IMS RFI 02 responseS.docx

DOCX document 16 KB Posted

Attached to
Z1DA--Upgrade 1W Building 506-20-201
Solicitation number
36C25020B0046
Issued by

About this file

This document includes a Request for Information (RFI) and responses related to an upgrade project at the Ann Arbor VA Medical Center in Michigan. The RFI solicits information on desired top treatments for roller shades and clarification on conflicting fabric and style listings in project drawings and schedules. It also seeks confirmation that Draper and Mecho are acceptable shade manufacturers and that all shades are double roller with blackout and 3% open shades. Additionally, it inquires about the intended purpose of roller shade tags notated in room drawings but absent from finish schedules. The response provides specifications for painted metal fascia roller shades and manufacturers listed as design basis. It also states all shades are double with blackout and 3" open components and clarifies the tags in question referred to new wall construction, not window treatments.

View the file

Other files

File Type Posted
36C25020B0046 0004.pdf PDF
RFI 005 - Response.docx DOCX document
RFI 1 work hours - response.docx DOCX document
RFI 004 - response.docx DOCX document
S02RFIFORM50620201.docx DOCX document
WAGE DET MI20200100 08072020 REV3.pdf PDF
RFI 3 project phasing - response.docx DOCX document
RFI 2 New FCU with Existing Reheat Coil - Response.pdf PDF
IMS-RFI 01 response.docx DOCX document
36C25020B0046 0003.pdf PDF
Contractor Addresses -.doc DOC document
RFI 001 (response).docx DOCX document
_506-20-201 VA Ann Arbor - 1W Upgrades - Addendum 01.pdf PDF
Sign In Sheet 506-20-201.pdf PDF
033000.pdf PDF
RFI Form 2 8-3-2020 - response.docx DOCX document
S04 - Pre-Bid Site Visit Agenda 506-20-201.pdf PDF
RFI 1. - Response.pdf PDF
36C25020B0046 0002.pdf PDF
36C25020B0046 0001.pdf PDF
Contractor EMR Certification Form 2020.docx DOCX document
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part2.pdf PDF
506-20-201_PROJECT MANUAL_VOL1_032019 SPECS.pdf PDF
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part3.pdf PDF
506-20-201_PROJECT MANUAL_VOL2_032019 SPECS.pdf PDF
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part1.pdf PDF
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part4.pdf PDF
WAGE DET MI20200100 07032020 REV2.pdf PDF
S02 - RFI Form 506-20-201.docx DOCX document
36C25020B0046_1.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

36C25020B0046

PROJECT NUMBER:
506-20-201
Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents. When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.
PROJECT TITLE:
Upgrade Building 1West
PROJECT LOCATION:
Department of Veterans Affairs

Ann Arbor VAMC 2215 Fuller Road Ann Arbor, MI 48105

SUBMITTED BY:
IMS Contracting – Dale Lamarche
City/State:
Escanaba, MI.
PHONE NO.:
906-789-9021 Ext. 26

TO: Kyle Lipper kyle.lipper@va.gov

RFI NO.: 02
DATE: 08/10/2020
REFERENCE:

REPLY NEEDED BY:

INFORMATION NEEDED:

· What is the desired top treatment for the roller shades?

· Finish key (sheet ID100) and Equipment Schedule (sheet A1400) have conflicting fabrics/styles listed. Should we assume Draper or Mecho are acceptable and all shades are double roller with a blackout shade and a 3% shade? Rooms A104 and A106 have roller shade “1” tag on drawings (sheet ID101) but these rooms are not included in the Finish Schedule (sheet ID100). Was this “1” tag intended to indicate the new wall construction?

REPLY:

· Painted metal fascia for roller shades.

· Manufacturers are listed solely as basis of design. All roller shades are to be double with a blackout shade and a 3” open shade. Disregard tag “1” in rooms A104 and A106 as those are an existing audio booth and control room with no access to the exterior windows.

REPLY FROM:

DATE:

ATTACHMENTS:

COPY TO: