S02 Liquidated Damages 36C24426R0008 595-26-201 Fire Alarm Replacement signed.pdf
PDF 225 KB Posted
- Solicitation number
- 36C24426R0008
About this file
This Liquidation Damages Formulation Memo relates to Solicitation Number 36C24426R0008 for a Campus Wide Fire Alarm Replacement project at VISN 4. The document calculates liquidated damages for delays, totaling $609.33 per calendar day of inexcusable project delay. The damages are composed of two primary components: $340.03 per day for Contracting, Engineering, and Legal reviews (involving personnel grades GS-11 to GS-14) and $269.30 per day for Facility Engineering reviews (involving Construction Manager and Project Engineer). The liquidated damages are based on the General Schedule Locality Pay Table for Lebanon County, effective January 1, 2025, and are designed to compensate the government for additional administrative time and resources required if the contractor fails to complete the work within the specified contract timeframe.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Liquidation Damages Formulation Memo
Solicitation Number: 36C24426R0008
595-26-201 D/B Campus Wide Fire Alarm Replacement
All Civilian wage rates are based upon the General Schedule Locality Pay Table (Lebanon County) effective January 1, 2025 for Contracting and Project Engineer and FMS Manager.
1. Estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews per day of inexcusable delay:
CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE
Contracting Officer
Supervisor
GS-14 / 5 $69.22 1 Hours $69.22
Contract Specialist
GS-13 / 5
GS-11 / 1
$58.58
$36.26
1 Hour
4 Hours
$58.58
$145.04
Legal Officer GS-14 / 4 $67.19 1 Hour $67.19
TOTAL PER DAY: $340.03
2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay:
CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE
Construction Manager GS-13 / 5 $58.58 2 Hours $117.16
Project Engineer GS-12 / 6 $50.71 3 Hours $152.14
TOTAL PER DAY: $269.30
Grand Total Per Day $ 609.33
3. The Contractor shall pay liquidated damages to the Government in the amount of $609.33 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.
4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition
Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.
Elijah McIntosh
| 2025-10-01T07:00:23-0400 | |
| ELIJAH MCINTOSH |