S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part3.pdf
PDF 10 MB Posted
- Attached to
- Z1DA--Upgrade 1W Building 506-20-201
- Solicitation number
- 36C25020B0046
About this file
This document package includes plans and specifications for a construction project to upgrade space in Building 1W at the Ann Arbor VA Medical Center. The project scope includes a complete renovation of approximately 4,200 square feet of vacated Audiology space, including structural, architectural, electrical, mechanical, fire protection and interior design work. Construction will adhere to building codes, VA standards, and sustainable design principles. The work site is the first floor of Building 1W and the period of performance is 180 calendar days after receipt of the notice to proceed, with work likely commencing in fall 2020.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PLUMBING GENERAL NOTES
1. COORDINATE ROUTING OF PIPING WITH ALL OTHER TRADES PRIOR TO
INSTALLATION TO AVOID CONFLICTS.
2. COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES.
3. PROVIDE ROUGH-INS AND FINAL CONNECTIONS TO FIXTURES AND EQUIPMENT
4. PROVIDE TRAP SEAL PROTECTION ON ALL FLOOR DRAINS, FLOOR SINKS AND
HUB DRAINS SUBJECT TO EVAPORATION. INSTALL PER MANUFACTURERS
RECOMMENDATIONS.
5. PROVIDE ASSE 1070 MIXING VALVE AT ALL BARRIER FREE SINKS AND ALL HAND
WASHING SINKS TO PROVIDE TEMPERED WATER TO HOT WATER SIDE OF
FAUCET.
6. PIPING INSTALLED IN THE WAY OF ACCESS OR MAINTENANCE TO EQUIPMENT
SHALL BE RELOCATED AT THE EXPENSE OF THE INSTALLING CONTRACTOR.
7. ALL PLUMBING WORK SHALL MEET MICHIGAN PLUMBING CODE 2015
REQUIREMENTS AS A MINIMUM UNLESS EXCEEDED BY PROJECT CONSTRUCTION
DOCUMENTS.
8. PROVIDE SHUTOFF VALVES AT ALL FIXTURES AND EQUIPMENT.
9. COORDINATE LOCATIONS OF FLOOR DRAINS AND FLOOR SINKS WITH LOCATIONS
OF EQUIPMENT AND EQUIPMENT HOUSEKEEPING PADS. COORDINATE WITH
SLOPING OF FLOOR SO THAT RIM OF DRAIN IS FLUSH WITH FINISH FLOOR.
10. COORDINATE HANGING AND SUPPORT OF PIPING WITH STRUCTURAL.
11. PROVIDE PIPE SLEEVES WHERE PIPES PENETRATE WALLS.
12. BALL VALVES SHALL BE 316 STAINLESS STEEL FOR DOMESTIC HOT WATER
SYSTEM AND BRASS FOR DOMESTIC COLD WATER SYSTEM.
13. INSTALL PIPING IN AN ORGANIZED MANNER. DO NOT ROUTE IN FRONT OF
WINDOWS.
14. THE INSTALLATION OF ALL PIPING SHALL BE CLOSELY COORDINATED WITH NEW
SHEET METAL. HVAC PIPING, ELECTRICAL, AND STRUCTURAL CONDITIONS. NOT
ALL REQUIRED OFFSETS AND FITTINGS ARE INDICATED, BUT SHALL BE
PROVIDED. REFER TO ARCHITECTURAL AND STRUCTURAL PLANS FOR
CLEARANCES.
15. PROVIDE WATER HAMMER ARRESTORS PER PDI WH-201 AND UP STREAM OF ALL
AUTOMATIC AND FAST CLOSING VALVES INCLUDING BUT NOT LIMITED TO
SOLENOID VALVES.
16. COORDINATION AND LAYOUT DRAWINGS SHALL BE SUBMITTED TO THE AE FOR
APPROVAL PRIOR TO INSTALL.
PLUMBING DEMOLITION NOTES
1. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE LOCAL, STATE AND/OR
REGULATORY AGENCIES, CODES AND REGULATIONS FOR NEW WORK.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR THE COORDINATION OF THEIR WORK
WITH OTHER TRADES AND WITH THE CONSTRUCTION MANAGER.
3. VERIFY ALL CONDITIONS IN FIELD BEFORE START OF CONSTRUCTION. NOTIFY
ARCHITECT/ENGINEER OF DISCREPANCIES BETWEEN DRAWINGS AND ACTUAL
FIELD CONDITIONS.
4. COORDINATE ALL WORK WITH APPROPRIATE TRADES.
5. COORDINATE ANY REQUIRED SHUTDOWN OF SERVICES OR EQUIPMENT WITH
OWNER'S REPRESENTATIVE, MINIMIZE INTERRUPTION OF EXISTING SERVICES.
VERIFY ALL SYSTEMS BEFORE STARTING DEMOLITION TO ASSURE OTHER AREAS
WILL NOT LOOSE SERVICE. AREAS SUCH AS THE SECOND FLOOR KITCHEN ARE
CRITICAL TO THE FACILITIES OPERATION.
6. COORDINATE FLOOR, WALL, AND ROOF PENETRATIONS ETC. WITH
ARCHITECTURAL TRADES. PROVIDE TEMPORARY WATER TIGHT SEAL FOR ALL
EXTERIOR WALL AND ROOF PENETRATION AS NECESSARY.
7. COORDINATE ALL FLOOR CUTTING WITH STRUCTURAL TRADES BEFORE
CUTTING.
8. HOLES AND PENETRATIONS IN RATED WALLS SHALL BE PATCHED WITH
APPROPRIATE FIRESTOP MATERIALS FOR RATING REQUIRED.
9. NO ITEMS TO BE ABANDONED IN PLACE.
10. ALL ITEMS TO BE DEMOLISHED TO BE REMOVED AND REMAINING OPEN SYSTEMS
TO BE PATCHED, CAPPED AND SEALED TO PROVIDE A FINISHED SYSTEM.
11. DEMOLISHED PLUMBING LINE SHALL NOT BE ALLOWED TO REMAIN OPEN, CAP
AND PROTECT TO AVOID CONTAMINATION TO AND FROM THE SURROUNDING
AREAS.
12. ALL SYSTEMS OPENED DURING DEMOLITION SHALL BE CLOSED AND RETURNED
TO OPERATION BY END OF SHIFT, NO SYSTEMS ALLOWED TO BE LEFT OPEN
WHEN NOT BEING SUPERVISED BY CONTRACTOR RESPONSIBLE FOR THAT WORK
TRADE.
PLUMBING ABBREVIATIONS
A/E ARCHITECT / ENGINEER
AD AREA DRAIN/ACCESS DOOR
AFF ABOVE FINISH FLOOR
AFG ABOVE FINISH GRADE
AG AIR GAP
AP ACCESS PANEL
AS AUTOMATIC SPRINKLER
ASD ADJUSTABLE SPEED DRIVES
ASD AUTOMATIC SPRINKLER DRAIN
ASHRAE AMERICAN SOCIETY OF HEATING,
REFRIGERATION, AIR CONDITIONING
ENGINEERS
ASME AMERICAN SOCIETY OF MECHANICAL
ENGINEERS
ASPE AMERICAN SOCIETY OF PLUMBING ENGINEERS
ASR AUTOMATIC SPRINKLER RISER
AV ACID VENT
AW ACID WASTE
BFP REDUCED PRESSURE BACKFLOW PREVENTER
BHP BREAK HORSEPOWER
BSP BLACK STEEL PIPE
BT BATHTUB
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNIT PER HOUR
C CELSIUS
CA COMPRESSED AIR
CGA COMPRESSED GAS ASSOCIATION
CFM CUBIC FEET PER MINUTE
CI CAST IRON
CO CLEANOUT
CS CLINICAL SINK
CV CONTROL VALVE
DCW DOMESTIC COLD WATER
DFU DRAINAGE FIXTURE UNITS
DHW DOMESTIC HOT WATER
DHWR DOMESTIC HOT WATER RETURN
DHWS DOMESTIC HOT WATER SUPPLY
DI DEIONIZED WATER
DN DOWN
DOE DEPARTMENT OF ENERGY
DS DOWNSPOUT
DW DISHWASHER
DWG DRAWING
DWH DOMESTIC WATER HEATER
DWR DRINKING WATER RETURN
DWS DRINKING WATER SUPPLY
DWV DRAIN WASTE VENT
EL ELEVATION
EMCS ENERGY MONOSERRAT AND CENTRAL SYSTEM
EPA ENVIROMENTAL PROTECTION AGENCY
EPACT ENERGY POLICY ACT
ESC ESCUTCHEON
ESH EMERGENCY SHOWER
ET EXPANSION TANK
EWH ELECTRIC WATER HEATER
EWS EYE WASH STATION
EWS/SH EYE WASH/DRENCH SHOWER
EX EXISTING
F FAHRENHEIT
FCO FLOOR CLEANOUT
FCW FILTERED COLD WATER
FD FLOOR DRAIN
FDC FIRE DEPARTMENT (HOSE) CONNECTION
FM FLOW METER
FOP FUEL OIL PUMP
FOR FUEL OIL RETURN
FOS FUEL OIL SUPPLY
FOV FUEL OIL VENT
FS FLOOR SINK
FS FLOW SWITCH
