S02 - Exhibit 01a 537-17-115 Construction IFC Narrative.pdf
PDF 7 MB Posted
- Attached to
- Z2DA--537-17-115: SPS Construction Phase 2, 3 &4 Federal contract opportunity
- Solicitation number
- 36C25225B0001
About this file
This is an IFC (Issued for Construction) narrative and cost estimate document for a VA Medical Center project to replace an air handling unit (AH-2) that services the Sterile Processing Service (SPS) area at Jesse Brown VA Medical Center in Chicago. The document details the mechanical design and cost estimate for replacing the existing AH-2 with a new 100% outside air unit featuring VFD supply fan, chilled water cooling coil, DX cooling coil, heat pipe reheat coil, hot water pre-heating coil, electrical humidifier, running glycol water heat recovery coil, and MERV filters.
The cost estimate dated June 13, 2024 projects a total construction cost of $4,489,751, with a 12-month construction duration starting March 16, 2025 and completing March 15, 2026. The work includes disconnecting and removing the existing AH-2, installing the new air handling unit, connecting it to existing building systems, and shifting six terminal units from AHU-2 to AHU-3. The estimate assumes traditional Design-Bid-Build procurement with SDVOSB general contractors. Major cost components include $1,760,722 for services (HVAC, plumbing, electrical), $557,228 for interiors, and $666,271 for general requirements. The document includes detailed mechanical calculations, equipment specifications, and cost breakdowns by CSI division.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S06 - 09 65 16 Resilient Sheet Flg.pdf | ||
| 36C25225B0001 0004.docx | DOCX document | |
| 36C25225B0001 0003.docx | DOCX document | |
| S04 - 537-17-115 Site visit 02242025.pdf | ||
| 36C25225B0001 0002.docx | DOCX document | |
| S06 - Requirements for Identification and Replacement of A307 Bolts Memo.pdf | ||
| 36C25225B0001 0001.docx | DOCX document | |
| S02 - Exhibit 01b2 537-17-115 PH3 DWGs Bid 20240701.pdf | ||
| S02 - Exhibit 01b1 537-17-115 PH2 DWGs Bid 20240701.pdf | ||
| S02 - Exhibit 02c1 - 537-17-115 SOW Att - Contract Progress Repor vha-10-6001a-fill.pdf | ||
| S02 - Wage Determination 1.10.25.pdf | ||
| S02 - Exhibit 01c1 537-17-115 Specs Vol 1 20240614.pdf | ||
| S02 - Exhibit 01b3 537-17-115 PH4 DWGs Bid 20240701.pdf | ||
| 36C25225B0001_3.docx | DOCX document | |
| S02 - Exhibit 01c2 537-17-115 Specs Vol 2 20240614.pdf | ||
| S02 - Ex 02c3 - 537-17-115 SOW Att - Subcontractor Payment Summary.xlsx | XLSX spreadsheet |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jesse Brown VAMC Project #537-17-115 Remodel Sterile Processing Service
Contract Number:
36C25218D0192
Task Order Number:
36C25219N0098
Issued for Construction
Narrative
June 13, 2024
Project #537-17-115 Remodel Sterile Processing Service Issued for Construction
Index
DESIGN ELEMENTS:
Mechanical
APPENDICES:
Appendix A ...................................................................................... Cost Estimate Appendix B ............................................................................................ Cutsheets Appendix C ......................................................................................... Calculations Appendix D ................................................................................. Client Comments
Mechanical Design Elements (Reference Codes, Standards and Design References section on Page 1)
Statement of Work
Chicago Jesse Brown VA Medical Center air handling unit, AH-2, services the sterile processing service (SPS) area. AH-2 is near its useful life and does not fulfill the dehumidification requirements in the SPS area because of the campus utility’s (chilled water, steam system) shortage, hence, VA prefers to replace the existing AH-2.
The primary role of the mechanical discipline for this project is to perform the design of the above tasks that meet the SPS HVAC requirements of applied codes and VA HVAC design manuals.
Design Conditions
1. Outside Air Temperatures:
a. The VA HVAC Design Guide lists temperatures for Chicago, Illinois. as follows:
i. Summer (0.4%): 91.4 Deg. F. DB; 74.3 Deg. F. WB.
ii. Winter (99.6%): -1.5 Deg. F.
Existing
The existing AH-2, which is in the mechanical room on the third floor, services the SPS and
SPD area. AH-2 is a 100% outside air unit with a VFD supply fan, a chilled-water cooling coil, a hot water heating coil, a steam humidifier, and a running glycol water heat recovery coil.
Design Concept
• Replace the existing AH-2 with a new unit to meet the SPS dehumidifying requirements.
The new air handling unit shall be 100% outside air, with a VFD supply fan, a chilled water cooling coil, a DX cooling coil, a heat pipe reheat coil, a hot water pre-heating coil, an electrical humidifier, a running glycol water heat recovery coil, the MERV 7 and 11 pre-filters and the MERV 14 final filters. The air-cooled condensing unit will be located outside of the mechanical room on the roof.
• the existing AH-2 shall remain in service during the installation of the new AHU.
Connection of the new AHU to the existing duct distribution system shall be made on weekends or at night.
• As required by the VA, terminal units of TU-2-1-3, TU-2-1-4, TU-2-1-5, TU-2-1-6, TU-2-
1-7, and TU-2-1-16 will be removed from the AHU-2 HVAC system and reconnected to the AHU-3 HVAC system.
• An instrument air compressor and its associated distribution piping system will be added to the VA-provided cabinets.
• A new PPE room is added to the SPS, the HVAC design of this PPE room will follow the requirements in the VA HVAC design manual-20240301, see below.
New work
1. Mechanical calculation.
2. Coordinate with the manufacturer for the customized new AHU.
3. Install the new AHU.
4. Connect the new AHU to the existing building HVAC duct distribution system and the existing building hot water system on weekends or at night.
5. Shift the 6 terminal units from the AHU-2 HVAC system to AHU-3 HVAC system.
Demolition work
1. Disconnect the existing AH-2 from the existing building HVAC duct distribution system and other utility systems.
2. Remove the existing AH-2.
3. Remove the existing ductwork servicing the new PPE room.
Appendix A Cost Estimate
JESSE BROWN VA MEDICAL CENTER
Remodel Sterile Processing Service
Chicago, IL
100% S & S – Statement of Probable Cost
Prepared by: John J. Carter, CPE
VA Project # 537-17-115
ACG # 18-327
Jesse Brown VA Medical Center
INDEX
1. Project Introduction
2. Assumptions / Qualifications
3. Project Data Sheet
4. Cost Estimate:
a. Level 1 Cost Summary Sheet
b. Level 3 Estimate Details
5. Market Survey Report
INTRODUCTION
Project Description
Chicago Jesse Brown VA Medical Center air handling unit, AH-2, services the sterile processing service (SPS) area. AH-2 is near its useful life and does not fulfill the dehumidification requirements in the SPS area because of the campus utility’s (chilled water, steam system) shortage, hence, VA prefers to replace the existing AH-2.
Basis of Estimate The estimate has been prepared using the following information:
1. Project Drawings – 100% S & S, dated June 13, 2024
Drawings on next page.
2. Project Narrative – 100% S & S, dated June 13, 2024
3. Project Specifications – 100% S & S, dated June 13, 2024
ASSUMPTIONS / QUALIFICATIONS
Construction Schedule A construction duration of twelve (12) months has been used for the costs for General Conditions. All work is assumed to be during regular business hours.
Method of Procurement The estimate is based on traditional Design-Bid-Build procurement competitively bid with a minimum of three (3) qualified SDVOSB General Contractors and a minimum of three (3) qualified subcontractors for major trades required for the project.
Basis for Quantities Wherever possible, this estimate has been based upon the actual measurement of different work items. For the remaining items, parametric measurements were used in conjunction with references from similar projects.
Basis for Unit Costs Unit costs are based on current bid prices in the Chicago, IL area. All subcontractors' overhead and profit are included in each line-item unit cost. This overhead and profit cover each subcontractor’s cost for labor burden, materials and equipment sales taxes, field overhead, home office overhead, and profit. The general contractor’s overhead and profit is shown separately in the Summary.
Sources for Pricing This estimate was prepared by qualified cost estimators experienced in estimating construction costs at all design stages. Pricing data to reflect current conditions in the Chicago, IL area. Some quotes may have been solicited from outside sources to substantiate in-house pricing data.
Design Allowances An allowance for undeveloped design details has been included in the summary of this estimate.
Escalation Allowance All labor and material prices herein are reflective of current prices. According to the VA Manual for Cost Estimates, two separate escalations are included on the summary level to take through the mid-point of construction.
Escalation from the date of the estimate to Contract Award assuming the Contract Award is nine (9) months from the date of 100% Sealed Bid Documents using a rate of 8.00% per annum for an escalation of 6.00%.
Escalation from the date of Contract Award to the mid-point of construction is based upon one-half of the estimated construction duration using a rate of 8.00% per annum for an escalation of 4.00%.
Estimated Start date: March 16, 2025 Midpoint of Construction: November 11, 2025 Estimated Completion date: March 15, 2026
Items Excluded From the Estimate, Unless Specifically Noted Otherwise
• Premium time beyond that noted.
• Owner’s field inspection costs.
• General building permit.
• Telephone equipment.
• Move-in costs or maintenance costs after move-in.
Items Affecting the Cost Estimate Items that may change the estimated construction cost include, but are not limited to:
• Modifications or changes to the scope of work.
• Unforeseen concealed conditions.
• Any specified equipment, material, or product item that cannot be obtained from at least three different sources.
• Any other non-competitive bid situations.
• Bids delayed beyond the projected schedule.
Statement of Probable Cost This opinion of the probable construction cost is based on the experience, qualifications, and best judgment of an estimator familiar with the construction industry.
PROJECT DATA SHEET
DATE: June 13, 2024
LOCATION: Chicago, IL PROJECT NO: 537-17-115
TITLE: Jesse Brown VA Medical Center
Submission No: 100% S & S - Statement of Probable Cost
Area Calculations
8,129 SF Approximate Area of Work
QUANTITATIVE BUILDING DESCRIPTION
INT. WALL: 8,700 sf new walls, 138 LF Patch and Repair as Needed
EXT. WALL: N/A
WINDOWS: N/A
EXT. DOORS: N/A
INT. DOORS: 7 EA
NO. OF FLOORS: 3
NO. OF ELEVATORS: N/A
QUALITATIVE BUILDING DESCRIPTION (TYPE & MATERIAL)
FOUNDATION: Existing SUBSTRUCTURE: Existing SUPERSTRUCTURE: Existing EXTERIOR CLOSURE: Existing ROOFING: Existing INTERIOR WALLS: Metal stud with drywall.
Level 1 Cost Summary Sheet Page 1
18-327 VA Chicago SPS - 100% 6/12/202411:12 AM
Estimator: John J. Carter, CPE
Level 1 Description Takeoff Quantity Labor
Amount
Material
Amount Equip Amount Total Cost/Unit Total Amount
A SUBSTRUCTURE 8,129.00 gsf 5,193 11,944 2.11 /gsf 17,137
C INTERIORS 8,129.00 gsf 259,229 297,999 68.55 /gsf 557,228
D SERVICES 8,129.00 gsf 664,033 1,090,053 6,636 216.60 /gsf 1,760,722
E EQUIPMENT & FURNISHINGS 8,129.00 gsf 14,738 25,071 4.90 /gsf 39,809
F SPECIAL CONSTRUCTION & DEMOLITION 8,129.00 gsf 197,963 35,837 28.76 /gsf 233,800
Z GENERAL 8,129.00 gsf 507,076 121,102 38,093 81.96 /gsf 666,271
Estimate Totals
Description Amount Totals Rate
Labor 1,648,232
Material 1,546,169
Equipment 80,566
Subtotal 3,274,967 3,274,967 Bonds & Insurance 98,249 3.000 %
Subtotal 98,249 3,373,216 GC Overhead 337,322 10.000 %
GC Profit 371,054 10.000 %
Subtotal 708,376 4,081,592 Design Contingency
Subtotal 4,081,592 Per 3.3.8 Escalation to Bid Date 03/16/25 244,895 6.000 %
Per 3.3.8 Escalation to Mid Construction 11/11/25 163,264 4.000 %
Total 4,489,751
Level 3 Estimate Details Page 1
18-327 VA Chicago SPS - 100% 6/12/202411:13 AM
Estimator: John J. Carter, CPE
Level 1 Level 2 Level 3 Description Takeoff Quantity Labor Price Labor
Amount Material Price
Material
Amount Equip Price
Equip
Amount Total Cost/Unit Total Amount
A SUBSTRUCTURE
A10 FOUNDATIONS
A1010 Standard Foundations
Interior Equipment Pads 25.00 cy 218.10 /mh 5,193 477.75 /cy 11,944 - - 685.47 /cy 17,137
A1010 Standard Foundations 8,129.00 gsf 5,193 11,944 2.11 /gsf 17,137
A10 FOUNDATIONS 8,129.00 gsf 5,193 11,944 2.11 /gsf 17,137
A SUBSTRUCTURE 8,129.00 gsf 5,193 11,944 2.11 /gsf 17,137
C INTERIORS
C10 INTERIOR CONSTRUCTION
C1010 Interior Partitions
Unfaced Batts @ Wall 3.5" 3,450.00 sf 218.10 /mh 5,016 1.22 /sf 4,489 - - 2.76 /sf 9,506
Unfaced Batts @ Wall 6" 900.00 sf 218.11 /mh 1,309 0.76 /sf 733 - - 2.27 /sf 2,041
Track 3 5/8" 20 Ga. 460.00 lf 218.11 /mh 1,003 2.03 /lf 1,000 - - 4.36 /lf 2,004
Track 6" 20 Ga. 120.00 lf 218.11 /mh 262 2.29 /lf 294 - - 4.63 /lf 556
Metal Studs @ Wall 3-5/8" 20 Ga. 5,032.50 lf 218.10 /mh 10,976 2.03 /lf 10,229 - - 4.21 /lf 21,205
Metal Studs @ Wall 6" 18 Ga. 1,260.00 lf 218.10 /mh 10,304 1.97 /lf 2,482 - - 10.15 /lf 12,786
GWB 5/8" @ Wall - Type X - FC Board 8,700.00 sf 218.10 /mh 18,975 1.48 /sf 13,746 - - 3.76 /sf 32,722
Taping GWB @ Level 4 Finish .... for Paint 8,700.00 sf 218.10 /mh 18,975 0.43 /sf 3,779 - - 2.62 /sf 22,754
Metal Stud Framing Screw - Self Drillers 2,644.80 ea - - 130.10 /box 23 - - 0.01 /ea 23
GWB to Stud Screw - Bugel Head 8,700.00 ea - - 74.87 /box 65 - - 0.01 /ea 65
Patch and Repair Wall as Needed 138.00 lf 217.61 /mh 45,022 34.75 /lf 4,795 - - 360.99 /lf 49,817
C1010 Interior Partitions 8,129.00 gsf 111,842 41,636 18.88 /gsf 153,479
C1020 Interior Doors
HM Single Frames - 3'0" x 7'0" 4.00 ea 217.61 /mh 3,482 498.19 /ea 1,993 - - 1,368.61 /ea 5,474
HM Single Frames - 3'8" x 7'0" 1.00 ea 217.61 /mh 870 451.69 /ea 452 - - 1,322.12 /ea 1,322
HM Double Frames - 6'0" x 6'8" 1.00 ea 217.61 /mh 1,741 996.36 /ea 996 - - 2,737.22 /ea 2,737
Wood Doors Interior 3'0" x 6'8" - Prefinished 2.00 ea 217.61 /mh 870 955.51 /ea 1,911 - - 1,390.72 /ea 2,781
Wood Doors Interior 3'0" x 7'0" - Prefinished 4.00 ea 217.61 /mh 1,741 1,129.23 /ea 4,517 - - 1,564.45 /ea 6,258
Wood Doors Interior 3'8" x 7'0" - Prefinished 1.00 ea 217.61 /mh 435 1,172.66 /ea 1,173 - - 1,607.88 /ea 1,608
Steel Windows by SF 60.00 sf 217.61 /mh 8,704 217.16 /sf 13,030 - - 362.23 /sf 21,734
Finish Hardware Wood Door - Single Set Medical Set 5.00 ea 217.61 /mh 5,440 985.04 /ea 4,925 - - 2,073.07 /ea 10,365
Finish Hardware Wood Door - Double Set Medical Set 1.00 ea 217.61 /mh 2,176 1,970.07 /ea 1,970 - - 4,146.14 /ea 4,146
Automatic Door Operators 1.00 ea 217.61 /mh 3,482 6,914.96 /ea 6,915 - - 10,396.67 /ea 10,397
Paint Interior Door Frames 6.00 ea 217.61 /mh 2,611 17.37 /ea 104 - - 452.59 /ea 2,716
C1020 Interior Doors 8,129.00 gsf 31,553 37,985 8.55 /gsf 69,538
C1030 Specialties
FR Access Doors 24 x 24 12.00 ea 217.61 /mh 6,528 391.85 /ea 4,702 - - 935.86 /ea 11,230
Wall Mount Corner Stainless Steel Guards 4'x4" 12.00 ea 217.61 /mh 5,223 217.16 /ea 2,606 - - 652.37 /ea 7,828
High Impact Wallcovering - HIW 170.00 sf 217.61 /mh 3,699 26.06 /sf 4,430 - - 47.82 /sf 8,129
Floor Bumpers - Steel 190.00 lf 217.61 /mh 4,135 41.26 /lf 7,839 - - 63.02 /lf 11,974
Soap Dispensers - Install Only 6.00 ea 217.61 /mh 392 3.48 /ea 21 - - 68.76 /ea 413
Towel Dispensers - Install Only 6.00 ea 217.60 /mh 326 3.47 /ea 21 - - 57.87 /ea 347
Sharps Disposal - Install Only 1.00 ea 217.61 /mh 870 3.48 /ea 3 - - 873.91 /ea 874
Pass Through Scope Cabinet - Install Only 4.00 ea 217.61 /mh 3,482 86.87 /ea 347 - - 957.29 /ea 3,829
Tube Storage Unit - Install Only 3.00 ea 217.61 /mh 2,611 17.37 /ea 52 - - 887.80 /ea 2,663
HLD Disinfector - Install Only 1.00 ea 217.61 /mh 870 86.86 /ea 87 - - 957.29 /ea 957
HLD Tee Probe Disinfector - Install Only 3.00 ea 217.61 /mh 2,611 86.87 /ea 261 - - 957.29 /ea 2,872
Floor Standing Storage Cabinet - Install Only 1.00 ea 217.11 /mh 868 86.86 /ea 87 - - 955.30 /ea 955
High Level Disinfector - Install Only 10.00 ea 217.11 /mh 8,684 86.86 /ea 869 - - 955.31 /ea 9,553
Ultrasonic Cleaner- Install Only 1.00 ea 217.11 /mh 868 86.86 /ea 87 - - 955.30 /ea 955
Pass Window - Install Only 1.00 ea 217.11 /mh 868 86.87 /ea 87 - - 955.31 /ea 955
Fire Extinguisher Cabinet Recessed 1.00 ea 217.11 /mh 543 461.01 /ea 461 - - 1,003.79 /ea 1,004
C1030 Specialties 8,129.00 gsf 42,580 21,960 7.94 /gsf 64,540
C10 INTERIOR CONSTRUCTION 8,129.00 gsf 185,976 101,582 35.37 /gsf 287,558
C30 INTERIOR FINISHES
C3020 Floor Finishes
Resnious Flooring & Base 4,375.00 sf 217.11 /mh 18,997 31.27 /sf 136,811 - - 35.61 /sf 155,808
LVT Flooring 506.00 sf 217.11 /mh 2,197 12.16 /sf 6,153 - - 16.50 /sf 8,351
Floor Prep 4,915.00 sf 217.11 /mh 21,342 1.30 /sf 6,404 - - 5.65 /sf 27,746
Cove Base 6" 534.00 lf 217.11 /mh 2,319 2.17 /lf 1,241 - - 6.67 /lf 3,560
Carpet Tile 34.00 sy 217.11 /mh 1,476 43.43 /sy 1,477 - - 86.85 /sy 2,953
C3020 Floor Finishes 8,129.00 gsf 46,331 152,086 24.41 /gsf 198,417
C3030 Ceiling Finishes
GWB 5/8" @ Ceiling - Sheathing Gypsum 847.00 sf 217.11 /mh 12,260 17.37 /sf 15,745 - - 33.06 /sf 28,004
2 x 2 Ceiling Textured Tile - ACT-1 1,675.00 sf 217.11 /mh 7,273 7.82 /sf 14,011 - - 12.71 /sf 21,285
2 x 2 Ceiling Textured Tile - ACT-2 1,197.00 sf 217.11 /mh 5,198 10.42 /sf 13,351 - - 15.50 /sf 18,548
C3030 Ceiling Finishes 8,129.00 gsf 24,730 43,107 8.35 /gsf 67,837
C3040 Interior Coatings & Special Finishes
Paint Walls 564.00 sf 194.26 /mh 2,191 2.17 /sf 1,225 - - 6.06 /sf 3,416
C3040 Interior Coatings & Special Finishes 8,129.00 gsf 2,191 1,225 0.42 /gsf 3,416
C30 INTERIOR FINISHES 8,129.00 gsf 73,253 196,417 33.17 /gsf 269,670
C INTERIORS 8,129.00 gsf 259,229 297,999 68.55 /gsf 557,228
D SERVICES
D20 PLUMBING
D2010 Plumbing Fixtures
Wall Hung - Hand Sink P-501 1.00 ea 221.58 /mh 1,773 3,564.89 /ea 3,565 - - 5,337.55 /ea 5,338
Floor Mounted Stainless Steel Triple Sink P-502 4.00 ea 221.58 /mh 7,091 10,081.43 /ea 40,326 - - 11,854.08 /ea 47,416
Wall Hung - Service Sink P-503 1.00 ea 221.58 /mh 1,773 3,512.01 /ea 3,512 - - 5,284.67 /ea 5,285
Floor Mounted Mop Sink P-504 1.00 ea 221.58 /mh 1,773 1,898.80 /ea 1,899 - - 3,671.45 /ea 3,671
Counter Top Sink P-505 2.00 ea 221.58 /mh 3,545 2,254.64 /ea 4,509 - - 4,027.30 /ea 8,055
Eyewash Station P-2000 4.00 ea 221.58 /mh 7,091 1,105.40 /ea 4,422 - - 2,878.05 /ea 11,512
Service Sink P-6500 1.00 ea 221.58 /mh 1,773 1,898.10 /ea 1,898 - - 3,670.75 /ea 3,671
D2010 Plumbing Fixtures 8,129.00 gsf 24,817 60,130 10.45 /gsf 84,948
D2020 Domestic Water Distribution
Water Pipe Copper Sweat - Valves 3/4" 4.00 lf 221.60 /mh 89 10.77 /lf 43 - - 32.93 /lf 132
Hydronic Pipe Steel Sch 40 Thr - Pipe 3/4" 167.00 lf 221.58 /mh 3,700 10.77 /lf 1,799 - - 32.93 /lf 5,499
Hydronic Pipe Steel Sch 40 Thr - Pipe 1 3/4" 28.00 lf 221.58 /mh 620 39.94 /lf 1,118 - - 62.10 /lf 1,739
Hydronic Pipe Steel Sch 40 Thr - Pipe 1 1/2" 45.00 lf 221.58 /mh 997 32.14 /lf 1,446 - - 54.30 /lf 2,443
Hydronic Pipe Steel Sch 40 Thr - Pipe 1" 55.00 lf 221.58 /mh 1,219 15.46 /lf 850 - - 37.62 /lf 2,069
Sanitary Pipe Steel Sch 40 Thr - Pipe 4" 126.00 lf 221.58 /mh 5,584 48.64 /lf 6,129 - - 92.96 /lf 11,713
Sanitary Pipe Steel Sch 40 Thr - Pipe 2" 99.00 lf 221.58 /mh 2,194 26.51 /lf 2,625 - - 48.67 /lf 4,818
Sanitary Vent Pipe Steel Sch 40 Thr - Pipe 2" 297.00 lf 221.58 /mh 6,581 26.51 /lf 7,874 - - 48.67 /lf 14,455
Hydronic Pipe Steel Sch 40 Thr - Pipe 1" 55.00 lf 221.58 /mh 1,219 15.46 /lf 850 - - 37.62 /lf 2,069
DHW Pipe Steel Sch 40 Thr - Pipe 1" 256.00 lf 221.58 /mh 5,672 15.46 /lf 3,958 - - 37.62 /lf 9,631
DHW Pipe Steel Sch 40 Thr - Pipe 3/4" 248.00 lf 221.58 /mh 5,495 10.77 /lf 2,671 - - 32.93 /lf 8,166
DHW Pipe Steel Sch 40 Thr - Pipe 1 1/4" 130.00 lf 221.58 /mh 2,881 33.88 /lf 4,404 - - 56.04 /lf 7,285
DHW Pipe Steel Sch 40 Thr - Pipe 1/4" 51.00 lf 221.58 /mh 1,130 11.73 /lf 598 - - 33.89 /lf 1,728
DI Pipe Steel Sch 40 Thr - Pipe 3/4" 42.00 lf 221.58 /mh 931 11.73 /lf 493 - - 33.88 /lf 1,423
Hydronic Pipe Steel Sch 40 Thr - Fittings 3/4" 25.00 ea 221.58 /mh 2,770 1.74 /ea 43 - - 112.53 /ea 2,813
Hydronic Pipe Steel Sch 40 Thr - Fittings 1 1/2" 10.00 ea 221.58 /mh 1,108 3.47 /ea 35 - - 114.27 /ea 1,143
Hydronic Pipe Steel Sch 40 Thr - Fittings 1 1/4" 5.00 ea 221.58 /mh 554 3.47 /ea 17 - - 114.26 /ea 571
DHW Pipe Steel Sch 40 Thr - Fittings 1" 30.00 ea 221.58 /mh 3,324 3.47 /ea 104 - - 114.27 /ea 3,428
HW Pipe Steel Sch 40 Thr - Fittings 3/4" 33.00 ea 221.58 /mh 3,656 1.74 /ea 57 - - 112.53 /ea 3,713
Sanitary Pipe Steel Sch 40 Thr - Fittings 4" 20.00 ea 221.58 /mh 2,216 5.21 /ea 104 - - 116.00 /ea 2,320
Sanitary Pipe Steel Sch 40 Thr - Fittings 2" 10.00 ea 221.58 /mh 1,108 3.48 /ea 35 - - 114.27 /ea 1,143
Sanitary Vent Pipe Steel Sch 40 Thr - Fittings 2" 30.00 ea 221.58 /mh 3,324 3.47 /ea 104 - - 114.27 /ea 3,428
DHW Pipe Steel Sch 40 Thr - Fittings 1 1/4" 30.00 ea 221.58 /mh 3,324 3.47 /ea 104 - - 114.27 /ea 3,428
HW Pipe Steel Sch 40 Thr - Fittings 3/4" 5.00 ea 221.58 /mh 554 1.74 /ea 9 - - 112.53 /ea 563
Level 3 Estimate Details Page 2
Estimator: John J. Carter, CPE
Level 1 Level 2 Level 3 Description Takeoff Quantity Labor Price Labor
Amount Material Price
Material
Amount Equip Price
Equip
Amount Total Cost/Unit Total Amount
D2020 Domestic Water Distribution
DHW Pipe Steel Sch 40 Thr - Fittings 1/4" 10.00 ea 221.58 /mh 1,108 1.74 /ea 17 - - 112.53 /ea 1,125
DI Pipe Steel Sch 40 Thr - Fittings 3/4" 5.00 ea 221.58 /mh 554 1.74 /ea 9 - - 112.53 /ea 563
3/4" Shut Off Valves 27.00 ea 221.58 /mh 11,965 43.43 /ea 1,173 - - 486.60 /ea 13,138
Expansion Tank Stainless Steel - 10 Gallon 1.00 ea 221.58 /mh 443 2,084.73 /ea 2,085 - - 2,527.89 /ea 2,528
Thermostatic Mixing Valve 4.00 ea 221.58 /mh 3,545 691.44 /ea 2,766 - - 1,577.77 /ea 6,311
D2020 Domestic Water Distribution 8,129.00 gsf 77,864 41,521 14.69 /gsf 119,385
D20 PLUMBING 8,129.00 gsf 102,681 101,652 25.14 /gsf 204,332
