This is a Self-Performed and Subcontracted Work Worksheet for general construction contractors bidding on federal contracts. The worksheet requires offerors in NAICS code 236220 (General Construction) to demonstrate that at least 15 percent of contract performance costs for personnel will be self-performed by the contractor's own employees or by employees of other eligible service-disabled veteran-owned small business (SDVOSB) concerns; specialty trade contractors must meet a 25 percent threshold. The form requests a detailed breakdown of personnel and material/equipment costs organized by specification division, with home office overhead, profit/fee, and bond costs to be added separately after subtotals are calculated.
The worksheet includes a calculation methodology for determining self-performed work percentages, requiring contractors to identify total personnel costs across prime and all subcontractors, subtract non-SDVOSB subcontractor personnel costs, and calculate the resulting self-performed percentage. Personnel costs are defined to include labor, mechanics, tradesmen, and directly charged office personnel such as project managers, superintendents, and administrative staff. An authorized representative must certify the accuracy of all representations on the worksheet. This template is designed specifically for the VA contract opportunity Z2DA—Install Humidification Monitoring and Control for Pharmacy Cache (Solicitation 36C25926Q0166).
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK
Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for specialty trade NAICS codes) of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other eligible service-disabled veteran-owned small business concerns. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
| Specification Division and name |
| SDVOSB Vendor (Y or N) |
| Personnel Cost |
| Material/Equipment Costs |
Division 01
| $ |
| $ |
Division 02
| $ |
| $ |
Division 03
| $ |
| $ |
(Add additional lines as necessary for each Division applicable to this project)
| $ |
| $ |
| $ |
| $ |
| Sub Total (Personnel Costs, Material/Equipment Costs) |
| $ |
| Profit |
| $ |
| Home Office Overhead |
| $ |
| Bond |
| $ |
| Grand Total |
| $ |
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $_________________
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $__________________
3. Remainder is ‘Total amount of work to be self-performed under the
| Contract’: | $__________________ | |
| 4. Self-performed work = Line 3/Line 1 x 100 = | ________________% |
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)
I certify the above representations are true and correct to the best of my knowledge.
| ________________________________________________ | ___________ |
| (Signature and Typed Name of Authorized Representative) | Date |