Amend 08 - Drawings for RFI 2 project 554-20-103.pdf
PDF 2 MB Posted
- Solicitation number
- 36C25921R0082
About this file
This solicitation is for installation of partitions at check-in desks within multiple buildings on a Veterans Affairs medical center campus. The solicitation number is 36C25921R0082 and seeks to install partitions at check-in desks for project 554-20-103. The work will take place at 1700 North Wheeling Street in Aurora, Colorado and involves multiple buildings including buildings G, E, and A at levels 1, 2, 3 and 4. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19. Responses are due by February 15, 2021. The awarded contractor will be responsible for installation of partitions as demolition and new work plans according to provided architectural drawings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25921R0082 0008.docx | DOCX document | |
| 36C25921R0082 0007.docx | DOCX document | |
| 36C25921R0082 0006.docx | DOCX document | |
| 36C25921R0082 0005.docx | DOCX document | |
| 36C25921R0082 0004.docx | DOCX document | |
| Amendment 03 - 36C25921R0082 0003.docx | DOCX document | |
| Amendment 02 - 36C25921R0082 0002.docx | DOCX document | |
| S04 - 2022-01-28-RFI_No_1-Project_554-20-103_Install_Partitions_at_Check-In_Desks-VEG-20-16.pdf | ||
| S04 - Site Visit Attendance.pdf | ||
| S06 - Amend 0001 - 36C25921R0082 0001.docx | DOCX document | |
| S02 - Drawings Part 4.pdf | ||
| S02 - Drawings Part 3.pdf | ||
| S02 - Drawings Part 2.pdf | ||
| S02 - Drawings Part 1.pdf | ||
| S02 - Specifications.pdf | ||
| S02 - Solicitation - 36C25921R0082.docx | DOCX document | |
| S02 - ICRA.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J
H
G
F
E
D
C
B
08-01-G3-04
AUDIOMETRIC
EXAM 4
08-01-C2-02
PAT TLT 1
08-01-G1-03
AUDIO TECH 3
08-01-H2-02
AUDIOLOGIST 6
08-01-E3-02
GROUP RM
08-01-F3-02
SPEECH 1
08-01-B3-01
MULTIFUNCT
TREAT/WORK
08-01-A3-02
GYM
08-01-C4-01
EXAM/TREATMENT
08-01-A1-01
WAIT
08-01-B3-03
TREAT 1
08-01-E2-01
SOILED UTIL08-01-E2-05
STAFF TLT 1
08-01-B4-05
PUBLIC TLT 1
08-01-B3-02
PUBLIC TLT 2
08-01-B3-04
OTBC TREAT
08-01-E2-02
STAFF TLT 2
08-01-E2-04
STAFF TLT 4
08-01-B2-03
OTBC
ORTHO/SPLINTING
08-01-C2-01
PAT TLT 2
08-01-E2-06
STAFF OFFICE 1
08-01-F2-01
AUDIOLOGIST 8
08-01-C2-04
STAFF OFFICE 3
08-01-H3-01
SINUSODIAL TEST
08-01-H4-01
PUBLIC TLT 3
08-01-B2-01
HAC
08-01-G4-02
WAIT
08-01-G3-03
AUDIOLOGIST 5
08-01-H4-02
CHIEF OFFICE
08-01-H3-07
SOC WORKER 4
08-01-H2-04
CONSULT
08-01-H2-06
OFFICE 6
08-01-H2-05
OFFICE 5
08-01-H2-07
INTERN OFFICE
08-01-H1-01
OFFICE
08-01-H1-02
CHIEF OFFICE
08-01-H1-03
SECR/WAIT
08-01-G1-02
AUDIO TECH 2
08-01-G1-01
AUDIO TECH 1
08-01-F1-05
OFFICE 1
08-01-F1-04
OFFICE 4
08-01-E1-01
STAFF LOUNGE
08-01-G4-01
AUDIOLOGIST 3
08-01-G3-02
AUDIOLOGIST 2
08-01-F4-03
CAT WORK
08-01-F3-03
SPEECH
THERAPY IND
08-01-H2-03
INST CAL/STOR
08-01-G2-03
AUDIOMETRIC
EXAM 3
08-01-G2-02
AUDIOMETRIC
EXAM 1
08-01-G2-01
AUDIOLOGIST 1
08-01-F2-04
HEARING AID FAB
08-01-F2-05
AUDIOLOGIST 7
08-01-F4-02
WAIT
08-01-F2-03
RESIDENT OFFICE
08-01-F2-02
STAFF TLT 3
08-01-C2-03
EXAM/TREATMENT
08-01-B2-04
TELEHEALTH 1
08-01-B2-05
PAT TLT 1
08-01-G3-01
AUDIOMETRIC
EXAM 2
08-01-F3-04
SPEECH
ANALYSIS
08-01-F3-01
SPEECH 2
08-01-E3-03
W.C. REPAIR
08-01-E2-03
OT/PT DME 2
08-01-A3-01
PLATFORM
08-01-F4-01
SPEECH
THERAPY GROUP
08-01-A1-02
RECEPT
08-01-A2-02
O2 STOR
08-01-A2-04
O2 COORD 5
08-01-A2-03
O2 COORD 4
08-01-A2-10
CORRIDOR
08-01-A3-11
ELEV LOBBY
08-01-C3-01
EXAM/TREATMENT
08-01-C3-02
ELECTROMYOGRAPHY
08-01-D2-03
LINEN ALCOVE
08-01-C2-10
CORRIDOR
08-01-C3-11
CORRIDOR
08-01-F3-11
CORRIDOR
08-01-B2-02
SHARED OFFICE
08-01-C3-12
CORRIDOR
08-01-F1-03
OFFICE 3
08-01-F1-06
OFFICE 2
08-01-F1-02
OFFICE 6
08-01-F1-01
OFFICE 5
08-01-E1-03
OFFICE 8
08-01-E1-02
OFFICE 7
08-01-D1-04
CLERICAL 2
08-01-D1-03
CLERICAL 1
08-01-D1-02
PROV CONSULT
08-01-D1-01
CONSULT
08-01-C1-03
OFFICE
08-01-C1-04
OFFICE
08-01-C1-02
PAT RM
08-01-C1-01
BRACE REPAIR
LAB
08-01-B1-02
PUR OFFICE
08-01-B1-01
EQUIP STOR
08-01-H2-01
HAC
08-01-H3-06
SOC WORKER 3
08-01-H3-05
SOC WORKER 2
08-01-H3-04
SOC WORKER 1
08-01-H3-03
SECT AND WAIT 1
08-01-C4-04
EDUCATION/TRAIN
08-01-H3-02
VESTIBULOGRAPHY
08-01-G4-03
AUDIOLOGIST 4
08-01-D2-05
STAFF TLT
08-01-G3-11
CORRIDOR
08-01-H3-11
CORRIDOR
08-01-J3-11
CORRIDOR
08-01-C4-02
WAIT
08-01-A4-11
CORRIDOR
08-01-E3-11
CORRIDOR
08-01-D3-11
CORRIDOR
08-01-C3-03
OTBC GYM
08-01-D3-01
ADL TLT
08-01-E3-10
CORRIDOR
08-01-C3-10
CORRIDOR
08-01-B1-03
WORK AREA
08-01-A4-02
RECEPT
08-01-D3-02
FITNESS ROOM
08-01-D4-01
COMM CTR
08-01-D2-01
CLEAN SUPPLY
08-01-D4-02
RECEPT
08-01-F4-04
RECEPT
08-01-A3-03
WAIT
08-01-F1-07
CORRIDOR
08-01-C2-T1
DEMARC ROOM
08-01-D2-E1
ELEC
08-01-D2-H2
CHUTE
08-01-E2-T2
DATA /
TELECOMM
08-01-G2-E2
ELEC
08-01-H2-T3
DATA /
TELECOMM
08-01-ST2
STAIR
08-01-SE5
ELEV
DN
UP
A. DISCONNECT FURNITURE POWER CIRCUITS. PRESERVE CIRCUIT FOR
FUTURE REUSE.