D30 HEATING, VENTILATION & AIR CONDITIONING
D3040 Distribution Systems
Gal Metal Duct 18 Ga. 10" Round 211.00 lbs 219.59 /mh 2,896 23.45 /lbs 5,691 - - 40.70 /lbs 8,587
Gal Metal Duct 18 Ga. 8" Round 298.00 lbs 219.59 /mh 4,090 23.45 /lbs 8,037 - - 40.70 /lbs 12,127
Gal Metal Duct 18 Ga. 10x10 75.00 lbs 219.60 /mh 1,029 23.45 /lbs 2,023 - - 40.70 /lbs 3,052
Gal Metal Duct 18 Ga. 18x12 319.00 lbs 219.59 /mh 4,378 23.45 /lbs 8,604 - - 40.70 /lbs 12,982
Gal Metal Duct 18 Ga. 12x10 105.00 lbs 219.60 /mh 1,441 23.45 /lbs 2,832 - - 40.70 /lbs 4,273
Gal Metal Duct 18 Ga. 16x10 288.00 lbs 219.59 /mh 3,953 23.45 /lbs 7,768 - - 40.70 /lbs 11,720
Gal Metal Duct 18 Ga. 6" Round 43.00 lbs 219.59 /mh 590 23.45 /lbs 1,160 - - 40.70 /lbs 1,750
Gal Metal Duct 18 Ga. 20x10 227.00 lbs 219.59 /mh 3,115 23.45 /lbs 6,122 - - 40.70 /lbs 9,238
Gal Metal Duct 18 Ga. 12x8 Transfer Elbow Duct 136.00 lbs 219.60 /mh 1,867 23.45 /lbs 3,668 - - 40.70 /lbs 5,535
Gal Metal Duct 18 Ga. 25x14 225.00 lbs 219.59 /mh 3,088 23.45 /lbs 6,069 - - 40.70 /lbs 9,157
VAV Box w/ HW Re-Heat Coil 500- 850 cfm 4.00 ea 219.59 /mh 7,027 3,908.88 /ea 15,636 - - 5,665.63 /ea 22,663
Supply Diffuser Aluminum Linear 2" 9.00 ea 219.59 /mh 346 304.02 /ea 2,736 - - 342.45 /ea 3,082
Exhaust Grille Aluminum Linear 2" 8.00 ea 219.60 /mh 307 304.02 /ea 2,432 - - 342.45 /ea 2,740
Air Handling Unit - 16,000 CFM 1.00 ea 219.59 /mh 26,351 382,201.31 /ea 382,201 165.91 /eh 1,327 409,879.90 /ea 409,880
Rooftop Condensing Unit 130Ton 1.00 ea 219.59 /mh 26,351 217,159.83 /ea 217,160 165.91 /eh 1,327 244,838.43 /ea 244,838
Air Compressor - 3 HP 1.00 ea 219.59 /mh 3,514 15,215.09 /ea 15,215 165.91 /eh 664 19,392.24 /ea 19,392
Steam Humidifier - 14,000 CFM 2.00 ea 219.59 /mh 7,027 28,665.10 /ea 57,330 165.91 /eh 1,327 32,842.25 /ea 65,684
Exhaust Fan - 7000 CFM - 5 HP 1.00 ea 219.59 /mh 8,784 9,555.03 /ea 9,555 165.91 /eh 664 19,002.44 /ea 19,002
Air Balance System 1.00 ea 219.59 /mh 8,784 9,555.03 /ea 9,555 165.91 /eh 664 19,002.45 /ea 19,002
Balancing Damper 8.00 ea 219.59 /mh 3,514 43.43 /ea 347 - /eh - 482.62 /ea 3,861
Refrigerant Suction and Liquid Line 132.00 lf 219.59 /mh 1,159 17.37 /lf 2,293 - /eh - 26.16 /lf 3,453
Air Compressor - 20 HP 1.00 ea 219.59 /mh 3,514 43,431.97 /ea 43,432 165.91 /eh 664 47,609.12 /ea 47,609
D3040 Distribution Systems 8,129.00 gsf 123,125 809,867 6,636 115.59 /gsf 939,628
D3060 Controls & Instrumentation
VAV Box DDC Controller 4.00 ea 219.59 /mh 7,027 1,389.83 /ea 5,559 - - 3,146.58 /ea 12,586
Temp Trak Room Monitor 1.00 ea 219.59 /mh 3,514 1,302.96 /ea 1,303 - - 4,816.46 /ea 4,816
Programming, Graphics, and Commissioning 1.00 ea 219.59 /mh 17,568 4,343.19 /ea 4,343 - - 21,910.74 /ea 21,911
Air Handler DDC Controller 1.00 ea 219.60 /mh 1,757 2,605.92 /ea 2,606 - - 4,362.68 /ea 4,363
Duct Temperature Sensors 5.00 ea 219.59 /mh 4,392 217.16 /ea 1,086 - - 1,095.54 /ea 5,478
Duct Humidity Sensors 3.00 ea 219.59 /mh 2,635 304.02 /ea 912 - - 1,182.40 /ea 3,547
Duct Differential Pressure Sensors 3.00 ea 219.60 /mh 2,635 868.64 /ea 2,606 - - 1,747.02 /ea 5,241
Duct Static Pressure Sensors 4.00 ea 219.59 /mh 3,514 868.64 /ea 3,475 - - 1,747.02 /ea 6,988
Duct Smoke Detector 1.00 ea 219.60 /mh 878 868.64 /ea 869 - - 1,747.02 /ea 1,747
OSA Damper Actuator 1.00 ea 219.59 /mh 1,757 217.16 /ea 217 - - 1,973.91 /ea 1,974
Hot Water Valve and Actuator 2" - AHJ 1.00 ea 219.60 /mh 1,757 2,605.91 /ea 2,606 - - 4,362.67 /ea 4,363
Chilled Water Valve and Actuator 3" - AHU 1.00 ea 219.60 /mh 1,757 3,127.10 /ea 3,127 - - 4,883.86 /ea 4,884
Temp Trak Room Monitor - Room Temp Sensors 7.00 ea 219.59 /mh 3,074 217.16 /ea 1,520 - - 656.35 /ea 4,594
Air Flow Monitoring Station 1.00 ea 219.59 /mh 1,757 1,346.39 /ea 1,346 - - 3,103.14 /ea 3,103
Humidifier Steam Valve and Actuator - 1" 1.00 ea 219.60 /mh 1,757 781.77 /ea 782 - - 2,538.53 /ea 2,539
VA Notebook Computers 3.00 ea 219.59 /mh 5,270 1,737.28 /ea 5,212 - - 3,494.03 /ea 10,482
VAV Box Control Valve and Actuator 4.00 ea 219.59 /mh 3,514 260.59 /ea 1,042 - - 1,138.97 /ea 4,556
D3060 Controls & Instrumentation 8,129.00 gsf 64,561 38,611 12.69 /gsf 103,172
D30 HEATING, VENTILATION & AIR
CONDITIONING
8,129.00 gsf 187,686 848,478 6,636 128.28 /gsf 1,042,800
D40 FIRE PROTECTION
D4040 Sprinklers
Sprinkler Head - Quick Response 16.00 ea 216.12 /mh 13,831 85.13 /ea 1,362 - - 949.59 /ea 15,193
Pendant Sprinkler Head 9.00 ea 216.12 /mh 7,780 43.43 /ea 391 - - 907.90 /ea 8,171
D4040 Sprinklers 8,129.00 gsf 21,612 1,753 2.87 /gsf 23,365
D4050 Fire Protection Specialties
FA Cable Connections 25.00 lf 217.61 /mh 2,720 6.08 /lf 152 - - 114.88 /lf 2,872
FA Horn Strobe 7.00 lf 217.61 /mh 6,093 701.86 /lf 4,913 - - 1,572.29 /lf 11,006
FA Pull Station 2.00 lf 217.61 /mh 1,741 194.58 /lf 389 - - 1,065.01 /lf 2,130
D4050 Fire Protection Specialties 8,129.00 gsf 10,554 5,454 1.97 /gsf 16,008
D40 FIRE PROTECTION 8,129.00 gsf 32,166 7,207 4.84 /gsf 39,373
D50 ELECTRICAL
D5010 Electrical Service & Distribution
120 208V Dist Panel MLO 100A R1C-1-3-AA 1.00 ea 217.61 /mh 1,741 2,048.26 /ea 2,048 - - 3,789.11 /ea 3,789
20A 1P Circuit Breaker 29.00 ea 217.61 /mh 12,621 72.97 /ea 2,116 - - 508.18 /ea 14,737
40A 3P Circuit Breaker 1.00 ea 217.61 /mh 435 1,025.00 /ea 1,025 - - 1,460.21 /ea 1,460
80A 3P Circuit Breaker - for AHU 1.00 ea 217.61 /mh 870 1,302.96 /ea 1,303 - - 2,173.38 /ea 2,173
20A 1P Circuit Breaker - P3C-3-3 AHU Light 1.00 ea 217.61 /mh 435 72.96 /ea 73 - - 508.18 /ea 508
277 480V Dist Panel MLO 100A 24 Circuit 1.00 ea 217.61 /mh 1,741 3,330.36 /ea 3,330 - - 5,071.22 /ea 5,071
300A 3P Circuit Breaker - for Condensing Unit 1.00 ea 217.61 /mh 870 2,423.50 /ea 2,424 - - 3,293.93 /ea 3,294
20A 3P Circuit Breaker - Condensing Unit Circuit 1.00 ea 217.61 /mh 435 806.10 /ea 806 - - 1,241.32 /ea 1,241
20A 1P Circuit Breaker - Humidifier 2.00 ea 217.61 /mh 870 72.97 /ea 146 - - 508.18 /ea 1,016
1" Conduit 124.00 lf 217.61 /mh 1,349 6.72 /lf 834 - - 17.60 /lf 2,183
1 14" Conduit 53.00 lf 217.61 /mh 577 8.25 /lf 437 - - 19.13 /lf 1,014
