have a 30-hour OSHA card), and that all contractor employees have received a minimum of ten (10) hours of OSHA construction safety training.
Contractor must submit a Site-Specific Safety Plan (SSSP) to include Activity Hazard Analysis (AHA) or Job Hazard Analysis (JHA) for each construction activity. This plan shall detail fire, construction and health-related safety measures, in addition to listing training records for all employees for the previous year.
This project shall conform 100% to all VA standards and specifications, OSHA, AIA Construction Guidelines, Joint Commission Environment of Care Standards, and applicable building codes. In addition, any part of any VA specification that is not up to current design and construction practice shall be brought to the attention of the CO and COR for further evaluation. Design is to follow all information outlined in VA Technical Information Library (TIL) located at http://www.cfm.va.gov/til/dGuide.asp unless otherwise approved in writing by VA.
Contractor shall completely prepare site for building operations, including any necessary demolition and removal of existing materials and structures, and furnish labor and materials to perform all work. Actual dimensions shall be verified by contractor before start of work. All utility shutdowns shall be coordinated with COR at least 14 days prior.
4.0 PROJECT MANAGEMENT:
Based on the above list of work items the general contractor selected must successfully manage a variety of trades and tasks, coordinate just-in-time delivery of materials, get those materials to the job site, and schedule the necessary labor to construct various parts of this project in a timely fashion. Therefore, a critical aspect of this contract is construction management including but not necessarily limited to:
| • | Scheduling using the critical-path-method |
| • | Running and documenting an OSHA-compliant construction safety program |
| • | Managing job site access and security |
| • | Getting all employees VA ID badges |
| • | Managing the separation of construction activities from on-going hospital patient-care operations. |
| • | Implementing and maintaining required interim life safety measures as needed. |
5.0 - APPLICABLE DOCUMENTS:
VA Barrier Free Design Standard -2017 Architectural Barriers Act Accessibility Standards (ABAAS) - 2015 VA Bariatric Safe Patient Handling and Mobility Guidebook - 2015 VA Architectural Design Manual – 2014 Project Drawings
VA Specification sections include but are not limited to:
| 00 01 10 | Table of Contents |
| 00 01 15 | List of Drawing Sheets |
| 01 00 00 | General Requirements |
| 01 32 16.15 | Project Schedules (Small Projects – Design/Bid/Build) |
| 01 33 23 | Shop Drawings, Product Data, and Samples |
| 01 35 26 | Safety Requirements |
| 01 42 19 | Reference Standards |
| 01 45 00 | Quality Control |
| 01 57 19 | Temporary Environmental Controls |
| 01 58 16 | Temporary Interior Signage |
| 01 74 19 | Construction Waste Managements |
| 06 10 00 | Rough Carpentry |
| 08 80 00 | Glazing |
| 09 65 13 | Resilient Base and Accessories |
| 09 84 33 | Sound-Absorbing Wall Units |
| 12 32 00 | Manufactured Wood Casework |
| 12 36 00 | Countertops |
| 26 05 11 | Requirements for Electrical Installations |
| 26 05 19 | Low-Voltage Electrical Power Conductors and Cables |
| 26 05 33 | Raceway and Boxes for Electrical Systems |
| 27 05 11 | Requirements for Communications Installations |
| 27 05 26 | Grounding and Bonding for Communications Systems |
| 27 05 33 | Raceways and Boxes for Communication Systems |
| 27 15 00 | Communications Structured Cabling |
Further VA specification sections available at the VA Technical Information Library: https://www.cfm.va.gov/til/spec.asp
6.0 - CODE & REGULATION COMPLIANCE:
The Contractor shall comply with public laws and statutes including all changes and amendments to federal, state and local environmental statutes and regulations in effect the date of issuance of this delivery order, including applicable portions of the documents cited in the basic contract and below:
1. NFPA 99-2015 Healthcare Facilities Codes.
1. 29 CFR 1910 Occupational Safety and Health Standards
1. 29 CFR 1926 Occupational Safety and Health Standards
1. ANSI/ASSE Z359
1. Acquiring permits for and managing hot work operations
1. Coordinating with VA construction personnel and other VA hospital personnel to maintain acceptable conditions for all on-going hospital functions affected
7.0 SUBMITTALS:
Contractor shall submit the following:
· Cost-Loaded Schedule within ten (10) calendar days of Notice to Proceed (NTP).