FU FIXTURE UNITS
GAL GALLON
GCO GRADE CLEANOUTS
GPD GALLONS PER DAY
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GPR GAS PRESSURE REGULATOR
GRS GAS REGULATOR STATION
GT GREASE TRAP
GVTR GAS VENT THROUGH ROOF
GWH GAS FIRED WATER HEATER
H&CW HOT AND COLD WATER
HB HOSE BIBB
HD HUB DRAIN
HEX HEAT EXCHANGER
HP HORSEPOWER
HS HAND SINK
HST HOT WATER STORAGE TANK (DOMESTIC)
HWB HOT WATER BOILER
HWCP HOT WATER CIRCULATING PUMP
HWP HOT WATER PUMP
HYD HYDRANT
ID INSIDE DIAMETER
IE INVERT ELEVATION
ICW INDUSTRIAL COLD WATER
IHW INDUSTRIAL HOT WATER
INV INVERT
IPC INTERNATIONAL PLUMBING CODE
IRW IRRIGATION WATER
IW INDIRECT WASTE
IWH INSTANTANEOUS WATER HEATER
IWR INDUSTRIAL WATER RETURN
IWS INDUSTRIAL WATER SUPPLY
KW KILOWATT
KWH KILOWATT-HOUR
L/S LITER PER SECOND
LA LABORATORY AIR
LAV LAVATORY
LBS/HR POUNDS PER HOUR
LCW LABORATORY COLD WATER
LHW LABORATORY HOT WATER
LNG LIQUID NATURAL GAS
LOX LIQUID OXYGEN
LV LABORATORY VACUUM
LW LOW WATER
M METER
MA MEDICAL AIR
MAV MANUAL AIR VENT
MBH 1000 BTUH
MED MEDICAL
MER MECHANICAL EQUIPMENT ROOM
MH MANHOLE
MOU MEMORANDUM OF UNDERSTADING
MSB MOP SERVICE BASIN
MV MEDICAL VACUUM
N2 NITROGEN
N20 NITROUS OXIDE
NC NORMALLY CLOSED
NG NATURAL GAS
NIC NOT IN CONTRACT
NO NORMALLY OPEN
NOM. NOMINAL
NPW NON POTABLE WATER
NTS NOT TO SCALE
O2 OXYGEN
OC ON CENTER
OD OUTSIDE DIAMETER
OFD OVERFLOW DRAIN
OR OPERATING ROOM
OVFL OVERFLOW
IPC INTERNATIONAL PLUMBING CODE
PA PASCAL
PD PRESSURE DROP OR DIFFERENCE
PDI PLUMBING AND DRAINAGE INSTITUTE
PG PRESSURE GAGE
PP PLUMBING PUMP
PPM PARTS PER MILLION
PRS PRESSURE REDUCING STATION
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIA POUNDS PER SQUARE INCH ATMOSPHERE
PSIG POUNDS PER SQUARE INCH GAGE
PTRV PRESSURE TEMPERATURE RELIEF VALVE
PW POTABLE WATER
RD ROOF DRAIN
RDL ROOF DRAIN LEADER
RL ROOF LEADER
RP RECIRCULATION PUMP
RO REVERSE OSMOSIS WATER
RWL RAIN WATER LEADER
SAN SANITARY SEWER
SMACNA SHEET METAL AND AIR CONDITIONING
CONTRACTORS NATIONAL ASSOCIATION
SCFM STANDARD CUBIC FOOT/MINUTE
SCW SOFTENED COLD WATER
SDMH STORM DRAIN MANHOLE
SMH SANITARY MANHOLE
SP SUMP PUMP
SPR SPRINKLER LINE
SQFT/SF SQUARE FEET
SS STAINLESS STEEL
ST STORAGE TANK
SW STORM WATER
TCV TEMPERATURE CONTROL VALVE
TD TEMPERATURE DIFFERENCE
TD TRENCH DRAIN
TDH TOTAL DYNAMIC HEAD
TEMP TEMPERATURE
TMV THERMOSTATIC MIXING VALVE
TP TRAP PRIMER
TSTAT THERMOSTAT
TWR TEMPERED WATER RETURN
TWS TEMPERED WATER SUPPLY
TYP TYPICAL
W WASTE PIPING
W&V WASTE AND VENT
PLUMBING TAGS SYMBOLS
1W-EX.P 3
BUILDING NUMBER WHERE EQUIPMENT IS LOCATED.
INDICATOR THAT COMPONENT IS EXISTING.
EQUIPMENT ABBREVIATION (PUMP)
PUMP NUMBER
(EXAMPLE: EXISTING PUMP NO.3 IN BUILDING 1 WEST.)
PLUMBING EQUIPMENT/FIXTURE TAG (EXISTING)
1W-P 4
BUILDING NUMBER WHERE EQUIPMENT IS LOCATED.
EQUIPMENT ABBREVIATION (PUMP)
PUMP NUMBER
(EXAMPLE: NEW PUMP NO.4 IN BUILDING 1 WEST.)
PLUMBING EQUIPMENT/FIXTURE TAG (NEW)
DEMOLITION NOTE TAG
PLAN NOTE TAG
A
PL105
SECTION LETTER
DRAWING NUMBER WHERE SHOWN
PL105
DETAIL NUMBER
DRAWING NUMBER WHERE SHOWN
GLOBE VALVE
PLUG VALVE
LINEAR STOP CHECK VALVE
PRESSURE RELIEF VALVE
CHECK VALVE W/ARROW INDICATING FLOW
GATE VALVE
PRESSURE REDUCING VALVE
GAS VALVE
PLUMBING SYMBOLS
SOLENOID VALVE
MOTORIZED CONTROL VALVE - 2-WAY
PRESSURE REGULATING VALVE - TWO
WAY
PRESSURE REGULATING VALVE - THREE WAY
ANGLE RELIEF VALVE
ANGLED STOP CHECK VALVE
BALANCING VALVE
BUTTERFLY VALVE
BALL VALVE
MOTORIZED CONTROL VALVE - 3-WAY
P
T
F
CB
PRESSURE INDICATOR
FLOW MEASURING DEVICE
MANUAL AIR VENT
TEMPERATURE INDICATOR
THERMOMETER
ANCHOR
CAP
CATCH BASIN
CO
END OF LINE, CLEANOUT
CO
FLOOR, CLEANOUT
WALL, CLEANOUT
WCO
EXPANSION COMPENSATOR OR EXPANSION JOINT
FLEXIBLE PIPE CONNECTOR
FD
FLOOR DRAINS
PIPE GUIDE
STRAINER
UNION
FD
HOSE BIBB
S
M
M
CW WASTEHW VENTDESCRIPTIONFIXTURE/TAG MAKE/MODEL
PLUMBING FIXTURE SCHEDULE
1/2" 2"1/2" 1-1/2"
1/2" 2"1/2" 1-1/2"
SINK (P-501)
MID MARK CASEWORK WITH
INTEGRAL SINK BY OTHERS
MANUAL GOOSENECK FAUCET
SINK (P-502)
BARRIER FREE
UNDERMOUNT
SINK: INTEGRAL TO CASEWORK. REFER TO ARCH PLANS.
TRIM: ANSI A112.18.1 CHROME PLATED, DECK MOUNTED WIDE SPREAD FAUCET WITH 5-1/4 INCH REACH RIGID GOOSENECK, 1.5 GPM LAMINAR FLOW OUTLET, 1/4 TURN CERAMIC DISC CARTRIDGES, 4 INCH WRIST BLADES, 4-INCH CENTERS.
ACCESSORIES: POLISHED CHROME PLATED, 17 GAUGE, BRASS P-TRAP WITH CLEANOUT PLUG, TAILPIECE AND ARM WITH ESCUTCHEON. OFFSET WASTE WITH PERFORATED OPEN STRAINER, UNDERSINK PROTECTIVE PIPE COVERS WITH ANTI-MICROBIAL, LAV GUARD BY TRUBRO.
SUPPLIES: LOOSE KEY STOP AND FLEXIBLE SUPPLY; ASSE 1070 MIXING VALVE.
BASIN: ANSI A112.19.3; SINGLE COMPARTMENT, 20 x 17 INCH OUTSIDE DIMENSIONS, 17 X 11 1/2 X 10 INCH DEEP INSIDE DIMENSIONS, 18 GAUGE, TYPE 304 STAINLESS STEEL, UNDER MOUNT WITH SOUND DEADENING UNDERCOATING, STAINLESS STEEL DRAINS WITH STAINLESS STEEL OPEN GRID STRAINER.
TRIM: ANSI A112.18.1 CHROME PLATED, DECK MOUNTED WIDE SPREAD FAUCET WITH 5-1/4 INCH REACH RIGID GOOSENECK, 1.5 GPM LAMINAR FLOW OUTLET, 1/4 TURN CERAMIC DISC CARTRIDGES, 4 INCH WRIST BLADES, 4-INCH CENTERS.
ACCESSORIES: POLISHED CHROME PLATED, 17 GAUGE, BRASS P-TRAP WITH CLEANOUT PLUG, TAILPIECE AND ARM WITH ESCUTCHEON. OFFSET WASTE WITH PERFORATED OPEN STRAINER, UNDERSINK PROTECTIVE PIPE COVERS WITH ANTI-MICROBIAL, LAV GUARD BY TRUBRO.
SUPPLIES: LOOSE KEY STOP AND FLEXIBLE SUPPLY; ASSE 1070 MIXING VALVE.
1/2" 2"-- 1-1/2"BOTTLE FILLER (P-601)
BARRIER FREE
WALL HUNG
FIXTURE: BOTTLE FILLING UNIT SHALL INCLUDE AN ELECTRONIC SENSOR FOR TOUCHLESS ACTIVATION WITH AUTO 20-SECOND SHUT-OFF TIMER. SHALL INCLUDE GREEN TICKER DISPLAYING COUNT OF PLASTIC BOTTLES SAVED FROM WASTE. BOTTLE FILLER SHALL PROVIDE 1.1 GPM FLOW RATE WITH LAMINAR FLOW TO MINIMIZE SPLASHING. SHALL INCLUDE THE 3000-GALLON CAPACITY FILTER, CERTIFIED TO NSF 42 AND 53, WITH VISUAL MONITOR TO INDICATE WHEN REPLACEMENT IS NECESSARY. SHALL INCLUDE ANTI-MICROBIAL PROTECTION IN KEY AREAS. UNIT SHALL MEET ADA GUIDELINES. UNIT SHALL BE LEAD-FREE DESIGN WHICH IS CERTIFIED TO NSF/ANSI 61 AND 372 AND MEETS FEDERAL AND STATE LOW-LEAD REQUIREMENTS. UNIT SHALL BE CERTIFIED TO UL399.