3 1/2" Conduit 77.00 lf 217.61 /mh 838 25.47 /lf 1,961 - - 36.35 /lf 2,799
500 KCMIL 77.00 lf 217.61 /mh 1,676 16.50 /lf 1,271 - - 38.26 /lf 2,946
#3 Cable 77.00 lf 217.61 /mh 1,676 4.20 /lf 324 - - 25.97 /lf 1,999
#4 Cable 77.00 lf 217.60 /mh 1,676 3.58 /lf 276 - - 25.34 /lf 1,951
#6 Cable 124.00 lf 217.61 /mh 2,698 2.71 /lf 336 - - 24.47 /lf 3,034
#8 Cable 15.00 lf 217.61 /mh 326 1.82 /lf 27 - - 23.58 /lf 354
277 480V Dist Panel MLO 100A 24 Circuit 1.00 ea 217.61 /mh 1,741 3,330.36 /ea 3,330 - - 5,071.22 /ea 5,071
1 14" Conduit - Condensing Unit 100.00 lf 217.60 /mh 1,088 8.25 /lf 825 - - 19.13 /lf 1,913
Panel - 480V 3Ph 4W NEMA 1 MLO 225A 42 Pole 1.00 ea 190.23 /mh 1,902 3,346.37 /ea 3,346 - - 5,248.69 /ea 5,249
Panel - 480V 3Ph 4W NEMA 1 MLO 600A 42 Pole 1.00 ea 190.23 /mh 3,044 4,997.25 /ea 4,997 - - 8,040.97 /ea 8,041
Relocate existing panel P4E-3-2A 1.00 ea 190.23 /mh 7,609 743.64 /ea 744 - - 8,352.92 /ea 8,353
Breaker 480v - 3 Pole 200A 1.00 ea 190.24 /mh 380 3,866.92 /ea 3,867 - - 4,247.39 /ea 4,247
D5010 Electrical Service & Distribution 8,129.00 gsf 46,600 35,846 10.14 /gsf 82,446
D5020 Lighting & Branch Wiring
Duplex Outlets 6.00 ea 217.61 /mh 2,611 43.43 /ea 261 - - 478.65 /ea 2,872
2x4 LED Lighting Fixtures 184.00 ea 217.61 /mh 160,159 260.59 /ea 47,949 - - 1,131.02 /ea 208,108
3/4" Conduit 66.00 lf 217.61 /mh 718 4.95 /lf 327 - - 15.83 /lf 1,045
#12 Cable 69.00 lf 217.60 /mh 1,501 1.65 /lf 114 - - 23.41 /lf 1,615
Wall Switch 35.00 ea 217.61 /mh 30,465 86.86 /ea 3,040 - - 957.29 /ea 33,505
6" Down Light 8.00 ea 217.61 /mh 6,963 165.04 /ea 1,320 - - 1,035.47 /ea 8,284
Exit Sign 8.00 ea 217.61 /mh 6,963 199.79 /ea 1,598 - - 1,070.22 /ea 8,562
Feed VAV 1.00 ea 217.61 /mh 435 347.46 /ea 347 - - 782.67 /ea 783
Feed Compressor 2.00 ea 217.61 /mh 870 347.46 /ea 695 - - 782.67 /ea 1,565
D5020 Lighting & Branch Wiring 8,129.00 gsf 210,687 55,651 32.76 /gsf 266,339
D5030 Communications & Security
IP Camera 2.00 ea 217.61 /mh 1,741 4,343.20 /ea 8,686 - - 5,213.63 /ea 10,427
Intercom 3.00 ea 217.61 /mh 2,611 2,084.74 /ea 6,254 - - 2,955.16 /ea 8,865
Data Port 6.00 ea 217.61 /mh 5,223 39.96 /ea 240 - - 910.39 /ea 5,462
Card Reader 2.00 ea 217.61 /mh 1,741 368.30 /ea 737 - - 1,238.73 /ea 2,477
Request to Exit 2.00 ea 217.61 /mh 1,741 119.87 /ea 240 - - 990.30 /ea 1,981
Electric Strike 2.00 ea 217.61 /mh 1,741 502.08 /ea 1,004 - - 1,372.51 /ea 2,745
Door Contact 4.00 ea 217.61 /mh 3,482 85.13 /ea 341 - - 955.55 /ea 3,822
Level 3 Estimate Details Page 3
Estimator: John J. Carter, CPE
Level 1 Level 2 Level 3 Description Takeoff Quantity Labor Price Labor
Amount Material Price
Material
Amount Equip Price
Equip
Amount Total Cost/Unit Total Amount
D5030 Communications & Security
CAT 6 Cable 2,345.00 lf 217.61 /mh 51,029 8.77 /lf 20,573 - - 30.53 /lf 71,602
Access Controller 2.00 ea 217.61 /mh 3,482 1,389.83 /ea 2,780 - - 3,130.68 /ea 6,261
J Hooks 105.00 ea 217.61 /mh 11,424 3.47 /ea 365 - - 112.28 /ea 11,789
D5030 Communications & Security 8,129.00 gsf 84,214 41,219 15.43 /gsf 125,433
D50 ELECTRICAL 8,129.00 gsf 341,501 132,717 58.34 /gsf 474,218
D SERVICES 8,129.00 gsf 664,033 1,090,053 6,636 216.60 /gsf 1,760,723
E EQUIPMENT & FURNISHINGS
E20 FURNISHINGS
E1020 Institutional Equipment
Stainless Steel Base Cabinets and Counter Top 1.00 ea 217.61 /mh 435 6,949.12 /ea 6,949 - - 7,384.33 /ea 7,384
Stainless Steel Work Table 1.00 ea 217.61 /mh 435 2,605.92 /ea 2,606 - - 3,041.13 /ea 3,041
Wall Bumpers - Wood 293.00 lf 217.61 /mh 6,376 34.75 /lf 10,180 - - 56.51 /lf 16,556
Handrails - Wood 25.00 lf 217.61 /mh 544 47.48 /lf 1,187 - - 69.24 /lf 1,731
Laboratory Storage Cabinets - Stainless Steel 4.00 ea 217.11 /mh 6,948 1,037.24 /ea 4,149 - - 2,774.13 /ea 11,097
E1020 Institutional Equipment 8,129.00 gsf 14,738 25,071 4.90 /gsf 39,809
E20 FURNISHINGS 8,129.00 gsf 14,738 25,071 4.90 /gsf 39,809
E EQUIPMENT & FURNISHINGS 8,129.00 gsf 14,738 25,071 4.90 /gsf 39,809
F SPECIAL CONSTRUCTION & DEMOLITION
F20 SELECTIVE BUILDING DEMOLITION
F2010 Building Elements Demolition
Equipment for Demolition 1.00 ls - - - - 33,181.97 /ls 33,182 33,181.97 /ls 33,182
Relocate Medivator - Provided by VA - Install Only 6.00 ea 160.47 /mh 15,405 - /ea - - - 2,567.56 /ea 15,405
Remove Misc Equipment Give to VA 2.00 ea 160.47 /mh 5,135 - /ea - - - 2,567.57 /ea 5,135
Relocate Steris Caviwave - Install Only 1.00 ea 160.47 /mh 2,568 - /ea - - - 2,567.57 /ea 2,568
Relocate Scope Processor - Install Only 1.00 ea 160.47 /mh 2,568 - /ea - - - 2,567.56 /ea 2,568
Relocate Wire Mesh Partition 1.00 ea 160.47 /mh 2,568 - /ea - - - 2,567.56 /ea 2,568
Demo Single Door & Frame 6.00 ea 160.47 /mh 3,851 - - - - 641.89 /ea 3,851
Demo Window Metal Mesh 109.00 lf 160.47 /mh 69,966 - - - - 641.89 /lf 69,966
Remove Tall Cabinets and Re-Install 4.00 lf 160.47 /mh 2,568 - - - - 641.89 /lf 2,568
Demo Shelving 36.00 sf 160.47 /mh 1,155 - - - - 32.09 /sf 1,155
Demo GWB Walls 3" Metal Stud 109.00 sf 160.47 /mh 292 - - - - 2.67 /sf 292
Demo LVT Flooring 1,425.00 sf 160.47 /mh 3,518 - - - - 2.47 /sf 3,518
Demo Ceiling Tile & Grid 4,003.00 sf 160.47 /mh 8,565 - - - - 2.14 /sf 8,565
Demo GWB Ceilings 142.00 sf 160.48 /mh 456 - - - - 3.21 /sf 456
Demo Handrail 15.00 lf 160.47 /mh 481 - - - - 32.09 /lf 481
Demo Casework and Sink 5.00 ea 160.47 /mh 3,209 - - - - 641.89 /ea 3,209
Demo Sprinkler Heads 18.00 ea 160.48 /mh 722 - - - - 40.12 /ea 722
Demo Pendant Sprinkler Heads 9.00 ea 160.47 /mh 361 - - - - 40.12 /ea 361
Demo Interior CS Pipe 1" 12.00 lf 160.44 /mh 33 - - - - 2.73 /lf 33
Demo Interior HW Pipe 1" 257.00 lf 160.48 /mh 701 - - - - 2.73 /lf 701
Demo Eyewash Sinks 2.00 ea 160.47 /mh 1,284 - - - - 641.89 /ea 1,284
Demo Double Sinks 3.00 ea 160.47 /mh 1,926 - - - - 641.89 /ea 1,926
Demo Air Handler Unit 1.00 ea 160.47 /mh 6,419 - - 165.91 /eh 1,327 7,746.19 /ea 7,746
Demo Ducts - Small 91.00 lf 160.47 /mh 730 - - - - 8.02 /lf 730
Demo VAV Boxes 2.00 ea 160.47 /mh 1,284 - - - - 641.89 /ea 1,284
Demo Ductwork 136.00 lf 160.47 /mh 2,182 - - - - 16.05 /lf 2,182
Demo Exhaust Fans 1.00 ea 160.47 /mh 1,284 - - - - 1,283.78 /ea 1,284