· Site-specific Safety Plan within ten (10) calendar days of NTP.
· Copies of manufacturer’s specifications for all materials and equipment planned for installation
· Dimensioned shop/site drawings and manufacturer’s details as noted in VA Specifications
· Inspection reports, manufacturer approval certificates and warranties as noted in specifications
· Site superintendent OSHA-30, and tradesmen/laborer OSHA-10 certificates. The site superintendent that meets these requirements must be on-site anytime work is being performed. Copies of the certifications shall be provided to the COR within ten (10) calendar days prior to start of work.
8.0 RESOURCES:
The Government will not furnish any resources for the fulfillment of services required under this contract. Contractor must provide all tools, equipment, materials, transportation, professional expertise, personnel, and supervision required under this contract.
9.0 TECHNICIAN/INSPECTOR QUALIFICATIONS:
The Government reserves the right to accept or reject Contractor’s staff for cause. Documented prior the work, Contractor shall provide technicians throughout the contract qualified to perform work. The Contractor shall notify the Government within 3 business days if it intends to replace a technician. At the time of notification, the Contractor shall submit all required certifications for all personnel working on the contract. In the event new, or replacement, personnel become involved in the contract, the Contractor must submit all required certification. Additions or changes in personnel require written approval of the Government. The Contractor shall have a back-up technician available in the event the primary technician is unable to perform his/her duties.
The Contractor shall ensure their personnel and subcontractor-personnel meet the privacy standards as set forth by HIPAA (Health Insurance Portability and Accountability Act of 1996) with respect to personal and confidential information that they may come upon, while contract work is being performed.
10.0 PERSONNEL ASSIGNMENTS:
The Contractor shall assign the appropriate quantity and type of personnel to successfully complete all functions specified in this SOW. The Contractor shall maintain throughout the life of this contract, a current list of technicians and their credentials available for inspection by the Government at any time.
11.0 ACCEPTANCE STANDARDS:
The VA reserves the right to dispute completion of contract scope if contract work is found not in accordance with manufacturer recommendations, is not satisfactorily executed, or if the system is not properly tested and inspected to achieve certification. All work completed by the Contractor must be reviewed and approved by the VA.
12.0 HOURS OF WORK:
Construction activities shall be conducted during off hours Monday thru Friday from 1700 hrs. to 0600 hrs. as well as over weekends (Saturday and Sunday) to lessen the impact on the facility. Work may also include Federal Holidays and any other day declared a federal holiday by the President of the United States listed below. Barricades, ICRA containment provisions shall be arranged to allow patients and staff unimpeded access (including wheelchairs and patient beds where applicable) to services and resources within the facility.
| New Year’s Day | Martin Luther King Jr’s Birthday | Presidents Day | ||
| Memorial Day | Juneteenth | Independence Day | ||
| Labor Day | Columbus Day | Veterans Day | ||
| Thanksgiving Day | Christmas Day |
If a holiday falls on Sunday, the following Monday will be observed as the National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by the U.S. Government agencies.
Upon arrival at the station, Contractor shall check-in with the COR and/or designee.
If contract work is delayed due to inclement weather the contractor shall inform the COR of said delay and submit an updated schedule.
There is NO SMOKING on any VA property.
13.0 MEETINGS:
A kick-off meeting and site walk will be held at a date and time specified by the COR to review project scope, site, and requirements, as well as provide answers to any questions.
Contractor shall begin work within ten (10) days of Notice to Proceed (NTP). Contractor shall meet with the COR weekly following NTP to provide progress-updates and attend a closeout meeting at period of performance end.
14.0 BADGES AND PARKING:
All Contractor personnel are required to comply with VAAR 852.273-74 (Available online at VA Technical Information Library) which covers the following requirements: Background checks, and the wearing of identification (I.D.) badges issued by the VA RMRVAMC while on VA property. Contractor must acquire PIV badge for all staff onsite prior to work beginning. Failure of the background check may result in specific personnel not being allowed to work on VA premises and the Contractor will need to provide replacement personnel. Contractor to take into account lead-time on PIV Badging process (usually 2+ weeks).
It is the responsibility of the Contractor’s personnel to park in the appropriate designated parking areas. The designated parking area will be specified by COR upon award of contract.