B. DISCONNECT DATA OUTLETS FROM NETWORK. PRESERVE CIRCUIT FOR
FUTURE REUSE.
C. AREAS SHOWN FOR DEMO WORK ARE ALSO AREAS FOR NEW WORK. SEE
SHEETS ED111 AND EP111 FOR REFERENCE.
D. DISCONNECT DURESS ALARM FROM CIRCUIT, PRESERVE CIRCUIT FOR
FUTURE USE.
E. SYSTEM FURNITURE WILL HAVE CHASE/POWER WHIP FOR INSTALLATION.
COORDINATE INSTALLATION REQUIREMENTS USING ARCHITECTURAL
DRAWINGS.
F. VERIFY ELECTRICAL CIRCUITS, VIA TRACING PRIOR TO WORK START.
ED111
ED111
ED111
EP111
EP111
EP111
1 2 3
4 4
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:2
:1
P
M
ED101
DEMOLITION PLAN AT BUILDING G
(08) LEVEL 1
INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
1. REUSE EXISTING CIRCUIT 8-NL12-28 AND 8-NL12-30. USE EXISTING CONDUIT
FOR NEW CIRCUIT.
2. REUSE EXISTING CIRCUIT 8-NL12-86 AND 8-NL12-88. USE EXISTING CONDUIT
FOR NEW CIRCUIT.
3. REUSE EXISTING CIRCUIT 8-NL11-35 AND 8-NL11-39. USE EXISTING CONDUIT
FOR NEW CIRCUIT.
4. LOCATION OF ELECTRICAL ROOM(S) TO PERFORM WORK.
32'16'8'4'2'0'
N o rt h
1/8" = 1'-0"
DEMOLITION PLAN AT BUILDING G (08) LEVEL 1
2 ELECTRICAL UPDATES 03/09/2022
H
G
F
E
D
C
B
08-03-E3-09
HAC 3
08-03-E1-06
STAFF TLT
08-03-H2-06
CHIEF OF STAFF 3
08-03-G4-07
PERS ASST 7
08-03-G4-02
PERS ASST 8
08-03-H4-01
WAIT/RECEP
08-03-H2-02
STAFF ASST 4
08-03-B3-10
CORRIDOR
08-03-H2-08
CHIEF OF STAFF
2 08-03-F2-01
CONSULT 1
08-03-H2-07
HSS ASST 3
08-03-H3-01
OFFICE 2
08-03-F2-03
SOC WORK 1
08-03-H2-01
STAFF ASST 3
08-03-G2-02
WORK ALCOVE
08-03-G3-13
CORRIDOR
08-03-E2-06
CORRIDOR
08-03-F3-11
CORRIDOR
08-03-H1-02
MEDICAL CENTER
DIR
08-03-G1-02
CHIEF OF STAFF 1
08-03-F1-01
STAFF LOUNGE
08-03-E1-05
STAFF LOCKERS
08-03-H1-01
STAFF TLT
08-03-G1-04
HSS ASST 4
08-03-G1-03
HSS ASST 5
08-03-G1-01
HSS ASST 6
08-03-G2-01
OFFICE 1
08-03-H2-03
STAFF ASST 7
08-03-H2-05
STAFF ASST 5
08-03-H2-04
STAFF ASST 6
08-03-G4-05
PERS ASST 5
08-03-G4-03
PERS ASST 3
08-03-G4-08
PERS ASST 6
08-03-G4-06
PERS ASST 4
08-03-G4-04
PERS ASST 2
08-03-G3-10
MAN SPEC 1
08-03-G3-07
MAN SPEC 5
08-03-G3-04
MAN SPEC RESP
08-03-G3-11
MAN SPEC 2
08-03-G3-08
MAN SPEC 6
08-03-G3-05
MAN SPEC RES 2
08-03-G3-12
MAN SPEC 3
08-03-G3-09
MAN SPEC 7
08-03-G3-06
WORKSTATION 1
08-03-G2-06
MAN SPEC 4
08-03-G2-05
MAN SPEC 8
08-03-G2-04
MAN SPEC 9
08-03-G4-01
PERS ASST 1
08-03-G3-03
MAN SPEC RES 3
08-03-G3-02
MAN SPEC RES 4
08-03-G3-01
WORKSTATION 2
08-03-F4-03
SEC OFFICE
08-03-F3-04
WORKSTATION 1
08-03-F3-05
WORKSTATION 2
08-03-F3-06
WORKSTATION 3
08-03-F4-02
WAIT
08-03-F4-01
CONF
08-03-E4-03
CHIEF OFFICE
08-03-F3-03
PIV ROOM
08-03-F3-02
WORK
08-03-F3-01
SECURE WORK
08-03-B5-10
CORRIDOR
08-03-E4-04
BIOFEEDBACK
TECH
08-03-E3-06
BIOFEEDBACK
LAB
08-03-E3-07
COMM CTR
08-03-D4-05
PUBLIC TLT 2
08-03-H3-05
HSS ASST 2
08-03-H3-03
CHIEF OF STAFF 4
08-03-H3-04
DEPUTY CHIEF OF
STAFF
08-03-H4-02
HSS ASST 1
08-03-H3-02
CONF
08-03-G2-07
SHARED OFFICE
08-03-G2-08
CHIEF OFFICE
08-03-F2-07
PERS ASST 9
08-03-F2-06
WORKSTATION 5
08-03-E3-08
SEC 1
08-03-E3-01
SHARED OFFICE
08-03-E3-10
PSYCH OFFICE 12
08-03-E3-02
INTERN 1
08-03-E3-03
INTERN 2
08-03-E3-04
INTERN 3
08-03-E3-05
INTERN 4
08-03-D3-07
GROUP TEST
08-03-D3-06
PSYCH OFFICE 11
08-03-D3-05
PSYCH OFFICE 10
08-03-D4-06
PSYCH OFFICE 9
08-03-D3-01
MULTIPURPOSE/CONTROL
08-03-D3-02
CONTROL
08-03-D3-04
PSYCH OFFICE 8
08-03-D4-01
PSYCH OFFICE 7
08-03-D4-02
PUBLIC TLT 2
08-03-C4-05
WAIT
08-03-B4-03
WAIT
08-03-C3-06
EXAM 1
08-03-C3-05
PSYCH OFFICE 6
08-03-C3-04
PSYCH OFFICE 5
08-03-C3-03
PSYCH OFFICE 4
08-03-C4-06
COMM CTR
08-03-C4-04
WORKSTATION 1
08-03-C4-03
WORKSTATION 2
08-03-C3-01
HEALTH PSYCH
08-03-C3-02
PSYCH OFFICE 3
08-03-C4-01
PSYCH OFFICE 2
08-03-C4-02
PSYCH OFFICE 1
08-03-B3-01
VISN OFFICE 1
08-03-B3-02
VISN OFFICE 2
08-03-B3-07
CONSULT 2
08-03-B3-06
CONSULT 1
08-03-B3-05
WORKSTATION 1
08-03-B3-04
WORKSTATION 2
08-03-B4-05
WORKSTATION 3
08-03-B4-04
SCHED
WORKSTATION 1
08-03-B4-06
WORKSTATION 4
08-03-B3-03
EXAM 1
08-03-B4-01
VITAL SIGNS
08-03-A3-04
CONF
08-03-B4-02
PUBLIC TLT 1
08-03-A3-03
CLASSROOM 1 CLASSROOM 2
08-03-B2-06
CRASH CART
ALCOVE
08-03-A2-01
PUBLIC TLT 1
08-03-A2-02
STAFF TLT
08-03-B2-03
STRETCHER/W. C.