Demo Rooftop Condensing Unit 1.00 ea 160.47 /mh 2,568 - - 165.91 /eh 1,327 3,894.84 /ea 3,895
Demo Ceiling Diffusers and Grilles 8.00 ea 160.47 /mh 2,568 - - - - 320.95 /ea 2,568
Remove Wall Louver and Re-Install 4.00 ea 160.47 /mh 5,135 - - - - 1,283.78 /ea 5,135
Demo Fume Hood 1.00 ea 160.47 /mh 1,284 - - - - 1,283.79 /ea 1,284
Relocate Thermostat 2.00 ea 160.47 /mh 642 - - - - 320.95 /ea 642
Demo Existing Light Switch 14.00 ea 160.47 /mh 4,493 - - - - 320.95 /ea 4,493
Demo Existing Outlets 32.00 ea 160.47 /mh 10,270 - - - - 320.95 /ea 10,270
Demo Existing Lay-In Light Fixture 2' x 4' 94.00 ea 160.47 /mh 30,169 - - - - 320.95 /ea 30,169
Demo Data Outlet 5.00 ea 160.47 /mh 802 - - - - 160.47 /ea 802
Demo Data JBox 1.00 ea 160.47 /mh 160 - - - - 160.47 /ea 160
Demo Key Pad 2.00 ea 160.47 /mh 642 - - - - 320.94 /ea 642
F2010 Building Elements Demolition 8,129.00 gsf 197,963 35,837 28.76 /gsf 233,800
F20 SELECTIVE BUILDING DEMOLITION 8,129.00 gsf 197,963 35,837 28.76 /gsf 233,800
F SPECIAL CONSTRUCTION & DEMOLITION 8,129.00 gsf 197,963 35,837 28.76 /gsf 233,800
Z GENERAL
Z10 GENERAL REQUIREMENTS
Z1020 Administrative Requirements
Project Manager - 1/2 Time 52.00 wk 3,040.24 /wk 158,092 - /wk - - - 3,040.24 /wk 158,092
Superintendent 52.00 wk 4,864.38 /wk 252,948 - /wk - - - 4,864.38 /wk 252,948
Scheduling Expense 1.00 ls 868.64 /ls 869 1,487.28 /ls 1,487 - - 2,355.92 /ls 2,356
Prints & Records 1.00 ls - - 3,718.19 /ls 3,718 - - 3,718.19 /ls 3,718
As Built Drawings & Records 1.00 ls - /ls - 3,718.20 /ls 3,718 - - 3,718.20 /ls 3,718
Project Photos 12.00 mo - - 297.46 /mo 3,569 - - 297.46 /mo 3,569
Weekly Auto Allowance - PM - 1/2 Time 52.00 wk - - /wk 66.36 /wk 3,451 66.36 /wk 3,451
Weekly Auto Allowance - Supt 52.00 wk - - /wk 132.73 /wk 6,902 132.73 /wk 6,902
Weekly Auto Fuel Allowance - PM - 1/2 Time 52.00 wk - - /wk 66.36 /wk 3,451 66.36 /wk 3,451
Weekly Auto Fuel Allowance - Supt 52.00 wk - - /wk 132.73 /wk 6,902 132.73 /wk 6,902
Telephone Charges - Land Line Install 1.00 ls - - 1,115.46 /ls 1,115 - - 1,115.46 /ls 1,115
Cell Phone - Per Person Per Month 12.00 mo - - 185.91 /mo 2,231 - - 185.91 /mo 2,231
Office Trailer 12.00 mo - - - /mo - 663.64 /mo 7,964 663.64 /mo 7,964
Tool Trailer 12.00 mo - - - /mo - 398.18 /mo 4,778 398.18 /mo 4,778
Office Trailer - Mob & Demob 1.00 ea 868.64 /ea 869 - /ea - 1,327.28 /ea 1,327 2,195.92 /ea 2,196
Office Trailer - Block & Level & Unblock 1.00 ea 140.29 /mh 2,245 - /ea - 1,327.28 /ea 1,327 3,571.84 /ea 3,572
Office Trailer - Stair & Rail 1.00 ea 140.29 /mh 5,611 - /ea - 1,990.92 /ea 1,991 7,602.33 /ea 7,602
Information Technology Expense 12.00 mo /ea 223.09 /mo 2,677 - - 223.09 /mo 2,677
Office Supply & Equip -GC 12.00 mo /ea 743.64 /mo 8,924 - - 743.64 /mo 8,924
Project Signs 12.00 ea 140.29 /mh 26,935 1,487.28 /ea 17,847 - - 3,731.84 /ea 44,782
Water Charges - Trailer 12.00 mo - - 185.91 /mo 2,231 - - 185.91 /mo 2,231
Electric Power - Trailer 12.00 mo - - 446.18 /mo 5,354 - - 446.18 /mo 5,354
Temporary Toilets 12.00 mo - - 409.00 /mo 4,908 - - 409.00 /mo 4,908
Punch List by LS 1.00 ls 4,343.19 /ls 4,343 3,718.20 /ls 3,718 - - 8,061.39 /ls 8,061
User Training 1.00 ls 868.64 /ls 869 2,230.92 /ls 2,231 - - 3,099.56 /ls 3,100
User Manuals 1.00 ls 868.64 /ls 869 2,230.91 /ls 2,231 - - 3,099.55 /ls 3,100
Weekly Cleaning 20.00 wk 1,737.28 /wk 34,746 223.09 /wk 4,462 - - 1,960.37 /wk 39,207
Final Cleaning 5,000.00 sf 1.30 /sf 6,515 1.49 /sf 7,436 - - 2.79 /sf 13,951
Dumpster Rental/Pick up 20.00 wk - - 892.37 /wk 17,847 - - 892.37 /wk 17,847
Temporary Protection 1.00 ls 2,605.91 /ls 2,606 2,230.92 /ls 2,231 - - 4,836.83 /ls 4,837
Contractor Employee ID Badges 10.00 ea - - 148.73 /ea 1,487 - - 148.73 /ea 1,487
Fire Extinguishers 5.00 ea 142.46 /mh 356 111.55 /ea 558 - - 182.77 /ea 914
Miscellaneous Safety 1.00 ls 868.64 /ls 869 2,230.92 /ls 2,231 - - 3,099.56 /ls 3,100
First Aid Kits & Safety Supplies 1.00 ls - - 371.82 /ls 372 - - 371.82 /ls 372
ICRA - Temp Dr - Hard Wall 188.00 lf 140.29 /mh 527 37.18 /lf 6,990 - - 39.99 /lf 7,518
ICRA - Zip Walls 50.00 lf 140.27 /mh 234 22.31 /lf 1,115 - - 26.99 /lf 1,349
ICRA - Sticky Mats 5.00 ea 140.29 /mh 7,014 23.80 /pad 5,949 - - 2,592.68 /ea 12,963
ICRA - HEPA Negative Air Unit 1.00 ea 140.29 /mh 561 4,461.84 /ea 4,462 - - 5,022.98 /ea 5,023
Z1020 Administrative Requirements 8,129.00 gsf 507,076 121,102 38,093 81.96 /gsf 666,271
Z10 GENERAL REQUIREMENTS 8,129.00 gsf 507,076 121,102 38,093 81.96 /gsf 666,271
Z GENERAL 8,129.00 gsf 507,076 121,102 38,093 81.96 /gsf 666,271
ACG Project:
VA Project #:
Location:
Estimate:
Date:
Major Market:
Travel Distance:
Travel Time:
Conclusion:
Source:
Davis Bacon Rates: Base Rate Fringe Total Rate Labor
Adjustment
Competition
Adjustment
ADJUSTED RATE
ESTIMATE
RATE*
Laborer 47.40$ 33.16$ 80.56$ 8.06$ 8.06$ 96.67$ 96.75$
Cement Mason 50.75$ 40.59$ 91.34$ 9.13$ 9.13$ 109.61$ 109.75$
Brick Layer 44.88$ 26.62$ 71.50$ 7.15$ 7.15$ 85.80$ 86.00$
Iron Worker 57.00$ 43.75$ 100.75$ 10.08$ 10.08$ 120.90$ 121.00$
Carpenter 52.01$ 38.85$ 90.86$ 9.09$ 9.09$ 109.03$ 109.25$
Drywall Finisher 50.30$ 31.07$ 81.37$ 8.14$ 8.14$ 97.64$ 97.75$
Roofer 49.00$ 28.38$ 77.38$ 7.74$ 7.74$ 92.86$ 93.00$
Painter 50.30$ 31.07$ 81.37$ 8.14$ 8.14$ 97.64$ 97.75$
Elevator Mechanic 67.84$ 37.89$ 105.73$ 10.57$ 10.57$ 126.88$ 127.00$
Sprinkler Fitter 56.60$ 34.00$ 90.60$ 9.06$ 9.06$ 108.72$ 108.75$
Plumber 56.80$ 36.02$ 92.82$ 9.28$ 9.28$ 111.38$ 111.50$
HVAC Mech. 49.10$ 42.91$ 92.01$ 9.20$ 9.20$ 110.41$ 110.50$
Electrician 52.05$ 39.12$ 91.17$ 9.12$ 9.12$ 109.40$ 109.50$
Machine Operator 55.30$ 47.70$ 103.00$ 10.30$ 10.30$ 123.60$ 123.75$
Crane Operator 56.60$ 47.70$ 104.30$ 10.43$ 10.43$ 125.16$ 125.25$
Availability:
Conclusion:
Availability:
Conclusion:
Availability:
Conclusion:
https://sam.gov/wage-determination/IL20240009/2
MARKET SURVEY REPORT
18-327 Chicago - Renovate SPS
537-17-115
Chicago, IL
100% S&S
6/13/2024
Chicago, IL
10 miles
Less than 30 minutes
No adjustments required for travel
Labor
Material
*Note: Minimum Labor Rates to be used is $45/ hr.
