RFI 1 work hours - response.docx
DOCX document 32 KB Posted
- Attached to
- Z1DA--Upgrade 1W Building 506-20-201
- Solicitation number
- 36C25020B0046
About this file
This document contains a federal contract opportunity solicitation and related request for information correspondence. The solicitation is for project number VA# 506-20-201 to upgrade an existing Audiology and ENT clinic space of approximately 4,200 square feet on the first floor of Building 1W at the Ann Arbor VA Medical Center located at 2215 Fuller Rd, Ann Arbor, Michigan. The contractor shall provide all labor, materials, equipment, supervision, as-built documentation and other information to complete a renovation of the vacated space adhering to all building codes, VA standards, and LEED green facility requirements over a 180 calendar day period of performance beginning in Fall 2020. The correspondence involves a question regarding whether the work area will be occupied during construction and if off-hours or weekend work will be required, to which the resolution confirms the space is intended to be occupied and swing space as well as after hours and weekend work are specified in the bid documents.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Siemens Industry, Inc
Request for Information
| Job Name: |
| VA Ann Arbor 1 West Building 1W |
| Job Number: |
| VA# 506-20-201 |
| Requested By: |
| Richard A. Darnell |
| RFI Number: |
| 1 |
| Contact: |
| richard.darnell@siemens.com |
| Date: |
| 8/11/2020 |
| To: |
| VA Ann Arbor |
| Attn: |
| Kyle Lipper kyle.lipper@va.gov |
Spec. Number
| Sketch (if required) |
| Drawing: |
Rev:
| System: |
| Work hours |
| Location: |
| Bldg: |
| Bldg 1W |
Level:
Other Drawing Affected:
No:
| Cost Impact: |
| unknown |
| Time Delay: |
| No |
Description of Problem: Will the area being worked in be occupied during construction? If so, will the work have to be done during off hours and weekends?
Resolution of Problem:
Space is intended to be occupied during construction. Phasing drawings show swing space to be provided for staff during construction. After hours or weekend work is specified in the bid documents.
Accepted:
General Cont.:
Date:
Arch/Eng:
Date:
Unrestricted Unrestricted Revised 7/26/01 image1.wmf