ALCOVE
08-03-B2-04
EXAM
08-03-B2-02
MED PREP
08-03-E1-03
RES
WORKSTATION 1
08-03-E1-01
NP PHY 3
08-03-D1-04
CHIEF NURSE 1
08-03-E1-04
NP PHY 2
08-03-E1-02
NP PHY 4
08-03-D1-05
NP PHY 1
08-03-D1-02
ASST DIET 1
08-03-D1-03
SUPP TECH 1
08-03-D1-01
CHIEF OFFICE
08-03-C1-03
ISO BED STATION
08-03-C1-02
DIALYSIS CHAIR 6
08-03-B1-04
DIALYSIS CHAIR 4
08-03-B1-02
DIALYSIS CHAIR 2
08-03-A1-03
RECEPT
08-03-A1-02
WAIT
08-03-A1-01
PAT ED KIOSK
08-03-A2-10
CORRIDOR
08-03-A3-11
ELEV LOBBY
08-03-B2-10
CORRIDOR
08-03-C1-01
DIALYSIS CHAIR 5
08-03-B1-03
DIALYSIS CHAIR 3
08-03-B1-01
DIALYSIS CHAIR 1
08-03-C1-04
ISO PAT TLT
08-03-F2-02
CONSULT 2
08-03-E2-04
EQUIP STOR
08-03-E2-03
STAFF TLT 1
08-03-E2-02
STAFF TLT 1 08-03-D2-03
EQUIP REPAIR
08-03-D2-02
EQUIP PROC
08-03-C2-05
DIALYSATE PREP
08-03-C2-04
WATER TREAT
08-03-C2-03
CLEAN SUPPLY
08-03-B2-01
NURSE STATION
08-03-B2-05
CORRIDOR
08-03-C2-01
HAC 1
08-03-D2-01
CLEAN LINEN
08-03-E2-01
SOILED UTIL
08-03-F2-04
WORKSTATION 4
08-03-E4-01
NEURO VOCA
REHAB
08-03-B3-11
CORRIDOR
08-03-C3-11
CORRIDOR08-03-D3-11
CORRIDOR
08-03-E3-11
CORRIDOR
08-03-H2-10
CORRIDOR
08-03-E4-02
PUBLIC TLT 3
08-03-C2-02
NOURISH
08-03-E2-05
LAB
08-03-E2-10
CORRIDOR
08-03-B5-10
CORRIDOR
08-03-A3-05
WAIT
08-03-H4-03
CORRIDOR
08-03-D4-07
CORRIDOR
08-03-D2-E1
ELEC
08-03-D2-H1
CHUTE
08-03-E2-T1
DATA /
TELECOMM
08-03-G2-E2
ELEC08-03-H2-T2
DATA /
TELECOMM
08-03-ST2
STAIR
08-03-SE5
ELEV
UP
DN
CR CR
A. DISCONNECT FURNITURE POWER CIRCUITS. PRESERVE CIRCUIT FOR
FUTURE REUSE.
B. DISCONNECT DATA OUTLETS FROM NETWORK. PRESERVE CIRCUIT FOR
FUTURE REUSE.
C. AREAS SHOWN FOR DEMO WORK ARE ALSO AREAS FOR NEW WORK. SEE
SHEETS ED111 AND EP111 FOR REFERENCE.
D. DISCONNECT DURESS ALARM FROM CIRCUIT, PRESERVE CIRCUIT FOR
FUTURE USE.
E. SYSTEM FURNITURE WILL HAVE CHASE/POWER WHIP FOR INSTALLATION.
COORDINATE INSTALLATION REQUIREMENTS USING ARCHITECTURAL
DRAWINGS.