All indices the Confindex tracks rose between Q4 2023 and Q1 2024. The overall Confindex is up 13.5% this quarter to a 109 rating. The largest increase was in the “business conditions” index, which jumped 25.3% to a 109 rating. The “financial conditions” and “current conditions” indices saw more modest gains, up 5.8% to 109 and 7.3% to 103 respectively.
Confindex respondents report a surging short-term optimism. “The order of magnitude seems really significant,” says Neil Shah, CFMA CEO and president. The “year ahead outlook” index increased 20.8% to a 116 rating—its highest reading since Q4 2021. CICI survey respondents appear to be moving in the same positive direction. The number of respondents who see a declining market 3-6 months from now (19.5%) is nearly halved from the
Q4 2023 reading (38.9%). Nearly 40% of firms see an improving market 12-18 months from now, up from 28%.
Longer construction durations and associated higher costs. Therefore, labor rates adjusted by 10%.
Source:
Cost Report - 1Q 2024 Cost Report: Construction Executive Optimism Surges, written by Jonathan Keller.
The Midwest Region currently has a March 2024 AIA billing index of 45.2. A value above 50 indicates an increase in construction. With a value of 45.2, this shows an decrease of 5.6 from February 2024 which had a billing index of 50.8. Over the past year, institutional projects (49.9) have seen stronger billings than that of the commerial/industrial (42.9) and residential (44.2) sectors which is showing a incease/decrease in billings (from March 2023 to
March 2024).
Lack of firms to competitively bid projects and supply chain issues. Therefore, labor rates are adjusted by 10%.
Source:
www.aia.org
Architecture Billings Index (ABI) - March 2024 https://www.enr.com/articles/58445-1q-2024-cost-report-construction-executive-optimism-surges
As of May 2024, ENR reports the Construction Cost Index has increased from April 13532.08 points to 13532.44 points. With the annual inflation rate increasing for the month for April 22: construction cost index of +1.8% (May 2024), building cost index of +3.1% (May 2024), and materials cost index
+0.0% (May 2024). ENR projects increase and/or decrease for the following materials in May 2024: Concrete Block, +0.2%; Ready-Mix Concrete, -1.3%;
Asphalt Paving, -0.7%; and Portland Cement, +0.2%. Pricing indices provided by RS Means and other sources.
Material prices from RS Means and vendors are used without adjustment.
Source:
www.rsmeansonline.com www.enr.com
Engineering News-Record (ENR) - May 6, 2024
Appendix B Cut Sheets
Job Summary Project Name: VA Chicago JB SPS Remodel Unit Tag(s): AHU-1 Quantity: 1 Environment: Indoor
Unit Overview Model Airflow (CFM) Altitude (ft) Weight (lbs)
XTI-75x81 14,000 0 10,300
Segment Sequence
(DP RF-2 FS)(CC-2 CC-1)(HM HC-2)(HC-1 RF-1 IP)
Unit Construction Casing Details
Segment(s) Thickness
(in) Exterior Paint Exterior Gauge and Material Interior Gauge and
Material
Insulation Thickness and
Material
Mylar Lining
Thermal Break
Bulkhead Material
IP, HM, DP 2" None Standard Ga. G- 90 Galvanized
Standard Ga. G- 90 Galvanized 2" Foam - - None
RF-1, HC-1, HC-2, CC-1, CC-2, FS,
RF-2 2" None Standard Ga. G-
90 Galvanized Standard Ga. G- 90 Galvanized 2" Foam - - Galvanized
Steel Base Details
Segment(s) Material Paint
IP, RF-1, HC-1, HC-2, HM, CC-1,
CC-2, FS, RF-2, DP 6" Formed Steel None
Floor Details Segment(s) Gauge and Material Paint Insulation Thermal Break Attachment Sub-Floor Gauge and Material
IP, RF-1, HC-1, HC-2, HM, CC-1,
CC-2, FS, RF-2, DP
Standard Ga. G-90
Galvanized None 2" - Screw Down None
Unit Electrical Circuit Details
Circuit # Component(s) V/Ph/Hz Full Load Amps (FLA) Minimum Current Ampacity (MCA)
Maximum Overcurrent Protection (MOP)
1 VFD on FS 460/3/60 36 45 80 2 Light Switch on FS 120/1/60 - - 15
Electrical Details Minimum Unit SCCR 100 kA rms Symmetrical ETL Label (UL1995/NEC-2002) Yes
Unit Light Type Light Switch Enclosure LED Indoor
Air Handling Unit Performance Report
Project Name: VA Chicago JB SPS Remodel Last Saved: 03/26/2024-11:26:21 AM (UTC) Estimate Name: VA Chicago JB SPS Remodel Software Version: 2024.03.19.001-hotfix
Supply Fan(s) Performance Details
Fan Manufacturer Model # Blades Class Size % Wheel
Width % Wheel Diameter Quantity Airflow per Fan
(CFM) Altitude (ft) TSP (in w.g)
ESP (in w.g)
Fan Speed
(RPM)
Fan Power
(BHP)
Lau DDPG2 0 II 300 100 100 1 14,000 0 8.68 2.50 1,807 27.97
Max RPM Wheel Type
Blade Type
Wheel Material Base Material Fan Flow
Isolation AirFlow
Monitoring Inverter Drive
Balancing Isolation Type Thrust Restraints
1,851 SWSI Airfoil Aluminum Galvanized Steel None Yes (K=4810.00) - 2" Spring Yes
Drive Type FEI FEP (KW) Inlet Screen Fan Cage Fan Stand Motor Removal Rail Seismic Snubber
Direct Drive 1.23 22.88 - - - - - Motor Details
Type / MFG Motor Power (HP) V/Ph/Hz Quantity Insulation Class RPM Frame Size FLA (Amps) Efficiency Location SGR
ODP / Baldor 30.0 460/3/60 1 H 1,800 286T 36.00 Premium Left Yes At Motor Synchronous Details
TSP (in w.g.) Total Air Flow (CFM) Fan Speed (RPM) Fan Power (BHP)
8.38 13,752 1,775 26.51
Notes Certified by the AHRI Central Station Air-Handling Unit (AHU) Certification Program, based on AHRI Standard 430/431. AHRI certified units are subject to rigorous and continuous testing, have performance ratings independently measured and are third-party verified. Certified units may be found in the AHRI Directory at www.ahridirectory.org
Water Coil(s) Coil Information
Segment[Index] Coil Tag Coil Duty Fluid Type Airflow (cfm) Flow Direction Density Altitude (ft) HC-2[1] - Heating Water 14000 Horizontal Standard 0 CC-1[1] - Heating Water 14000 Horizontal Standard 0 CC-1[2] - Cooling Water 14000 Horizontal Standard 0 CC-2[3] - Heating Water 14000 Horizontal Standard 0
Coil Bank Configuration
Segment[Index] Tube Diameter
(in) Fin Type
Total Fin Height (in)
Fin Length per Coil (in)
Face Velocity (fpm)
Stacking Rack Material Coils High Coils
Wide Coil
Configuration
Coil Stagger
(in)
Coil Pull Panel
HC-2[1] 0.500
Corrugated 65.00 69.00 449 - 2 1 Standard 0 Left Side
CC-1[1] 0.500
Corrugated 65.00 65.00 477 - 2 1 Standard 0 Left Side
CC-1[2] 0.500
Corrugated 65.00 65.00 477 - 2 1 Standard 0 Left Side
CC-2[3] 0.500
Corrugated 65.00 65.00 477 - 2 1 Standard 0 Left Side
Airside Performance Segment[Index] EAT-DB (°F) EAT-WB (°F) LAT-DB (°F) LAT-WB (°F) TMBH SMBH Air Pressure Drop (in w.g.)
