IMS-RFI 01 response.docx

DOCX document 16 KB Posted

Attached to
Z1DA--Upgrade 1W Building 506-20-201
Solicitation number
36C25020B0046
Issued by

About this file

This document contains responses to a Request for Information (RFI) regarding a federal construction project to upgrade Building 1West at the Department of Veterans Affairs Ann Arbor VAMC medical center in Ann Arbor, Michigan. The contractor submitted questions to clarify details on drawings and specifications for items like foam insulation, concrete floor infills, wall blocking, and personnel requirements. The project involves renovating approximately 4,200 square feet of existing Audiology and ENT clinic space, and construction will adhere to building codes, VA standards, and energy efficiency guidelines. The period of performance is 180 calendar days from notice to proceed, with work likely commencing in fall 2020 at the specified medical center location. The VA contracting office will provide responses to questions around interpretation of specification requirements for site supervisors and managers.

View the file

Other files

File Type Posted
36C25020B0046 0004.pdf PDF
RFI 005 - Response.docx DOCX document
RFI 1 work hours - response.docx DOCX document
RFI 004 - response.docx DOCX document
S02RFIFORM50620201.docx DOCX document
WAGE DET MI20200100 08072020 REV3.pdf PDF
RFI 3 project phasing - response.docx DOCX document
RFI 2 New FCU with Existing Reheat Coil - Response.pdf PDF
IMS RFI 02 responseS.docx DOCX document
36C25020B0046 0003.pdf PDF
Contractor Addresses -.doc DOC document
RFI 001 (response).docx DOCX document
_506-20-201 VA Ann Arbor - 1W Upgrades - Addendum 01.pdf PDF
Sign In Sheet 506-20-201.pdf PDF
033000.pdf PDF
RFI Form 2 8-3-2020 - response.docx DOCX document
S04 - Pre-Bid Site Visit Agenda 506-20-201.pdf PDF
RFI 1. - Response.pdf PDF
36C25020B0046 0002.pdf PDF
36C25020B0046 0001.pdf PDF
Contractor EMR Certification Form 2020.docx DOCX document
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part2.pdf PDF
506-20-201_PROJECT MANUAL_VOL1_032019 SPECS.pdf PDF
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part3.pdf PDF
506-20-201_PROJECT MANUAL_VOL2_032019 SPECS.pdf PDF
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part1.pdf PDF
S02 506-20-201 1W Upgrades - 100 Percent DRAWINGS_Part4.pdf PDF
WAGE DET MI20200100 07032020 REV2.pdf PDF
S02 - RFI Form 506-20-201.docx DOCX document
36C25020B0046_1.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

36C25020B0046

PROJECT NUMBER:
506-20-201
Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents. When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.
PROJECT TITLE:
Upgrade Building 1West
PROJECT LOCATION:
Department of Veterans Affairs

Ann Arbor VAMC 2215 Fuller Road Ann Arbor, MI 48105

SUBMITTED BY:
IMS Contracting – Dale Lamarche
City/State:
Escanaba, MI.
PHONE NO.:
906-789-9021 Ext. 26

TO: Kyle Lipper kyle.lipper@va.gov

RFI NO.: 01
DATE: 07/29/2020
REFERENCE:

REPLY NEEDED BY:

INFORMATION NEEDED:

1. Ref drawing AI600- detail 4 and 6 call out foam in place insulation. No further details appear on wall type drawing GI003, 1st floor plan AE101 and no specification provided. Will foam in place insulation be required, and if so, will further details and specifications be provided? – foam in place insulation only at exterior wall conditions and window in-fill location.

1. Ref drawing AE001- will specifications be provided for concrete floor infills? – see attached spec section.

1. Ref drawing AI401B- Is wall blocking be required for equipment and bumper guard/handrail in wall cavities where walls and finishes are to remain? – where existing handrails are already installed, blocking will not be required. Where we call for new handrail to be installed, blocking will need to be installed. Provide fire treated blocking where new blocking is installed.

1. Ref specification 01 35 26, 1.7 D and spec 01 45 00, 3.4 A & B- Based on specifications a SSHO and QC manager are required to be onsite full time and need to be separate individuals. The CQC manager can have dual roles as the site superintendent but is required to be a graduate of engineering, architecture or construction management. My interpretation of the spec appears 2 full time managers are required at minimum and 3 full time managers are required if the superintendent does not have a degree in engineering, architecture or construction management. Please confirm my interpretation is correct as the spec appears overwritten for project of this size. – VA contracting to provide response.

REPLY:

REPLY FROM:

DATE:

ATTACHMENTS:

COPY TO:

File details come from the government source that posted it. Updated .