F. VERIFY ELECTRICAL CIRCUITS, VIA TRACING PRIOR TO WORK START.
ED111
EP111
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:2
:1
P
M
ED102
DEMOLITION PLAN AT BUILDING G
(08) LEVEL 3
INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
1. REUSE EXISTING CIRCUIT AND CONDUIT FOR RECEPTACLES.
2. LOCATION OF ELECTRICAL ROOM(S) TO PERFORM WORK.
32'16'8'4'2'0'
N o rt h
1/8" = 1'-0"
DEMOLITION PLAN AT BUILDING G (08) LEVEL 3
2 ELECTRICAL UPDATES 03/09/2022
H
G
F
E
D
C
B
09-01-B4-01
OFFICE
09-01-B2-03
TRAVEL
09-01-B2-02
TRAVEL
09-01-B1-02
TRAINER
09-01-A1-01
STRETCHER/W.C.STOR
09-01-A4-03
OFFICE
09-01-B3-03A
OFFICE
09-01-A3-05
OFFICE
09-01-A3-04
OFFICE
09-01-B1-03
OFFICE
09-01-C1-01
OFFICE
09-01-G2-06
PHOTOTHERAPY
TREAT
09-01-G2-05
PHOTOTHERAPY
SHOWER
09-01-H2-02
MED PREP/STOR
09-01-H2-03
TREAT/PROCEDURE
09-01-A1-03
PHONE INTAKE
09-01-A1-02
PHONE INTAKE
09-01-B1-01
PHONE INTAKE
09-01-C2-04
PROCEDURE
09-01-B2-01
HAC
09-01-H4-02
EXAM
09-01-H3-07
EXAM
09-01-H3-06
EXAM
09-01-H3-05
EXAM
09-01-H2-06
EXAM
09-01-H2-05
EXAM
09-01-C3-05
NURSE
STATION/MED
09-01-E2-06
PROCEDURE
09-01-C3-08
WEIGHT STN
09-01-D3-02
WEIGHT STN09-01-E3-09
WEIGHT STN
09-01-F3-02
WEIGHT STN
09-01-E2-01
SOILED UTIL
09-01-B2-05
CLEAN SUPPLY
09-01-F2-01
CLEAN SUPPLY
09-01-B4-03
WAIT
09-01-G4-02
WAIT
09-01-H3-02
NURSE
STATION/MED
09-01-D2-02
EXAM
09-01-F2-03
CONSULT
09-01-H4-01
CONSULT
09-01-H1-03
OFFICE
09-01-H1-04
OFFICE
09-01-H1-05
OFFICE
09-01-H1-01
OFFICE
09-01-H1-02
OFFICE
09-01-G1-05
OFFICE
09-01-G1-06
OFFICE
09-01-G1-03
OFFICE
09-01-G1-04
OFFICE
09-01-G1-01
OFFICE
09-01-H2-04
DERMATOLOGY
LAB
09-01-F1-02
OFFICE
09-01-F1-03
OFFICE
09-01-D1-02
OFFICE
09-01-D1-01
OFFICE
09-01-D1-04
OFFICE
09-01-D1-05
OFFICE
09-01-D1-06
OFFICE
09-01-C1-05
OFFICE
09-01-C4-03
ONSTAGE AREA
09-01-E4-03
ONSTAGE AREA
09-01-C3-07
PRECEPTOR RM
09-01-F2-02
PRECEPTOR RM
09-01-G3-08
WEIGHT STN
09-01-H3-04
WEIGHT STN
09-01-C1-06
OFFICE
09-01-C1-03
OFFICE
09-01-C1-04
OFFICE
09-01-B1-06
OFFICE
09-01-G2-02
HAC
09-01-E2-04
CONSULT
09-01-G4-03
ONSTAGE AREA
09-01-F1-01
CONF
09-01-E1-02
STAFF TLT
09-01-G2-01
SOILED UTIL
09-01-B2-07
WAIT
09-01-B2-04
TRAVEL
09-01-D4-03
WAIT
09-01-C4-02
WAIT
09-01-B1-05
OFFICE
09-01-B1-04
OFFICE
09-01-E2-05
EQUIP STOR
09-01-A3-06
RECEPT
09-01-E4-02
WAIT
09-01-F4-03
WAIT
09-01-B3-05
CORRIDOR
09-01-C3-06
CORRIDOR
09-01-E3-07
CORRIDOR
09-01-G3-06
CORRIDOR
09-01-H3-03
CORRIDOR
09-01-E1-01
STAFF TLT
09-01-D4-01
PUBLIC TLT09-01-F4-01
PUBLIC TLT
09-01-E1-03
STAFF LOUNGE
09-01-D1-03
SECRETARY
09-01-A2-01
CONSULT
09-01-A1-04
CORRIDOR
09-01-B4-02
EXAM/FITTING
09-01-G3-04
CORRIDOR
09-01-H3-01
STAFF TLT
09-01-G3-05
PAT TLT
09-01-E3-08
PRECEPTOR RM
09-01-G3-07
PRECEPTOR RM
09-01-F3-01
PAT TLT
09-01-E3-05
STAFF TLT
09-01-E3-06
CLEAN SUPPLY
09-01-E3-04
CORRIDOR
09-01-F3-03
CORRIDOR
09-01-E4-04
HAS
09-01-C4-04
HAS
09-01-C3-04
PAT TLT
09-01-D3-01
PAT TLT
09-01-D3-03
CORRIDOR
09-01-C3-09
CORRIDOR
09-01-A3-03
OFFICE
09-01-B3-01
WORK
09-01-B3-04
OFFICE
09-01-A4-05
OFFICE
09-01-A4-04
OFFICE
09-01-C4-01
CONSULT
09-01-B3-09
EXAM
09-01-C3-03
EXAM
09-01-B3-08
EXAM
09-01-C3-02
EXAM
09-01-B3-06
RECEPT
09-01-C3-01
EXAM
09-01-C2-02
EXAM
09-01-B2-06
OFFICE
09-01-C2-01
EXAM09-01-C2-03
STOR
09-01-D2-01
CAST/PODIATRY
09-01-E4-01
EXAM
09-01-D4-02
EXAM
09-01-E3-03
EXAM
09-01-D3-06
EXAM
09-01-E3-02
EXAM
09-01-D3-05
EXAM
09-01-E3-01
EXAM
09-01-D3-04
EXAM
09-01-E2-03
EXAM
09-01-D2-04
EXAM
09-01-E2-02
EXAM
09-01-D2-03
EXAM
09-01-F4-02
EXAM
09-01-G4-01
EXAM
09-01-F3-06
EXAM
09-01-G3-03
EXAM
09-01-F3-05
EXAM
09-01-G3-02
EXAM
09-01-F3-04
EXAM
09-01-G3-01
EXAM
09-01-F2-05
EXAM
09-01-G2-04
EXAM
09-01-F2-04
EXAM
09-01-G2-03
EXAM
09-01-G4-04
HAS
09-01-D1-07
CORRIDOR
09-01-F1-04
CORRIDOR
09-01-A4-06
CLINIC WAITING
09-01-B3-07
RECEPT
09-01-B3-02
OFFICE
09-01-B3-03
OFFICE
09-01-D2-E1
ELEC
09-01-D2-H2
CHUTE
09-01-E2-T1
DATA /
TELECOMM
09-01-G2-E2
ELEC09-01-H2-T2
DATA /
TELECOMM
09-01-ST2
STAIR
09-01-SE6
ELEV
DN
UP
A. DISCONNECT FURNITURE POWER CIRCUITS. PRESERVE CIRCUIT FOR
FUTURE REUSE.
B. DISCONNECT DATA OUTLETS FROM NETWORK. PRESERVE CIRCUIT FOR
FUTURE REUSE.
C. AREAS SHOWN FOR DEMO WORK ARE ALSO AREAS FOR NEW WORK. SEE
SHEETS ED111 AND EP111 FOR REFERENCE.
D. DISCONNECT DURESS ALARM FROM CIRCUIT, PRESERVE CIRCUIT FOR
FUTURE USE.
E. SYSTEM FURNITURE WILL HAVE CHASE/POWER WHIP FOR INSTALLATION.
COORDINATE INSTALLATION REQUIREMENTS USING ARCHITECTURAL
DRAWINGS.
F. VERIFY ELECTRICAL CIRCUITS, VIA TRACING PRIOR TO WORK START.
ED111
ED111
ED111
EP111
EP111
EP111
1 2 3
4 4
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:2
:2
P
M
ED103
DEMOLITION PLAN AT BUILDING E
(09) LEVEL 1
INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
1. REUSE EXISTING CIRCUIT 09-NL11-39 AND 09-NL11-41. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
2. REUSE EXISTING CIRCUIT 09-NL11-08 AND 09-NL11-10. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
3. REUSE EXISTING CIRCUIT 09-NL12-30. AND 09-NL12-28 USE EXISTING
CONDUIT FOR NEW CIRCUIT.
4. LOCATION OF ELECTRICAL ROOM(S) TO PERFORM WORK.
32'16'8'4'2'0'
N o rt h
1/8" = 1'-0"
DEMOLITION PLAN AT BUILDING E (09) LEVEL 1
2 ELECTRICAL UPDATES 03/09/2022
H
G
F
E
D
C
B
09-02-E2-04
W.C. ALCOVE
09-02-H3-02
NURSE
STATION/MED
09-02-B2-06
EXAM/SCREEN
09-02-B2-05
EXAM/SCREEN
09-02-B3-03
PRECEPTOR
09-02-E3-02
PRECEPTOR
09-02-F3-06
PRECEPTOR
09-02-B3-06
EXAM
09-02-B3-08
EXAM09-02-G3-06
EXAM
09-02-G2-06
EXAM
09-02-H3-04
EXAM
09-02-B2-02
PROC TLT
09-02-H2-01
EQUIP STOR
09-02-B3-07
EXAM
09-02-H2-04
EXAM
09-02-H2-03
EXAM
09-02-C4-01
OFFICE
09-02-C3-03
EXAM
09-02-C3-02
EXAM
09-02-C2-02
EXAM
09-02-C3-08
EXAM
09-02-D3-05
EXAM
09-02-D2-05
EXAM
09-02-E2-05
EXAM
09-02-H4-03
OFFICE
09-02-F3-04
EXAM
09-02-F2-05
EXAM
09-02-G3-01
EXAM
09-02-G2-04
EXAM
09-02-G4-01
EXAM
09-02-G2-05
EXAM
09-02-F3-02
CLEAN SUPPLY
09-02-B4-01
CONSULT
09-02-A2-03
PROCEDURE
09-02-H4-01
CONSULT
09-02-E2-01
SOILED UTIL
09-02-B2-04
CLEAN SUPPLY
09-02-B2-03
PROCEDURE
09-02-C2-01
EQUIP STOR
09-02-A4-02
HUB
09-02-F4-03
HUB
09-02-G2-01
HAC
09-02-F3-07
WEIGHT STN
09-02-G3-02
WEIGHT STN
09-02-G1-05
OFFICE
09-02-G2-02
CLEAN SUPPLY
09-02-H1-05
OFFICE
09-02-H1-06
OFFICE
09-02-B1-03
OFFICE
09-02-B1-05
OFFICE
09-02-B1-04
OFFICE
09-02-B1-06
OFFICE
09-02-C1-02
OFFICE
09-02-C1-01
OFFICE
09-02-C1-04
OFFICE
09-02-C1-03
OFFICE
09-02-C1-06
OFFICE
09-02-C1-05
OFFICE
09-02-D1-04
OFFICE
09-02-D1-03
OFFICE
09-02-D1-06
OFFICE
09-02-D1-05
OFFICE
09-02-D2-01
LINEN ALCOVE
09-02-F2-03
PROCEDURE
09-02-B3-04
WEIGHT STN
09-02-G1-03
NURSE
09-02-G1-04
NURSE
09-02-G1-01
NURSE
09-02-G1-02
NURSE
09-02-G1-06
NURSE
09-02-F1-03
OFFICE
09-02-F1-02
OFFICE
09-02-D1-02
OFFICE
09-02-H1-02
OFFICE
09-02-H1-01
OFFICE
09-02-H1-04
OFFICE
09-02-H1-03
OFFICE
09-02-D1-01
OFFICE
09-02-A1-02
OFFICE
09-02-A1-01
OFFICE
09-02-A1-04
OFFICE
09-02-A1-03
OFFICE
09-02-B1-02
OFFICE
09-02-B1-01
OFFICE
09-02-F1-01
PAT ED CONF
09-02-H3-03
CRASH CART
ALCOVE
09-02-F2-04
OFFICE
09-02-G2-03
OFFICE
09-02-E1-02
STAFF TLT
09-02-C4-04
CONSULT
09-02-D3-02
NURSE
STATION/MED
09-02-D4-04
HUB
09-02-B3-02
NURSE
STATION/MED
09-02-B4-02
EXAM
09-02-C3-01
EXAM
09-02-A4-03
HAS
09-02-D3-07
WEIGHT STN
09-02-A3-07
WEIGHT STN
09-02-E3-03
WEIGHT STN
09-02-A3-04
CORRIDOR
09-02-A3-06
CORRIDOR
09-02-B3-05
CORRIDOR
09-02-C3-04
CORRIDOR
09-02-D3-04
CORRIDOR
09-02-E3-04
CORRIDOR
09-02-F3-03
CORRIDOR
09-02-G3-05
CORRIDOR
09-02-G3-03
CORRIDOR
09-02-H3-05
CORRIDOR
09-02-D3-03
EXAM
09-02-D4-01
OFFICE
09-02-H3-08
EXAM
09-02-H3-07
EXAM
09-02-H3-06
EXAM
09-02-H2-05
EXAM
09-02-F4-01
PUBLIC TLT
09-02-E1-03
STAFF LOUNGE
09-02-E4-02
WAIT
09-02-F4-02
WAIT
09-02-F2-02
PROC TLT
09-02-E1-01
STAFF TLT
09-02-E2-06
EDUCATION
09-02-E3-07
EDUCATION
09-02-H2-02
OFFICE
09-02-D3-06
CORRIDOR
09-02-D1-07
CORRIDOR
09-02-A2-04
ALCOVE
09-02-F2-06
ALCOVE
09-02-F2-01
OFFICE
09-02-G3-04
PAT TLT
09-02-H3-01
STAFF TLT
09-02-F3-01
PAT TLT
09-02-E3-05
STAFF TLT
09-02-F3-05
CORRIDOR
09-02-E3-06
CORRIDOR
09-02-B3-01
PAT TLT
09-02-A3-05
PAT TLT
09-02-C3-09
CRASH CART
ALCOVE 09-02-C3-06
CORRIDOR
09-02-C3-05
PAT TLT
09-02-D3-01
PAT TLT
09-02-D4-05
HAS
09-02-F4-04
HAS
09-02-E4-01
PUBLIC TLT
09-02-C4-05
WAIT
09-02-D4-02
WAIT
09-02-B4-03
WAIT
09-02-C4-02
WAIT
09-02-G4-02
WAIT
09-02-H4-02
WAIT
09-02-E3-01
EXAM
09-02-E2-03
EXAM
09-02-E2-02
OFFICE
09-02-C2-04
EXAM
09-02-C2-03
OFFICE
09-02-D2-03
EXAM
09-02-D2-02
EXAM
09-02-B2-01
HAC
09-02-F1-04
CORRIDOR
09-02-D2-04
EXAM
09-02-D2-E1
ELEC
09-02-D2-H1
CHUTE
09-02-E3-T1
DATA /
TELECOMM
09-02-G2-E2
ELEC
09-02-H2-T2
DATA /
TELECOMM
09-02-SE6
ELEV
09-02-ST2
STAIR
UP
DN
A. DISCONNECT FURNITURE POWER CIRCUITS. PRESERVE CIRCUIT FOR
FUTURE REUSE.
B. DISCONNECT DATA OUTLETS FROM NETWORK. PRESERVE CIRCUIT FOR
FUTURE REUSE.
C. AREAS SHOWN FOR DEMO WORK ARE ALSO AREAS FOR NEW WORK. SEE
SHEETS ED111 AND EP111 FOR REFERENCE.
D. DISCONNECT DURESS ALARM FROM CIRCUIT, PRESERVE CIRCUIT FOR
FUTURE USE.
E. SYSTEM FURNITURE WILL HAVE CHASE/POWER WHIP FOR INSTALLATION.
COORDINATE INSTALLATION REQUIREMENTS USING ARCHITECTURAL
DRAWINGS.