HC-2[1] 17.0 - 58.3 - 624 624 0.03
CC-1[1] 20.0 - 90.1 - 1061 1061 0.11
CC-1[2] 82.7 71.9 46.5 46.5 1085 568 1.98
CC-2[3] 20.0 - 90.1 - 1061 1061 0.11
Air Handling Unit Performance Report
Project Name: VA Chicago JB SPS Remodel Last Saved: 03/26/2024-11:26:21 AM (UTC) Estimate Name: VA Chicago JB SPS Remodel Software Version: 2024.03.19.001-hotfix
Fluidside Performance Segment[Index] EFT (°F) LFT (°F) Fluid Velocity
(fps) Fluid Flow (gpm) Fluid Pressure Drop (ft) Rows Tubes Per
Circuit Reynolds Number
HC-2[1] 200.0 179.9 4.2 64.2 3.6 1 2 48964
CC-1[1] 180.0 160.1 3.6 109.4 3.0 2 2 36829
CC-1[2] 44.0 55.9 4.0 181.1 11.7 12 8 11685
CC-2[3] 180.0 160.1 3.6 109.4 3.0 2 2 36829
Fin and Tube Configuration Segment[Index] Fin Thickness (in) / Material Fin Spacing
(fpi) Tube Thickness (in) Return Bend Thickness Casing Material Coil Coating Fouling Factor
(hr.ft².°F/BTU) HC-2[1] 0.006 Aluminum 8 0.016 0.016 Galvanized None - CC-1[1] 0.008 Aluminum 8 0.016 0.016 Galvanized None - CC-1[2] 0.010 Aluminum 12 0.016 0.016 Galvanized None - CC-2[3] 0.008 Aluminum 8 0.016 0.016 Galvanized None -
Header and Connection Configuration Segment[Index] Header
Material Connection
Material Connection Diameter
(in) Connection Offset
(in) Connection
Type Connection Location/Rotation
HC-2[1] Copper Steel 2 0 MPT Left CC-1[1] Copper Steel 2.5 0 MPT Left CC-1[2] Copper Steel 3 0 MPT Left CC-2[3] Copper Steel 2.5 0 MPT Left
Other Performance Segment[Index] Dry Weight (lbs) Fluid Weight (lbs) Internal Volume (ft³)
HC-2[1] 158 42 0.7
CC-1[1] 228 72 1.2
CC-1[2] 1214 300 5.2
CC-2[3] 228 72 1.2
Notes
● Performance is shown for the entire coil bank. Performance is not per coil.
● Coil index indicates position in segment. Example: CC-1, index 1; Spacer, index 2; CC-1, index 3
● Ratings are for coils manufactured by Johnson Controls, Inc., 507 E. Michigan St., Milwaukee WI 53202.
● All Coils: Johnson Controls suggests using red brass or copper connectors when the coil is to be attached to a copper or brass piping system.
● All Coils: AHRI Certified: Yes. Certified in accordance with the AHRI Forced-Circulation Air-Cooling and Air-Heating Coils Certification Program which is based on AHRI Standard 410 within the range of Standard rating conditions listed in Table 1 of the Standard. Certified units may be found in the AHRI Directory at www.ahridirectory.org.
● All Coils: BDW Tube Spacing: 1.25 x 1.08
● All Coils: Coil Dll Version: 8.6
Glycol Coil(s)
Segment[Index] Coil Tag Coil Duty Fluid Type Glycol Percentage Airflow (cfm) Flow Direction Density Altitude (ft)
HC-1[1] - Heating Propylene Glycol 30 14000 Horizontal Standard 0 Coil Bank Configuration
Segment[Index] Tube Diameter
(in) Fin Type
Total Fin Height (in)
Fin Length per Coil (in)
Face Velocity (fpm)
Stacking Rack Material Coils High Coils
Wide Coil
Configuration
Coil Stagger
(in)
Coil Pull Panel
HC-1[1] 0.500
Corrugated 65.00 69.00 449 - 2 1 Standard 0 Left Side
Air Handling Unit Performance Report
Project Name: VA Chicago JB SPS Remodel Last Saved: 03/26/2024-11:26:21 AM (UTC) Estimate Name: VA Chicago JB SPS Remodel Software Version: 2024.03.19.001-hotfix
Airside Performance Segment[Index] EAT-DB (°F) EAT-WB (°F) LAT-DB (°F) LAT-WB (°F) TMBH SMBH Air Pressure Drop (in w.g.)
HC-1[1] -1.5 - 21.8 - 345 345 0.39
Fluidside Performance
Segment[Index] EFT (°F) LFT (°F) Fluid Velocity (fps) Fluid Flow (gpm) Fluid Pressure
Drop (ft) Rows Tubes Per Circuit Reynolds Number
HC-1[1] 44.3 26.4 2.1 40.7 9.3 8 12 1403
Fin and Tube Configuration
Segment[Index] Fin Thickness (in) / Material Fin Spacing (fpi) Tube Thickness (in) Return Bend
Thickness Casing Material Coil Coating Fouling Factor (hr.ft².°F/BTU)
HC-1[1] 0.008 Aluminum 8 0.016 0.016 Galvanized None - Header and Connection Configuration
Segment[Index] Header Material
Connection Material
Connection Diameter (in)
Connection Offset (in)
Connection Type Connection Location/Rotation
HC-1[1] Copper Steel 1.5 0 MPT Left Other Performance
Segment[Index] Dry Weight (lbs) Fluid Weight (lbs) Internal Volume (ft³)
HC-1[1] 656 194 3.3
Notes
● Performance is shown for the entire coil bank. Performance is not per coil.
● Coil index indicates position in segment. Example: CC-1, index 1; Spacer, index 2; CC-1, index 3
● Ratings are for coils manufactured by Johnson Controls, Inc., 507 E. Michigan St., Milwaukee WI 53202.
● All Coils: AHRI Certified: Yes. Certified in accordance with the AHRI Forced-Circulation Air-Cooling and Air-Heating Coils Certification Program which is based on AHRI Standard 410 within the range of Standard rating conditions listed in Table 1 of the Standard. Certified units may be found in the AHRI Directory at www.ahridirectory.org.
● All Coils: BDW Tube Spacing: 1.25 x 1.08
DX Coil(s)
Segment[Index] Coil Tag Coil Duty Fluid Type Airflow (cfm) Flow Direction Density Altitude (ft) CC-2[1] - Cooling Direct Expansion 14000 Horizontal Standard 0
Coil Bank Configuration
Segment[Index] Tube Diameter
(in) Fin Type
Total Fin Height (in)
Fin Length per Coil (in)
Face Velocity (fpm)
Stacking Rack Material Coils High Coils
Wide Coil
Configuration
Coil Stagger
(in)
Coil Pull Panel
CC-2[1] 0.500
Corrugated 65.00 65.00 477 - 2 1 Standard 0 Left Side
Airside Performance Segment[Index] EAT-DB (°F) EAT-WB (°F) LAT-DB (°F) LAT-WB (°F) TMBH SMBH Air Pressure Drop (in w.g.)
CC-2[1] 82.5 71.8 45.5 45.4 1115 580 1.33
Fluidside Performance
Segment[Index] EFT (°F) LFT (°F) Fluid Velocity (fps)
Fluid Flow (gpm)
Suction Saturation
Temperature (°F)
Refrigerant Type
Refrigerant Pressure Drop (ft)
Rows Tubes Per Circuit Reynolds Number
CC-2[1] 0.0 0.0 0.0 0.0 40.0 R-410a 8.8 10 10 0
Air Handling Unit Performance Report
Project Name: VA Chicago JB SPS Remodel Last Saved: 03/26/2024-11:26:21 AM (UTC) Estimate Name: VA Chicago JB SPS Remodel Software Version: 2024.03.19.001-hotfix
Fin and Tube Configuration Segment[Index] Fin Thickness (in) / Material Fin Spacing
(fpi) Tube Thickness (in) Return Bend Thickness Casing Material Coil Coating Fouling Factor
(hr.ft².°F/BTU) CC-2[1] 0.008 Aluminum 11 0.016 0.016 Galvanized None -
Header and Connection Configuration
Segment[Index] Header Material
Connection Material Circuits Distributor
Count
Connection Diameter
(in)
Connection Offset (in)
Connection Type Connection Location/Rotation
CC-2[1] Copper Copper 52 4 2.13 0 Sweat Left Other Performance
Segment[Index] Dry Weight (lbs) Fluid Weight (lbs) Internal Volume (ft³)
CC-2[1] 870 66 4.0
Notes
● Performance is shown for the entire coil bank. Performance is not per coil.
● Coil index indicates position in segment. Example: CC-1, index 1; Spacer, index 2; CC-1, index 3
● Ratings are for coils manufactured by Johnson Controls, Inc., 507 E.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .