S02 - ICRA.pdf
PDF 211 KB Posted
- Solicitation number
- 36C25921R0082
About this file
This document outlines an Infection Control Risk Assessment (ICRA) process for construction projects at a healthcare facility. It defines four types of construction activities from minor to major and provides corresponding infection control precautions. Type A involves inspection and non-invasive activities requiring no ICRA. Type B covers small-scale, short duration work creating minimal dust. Type C encompasses major activities generating moderate to high dust levels. Type D consists of major demolition and construction over consecutive shifts. The ICRA assigns risk groups based on the location's risk level and construction type, determining appropriate infection control class and precautions for dust containment, barrier implementation, airflow control, and cleaning measures.
The related federal contract opportunity is a solicitation from the Department of Veterans Affairs to install partitions at check-in desks for $36C25921R0082 as part of project Z1DA--554-20-103.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 08 - Drawings for RFI 2 project 554-20-103.pdf | ||
| 36C25921R0082 0008.docx | DOCX document | |
| 36C25921R0082 0007.docx | DOCX document | |
| 36C25921R0082 0006.docx | DOCX document | |
| 36C25921R0082 0005.docx | DOCX document | |
| 36C25921R0082 0004.docx | DOCX document | |
| Amendment 03 - 36C25921R0082 0003.docx | DOCX document | |
| Amendment 02 - 36C25921R0082 0002.docx | DOCX document | |
| S04 - 2022-01-28-RFI_No_1-Project_554-20-103_Install_Partitions_at_Check-In_Desks-VEG-20-16.pdf | ||
| S04 - Site Visit Attendance.pdf | ||
| S06 - Amend 0001 - 36C25921R0082 0001.docx | DOCX document | |
| S02 - Drawings Part 4.pdf | ||
| S02 - Drawings Part 3.pdf | ||
| S02 - Drawings Part 2.pdf | ||
| S02 - Drawings Part 1.pdf | ||
| S02 - Specifications.pdf | ||
| S02 - Solicitation - 36C25921R0082.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Completing the Infection Control Risk Assessment (ICRA) Step 1: Determine type of construction based on amount of demolition and duration.
Step 2: Determine location of construction and patient risk level.
Step 3: Use graph to determine class of Infection Control containment for the ICRA.
CONSTRUCTION ACTIVITY
Type A: Inspection and Non-Invasive Activities. No ICRA needed unless in a high risk area.
Includes, but is not limited to:
1. Small scale removal of ceiling tiles for visual inspection or minor installation.
2. Painting (but not sanding).
3. Wall covering, electrical trim work, minor plumbing, and activities that do not generate dust or require cutting of walls.
Type B: Small scale, short duration activities that create minimal dust. No ICRA needed unless high risk area.
Includes, but is not limited to:
1. Installation of telephone & computer cables
2. Access to chase spaces.
3. Cutting of walls or ceiling where dust migration can be controlled.
Type C: Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components and assemblies or new construction.
Includes, but is not limited to:
1. Sanding of walls for painting or wall covering.
2. Removal of floor coverings, ceiling tiles, and casework.
3. New wall construction.
4. Minor, uncontained duct, HVAC or electrical work above ceiling
5. Major cabling activities.
6. Any other project that cannot be completed within a single work shift.
7. Any work involving modifications to the domestic water system.
Type D: Major demolition & construction projects.
1. Activities requiring consecutive work shifts
2. Activities requiring heavy demolition/removal of complete cabling system
3. New construction Exterior Construction: Activities such as excavation within close proximity of healthcare building that may produce dust or other infection control concerns. Requires case by case review by ICRA team.
LOW RISK MEDIUM RISK HIGH RISK
Administrative Offices Lobbies Public Corridors Public Restrooms Elevators Day Rooms Retail Store File Rooms Med Records Coffee Shop Warehouse
CBS: MH Outpatient CBC: Podiatry
CBN: PT/OT
DAT-S: Radiology, Dental, Bronchoscopy, GI DAT-N: Sleep Lab IBN: SCI Outpatient IBS: Mental Health Inpatient Research: Lab Areas F/NS Patient Kitchen All Outpatient Clinics Canteen Morgue All Sterile Storage
CBC: Infusion CBN: Dialysis DAT-S: Lab, ED, Pre-op, PACU, Minor Procedure, OR (use OR-specific ICRA), Oral Surgery DAT-N: Pharmacy, Pulmonary, Cath Lab, SPS IBS: ICU, SCI Inpatient IBN: Med/Surg Units (K2 and K3) Research: Vivarium
TYPE A TYPE B TYPE C TYPE D
LOW Risk
I II II III/IV
MEDIUM Risk
I II III IV
HIGH Risk
II III/IV III/IV IV
INFECTION CONTROL RISK ASSESSMENT (ICRA)
PROJECT:
Location of Construction: Project Start Date:
Contractor Performing Work and Phone Extension: Estimated Duration:
CONSTRUCTION ACTIVITY IC RISK GROUP
Type A: Inspection, non-invasive, minor x Low Risk
Type B: Small scale, short duration, moderate levels. Medium Risk x Type C: Major activity generates moderate to high levels of dust. High Risk
Type D: Major activity–large area, major relocation of staff/pts
A pre-construction risk assessment for tuberculosis (TB) has been completed. Patient population, site location and hospital layout have been reviewed and there is no increased risk for TB.
INFECTION CONTROL PRECAUTIONS INFECTION CONTROL COMMENTS
Class I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection (open ceiling tiles will not be abandoned).
3. Replace any stained/soiled or damaged ceiling tile with new tile.
Class II
In addition to Class I Precautions above:
1. Provides active means to prevent airborne dust from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with painter’s tape.
4. Block off and seal air vents.
5. Place sticky mat at entrance and exit of work area—change frequently.
6. Contain construction waste before transport in tightly covered containers. Wipe down equipment before removing from the worksite.
7. Upon completion, wipe work surfaces with disinfectant, wet mop and/or vacuum and remove isolation of HVAC system.
8. Properly flush and disinfect any newly installed domestic water piping systems prior to placing in service.
Class III
In addition to Class I & II Precautions above:
1. Obtain Infection Control involvement before construction begins.
2. Complete all critical barriers or implement control cube method before construction begins.
3. Control airflow: Isolate HVAC system in areas where work is being performed and maintain negative air pressure within work site.
4. Cover transport receptacles or carts. Wipe down equipment before removing from the worksite.
5. Seal holes, pipes, conduits, and punctures appropriately
6. Use appropriate protective clothing.
7. Upon completion, do not remove barriers until inspected by Safety and Infection Control and thoroughly cleaned by housekeeping. Remove barrier materials carefully, roll plastic on to itself and clean hard walls, to minimize spreading of dirt and debris.
Class IV
In addition to Class I, II & III Precautions above:
1. Relocate vulnerable patients or
2. Relocate all patients and staff
Exterior Requires case-by-case assessment by the ICRA team: May include more frequent air handler / filter checks if near patient care air intakes or other measures as noted to the right.
OTHER COMMENTS: Call EMS for terminal clean before taking down containment: 720-470-2492
Permit Requested By:. Infection Control: ext. Date: