RFI 3 project phasing - response.docx
DOCX document 32 KB Posted
- Attached to
- Z1DA--Upgrade 1W Building 506-20-201
- Solicitation number
- 36C25020B0046
About this file
This document contains a request for information and related federal contract opportunity. The request for information pertains to project phasing for the VA Ann Arbor 1 West Building renovation and asks whether phases must be 100% complete before the next phase starts or if phases can run concurrently. The resolution confirms that phases need to be fully complete, with punchlist items resolved, before the next phase begins per the general construction notes.
The related federal contract opportunity is a solicitation to upgrade the 1st floor of Building 1W at the Ann Arbor VA Medical Center involving approximately 4,200 square feet. The renovation includes structural, architectural, electrical, mechanical, fire protection and interior design work to result in complete and usable clinic spaces. The contractor must provide all labor, materials, equipment, supervision and documentation to adhere to building codes, VA standards, and sustainable design principles. The period of performance is 180 days from notice to proceed with work expected to commence in fall 2020. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Siemens Industry, Inc
Request for Information
| Job Name: |
| VA Ann Arbor 1 West Building 1W |
| Job Number: |
| VA# 506-20-201 |
| Requested By: |
| Richard A. Darnell |
| RFI Number: |
| 3 |
| Contact: |
| richard.darnell@siemens.com |
| Date: |
| 8/11/2020 |
| To: |
| VA Ann Arbor |
| Attn: |
| Kyle Lipper kyle.lipper@va.gov |
Spec. Number
| Sketch (if required) |
| Drawing: |
Rev:
| System: |
| Project phasing |
| Location: |
| Bldg: |
| Bldg 1W |
Level:
Other Drawing Affected:
No:
| Cost Impact: |
| unknown |
| Time Delay: |
| No |
Description of Problem: Will a phase have to be 100% complete before the next phase is started?
Resolution of Problem:
According to phasing plans, phases need to be complete before the next phase is started; punchlist items will need to be completed prior to start of next phase. Phases should not run concurrently. Refer to general construction notes, item 1 on GC101 – GC104.
Accepted:
General Cont.:
Date:
Arch/Eng:
Date:
Unrestricted Unrestricted Revised 7/26/01 image1.wmf