VERIFY COMPATIBILITY OF BOTTLE FILLING STATION WITH EXISTING ELECTRIC WATER COOLER BASE.
3/ 4"
D H
W
3/ 4"
D H
W
3/ 4"
D H
W
3/ 4"
D H
W R
1/
4" V
3/ 4"
D C
W
1/
4" V
3/ 4"
D C
W
ROUTE DHW DN TO
SINK AND BACK UP
WALL, CONTINUE
TO DOWN STREAM
FIXTURE(S) AS
SHOWN ON PLANS
SINK SINK
MINIMIZE PIPE DISTANCE
TO FAUCET HANDLE
CEILING
2" SAN 2" SAN
MINIMIZE PIPE DISTANCE
TO FAUCET HANDLE
3/4" DHW
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o n e o e q u a rt e r in c h o th re e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PL000
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
GENERAL PLUMBING
INFORMATION
UPGRADE 1 WEST -
BLDG 1W
PLUMBING SHEET INDEX
NUMBER DESCRIPTION
PL000 GENERAL PLUMBING INFORMATION
PD001 BASEMENT PLUMBING DEMOLITION PLAN
PD101A FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA A
PD101B FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA B
PD101C FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA C
PL001 BASEMENT PLUMBING PLAN
PL101A FIRST FLOOR PLUMBING PLAN - AREA A
PL101B FIRST FLOOR PLUMBING PLAN - AREA B
PL101C FIRST FLOOR PLUMBING PLAN - AREA C
PL111A FIRST FLOOR MEDICAL GAS PLAN - AREA A
PL111B FIRST FLOOR MEDICAL GAS PLAN - AREA B
PL111C FIRST FLOOR MEDICAL GAS PLAN - AREA C
Grand total: 12
COMPLETE LAYOUT DRAWINGS SHALL BE REQUIRED BY SPECIFICATION SECTION 220511, PARAGRAPH 1.4 - SUBMITTALS. CONSTRUCTION WORK SHALL NOT START ON ANY SYSTEM UNTIL THE LAYOUT DRAWINGS HAVE BEEN APPROVED BY VA.
NOT TO SCALE
CONTINUOUS DOMESTIC HOT WATER ROUTING DETAIL
73REVISIONS DATE
EX.2"
SAN
UP
EX.5"SAN
EX.2"V
RISER
EX.2"
SAN
UP
EX.4"SAN
RISER
EX.2"SAN
E X
.3 "S
A N
EX.3"SAN
RISER
EX.CO
EX.4"SAN
RISER
EX.CO
EX.4"SAN
EX.4"SAN
DN
E X
.2 "S
A N
E X
.2 "S
A N
E X
.2 "S
A N
EX.2"SAN
EX.2"
SAN
EX.4"SAN
EX.2"V
RISER
EX.2"V
EX.4"SAN
RISER
EX.3"SAN
RISER
RISER
EX.4"SAN
RISER
EX.4"SAN
RISEREX.2"
EX.2"SANEX.2"SAN
UP TO EX. SK
TO REMAIN
EX.2"SAN
UP TO EX. SK
TO REMAIN
4'
7'
3.9
1'
2'
3'
EX. 4" SAN EX.4"SAN
RISER
DN
EX.4"SAN
C1
CORRIDOR
AB01
EVS STORAGE
AB08
CLEAN UTILITY
AB09A
TREATMENT 5
AB09D
TREATMENT 2
AB09E
TREATMENT 1
AB10
DECON/PROCESSING
AB10A
DECON
CB29
CORRIDOR
CB28
CORRIDOR
AB09N
NOUR
AB09K
MEDS
CB36
PASSAGE
AB09L
MENTOR
AB09I
CHARTING
AB09H
MD WORK
AB09F
WORK
AB09
NURSE
AB09M
NURSE
TRAUMA 1
TRAUMA 2
AB09Z
OBSERVATION 1
AB09Y
OBSERVATION 2
AB09X
OBSERVATION 3
AB09W
OBSERVATION 4
AB15
ANTE RM
AB15A
ISO. RM
AB15A
TOILET RM
AB18
ER NURSE
EDUCATIONAB09V
EXAM 4
AB09U
EXAM 3
AB09T
EXAM 2
AB09S
EXAM 1
AB09R
TRIAGE
AB20
CHIEF
AB22
DIRECTOR
AB24
MENTAL HEALTH
AB30
WOMENS TOILET
CB30
CORRIDOR
CB33
CORRIDOR
C1
CORRIDOR
AB03
WOMEN'S
LOCKER RM
A8B
ELEC A8
ELECTRICAL
AB02
VOLUNTARY
SERVICE
STORAGE
STAIR #2
STAIR #1
AB91
COMM CLOSET
AB90
TEL CLOSET
PATIENT TOILET
AB09B
TREATMENT 4
AB09C
TREATMENT 3
PLUMBING DEMOLITION KEYNOTES??
1. REMOVE EXISTING SANITARY PIPING AND ACCESSORIES AS INDICATED.
PREPARE FOR NEW CONNECTIONS. CONTRACTOR SHALL NOT CREATE DEAD
LEGS AND SHALL REMOVE EXISTING DEAD LEGS.
PLUMBING DEMOLITION NOTES
1. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE LOCAL, STATE AND/OR
REGULATORY AGENCIES, CODES AND REGULATIONS FOR NEW WORK.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR THE COORDINATION OF THEIR WORK
WITH OTHER TRADES AND WITH THE CONSTRUCTION MANAGER.
3. VERIFY ALL CONDITIONS IN FIELD BEFORE START OF CONSTRUCTION. NOTIFY
ARCHITECT/ENGINEER OF DISCREPANCIES BETWEEN DRAWINGS AND ACTUAL
FIELD CONDITIONS.
4. COORDINATE ALL WORK WITH APPROPRIATE TRADES.
5. COORDINATE ANY REQUIRED SHUTDOWN OF SERVICES OR EQUIPMENT WITH
OWNER'S REPRESENTATIVE, MINIMIZE INTERRUPTION OF EXISTING SERVICES.
VERIFY ALL SYSTEMS BEFORE STARTING DEMOLITION TO ASSURE OTHER AREAS
WILL NOT LOOSE SERVICE. AREAS SUCH AS THE SECOND FLOOR KITCHEN ARE
CRITICAL TO THE FACILITIES OPERATION.
6. COORDINATE FLOOR, WALL, AND ROOF PENETRATIONS ETC. WITH
ARCHITECTURAL TRADES. PROVIDE TEMPORARY WATER TIGHT SEAL FOR ALL
EXTERIOR WALL AND ROOF PENETRATION AS NECESSARY.
7. COORDINATE ALL FLOOR CUTTING WITH STRUCTURAL TRADES BEFORE
CUTTING.
8. HOLES AND PENETRATIONS IN RATED WALLS SHALL BE PATCHED WITH
APPROPRIATE FIRESTOP MATERIALS FOR RATING REQUIRED.
9. NO ITEMS TO BE ABANDONED IN PLACE.
10. ALL ITEMS TO BE DEMOLISHED TO BE REMOVED AND REMAINING OPEN SYSTEMS
TO BE PATCHED, CAPPED AND SEALED TO PROVIDE A FINISHED SYSTEM.
11. DEMOLISHED PLUMBING LINE SHALL NOT BE ALLOWED TO REMAIN OPEN, CAP
AND PROTECT TO AVOID CONTAMINATION TO AND FROM THE SURROUNDING
AREAS.
12. ALL SYSTEMS OPENED DURING DEMOLITION SHALL BE CLOSED AND RETURNED
TO OPERATION BY END OF SHIFT, NO SYSTEMS ALLOWED TO BE LEFT OPEN
WHEN NOT BEING SUPERVISED BY CONTRACTOR RESPONSIBLE FOR THAT WORK
TRADE.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PD001
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
BASEMENT PLUMBING
DEMOLITION PLAN
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/8" = 1'-0"
BASEMENT PLUMBING DEMOLITION PLAN
EX.1 1/4"DHWR
EX.1 1/4"DHW
EX.2"DCW
UP/DN
UP
EX.1 1/2"DCW DN
EX.O2
EX.VAC
EX.MA
EX.3/4"O2
EX.3/4"VAC
EX.3/4"MA
EX.MED GAS
ZONE VALVE BOX
TO REMAIN
EX.1"DHWR
EX.1"DHW
EX.2"DCW
UP/DN
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
UPEX.3"SAN
EX.2"V
RISER
EX.3/4"
EX.3/4"
EX.3/4"
MA
VAC
O2
EX.2"V
EX.4"SAN
RISER
E X
.1
/4 "V
EX.4"SAN
EX.2"V
RISER
EX.SS TO
REMAIN
E X
.V
E X
.3 /4
"V A
C
E X
.3 /4
EX.2"V
EX.4"SAN
RISER
E X
.1
/2 "V
EX.3/4"
VAC
4'
7'
3.9
E X
.3 /4
"D H
W R
E X
.1 "D
H W
E X
.1 "D
C W
EX.3/4"DHWR
EX.3/4"DHW
EX.3/4"DCW
/4
"D C
W
/4
"D H
W
EX.3/4"DCW
EX.3/4"DHW
EX.3/4"DHWR
RISER
EX.4"SAN
EX.1 1/2"V
UP
RISER
UP
EX.1 1/2"V
EX.4"SAN
E X
.3 /4
"D C
W
E X
.1
/4 "V
EX.5"SAN
EX.2"V
RISER
RISER
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
A130
NURSE
A129
COPY RM
A127
EXAM
A128
VOICE EXAM
A124
ENT/AUDIO
PREP
A146E
EXAM
A112
GROUP
THERAPY A114
EAR MOLD
FAB/HEARING
AID REPAIR
A110
HEARING
AID FIT
COCHLEAR
IMPLANT
A106
AUDIO EXAM
A104
CONTROL
RM
A100
AUDIO EXAM
A102
CONTROL
RM
C1-102
CORRIDOR
A101
AUDIO EXAM
A103
CONTROL
RM
A107
AUDIOLOGIST
A105
CONTROL
RM
A109
HEARING
AID FIT
A109A
STORAGE
A115
ENT
TREATEMENT
A117
ENT EXAM
C1-102A
CORRIDOR
A133
STAIR
A113
ELEC
PLUMBING DEMOLITION NOTES
1. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE LOCAL, STATE AND/OR
REGULATORY AGENCIES, CODES AND REGULATIONS FOR NEW WORK.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR THE COORDINATION OF THEIR WORK
WITH OTHER TRADES AND WITH THE CONSTRUCTION MANAGER.