F. VERIFY ELECTRICAL CIRCUITS, VIA TRACING PRIOR TO WORK START.
ED111
ED111
ED111
EP111
EP111
3 EP111
4 4
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:2
:2
P
M
ED104
DEMOLITION PLAN AT BUILDING E
(09) LEVEL 2
INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
32'16'8'4'2'0'
N o rt h
1/8" = 1'-0"
DEMOLITION PLAN AT BUILDING E (09) LEVEL 2
2 ELECTRICAL UPDATES 03/09/2022
1. REUSE EXISTING CIRCUIT 09-NL21-39 AND 09-NL21-41. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
2. REUSE EXISTING CIRCUIT 09-NL22-81 AND 09-NL22-81. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
3. REUSE EXISTING CIRCUIT 09-NL22-44 AND 09-NL22-46. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
4. LOCATION OF ELECTRICAL ROOM(S) TO PERFORM WORK.
H
G
F
E
D
C
B
09-03-B3-07
VISUAL FIELD
09-03-B3-04
PHOTOGRAPHY
09-03-B4-03
LASER ROOM
09-03-A2-03
PROCEDURE
09-03-A1-01
OFFICE
09-03-C1-01
OFFICE09-03-C1-04
WORK
09-03-C1-05
WORK
09-03-C1-03
OFFICE
09-03-C1-02
OFFICE
09-03-B1-05
OFFICE
09-03-A1-02
OFFICE
09-03-B1-06
OFFICE
09-03-B1-03
OFFICE
09-03-B1-04
OFFICE
09-03-B1-01
OFFICE
09-03-B1-02
OFFICE
09-03-B3-06
EXAM/TREATMENT
09-03-B3-05
EXAM/TREATMENT
09-03-B2-03
EXAM/TREATMENT09-03-B2-06
EXAM/TREATMENT
09-03-A3-06
EXAM/TREATMENT
09-03-A4-02
EXAM/TREATMENT
09-03-A2-02
EXAM/TREATMENT
09-03-A1-03
OFFICE
09-03-D4-01
ONSTAGE AREA
09-03-E1-03
STAFF LOUNGE
09-03-E3-05
WEIGHT STN
09-03-H2-03
NOURISH
09-03-F4-01
ONSTAGE AREA
09-03-B2-01
HAC
09-03-G2-01
HAC
09-03-H3-01
ONSTAGE AREA
09-03-A4-03
HAS
09-03-D1-01
OFFICE
09-03-F1-03
OFFICE
09-03-F1-02
OFFICE
09-03-D1-03
OFFICE
09-03-D1-02
OFFICE
09-03-G1-02
OFFICE
09-03-G1-01
OFFICE
09-03-H1-06
OFFICE
09-03-G1-05
OFFICE
09-03-H2-05
CHEMO PREP
09-03-G2-06
PREP
09-03-H2-02
REFERENCE
09-03-H1-01
OFFICE
09-03-H1-02
OFFICE
09-03-B3-03
ULTRASOUND RM
09-03-E2-01
SOILED UTIL
09-03-C2-01
EXAM
09-03-D4-03
EXAM
09-03-D3-06
EXAM
09-03-D3-05
EXAM
09-03-D3-04
EXAM
09-03-D2-04
EXAM
09-03-D2-03
EXAM
09-03-C4-01
EXAM
09-03-C3-03
EXAM
09-03-C3-02
EXAM
09-03-C3-01
EXAM
09-03-E2-03
EXAM
09-03-C4-02
WAIT
09-03-E4-02
WAIT
09-03-B4-04
WAIT
09-03-F4-05
WAIT
09-03-G4-02
WAIT
09-03-D3-02
NURSE
STATION/MED
09-03-D3-01
STAFF TLT
09-03-G1-04
OFFICE
09-03-E1-01
STAFF TLT
09-03-H4-01
FAMILY COUNSEL
09-03-C2-02
EXAM
09-03-D3-03
PRECEPTOR RM
09-03-F1-01
CONF
09-03-F2-03
EXAM
09-03-F3-08
WEIGHT STN
09-03-F3-02
EQUIP STOR
09-03-G2-02
SOILED UTIL
09-03-F2-02
CLEAN SUPPLY
09-03-E2-05
PROCEDURE
09-03-E2-04
PROC TLT
09-03-F2-04
PROCEDURE
09-03-G1-03
OFFICE
09-03-G4-01
EXAM
09-03-G3-03
EXAM
09-03-G3-02
EXAM
09-03-G4-03
HUB
09-03-F3-03
PRECEPTOR RM
09-03-E2-02
EXAM
09-03-F4-04
EXAM
09-03-F3-06
EXAM
09-03-F3-05
EXAM
09-03-F3-04
EXAM
09-03-F2-06
EXAM
09-03-F2-05
EXAM
09-03-G3-01
EXAM
09-03-G2-04
EXAM
09-03-G2-03
EXAM
09-03-B2-02
EXAM/TREATMENT
09-03-H1-05
OFFICE
09-03-D1-05
TECH
09-03-D1-04
TECH
09-03-B4-01
COHERENCE
TOMOGRAPHY
09-03-A3-05
PUBLIC TLT
09-03-B2-04
CLEAN SUPPLY
09-03-A3-04
EQUIP STOR
09-03-H1-04
OFFICE
09-03-H1-03
OFFICE
09-03-B3-02
MED EQUIP
ALCOVE
09-03-G3-05
CHEMO TLT
09-03-H2-01
STOR
09-03-B3-01
W.C. ALCOVE
09-03-G2-07
PREP
09-03-C2-03
WORKROOM
09-03-D2-02
ENDO CLEAN
ROOM 1
09-03-C2-04
PROCEDURE
09-03-D2-01
CYSTO
09-03-D4-04
WAIT
09-03-G2-08
PAT TLT
09-03-G3-06
TLT
09-03-G3-04
EXAM
09-03-E1-02
STAFF TLT
09-03-E3-01
EXAM
09-03-E3-02
EXAM
09-03-E3-03
EXAM
09-03-E4-01
CONSULT/PROCEDURE
09-03-C3-05
WEIGHT STN
09-03-A2-04
CORRIDOR
09-03-A3-07
CORRIDOR
09-03-B2-07
CORRIDOR
09-03-C3-07
CORRIDOR
09-03-D3-07
CORRIDOR
09-03-D3-08
WEIGHT STN
09-03-E2-06
CORRIDOR
09-03-E3-06
CORRIDOR
09-03-G3-07
WEIGHT STN
09-03-H2-06
CORRIDOR
09-03-C3-04
PAT TLT
09-03-D1-07
CORRIDOR
09-03-E3-04
PAT TLT
09-03-F3-01
PAT TLT
09-03-H2-04
NURSE
STATION/MED 09-03-F3-07
CORRIDOR
09-03-C4-03
HAS
09-03-E4-03
HAS
09-03-G4-04
HAS
09-03-F4-02
PUBLIC TLT 09-03-D4-02
PUBLIC TLT
09-03-G3-08
CORRIDOR
09-03-H3-03
CORRIDOR
09-03-C3-06
CORRIDOR
09-03-F1-04
CORRIDOR
09-03-G2-05
60 SF /89 SF
ANTEROOM
09-03-E4-04
WAIT
09-03-F4-03
WAIT
09-03-B2-05
EXAM/TREATMENT
09-03-F2-01
RENAL ALCOVE
09-03-H3-02C
INFUSION
CENTER
09-03-H3-02B
INFUSION
09-03-H3-02A
INFUSION
CENTER
09-03-H3-02D
INFUSION
09-03-C2-E1
ELEC
09-03-D2-H1
CHUTE
09-03-E2-T1
DATA /
TELECOMM
09-03-G2-E2
ELEC
09-03-H2-T2
DATA /
TELECOMM
09-03-SE6
ELEV
09-03-ST2
STAIR
DN
UP
N U
A. DISCONNECT FURNITURE POWER CIRCUITS. PRESERVE CIRCUIT FOR
FUTURE REUSE.