15.0 KEYS:
Under no circumstances are Contractor personnel to remove VA keys from VA premises. Lost keys shall be replaced by contractor at costs beginning at $250.00/key. Cost to replace lost keys varies based on scope of access provided by keys.
16.0 VHA Supplemental Contract Requirements for Combatting COVID-19:
1. Contractor employees who work in or travel to VHA locations must comply with the following:
a. Documentation requirements:
1) If fully vaccinated, contractors shall show proof of vaccination.
i. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.
2) If unvaccinated, contractors shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test that includes an affiliated telehealth service.
3) Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
4) Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
2. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
a. Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
3. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
For indefinite delivery contracts: Contractor agrees to comply with VHA Supplemental Contract Requirements for any task or delivery orders issued prior to this modification when performance has already commenced.
17.0 PERIOD OF PERFORMANCE:
Period of performance including lead time for materials and submittals: two hundred and forty (240) calendar days from NTP.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR PROPOSAL
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ prior to award.
I.2A SELECTION PROCEDURES
This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.
I.3A PRE-PROPOSAL SITE VISIT
See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.
I.4A SELECTION CRITERIA
This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.
The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:
Factor 1 – Past Performance Factor 2 – Price In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
Past performance will be evaluated on a basis of significantly more important than, cost or price.
Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:
| ASSESSMENT |
| DESCRIPTION |
| Substantial Confidence | |
| Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort. |
| Satisfactory Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort. |
| Limited Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort. |
| No Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort. |
| Unknown Confidence (Neutral) |
| No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. |
Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.
(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.
| (1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection. | |
| (2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror. | |
| (b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment. |
Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.
Factor 1-Past Performance
(a) Solicitation Submittal Requirements:
Offerors shall provide a maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings, and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Daniel Payne, daniel.payne@va.gov.
Recency – a recent project is defined as being completed within five years of the due date of this solicitation.
Relevant – includes performance of efforts in a project of renovation or remodeling that include general construction in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.
Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.
(b) – Basis of Evaluation:
The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.
Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.
If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.
If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.
Factor 2 – Price:
(a) Solicitation Submittal Requirements:
· Standard Form 1442, Solicitation Offer and Award
· All pages of the SF1442 Continuation Sheet
(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
· Comparison of proposed prices received in response to the RFP
· Comparison of proposed prices with the IGCE.
· Comparison of proposed prices with available historical information.
Special Standard of Responsibility Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
1. OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.
2. Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
3. Limitation on Subcontracting:
IAW VAAR 852.219-77 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal documents. Failure to comply with this requirement will result in removal of proposal for consideration for award.
Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Between $500,000.00 and $1,000,000.00
I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.
I.3B METRIC PRODUCTS:
Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.
If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
I.4B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.5B PROPOSAL REQUIREMENTS
General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email daniel.payne@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.
Proposals shall be received by 1:00 P.M. Mountain Time on February 11, 2022. There will be no public opening of the proposals. Submit proposals to: daniel.payne@va.gov.
Submit bid bonds to:
Department of Veterans Affairs
NCO 19
ATTN: Daniel Payne 6162 S Willow Dr., Ste 300 Greenwood Village, CO 80111
Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
I.6B PROPOSAL REVISIONS
If it is determined to be necessary, proposal revisions will be requested from the offers received. The Contracting Officer may identify those offerors, whose proposals are within the competitive range based upon the selection criteria identified in this solicitation. Negotiations may be conducted with those firms falling within the competitive range, after which proposal revisions may be requested. Offerors submitting proposal revisions will not be required to re-submit any documents which are unchanged from their proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with the Table of Contents that clarifies where within the initial proposal the additional information and/or changed document would be placed. A new bid bond shall be submitted only if the final cost proposal revisions are greater than its initial cost proposal.
1.7B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER
Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.
In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.
Acceptable Electronic Formats (Software) for Submission of Offers
1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files).
2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.
3. Another electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.
4. Please note that we can no longer accept .zip files due to increasing security concerns.
E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.
a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, Proposal, or Bid depending on the solicitation type.
b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.
c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.
Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)
The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipient’s “inbox” is the official record of receipt.
Security Issues, Late Bids, Unreadable Offers
1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.
2. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.
3. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).
4. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.
5. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) ALTERNATE I (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this…