3. VERIFY ALL CONDITIONS IN FIELD BEFORE START OF CONSTRUCTION. NOTIFY
ARCHITECT/ENGINEER OF DISCREPANCIES BETWEEN DRAWINGS AND ACTUAL
FIELD CONDITIONS.
4. COORDINATE ALL WORK WITH APPROPRIATE TRADES.
5. COORDINATE ANY REQUIRED SHUTDOWN OF SERVICES OR EQUIPMENT WITH
OWNER'S REPRESENTATIVE, MINIMIZE INTERRUPTION OF EXISTING SERVICES.
VERIFY ALL SYSTEMS BEFORE STARTING DEMOLITION TO ASSURE OTHER AREAS
WILL NOT LOOSE SERVICE. AREAS SUCH AS THE SECOND FLOOR KITCHEN ARE
CRITICAL TO THE FACILITIES OPERATION.
6. COORDINATE FLOOR, WALL, AND ROOF PENETRATIONS ETC. WITH
ARCHITECTURAL TRADES. PROVIDE TEMPORARY WATER TIGHT SEAL FOR ALL
EXTERIOR WALL AND ROOF PENETRATION AS NECESSARY.
7. COORDINATE ALL FLOOR CUTTING WITH STRUCTURAL TRADES BEFORE
CUTTING.
8. HOLES AND PENETRATIONS IN RATED WALLS SHALL BE PATCHED WITH
APPROPRIATE FIRESTOP MATERIALS FOR RATING REQUIRED.
9. NO ITEMS TO BE ABANDONED IN PLACE.
10. ALL ITEMS TO BE DEMOLISHED TO BE REMOVED AND REMAINING OPEN SYSTEMS
TO BE PATCHED, CAPPED AND SEALED TO PROVIDE A FINISHED SYSTEM.
11. DEMOLISHED PLUMBING LINE SHALL NOT BE ALLOWED TO REMAIN OPEN, CAP
AND PROTECT TO AVOID CONTAMINATION TO AND FROM THE SURROUNDING
AREAS.
12. ALL SYSTEMS OPENED DURING DEMOLITION SHALL BE CLOSED AND RETURNED
TO OPERATION BY END OF SHIFT, NO SYSTEMS ALLOWED TO BE LEFT OPEN
WHEN NOT BEING SUPERVISED BY CONTRACTOR RESPONSIBLE FOR THAT WORK
TRADE.
PLUMBING DEMOLITION KEYNOTES??
1. REMOVE EXISTING LAVATORY OR SINK, ASSOCIATED PIPING AND
ACCESSORIES. REMOVE EXISTING DOMESTIC WATER, SANITARY AND VENT
PIPING AS INDICATED. CONTRACTOR SHALL NOT CREATE DEAD LEGS AND
SHALL REMOVE EXISTING DEAD LEGS.
2. REMOVE EXISTING MEDICAL GAS PIPING AND ALL ASSOCIATED ACCESSORIES
AS INDICATED.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PD101A
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR PLUMBING
DEMOLITION PLAN - AREA A
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/4" = 1'-0"
FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA A
EX.1 1/4"DHWR
EX.1 1/4"DHW
EX.2"DCW
UP/DN
UP
EX.1 1/2"DCW DN
EX.O2
EX.VAC
EX.MA
EX.3/4"O2
EX.3/4"VAC
EX.3/4"MA
E X
.1 "D
C W
E X
.1 "D
H W
E X
.3 /4
"D H
W R
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
EX.2"V
UP
EX.4"SANEX.4"SAN
EX.2"V
UP
EX.4"
REMOVE
SAN
DN
EX.4"
REMOVE
SAN
DN
E X
.4 "S
A N
E X
.4
UP
EX.3/4"DCW
EX.3"SAN
EX.2"V
RISER
E X
.1
/4 "V
EX.4"SAN
EX.2"V
RISER
EX.SS TO
REMAIN
E X
.V
E X
.3 /4
"V A
C
E X
.3 /4
EX.2"V
EX.4"SAN
RISER
E X
.1
/2 "V
EX.3/4"
VAC
E X
.1
/4 "V
E X
.3 /4
E X
.3 /4
E X
.3 /4
E X
.1
/2
D H
W
REMOVE EX.
DHW PIPING
AS INDICATED
REUSE EX. WALL-HUNG
LAVATORY BOWL AND
FAUCET IN NEW WORK
PHASE. REFER TO ROOM A114
PROCEDURE ON SHEET P101A
4'
3.9
1'
2'
3'
E X
.3 /4
"D H
W R
E X
.1 "D
H W
E X
.1 "D
C W
EX.3/4"DCW
REUSE EX. WALL-HUNG
LAVATORY BOWL AND
FAUCET IN NEW WORK
PHASE. REFER TO ROOM A124
SOILED ON SHEET P101A
A138
CHIEF
AUDIO/SPEECH
PATH
A136
AUDIOLOGIST
A139
CHIEF ENT
A137
AUDIOLOGIST
A135
AUDIO CLIN
FELLOWS
A133
AUDIO
TECHS
A132
ENT NURSE
PRACTITIONER
A130
NURSE
A131
HEALTH
TECHNICIAN
A129
COPY RM
A134
AUDIOLOGIST
A127
EXAM
A128
VOICE EXAM
A124
ENT/AUDIO
PREP
A146E
EXAM
C
-1
C O
R R
ID
O
R
A146D
OFFICE
A146C
OFFICE
A146B
HEARING
AID REPAIR
A114
EAR MOLD
FAB/HEARING
AID REPAIR
C1-102A
CORRIDOR
PLUMBING DEMOLITION NOTES
1. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE LOCAL, STATE AND/OR
REGULATORY AGENCIES, CODES AND REGULATIONS FOR NEW WORK.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR THE COORDINATION OF THEIR WORK
WITH OTHER TRADES AND WITH THE CONSTRUCTION MANAGER.
3. VERIFY ALL CONDITIONS IN FIELD BEFORE START OF CONSTRUCTION. NOTIFY
ARCHITECT/ENGINEER OF DISCREPANCIES BETWEEN DRAWINGS AND ACTUAL
FIELD CONDITIONS.
4. COORDINATE ALL WORK WITH APPROPRIATE TRADES.
5. COORDINATE ANY REQUIRED SHUTDOWN OF SERVICES OR EQUIPMENT WITH
OWNER'S REPRESENTATIVE, MINIMIZE INTERRUPTION OF EXISTING SERVICES.
VERIFY ALL SYSTEMS BEFORE STARTING DEMOLITION TO ASSURE OTHER AREAS
WILL NOT LOOSE SERVICE. AREAS SUCH AS THE SECOND FLOOR KITCHEN ARE
CRITICAL TO THE FACILITIES OPERATION.
6. COORDINATE FLOOR, WALL, AND ROOF PENETRATIONS ETC. WITH
ARCHITECTURAL TRADES. PROVIDE TEMPORARY WATER TIGHT SEAL FOR ALL
EXTERIOR WALL AND ROOF PENETRATION AS NECESSARY.
7. COORDINATE ALL FLOOR CUTTING WITH STRUCTURAL TRADES BEFORE
CUTTING.
8. HOLES AND PENETRATIONS IN RATED WALLS SHALL BE PATCHED WITH
APPROPRIATE FIRESTOP MATERIALS FOR RATING REQUIRED.
9. NO ITEMS TO BE ABANDONED IN PLACE.
10. ALL ITEMS TO BE DEMOLISHED TO BE REMOVED AND REMAINING OPEN SYSTEMS
TO BE PATCHED, CAPPED AND SEALED TO PROVIDE A FINISHED SYSTEM.
11. DEMOLISHED PLUMBING LINE SHALL NOT BE ALLOWED TO REMAIN OPEN, CAP
AND PROTECT TO AVOID CONTAMINATION TO AND FROM THE SURROUNDING
AREAS.
12. ALL SYSTEMS OPENED DURING DEMOLITION SHALL BE CLOSED AND RETURNED
TO OPERATION BY END OF SHIFT, NO SYSTEMS ALLOWED TO BE LEFT OPEN
WHEN NOT BEING SUPERVISED BY CONTRACTOR RESPONSIBLE FOR THAT WORK
TRADE.
PLUMBING DEMOLITION KEYNOTES??
1. REMOVE EXISTING LAVATORY OR SINK, ASSOCIATED PIPING AND
ACCESSORIES. REMOVE EXISTING DOMESTIC WATER, SANITARY AND VENT
PIPING AS INDICATED. CONTRACTOR SHALL NOT CREATE DEAD LEGS AND
SHALL REMOVE EXISTING DEAD LEGS.
2. REMOVE EXISTING MEDICAL GAS PIPING AND ALL ASSOCIATED ACCESSORIES
AS INDICATED.