B. DISCONNECT DATA OUTLETS FROM NETWORK. PRESERVE CIRCUIT FOR
FUTURE REUSE.
C. AREAS SHOWN FOR DEMO WORK ARE ALSO AREAS FOR NEW WORK. SEE
SHEETS ED111 AND EP111 FOR REFERENCE.
D. DISCONNECT DURESS ALARM FROM CIRCUIT, PRESERVE CIRCUIT FOR
FUTURE USE.
E. SYSTEM FURNITURE WILL HAVE CHASE/POWER WHIP FOR INSTALLATION.
COORDINATE INSTALLATION REQUIREMENTS USING ARCHITECTURAL
DRAWINGS.
F. VERIFY ELECTRICAL CIRCUITS, VIA TRACING PRIOR TO WORK START.
ED111
ED111
ED111
ED111
EP111
EP111
EP111
3EP111
1 2 3 4
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:2
:2
P
M
ED105
DEMOLITION PLAN AT BUILDING E
(09) LEVEL 3
INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
32'16'8'4'2'0'
N o rt h
1/8" = 1'-0"
DEMOLITION PLAN AT BUILDING E (09) LEVEL 3
2 ELECTRICAL UPDATES 03/09/2022
1. REUSE EXISTING CIRCUIT 09-NL31-81 AND 09-NL31-87. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
2. REUSE EXISTING CIRCUIT 09-NL31-28 AND 09-NL31-28. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
3. REUSE EXISTING CIRCUIT 09-NL32-34 AND 09-NL32-36. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
4. REUSE EXISTING CIRCUIT 09-NL32-53 AND 09-NL32-81. USE EXISTING
CONDUIT FOR NEW CIRCUIT.
5. LOCATION OF ELECTRICAL ROOM(S) TO PERFORM WORK.
1.1
2.5
A
A.1
B
B.1
B.5
B.7
C
FEMALE PUBLIC
TLT
10-04-C4-04
CORRIDOR
D
OFFICE
COMPUTER RM
10-04-C5-05 10-04-C5-07
UPS SERVICE DESK
10-04-C5-08
CUSTOMER
PAT
RECORDS
10-04-C8-12
INTAKE/TRIAGE/TEST
10-04-C8-08
10-04-C8-13
COPY/FAX
10-04-C6-05
WAIT
10-04-C5-03
10-04-C5-02
HAC
10-04-C5-04
VEST
10-04-C6-02
ELEC
10-04-C6-04
ELEV 10-04-C7-03
NCOIC MHS
10-04-C7-05
RECEP
10-04-C8-03
CORRIDOR
10-04-C7-06
EYE LANE
10-04-C8-04
EYE LANE
INTAKE/TRIAGE/TEST
10-04-C8-02
CORRIDOR
10-04-C6-03
VEST 10-04-C7-01
CORRIDOR
EQUIP STOR
10-04-C8-07
10-04-B3-15
10-04-B2-07
CORRIDOR
10-04-B3-11
CORRIDOR
10-04-B4-10
VEST
10-04-B4-09
CORRIDOR
MALE PUBLIC TLT
10-04-C5-01
10-04-C6-01
ELEV
10-04-C7-02
HAC
VISUAL/FUNDUS
CAMERA
10-04-C7-04
FITTING/DISPENSING
10-04-C8-01
PATIENT TLT
10-04-B8-10
10-04-B8-11
SAT LAB
10-04-C8-06
TELECOM
COMMUNICATIONS
10-04-C8-05
10-04-C9-01
SHAFT
10-04-B8-12
EXAM
10-04-B9-09
EXAM
10-04-B6-02
LOBBY
ISOLATION TLT
10-04-B7-05
10-04-B9-08
CORRIDOR
10-04-B4-03
10-04-B7-02
EXAM
10-04-B7-06
CORRIDOR
10-04-B7-03
EXAM
10-04-B8-07
EXAM
RECEP/OFFICE
10-04-B7-01
10-04-B8-01
OFFICE
10-04-B8-02
MED TECH
10-04-B8-04
OFFICE
10-04-B8-03
MED TECH
10-04-B8-08
EXAM
10-04-B8-09
EXAM
10-04-B8-13
CORRIDOR
10-04-B9-05
10-04-B8-05
OFFICE
10-04-B8-06
OFFICE
10-04-B9-01
E
10-04-B1-02
MDOS/CC1
10-04-B1-03
MDSS/CC1
10-04-B1-04
OFFICE
10-04-B1-05
SGN
10-04-C2-02
CORRIDOR
10-04-B2-08
COPY/FAX
ALCOVE
10-04-B3-12
STAFF TLT
10-04-B2-09
COPY/FAX
10-04-C3-01
TECH
10-04-C3-02
TECH
CLASSROOM
10-04-C2-01 10-04-C2-02
CORRIDOR 10-04-C3-03
COPY/FAX
10-04-C3-04
TELECOM
COMMUNICATIONS
10-04-C3-05
10-04-C3-06
FILE
10-04-C4-02
SHAFT
EQUIP STOR
10-04-C4-03
STAFF LOUNGE
10-04-C3-07
10-04-C4-05
OFFICE
10-04-C3-08
CORRIDOR
A
10-04-C4-06
OFFICE FACILITY MGMT
10-04-C4-08 10-04-C4-10
MEDIA
10-04-C5-06
WORK
10-04-C5-12
OFFICE
10-04-C5-11
10-04-C5-13
OFFICE
POS PHARMACY
10-04-C6-07
FACILITY MGMT
10-04-C4-07
INFO/NCOIC
10-04-C4-09
10-04-C7-08
OFFICE
10-04-C7-09
WAIT
10-04-C7-07
CORRIDOR
10-04-C8-10
RECEPT
10-04-C8-11
OUTREACH
NURSE
10-04-C4-01
EX STAIR 1
10-04-B3-13
STAFF TLT
10-04-B3-14
RECORDS STOR
10-04-B4-11
TECH OFFICE
10-04-B5-08
10-04-B5-07
HALL
10-04-B5-09
RECORDS
WINDOW
TECH OFFICE
10-04-B5-12
TECH OFFICE
10-04-B5-11
TECH OFFICE
10-04-B5-13
10-04-B2-05
TECH
10-04-B2-06
TECH
10-04-B3-04
OFFICE
10-04-A2-04
CORRIDOR
10-04-B1-01
STAFF TLT
10-04-B2-01
SECR/WAIT
10-04-B2-02
TECH
10-04-B2-03
TECH
10-04-B2-04
TECH
10-04-B3-03
OFFICE
10-04-B3-06
OFFICE
10-04-B3-10
OFFICE
10-04-B3-09
OFFICE TECH OFFICE
TECH OFFICE
10-04-B4-02
10-04-B4-05
OFFICE
TECH OFFICE
10-04-B4-08
TECH OFFICE
10-04-B5-03
TECH OFFICE
10-04-B4-07
TECH OFFICE
10-04-B5-02
10-04-B5-05
TECH
10-04-B5-06
RECEPT
10-04-B3-01
OFFICE
10-04-B3-02
OFFICE
10-04-B3-05
AUDITOR
10-04-B3-07
GPM1
10-04-B3-08
OFFICE
10-04-B4-01
HCI/UM
10-04-B4-04
HCI/UM
10-04-B4-06
BCAC
10-04-B5-01
MEB
10-04-B5-04
MEB
10-04-B6-01
RECEPT
10-04-A4-04
CORRIDOR
10-04-B5-14
CORRIDOR
10-04-A4-01
OIC TOPA NCOIC TOPA
10-04-A4-02 10-04-A4-03
OFFICE
10-04-A5-01
OFFICE
10-04-A5-02
CONF
NCOIC/RMO/CSS/SUP1
10-04-A2-02
10-04-A1-01
MDG/CC1
10-04-B7-04
EXAM
10-04-A1-02
OFFICE
10-04-A2-01
OFFICE
10-04-A2-03
OIC RMO
10-04-A3-01
CODER
10-04-A3-02
OFFICE 10-04-A3-03
ARMY/NAVY
LIASON
10-04-A3-04
ARMY/NAVY
LIASON
N U
A. DISCONNECT FURNITURE POWER CIRCUITS. PRESERVE CIRCUIT FOR
FUTURE REUSE.
B. DISCONNECT DATA OUTLETS FROM NETWORK. PRESERVE CIRCUIT FOR
FUTURE REUSE.
C. AREAS SHOWN FOR DEMO WORK ARE ALSO AREAS FOR NEW WORK. SEE
SHEETS ED111 AND EP111 FOR REFERENCE.
D. DISCONNECT DURESS ALARM FROM CIRCUIT, PRESERVE CIRCUIT FOR
FUTURE USE.
E. SYSTEM FURNITURE WILL HAVE CHASE/POWER WHIP FOR INSTALLATION.
COORDINATE INSTALLATION REQUIREMENTS USING ARCHITECTURAL
DRAWINGS.
F. VERIFY ELECTRICAL CIRCUITS, VIA TRACING PRIOR TO WORK START.
ED111
EP111
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:2
:3
P
M
ED106
DEMOLITION PLAN AT BUILDING A
(10) LEVEL 4
INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
32'16'8'4'2'0'
N o rt h
1/8" = 1'-0"
DEMOLITION PLAN AT BUILDING A (10) LEVEL 4
2 ELECTRICAL UPDATES 03/09/2022
1. REUSE EXISTING CIRCUIT 10-L4B2-4 AND 10-L4B2-6. USE EXISTING CONDUIT
FOR NEW CIRCUIT.
2. LOCATION OF ELECTRICAL ROOM(S) TO PERFORM WORK.
N U
N U
CR
N U
N U
33 4
44 4
5 5 5
6 6
A. REUSE EXISTING POWER CIRCUITS TO PROVIDE POWER TO THE
RECEPTIONIST DESKS.
B. COORDINATE DATA AND POWER RECEPTACLE LABELS WITH EXISTING
RECEPTACLE LABELING.
C. ALL RECEPTACLES SHALL SHOW CIRCUIT NUMBER BACK TO PANEL OF
ORIGIN.
D. REUSE EXISTING WIRING FOR DURESS ALARM.
E. REFER TO INTERIOR DRAWING SET FOR PHASING AND WORK HOUR
COORDINATION.
F. CONNECT DESK POWER CABLE WHIP TO EXISTING CIRCUIT.
G. ALL RECEPTACLES NEED TO BE INSTALLED WITHIN THE CASEWORK,
UNLESS OTHERWISE NOTED.
4 3
45 4 35 4
7 2
4 53 4 4 53 4 4 5 4 4 5 43 3
4 4 4 43 4 4 3 4 45 555
00KEYNOTES
KEY PLAN
GENERAL NOTES
North
11 12 08 (G)
(E)
(A)
030405
Key Plan
E C
O L F
A X
A V
E
N WHEELING ST
Drawing Title
VA FORM 08 - 6231
F
CONSULTANTS:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307 WWW.VALHALLAENGINEERING.COMDate:Number:
10987654321
10987654321
E
D
C
B
A
F
E
D
C
B
A
ARCHITECT/ENGINEERS: STAMP:
Approved: Project Director
Phase Project Title
Location
Issue Date Checked Drawn
Project Number
Drawing Number
Building Number
Revisions:
C R e v it
\5
-2 -1
C h e c k -I n
E L
E C
R m lu g o W
Q
P M
.r v t
/1
/2
:0
:3
P
M
EP111
ELECTRICAL POWER PLAN INSTALL PARTITIONS AT CHECK-IN
DESKS
1700 N WHEELING ST, AURORA, CO 80045
554-20-103
08,09,10
02/15/2021 CPR MLS
100% CONSTRUCTION
DOCUMENTS
VEG 20.17
32'16'8'4'2'0'
N o rt h
1/2" = 1'-0"
TYPICAL ENLARGED FLOOR POWER PLAN AT BUILDING "E"
1. DURESS ALARM, REUSE EXISTING CIRCUIT FOR DURESS ALARM.
2. REUSE EXISTING CARD READER WIRING, REDIRECT TO NEW LOCATION AS
SHOWN ON THE DRAWINGS.
3. RECEPTACLES MOUNTED 3' 0" ON CENTER AFF.
4. RECEPTACLES MOUNTED 1' 6" AFF.
5. DATA OUTLET FOR PHONE CONNECTIONS. REUSE EXISTING CIRCUIT.
MOUNTED 1' 6" AFF.
6. REUSE EXISTING CIRCUITS PRESERVED DURING DEMOLITION.
7. REUSE EXISTING THERMOSTAT WIRING, REDIRECT TO NEW LOCATION AS
SHOWN ON THE DRAWINGS.
32'16'8'4'2'0'
N o rt h
1/2" = 1'-0"
ENLARGED FLOOR POWER PLAN AT BLDG G LVL 3
32'16'8'4'2'0'
N o rt h
1/2" = 1'-0"
ENLARGED FLOOR POWER PLAN AT BLDG A LVL 4
32'16'8'4'2'0'
N o rt h
1/2" = 1'-0"
TYPICAL ENLARGED FLOOR POWER PLAN BUILDING "G" & "E"
1 ELECTRICAL UPDATES 02/17/2022
2 ELECTRICAL UPDATES 03/09/2022
| Sheets |
| ED101 - DEMOLITION PLAN AT BUILDING G (08) LEVEL 1 |
| ED102 - DEMOLITION PLAN AT BUILDING G (08) LEVEL 3 |
| ED103 - DEMOLITION PLAN AT BUILDING E (09) LEVEL 1 |
| ED104 - DEMOLITION PLAN AT BUILDING E (09) LEVEL 2 |
| ED105 - DEMOLITION PLAN AT BUILDING E (09) LEVEL 3 |
| ED106 - DEMOLITION PLAN AT BUILDING A (10) LEVEL 4 |
File details come from the government source that posted it. Updated .