This is an Itemized Schedule of Values cost breakdown template for a federal construction contract solicitation. The document provides a standardized Excel-based pricing template for bidders responding to solicitation 36C10F26B0001 for Phase 3 Expansion & Improvements - Additional Road Repairs at Fort Sam Houston National Cemetery in San Antonio, Texas. The template is structured to accommodate two bid items: BID ITEM I (CLIN 0001) for the Base Bid and BID ITEM II (CLIN 1001) for a Bid Option Additive, allowing the Department of Veterans Affairs to evaluate both the core project scope and optional enhancements.
The cost breakdown template requires bidders to segregate labor and material costs across 27 construction divisions using the MasterFormat classification system, including General Requirements, Concrete, Masonry, Metals, HVAC, Electrical, Earthwork, Exterior Improvements, and Transportation, among others. Bidders must enter division-level labor and material costs, which automatically calculate total divisional costs. The template then computes overhead, profit, and bond percentages as markups applied sequentially to the division subtotals, with the final calculation yielding the Total Base Bid Offer for each item. This is a blank template with all cost fields showing zero values, designed to be completed by offerors as part of their bid response to this Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation with an estimated project magnitude between $1,000,000 and $2,000,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offer Breakdown - BID ITEM I
36C10F26B0001 CLIN 0001 - Base Bid Offer Cost Breakdown
Project Number 846-045B Edward L Roy: VA assigned project #
| Date | |
| Project Title | Phase 3 Expansion & Improvements Additional Road Repairs |
Edward L Roy: VA assigned Project Title
| Project Location | Fort Sam Houston National Cemetery | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | $ - 0 | $ - 0 | $ - 0 |
| Division 3 | Concrete | $ - 0 | $ - 0 | $ - 0 |
| Division 4 | Masonry | $ - 0 | $ - 0 | $ - 0 |
| Division 5 | Metals | $ - 0 | $ - 0 | $ - 0 |
| Division 6 | Wood and Plastic | $ - 0 | $ - 0 | $ - 0 |
| Division 7 | Thermal & Moisture Protect | $ - 0 | $ - 0 | $ - 0 |
| Division 8 | Doors and Windows | $ - 0 | $ - 0 | $ - 0 |
| Division 9 | Finishes | $ - 0 | $ - 0 | $ - 0 |
| Division 10 | Specialties | $ - 0 | $ - 0 | $ - 0 |
| Division 11 | Equipment | $ - 0 | $ - 0 | $ - 0 |
| Division 12 | Furnishings | $ - 0 | $ - 0 | $ - 0 |
| Division 13 | Special Construction | $ - 0 | $ - 0 | $ - 0 |
| Division 14 | Conveying Equipment | $ - 0 | $ - 0 | $ - 0 |
| Division 21 | Fire Suppression | $ - 0 | $ - 0 | $ - 0 |
| Division 22 | Plumbing | $ - 0 | $ - 0 | $ - 0 |
| Division 23 | HVAC | $ - 0 | $ - 0 | $ - 0 |
| Division 26 | Electrical | $ - 0 | $ - 0 | $ - 0 |
| Division 27 | Communications | $ - 0 | $ - 0 | $ - 0 |
| Division 28 | Electronic Safety & Security | $ - 0 | $ - 0 | $ - 0 |
| Division 31 | Earthwork | $ - 0 | $ - 0 | $ - 0 |
| Division 32 | Exterior Improvements | $ - 0 | $ - 0 | $ - 0 |
| Division 33 | Utilities | $ - 0 | $ - 0 | $ - 0 |
| Division 34 | Transportation Subtotal | $ - 0 | $ - 0 | $ - 0 |
| Division Subtotals | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| $ - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | $ - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| $ - 0 | ||
| Overhead/Profit Subtotals | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Bid Offer $ - 0 $ - 0 $ - 0
Offer Breakdown - BID ITEM II
36C10F26B0001 CLIN 1001 - Bid Option Additive Offer Cost Breakdown
Project Number 846-045B Edward L Roy: VA assigned project #
| Date | |
| Project Title | Phase 3 Expansion & Improvements Additional Road Repairs |
Edward L Roy: VA assigned Project Title
| Project Location | Fort Sam Houston National Cemetery | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | $ - 0 | $ - 0 | $ - 0 |
| Division 3 | Concrete | $ - 0 | $ - 0 | $ - 0 |
| Division 4 | Masonry | $ - 0 | $ - 0 | $ - 0 |
| Division 5 | Metals | $ - 0 | $ - 0 | $ - 0 |
| Division 6 | Wood and Plastic | $ - 0 | $ - 0 | $ - 0 |
| Division 7 | Thermal & Moisture Protect | $ - 0 | $ - 0 | $ - 0 |
| Division 8 | Doors and Windows | $ - 0 | $ - 0 | $ - 0 |
| Division 9 | Finishes | $ - 0 | $ - 0 | $ - 0 |
| Division 10 | Specialties | $ - 0 | $ - 0 | $ - 0 |
| Division 11 | Equipment | $ - 0 | $ - 0 | $ - 0 |
| Division 12 | Furnishings | $ - 0 | $ - 0 | $ - 0 |
| Division 13 | Special Construction | $ - 0 | $ - 0 | $ - 0 |
| Division 14 | Conveying Equipment | $ - 0 | $ - 0 | $ - 0 |
| Division 21 | Fire Suppression | $ - 0 | $ - 0 | $ - 0 |
| Division 22 | Plumbing | $ - 0 | $ - 0 | $ - 0 |
| Division 23 | HVAC | $ - 0 | $ - 0 | $ - 0 |
| Division 26 | Electrical | $ - 0 | $ - 0 | $ - 0 |
| Division 27 | Communications | $ - 0 | $ - 0 | $ - 0 |
| Division 28 | Electronic Safety & Security | $ - 0 | $ - 0 | $ - 0 |
| Division 31 | Earthwork | $ - 0 | $ - 0 | $ - 0 |
| Division 32 | Exterior Improvements | $ - 0 | $ - 0 | $ - 0 |
| Division 33 | Utilities | $ - 0 | $ - 0 | $ - 0 |
| Division 34 | Transportation Subtotal | $ - 0 | $ - 0 | $ - 0 |
| Division Subtotals | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| $ - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | $ - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| $ - 0 | ||
| Overhead/Profit Subtotals | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Bid Offer $ - 0 $ - 0 $ - 0
File details come from the government source that posted it. Updated .