3. REMOVE EXISTING ELECTRIC WATER COOLER. PREPARE PIPING FOR NEW
CONNECTION.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PD101B
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR PLUMBING
DEMOLITION PLAN - AREA B
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/4" = 1'-0"
FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA B
1 1
EX.1 1/4"DHWR
EX.1 1/4"DHW
EX.2"DCW
UP/DN
UP
EX.1 1/2"DCW DN
EX.O2
EX.VAC
EX.MA
EX.3/4"O2
EX.3/4"VAC
EX.3/4"MA
EX.MED GAS
ZONE VALVE BOX
TO REMAIN
EX.1"DHWR
EX.1"DHW
EX.2"DCW
UP/DN
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
UP
EX.3/4"DCW
EX.3/4"DHW
EX.3/4"DHWR
EX.3"SAN
EX.2"V
RISER
EX.3/4"
EX.3/4"
EX.3/4"
MA
VAC
O2
EX.2"V
EX.4"SAN
RISER
E X
.1
/4 "V
EX.4"SAN
EX.2"V
RISER
EX.SS TO
REMAIN
E X
.V
E X
.3 /4
"V A
C
E X
.3 /4
EX.2"V
EX.4"SAN
RISER
E X
.1
/2 "V
EX.3/4"
VAC
EX.1 1/4"V
E X
.1
/2 "V
REUSE EX. WALL-HUNG
LAVATORY BOWL AND
FAUCET IN NEW WORK
PHASE. REFER TO ROOM A114
PROCEDURE ON SHEET P101A
4'
7'
3.9
E X
.3 /4
"D H
W R
E X
.1 "D
H W
E X
.1 "D
C W
EX.3/4"DHWR
EX.3/4"DHW
EX.3/4"DCW
/4
"D C
W
/4
"D H
W
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.1
/4 "V
REUSE EX. WALL-HUNG
LAVATORY BOWL AND
FAUCET IN NEW WORK
PHASE. REFER TO ROOM A124
SOILED ON SHEET P101A
A129
COPY RM
A127
EXAM
A128
VOICE EXAM
A124
ENT/AUDIO
PREP
A146E
EXAM
A146D
OFFICE
A146C
OFFICE
A146B
HEARING
AID REPAIR
A114
EAR MOLD
FAB/HEARING
AID REPAIR
A115
ENT
TREATEMENT
A117
ENT EXAM
A119
ENT EXAM
A121
ENT EXAM
A123
ENT NURSE
PRACTIT.
C1-102A
CORRIDOR
A133
STAIR
A113
ELEC
PLUMBING DEMOLITION NOTES
1. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE LOCAL, STATE AND/OR
REGULATORY AGENCIES, CODES AND REGULATIONS FOR NEW WORK.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR THE COORDINATION OF THEIR WORK
WITH OTHER TRADES AND WITH THE CONSTRUCTION MANAGER.
3. VERIFY ALL CONDITIONS IN FIELD BEFORE START OF CONSTRUCTION. NOTIFY
ARCHITECT/ENGINEER OF DISCREPANCIES BETWEEN DRAWINGS AND ACTUAL
FIELD CONDITIONS.
4. COORDINATE ALL WORK WITH APPROPRIATE TRADES.
5. COORDINATE ANY REQUIRED SHUTDOWN OF SERVICES OR EQUIPMENT WITH
OWNER'S REPRESENTATIVE, MINIMIZE INTERRUPTION OF EXISTING SERVICES.
VERIFY ALL SYSTEMS BEFORE STARTING DEMOLITION TO ASSURE OTHER AREAS
WILL NOT LOOSE SERVICE. AREAS SUCH AS THE SECOND FLOOR KITCHEN ARE
CRITICAL TO THE FACILITIES OPERATION.
6. COORDINATE FLOOR, WALL, AND ROOF PENETRATIONS ETC. WITH
ARCHITECTURAL TRADES. PROVIDE TEMPORARY WATER TIGHT SEAL FOR ALL
EXTERIOR WALL AND ROOF PENETRATION AS NECESSARY.
7. COORDINATE ALL FLOOR CUTTING WITH STRUCTURAL TRADES BEFORE
CUTTING.
8. HOLES AND PENETRATIONS IN RATED WALLS SHALL BE PATCHED WITH
APPROPRIATE FIRESTOP MATERIALS FOR RATING REQUIRED.
9. NO ITEMS TO BE ABANDONED IN PLACE.
10. ALL ITEMS TO BE DEMOLISHED TO BE REMOVED AND REMAINING OPEN SYSTEMS
TO BE PATCHED, CAPPED AND SEALED TO PROVIDE A FINISHED SYSTEM.
11. DEMOLISHED PLUMBING LINE SHALL NOT BE ALLOWED TO REMAIN OPEN, CAP
AND PROTECT TO AVOID CONTAMINATION TO AND FROM THE SURROUNDING
AREAS.
12. ALL SYSTEMS OPENED DURING DEMOLITION SHALL BE CLOSED AND RETURNED
TO OPERATION BY END OF SHIFT, NO SYSTEMS ALLOWED TO BE LEFT OPEN
WHEN NOT BEING SUPERVISED BY CONTRACTOR RESPONSIBLE FOR THAT WORK
TRADE.
PLUMBING DEMOLITION KEYNOTES??
1. REMOVE EXISTING LAVATORY OR SINK, ASSOCIATED PIPING AND
ACCESSORIES. REMOVE EXISTING DOMESTIC WATER, SANITARY AND VENT
PIPING AS INDICATED. CONTRACTOR SHALL NOT CREATE DEAD LEGS AND
SHALL REMOVE EXISTING DEAD LEGS.
2. REMOVE EXISTING MEDICAL GAS PIPING AND ALL ASSOCIATED ACCESSORIES
AS INDICATED.
3. REMOVE EXISTING ELECTRIC WATER COOLER. PREPARE PIPING FOR NEW
CONNECTION.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PD101C
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR PLUMBING
DEMOLITION PLAN - AREA C
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/4" = 1'-0"
FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA C
I F'' G'F'E' H'
A' C'B' D'
J
1'
2'
3'
4'
7'
3.9
UP TO
NEW SINK
UP TO
NEW SINK
2"SAN
UP TO
NEW SINK
UP TO
NEW SINK
UP TO
NEW SINK
UP TO
NEW SINK
UP TO
NEW SINK
E X
.2 "S
A N
E X
.2 "S
A N
E X
.2 "S
A N
EX.4"SAN
E X
.2 "S
A N
EX.2"SAN
2"SAN
2"SAN
UP TO
NEW SINK
2"SAN
EX.4"SAN
2"SAN
UP TO
NEW SINK
EX.2"SAN
2"SAN
EX.4"SAN
RISER
EX.4"SAN
DN
RISER
EX.4"SAN
EX.4"SAN
RISER
EX.3"SAN
UP TO
NEW SINK
EX.3"SAN
UP TO EX.
MOP SINK
EX.3"SAN
EX.3"SAN
RISER
2"SAN
UP TO
NEW SINK
EX.4"SAN
RISER
UP TO
NEW SINK
EX.4"SAN
RISER
2"SAN
UP TO
NEW SINK
2"SAN
RISER
EX.4"SAN
3/4"C
UP TO
FCU
3/4"C 3/4"C
UP TO
FCU
EX.2"SAN
UP TO
NEW SINK
3/4"C
UP TO
FCU
"S
A N
UP TO
NEW SINK
2"SAN
3/4"C
"C
EX.2"SAN
UP TO
NEW SINK
EX.V
EX.SAN
EX.2"SAN
UP TO SINK
EX.2"SAN
UP TO SINK
2" SAN
UP TO
NEW SINK
EX.2"V
EX.4"SAN
RISER
UP/DN
EX.2"V
EX.4"SAN
RISER
UP/DN
3/4"C
UP
CO
3/4"C
UP
/4
"C
CO
CO
1"C CO
RISER
CO
CO
4"SAN
UP
CO
1"C
CO
CO
EX.4"SAN
RISER
EX.4"SAN
RISER
2 2
C1
CORRIDOR
AB01
EVS STORAGE
AB08
CLEAN UTILITY
AB09A
TREATMENT 5
AB09B
TREATMENT 4
AB09E
TREATMENT 1
AB10
DECON/PROCESSING
AB10A
DECON
CB29
CORRIDOR
CB28
CORRIDOR
AB09N
NOUR
AB09K
MEDS
CB36
PASSAGE
AB09L
MENTOR
AB09I
CHARTING
AB09H
MD WORKAB09F
WORK
AB09
NURSE
AB09M
NURSE
TRAUMA 1
TRAUMA 2
AB09Z
OBSERVATION 1
AB09Y
OBSERVATION 2
AB09X
OBSERVATION 3
AB09W
OBSERVATION 4
AB15
ANTE RM
AB15A
ISO. RM
AB15A
TOILET RM
AB18
ER NURSE
EDUCATIONAB09V
EXAM 4
AB09U
EXAM 3
AB09T
EXAM 2
AB09S
EXAM 1
AB09R
TRIAGE
AB20
CHIEF
AB22
DIRECTOR
AB30
WOMENS TOILET
CB30
CORRIDOR
CB33
CORRIDOR
C1
CORRIDOR
AB03
WOMEN'S
LOCKER RM
A8B
ELEC
A8
ELECTRICAL
AB02
VOLUNTARY
SERVICE
STORAGE
STAIR #2
STAIR #1
AB91
COMM CLOSET
AB90
TEL CLOSET
PATIENT TOILET
AB09C
TREATMENT 3
AB09C
TREATMENT 3
"S
A N
2"SAN
PLUMBING GENERAL NOTES
1. COORDINATE ROUTING OF PIPING WITH ALL OTHER TRADES PRIOR TO
INSTALLATION TO AVOID CONFLICTS.
2. COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES.
3. PROVIDE ROUGH-INS AND FINAL CONNECTIONS TO FIXTURES AND EQUIPMENT
4. PROVIDE TRAP SEAL PROTECTION ON ALL FLOOR DRAINS, FLOOR SINKS AND
HUB DRAINS SUBJECT TO EVAPORATION. INSTALL PER MANUFACTURERS
RECOMMENDATIONS.
5. PROVIDE ASSE 1070 MIXING VALVE AT ALL BARRIER FREE SINKS AND ALL HAND
WASHING SINKS TO PROVIDE TEMPERED WATER TO HOT WATER SIDE OF
FAUCET.
6. PIPING INSTALLED IN THE WAY OF ACCESS OR MAINTENANCE TO EQUIPMENT
SHALL BE RELOCATED AT THE EXPENSE OF THE INSTALLING CONTRACTOR.
7. ALL PLUMBING WORK SHALL MEET MICHIGAN PLUMBING CODE 2015
REQUIREMENTS AS A MINIMUM UNLESS EXCEEDED BY PROJECT CONSTRUCTION
DOCUMENTS.
8. PROVIDE SHUTOFF VALVES AT ALL FIXTURES AND EQUIPMENT.
9. COORDINATE LOCATIONS OF FLOOR DRAINS AND FLOOR SINKS WITH LOCATIONS
OF EQUIPMENT AND EQUIPMENT HOUSEKEEPING PADS. COORDINATE WITH
SLOPING OF FLOOR SO THAT RIM OF DRAIN IS FLUSH WITH FINISH FLOOR.
10. COORDINATE HANGING AND SUPPORT OF PIPING WITH STRUCTURAL.
11. PROVIDE PIPE SLEEVES WHERE PIPES PENETRATE WALLS.
12. BALL VALVES SHALL BE 316 STAINLESS STEEL FOR DOMESTIC HOT WATER
SYSTEM AND BRASS FOR DOMESTIC COLD WATER SYSTEM.
13. INSTALL PIPING IN AN ORGANIZED MANNER. DO NOT ROUTE IN FRONT OF
WINDOWS.
14. THE INSTALLATION OF ALL PIPING SHALL BE CLOSELY COORDINATED WITH NEW
SHEET METAL. HVAC PIPING, ELECTRICAL, AND STRUCTURAL CONDITIONS. NOT
ALL REQUIRED OFFSETS AND FITTINGS ARE INDICATED, BUT SHALL BE
PROVIDED. REFER TO ARCHITECTURAL AND STRUCTURAL PLANS FOR
CLEARANCES.
15. PROVIDE WATER HAMMER ARRESTORS PER PDI WH-201 AND UP STREAM OF ALL
AUTOMATIC AND FAST CLOSING VALVES INCLUDING BUT NOT LIMITED TO
SOLENOID VALVES.
16. COORDINATION AND LAYOUT DRAWINGS SHALL BE SUBMITTED TO THE AE FOR
APPROVAL PRIOR TO INSTALL.
PLUMBING KEYNOTES?
1. ROUTE CONDENSATE DRAIN LINE TO SANITARY HUB OUTLET. DISCHARGE
WITH AIR GAP.
2. COORDINATE ACCESS TO BASEMENT AREAS WITH COR. WORK SHALL BE
PERFORMED DURING PREMIUM/AFTER HOURS IN OCCUPIED SPACES.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PL001
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
BASEMENT PLUMBING PLAN UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/8" = 1'-0"
BASEMENT PLUMBING PLAN
A101
SHARED NP OFFICE
A103
SHARED MD OFFICE
A105
SHARED LPN WORK
ROOM
A100
CVT STATION
A102
ENT CHIEF OFFICE
A104
EXIST. CONTROL ROOM
A106
EXIST. AUDIO EXAM
ROOM
C1-102
CORRIDOR
C1-102A
CORRIDOR
A110
PROCEDURE
A112
ENT PROCEDURE
A114
PROCEDURE
A109
SHARED STAFF OFFICE
A133
STAIR
C1-102A
CORRIDOR
A113
ELEC
A115
ENT TREATMENT
A117
ENT EXAM
A116
HAC
A124
SOILED
A128
SPEECH/PATH EXAM
A140
CORRIDOR
EX.1 1/4"DHWR
EX.1 1/4"DHW
EX.2"DCW
UP/DN
UP
EX.1 1/2"DCW DN
EX.2"DCW
EX.1"DHW
EX.1"DHWR
UP/DN
P-501
P-501
E X
.1
/2 "V
EX.V UP
EX.SAN RISER
3/4"DHW
1 1/4"V
3/4"DCW
3/4"DCW
1 1/2"V
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
EX.3/4"DCW
EX.1 1/4"V
EX.V
EX.SAN
3/ 4"
D C
W
3/ 4"
D H
W
E X
.3 /4
"D H
W R
E X
.3 /4
"D H
W E
X .3
/4 "D
C W
1W-FCU-1 1W-FCU-1 1W-FCU-2
1W-FCU-1 1W-FCU-1
1W-FCU-1
A146F
ALCOVE
EX.FCU
1W-FCU-2
EX.FCU
2 2
2 2 2
1W-FCU-2 1W-FCU-2
EX.FCU
1/
4" V
EX.SS TO
REMAIN
REUSE EX. WALL-HUNG LAVATORY
AND FAUCET (REFER TO SHEET
PD101C). INSTALL NEW P-TRAP,
MIXING VALVE, PIPING AND
ACCESSORIES
A111
EXIST. CONFERENCE
ROOM
4'
7'
3.9
P-501
P-501
EX.2"V EX.4"SAN
RISER
1/
2" V
3/4"DHW
3/4"DCW
CONNECT TO EXISTING
CONDENSATE DRAIN
EX.2"V
EX.5"SAN
EX.4"SAN
RISER
RISER
EX.2"V
1"DHW
1 1/2"V
1"DCW
EX.1 1/4"V
EX.3/4"DCW
EX.1 1/4"V
EX.3/4"DCW
EX.3/4"DHW
EX.3/4"DCW
EX.1 1/4"V
3/4"DCW
1 1/4"V
3/4"DHW
EX.FCU1W-FCU-2
CONNECT TO EXISTING
CONDENSATE DRAIN
P-601
EX.4"SAN
RISER
EX.4"SAN
RISER
EX.3/4"DHWR
3/4"DHWR
3/ 4"
D H
W
EX.3/4"DHWR
P-501
3/4"DHW
3/4"DHW
3/ 4"
D H
W R
PLUMBING GENERAL NOTES
1. COORDINATE ROUTING OF PIPING WITH ALL OTHER TRADES PRIOR TO
INSTALLATION TO AVOID CONFLICTS.
2. COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES.
3. PROVIDE ROUGH-INS AND FINAL CONNECTIONS TO FIXTURES AND EQUIPMENT
4. PROVIDE TRAP SEAL PROTECTION ON ALL FLOOR DRAINS, FLOOR SINKS AND
HUB DRAINS SUBJECT TO EVAPORATION. INSTALL PER MANUFACTURERS
RECOMMENDATIONS.
5. PROVIDE ASSE 1070 MIXING VALVE AT ALL BARRIER FREE SINKS AND ALL HAND
WASHING SINKS TO PROVIDE TEMPERED WATER TO HOT WATER SIDE OF
FAUCET.
6. PIPING INSTALLED IN THE WAY OF ACCESS OR MAINTENANCE TO EQUIPMENT
SHALL BE RELOCATED AT THE EXPENSE OF THE INSTALLING CONTRACTOR.
7. ALL PLUMBING WORK SHALL MEET MICHIGAN PLUMBING CODE 2015
REQUIREMENTS AS A MINIMUM UNLESS EXCEEDED BY PROJECT CONSTRUCTION
DOCUMENTS.
8. PROVIDE SHUTOFF VALVES AT ALL FIXTURES AND EQUIPMENT.
9. COORDINATE LOCATIONS OF FLOOR DRAINS AND FLOOR SINKS WITH LOCATIONS
OF EQUIPMENT AND EQUIPMENT HOUSEKEEPING PADS. COORDINATE WITH
SLOPING OF FLOOR SO THAT RIM OF DRAIN IS FLUSH WITH FINISH FLOOR.
10. COORDINATE HANGING AND SUPPORT OF PIPING WITH STRUCTURAL.
11. PROVIDE PIPE SLEEVES WHERE PIPES PENETRATE WALLS.
12. BALL VALVES SHALL BE 316 STAINLESS STEEL FOR DOMESTIC HOT WATER
SYSTEM AND BRASS FOR DOMESTIC COLD WATER SYSTEM.
13. INSTALL PIPING IN AN ORGANIZED MANNER. DO NOT ROUTE IN FRONT OF
WINDOWS.
14. THE INSTALLATION OF ALL PIPING SHALL BE CLOSELY COORDINATED WITH NEW
SHEET METAL. HVAC PIPING, ELECTRICAL, AND STRUCTURAL CONDITIONS. NOT
ALL REQUIRED OFFSETS AND FITTINGS ARE INDICATED, BUT SHALL BE
PROVIDED. REFER TO ARCHITECTURAL AND STRUCTURAL PLANS FOR
CLEARANCES.
15. PROVIDE WATER HAMMER ARRESTORS PER PDI WH-201 AND UP STREAM OF ALL
AUTOMATIC AND FAST CLOSING VALVES INCLUDING BUT NOT LIMITED TO
SOLENOID VALVES.
16. COORDINATION AND LAYOUT DRAWINGS SHALL BE SUBMITTED TO THE AE FOR
APPROVAL PRIOR TO INSTALL.
PLUMBING KEYNOTES?
1. ROUTE 3/4" DOMESTIC HOT WATER DOWN WALL TO SINK. TAP CONTINUATION
OF 3/4" DOMESTIC HOT WATER AS CLOSE AS POSSIBLE TO SINK STOP. ROUTE
CONTINUATION OF HOT WATER PIPING BACK UP WALL AND TO NEXT FIXTURE
DOWNSTREAM. REFER TO DETAIL ON PL000.
2. ROUTE CONDENSATE PIPING DOWN TO FLOOR BELOW.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PL101A
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR PLUMBING
PLAN - AREA A
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/4" = 1'-0"
FIRST FLOOR PLUMBING PLAN - AREA A
A114
PROCEDURE
A116
HAC
A124
SOILED
A128
SPEECH/PATH EXAM
A140
CORRIDOR
A130
SPEECH/PATH OFFICE
A132
STAFF OFFICE
A134
STAFF OFFICE
A136
SPUTUM
A138
EVAL. HOME/DME
A139
PFT BODY BOX 1
A137
PFT BODY BOX 2
A131
PFT BODY BOX 3
A129
SPEECH/PATH EXAM
A127
SPEECH/PATH EXAM
A146E
SOILED SCOPE
A146D
INTAKE / VITALS
A146B
CLEAN
C1-102A
CORRIDOR
EX.1 1/4"DHWR
EX.1 1/4"DHW
EX.2"DCW
UP/DN
UP
EX.1 1/2"DCW DN
A135
PORTABLE GAS
STORAGE
EX.3/4"DCW
P-501
P-501
P-501
P-501
P-501
E X
.1
/4 "V
3/4"DCW
1 1/4"V
E X
.1
/4 "V
E X
.1
/2 "V
EX.V UP
EX.V UP
EX.SAN
EX.SAN RISER
RISER
3/4"DCW
1 1/2"V
E X
.3 /4
"D H
W R
E X
.3 /4
"D H
W E
X .3
/4 "D
C W
E X
.3 /4
"D H
W R
E X
.1 "D
C W
E X
.3 /4
"D H
W R
E X
.3 /4
"D H
W E
X .3
/4 "D
C W
A146F
ALCOVE
EX.FCU
1W-FCU-2 1W-FCU-2
EX.SS TO
REMAIN
P-501
3/4"DHW
3/4"DCW
1 1/4"V
P-502
P-502
EX.FCU
EX.FCU
EX.FCU
EX.FCU
EX.FCU
EX.FCU
EX.FCU EX.FCU
1W-FCU-3
1W-FCU-3
1W-FCU-3
REUSE EX. WALL-HUNG LAVATORY
AND FAUCET (REFER TO SHEET
PD101C). INSTALL NEW P-TRAP,
MIXING VALVE, PIPING AND
ACCESSORIES
4'
3.9
1'
2'
3'
P-501
DN
4"SAN
E X
.4 "S
A N
3/ 4"
C
3/4"C
3/4"C
3/ 4"
C
DN
3/4"C DN
3/ 4"
D C
W
EX.4"SAN
RISER
EX.2"V
3/4"DHWR
2"V
3/4"DCW
3/4"DHW
3/4"DCW
P-501
EX.2"V EX.4"SAN
RISER
1/
2" V
3/4"DHW
3/4"DCW
CONNECT TO EXISTING
CONDENSATE DRAIN
EX.3"SAN
EX.2"V
EX.4"SAN
RISER
EX.2"V
1"DHW
1 1/2"V
1"DCW
EX.1 1/4"V
EX.3/4"DCW
EX.1 1/4"V
EX.3/4"DCW
EX.3/4"DHW
3/4"DHW
3/4"DHWR
EX.3/4"DCW
P-601
3/4"DHWR
3/ 4"
D H
W
EX.3/4"DHWR
EX. FCU RELOCATED.
RECONNECT TO EX.
CONDENSATE DRAIN
EX. FCU
3/ 4"
D H
W
4" S
A N
1"DHW
3/4"DHWR
3/4"DHWR
3/4"DHWR
3/ 4"
D H
W
3/4"DHW
P-501
P-501
PLUMBING GENERAL NOTES
1. COORDINATE ROUTING OF PIPING WITH ALL OTHER TRADES PRIOR TO
INSTALLATION TO AVOID CONFLICTS.
2. COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES.
3. PROVIDE ROUGH-INS AND FINAL CONNECTIONS TO FIXTURES AND EQUIPMENT
4. PROVIDE TRAP SEAL PROTECTION ON ALL FLOOR DRAINS, FLOOR SINKS AND
HUB DRAINS SUBJECT TO EVAPORATION. INSTALL PER MANUFACTURERS
RECOMMENDATIONS.
5. PROVIDE ASSE 1070 MIXING VALVE AT ALL BARRIER FREE SINKS AND ALL HAND
WASHING SINKS TO PROVIDE TEMPERED WATER TO HOT WATER SIDE OF
FAUCET.
6. PIPING INSTALLED IN THE WAY OF ACCESS OR MAINTENANCE TO EQUIPMENT
SHALL BE RELOCATED AT THE EXPENSE OF THE INSTALLING CONTRACTOR.
7. ALL PLUMBING WORK SHALL MEET MICHIGAN PLUMBING CODE 2015
REQUIREMENTS AS A MINIMUM UNLESS EXCEEDED BY PROJECT CONSTRUCTION
DOCUMENTS.
8. PROVIDE SHUTOFF VALVES AT ALL FIXTURES AND EQUIPMENT.
9. COORDINATE LOCATIONS OF FLOOR DRAINS AND FLOOR SINKS WITH LOCATIONS
OF EQUIPMENT AND EQUIPMENT HOUSEKEEPING PADS. COORDINATE WITH
SLOPING OF FLOOR SO THAT RIM OF DRAIN IS FLUSH WITH FINISH FLOOR.
10. COORDINATE HANGING AND SUPPORT OF PIPING WITH STRUCTURAL.
11. PROVIDE PIPE SLEEVES WHERE PIPES PENETRATE WALLS.
12. BALL VALVES SHALL BE 316 STAINLESS STEEL FOR DOMESTIC HOT WATER
SYSTEM AND BRASS FOR DOMESTIC COLD WATER SYSTEM.
13. INSTALL PIPING IN AN ORGANIZED MANNER. DO NOT ROUTE IN FRONT OF
WINDOWS.
14. THE INSTALLATION OF ALL PIPING SHALL BE CLOSELY COORDINATED WITH NEW
SHEET METAL. HVAC PIPING, ELECTRICAL, AND STRUCTURAL CONDITIONS. NOT
ALL REQUIRED OFFSETS AND FITTINGS ARE INDICATED, BUT SHALL BE
PROVIDED. REFER TO ARCHITECTURAL AND STRUCTURAL PLANS FOR
CLEARANCES.
15. PROVIDE WATER HAMMER ARRESTORS PER PDI WH-201 AND UP STREAM OF ALL
AUTOMATIC AND FAST CLOSING VALVES INCLUDING BUT NOT LIMITED TO
SOLENOID VALVES.
16. COORDINATION AND LAYOUT DRAWINGS SHALL BE SUBMITTED TO THE AE FOR
APPROVAL PRIOR TO INSTALL.
PLUMBING KEYNOTES?
1. ROUTE 1/2" DOMESTIC HOT WATER DOWN WALL TO SINK. TAP CONTINUATION
OF 1/2" DOMESTIC HOT WATER AS CLOSE AS POSSIBLE TO SINK STOP. ROUTE
CONTINUATION OF HOT WATER PIPING BACK UP WALL AND TO NEXT FIXTURE
DOWNSTREAM. REFER TO DETAIL ON PL000.
2. ROUTE CONDENSATE PIPING DOWN TO FLOOR BELOW.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PL101B
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR PLUMBING
PLAN - AREA B
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/4" = 1'-0"
FIRST FLOOR PLUMBING PLAN - AREA B
A112
ENT PROCEDURE
A114
PROCEDURE
A133
STAIR
C1-102A
CORRIDOR
A113
ELEC
A115
ENT TREATMENT
A117
ENT EXAM
A116
HAC
A124
SOILED
A128
SPEECH/PATH EXAM
A140
CORRIDOR
A129
SPEECH/PATH EXAM
A127
SPEECH/PATH EXAM
A146E
SOILED SCOPE
A146D
INTAKE / VITALS
A146B
CLEAN
C1-102A
CORRIDOR
A119
ENT EXAM
A121
ENT EXAM
A123
ENT EXAM
EX.1 1/4"DHWR
EX.1 1/4"DHW
EX.2"DCW
UP/DN
UP
EX.1 1/2"DCW DN
EX.3/4"DCW
EX.3/4"DHW
EX.3/4"DHWR
EX.2"DCW
EX.1"DHW
EX.1"DHWR
UP/DN
P-501 P-501 P-501 P-501
P-501
E X
.1
/2 "V
EX.V UP
EX.SAN RISER
3/4"DCW
1 1/2"V
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
E X
.3 /4
"D H
W R
EX.V
EX.SAN
3/ 4"
D C
W
3/ 4"
D H
W
E X
.3 /4
"D H
W R
E X
.3 /4
"D H
W E
X .3
/4 "D
C W
A146F
ALCOVE
EX.FCU
1W-FCU-2 1W-FCU-2
1/
4" V
EX.SS TO
REMAIN
P-502
P-502
EX.FCU
EX.FCU EX.FCU
REUSE EX. WALL-HUNG LAVATORY
AND FAUCET (REFER TO SHEET
PD101C). INSTALL NEW P-TRAP,
MIXING VALVE, PIPING AND
ACCESSORIES
4'
7'
3.9
P-501
3/ 4"
D C
W
EX.4"SAN
RISER
EX.2"V
3/4"DHWR
2"V
3/4"DCW
3/4"DHW
3/4"DCW
P-501
EX.2"V EX.4"SAN
RISER
1/
2" V
3/4"DHW
3/4"DCW
CONNECT TO EXISTING
CONDENSATE DRAIN
E X
.1
/2 "V
E X
.3 /4
"D C
W E
X .3
/4 "D
H W
EX.1 1/4"V
E X
.3 /4
"D C
W
E X
.3 /4
"D H
W
EX.1 1/2"V
EX.3"SAN
RISER
EX.3"SAN
EX.2"V
EX.4"SAN
RISER
EX.2"V
1"DHW
1 1/2"V
1"DCW
EX.1 1/4"V
EX.3/4"DCW
EX.1 1/4"V
EX.3/4"DCW
EX.3/4"DHW
EX.FCU1W-FCU-2
CONNECT TO EXISTING
CONDENSATE DRAIN
P-601
3/4"DHWR
3/
4" D
H W
EX.3/4"DHWR
3/4"DHWR
3/ 4"
D H
W
3/4"DHW
3/4"DHW
3/ 4"
D H
W R
P-501
EX.FCU EX.FCU
3/4"DHW
3/ 4"
D H
W R
3/4"DHW
3/ 4"
D H
W R
PLUMBING GENERAL NOTES
1. COORDINATE ROUTING OF PIPING WITH ALL OTHER TRADES PRIOR TO
INSTALLATION TO AVOID CONFLICTS.
2. COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES.
3. PROVIDE ROUGH-INS AND FINAL CONNECTIONS TO FIXTURES AND EQUIPMENT
4. PROVIDE TRAP SEAL PROTECTION ON ALL FLOOR DRAINS, FLOOR SINKS AND
HUB DRAINS SUBJECT TO EVAPORATION. INSTALL PER MANUFACTURERS
RECOMMENDATIONS.
5. PROVIDE ASSE 1070 MIXING VALVE AT ALL BARRIER FREE SINKS AND ALL HAND
WASHING SINKS TO PROVIDE TEMPERED WATER TO HOT WATER SIDE OF
FAUCET.
6. PIPING INSTALLED IN THE WAY OF ACCESS OR MAINTENANCE TO EQUIPMENT
SHALL BE RELOCATED AT THE EXPENSE OF THE INSTALLING CONTRACTOR.
7. ALL PLUMBING WORK SHALL MEET MICHIGAN PLUMBING CODE 2015
REQUIREMENTS AS A MINIMUM UNLESS EXCEEDED BY PROJECT CONSTRUCTION
DOCUMENTS.
8. PROVIDE SHUTOFF VALVES AT ALL FIXTURES AND EQUIPMENT.
9. COORDINATE LOCATIONS OF FLOOR DRAINS AND FLOOR SINKS WITH LOCATIONS
OF EQUIPMENT AND EQUIPMENT HOUSEKEEPING PADS. COORDINATE WITH
SLOPING OF FLOOR SO THAT RIM OF DRAIN IS FLUSH WITH FINISH FLOOR.
10. COORDINATE HANGING AND SUPPORT OF PIPING WITH STRUCTURAL.
11. PROVIDE PIPE SLEEVES WHERE PIPES PENETRATE WALLS.
12. BALL VALVES SHALL BE 316 STAINLESS STEEL FOR DOMESTIC HOT WATER
SYSTEM AND BRASS FOR DOMESTIC COLD WATER SYSTEM.
13. INSTALL PIPING IN AN ORGANIZED MANNER. DO NOT ROUTE IN FRONT OF
WINDOWS.
14. THE INSTALLATION OF ALL PIPING SHALL BE CLOSELY COORDINATED WITH NEW
SHEET METAL. HVAC PIPING, ELECTRICAL, AND STRUCTURAL CONDITIONS. NOT
ALL REQUIRED OFFSETS AND FITTINGS ARE INDICATED, BUT SHALL BE
PROVIDED. REFER TO ARCHITECTURAL AND STRUCTURAL PLANS FOR
CLEARANCES.
15. PROVIDE WATER HAMMER ARRESTORS PER PDI WH-201 AND UP STREAM OF ALL
AUTOMATIC AND FAST CLOSING VALVES INCLUDING BUT NOT LIMITED TO
SOLENOID VALVES.
16. COORDINATION AND LAYOUT DRAWINGS SHALL BE SUBMITTED TO THE AE FOR
APPROVAL PRIOR TO INSTALL.
PLUMBING KEYNOTES?
1. ROUTE 1/2" DOMESTIC HOT WATER DOWN WALL TO SINK. TAP CONTINUATION
OF 1/2" DOMESTIC HOT WATER AS CLOSE AS POSSIBLE TO SINK STOP. ROUTE
CONTINUATION OF HOT WATER PIPING BACK UP WALL AND TO NEXT FIXTURE
DOWNSTREAM. REFER TO DETAIL ON PL000.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PL101C
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR PLUMBING
PLAN - AREA C
UPGRADE 1 WEST -
BLDG 1W
NORTH
SCALE: 1/4" = 1'-0"
FIRST FLOOR PLUMBING PLAN - AREA C
UP
EX.O2
EX.VAC
EX.MA
EX.3/4"O2
EX.3/4"VAC
EX.3/4"MA
A101
SHARED NP OFFICE
A103
SHARED MD OFFICE
A105
SHARED LPN WORK
ROOM
A100
CVT STATION
A102
ENT CHIEF OFFICE
A104
EXIST. CONTROL ROOM
A106
EXIST. AUDIO EXAM
ROOM
A110
PROCEDURE
A112
ENT PROCEDURE
A114
PROCEDURE
A109
SHARED STAFF OFFICE
C1-102A
CORRIDOR
C1-102A
CORRIDOR
A115
ENT TREATMENT
A117
ENT EXAM
A133
STAIR
A113
ELEC
A124
SOILED
A128
SPEECH/PATH EXAM
A140
CORRIDOR
A127
SPEECH/PATH EXAM
/4
"O
E X
.3 /4
"V A
C
/4
"M A
EX.ZONE
VALVE BOX
TO REMAIN
A111
EXIST. CONFERENCE
ROOM
4'
7'
3.9
EX.3/4"O2
EX.3/4"VAC
EX.3/4"MA
1/2"O2
1/2"O2
3/4"MA
3/4"VAC
3/4"O2
A146F
ALCOVE
3/4"VAC
1/2"O2
1/2"MA
1/2"MA
1/2"O2
3/4"VAC3/4"VAC
1/2"O2
1/2"MA 1/2"MA
1/2"O2
3/4"VAC
MEDICAL GAS GENERAL NOTES
1. COORDINATE ROUTING OF PIPING WITH ALL OTHER TRADES PRIOR TO
INSTALLATION TO AVOID CONFLICTS.
2. COMPLY WITH ALL APPLICABLE LOCAL AND STATE CODES.
3. PROVIDE ROUGH-INS AND FINAL CONNECTIONS TO FIXTURES AND EQUIPMENT.
4. PIPING INSTALLED IN THE WAY OF ACCESS OR MAINTENANCE TO EQUIPMENT
SHALL BE RELOCATED AT THE EXPENSE OF THE INSTALLING CONTRACTOR.
5. COORDINATE HANGING AND SUPPORT OF PIPING WITH STRUCTURAL.
6. PROVIDE PIPE SLEEVES WHERE PIPES PENETRATE WALLS.
7. INSTALL PIPING IN AN ORGANIZED MANNER. DO NOT ROUTE IN FRONT OF
WINDOWS.
8. THE INSTALLATION OF ALL PIPING SHALL BE CLOSELY COORDINATED WITH NEW
SHEET METAL. HVAC PIPING, ELECTRICAL, AND STRUCTURAL CONDITIONS. NOT
ALL REQUIRED OFFSETS AND FITTINGS ARE INDICATED, BUT SHALL BE
PROVIDED. REFER TO ARCHITECTURAL AND STRUCTURAL PLANS FOR
CLEARANCES.
9. COORDINATION AND LAYOUT DRAWINGS SHALL BE SUBMITTED TO THE AE FOR
APPROVAL PRIOR TO INSTALL.
10. ALL MEDICAL GAS WORK SHALL MEET THE VA TIL GUIDELINES AND BE
COMPLETED BY ASSE G010 CERTIFIED INSTALLER.
11. ALL LINES MUST BE TESTED AND CERTIFIED BEFORE USE.
AREA A
AREA B
AREA C
AREA D
AREA LEG END
KEY PLAN
AREA 'A'
AREA 'C'
AREA 'B'
1811 4 Mile Rd N.E., Grand Rapids, MI 49525 www.progressiveae.com
616 361 2664 OFFICE 616 361 1493 FAX
600 E. Michigan Avenue, Suite B
Kalamazoo, MI 49007
P: 269.927.0144 www.7GenAE.com
2850 Eisenhower Ave, Suite 310
Alexandria, VA 22314
P: 202.617.8485 www.alliance.us.com
2 3 4 5 6 7 8 9
2 3 4 5 6 7 8 91
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANTS ARCHITECT/ENGINEERS
DRAWING TITLE:
APPROVED: PROJECT DIRECTOR LOCATION:
PROJECT TITLE:
DATE: CHECKED: DRAWN:
PROJECT NUMBER:
BUILDING NUMBER:
DRAWING NUMBER:
DWG. ___ OF ___
7GAE PROJECT NO.: XXXXXX FILE NAME: TITL-BLK-3042-VA.DWG
Office of
Construction and Facilities
Management
VA FORM 08-6231
o n e e ig h th i n c h o e q u a rt e r in c h o e e ig h th s in c h o e h a lf i n c h o e q u a rt e rs i n c h o e i n c h o e a n d o n e h a lf i n c h e s o e i n c h e s o
6 "
Department of Veterans Affairs
PL111A
506-20-201
ANN ARBOR VAMC
MARCH 22, 2019 MMK JDK
FIRST FLOOR MEDICAL GAS
PLA…