S02 013200 Construction Documentation.docx

DOCX document 21 KB Posted

Attached to
Y1DZ--NRM-CONST 526-22-115 - UPGRADE OR & PHARMACY DUMBWAITERS
Solicitation number
36C24226B0003
Issued by

About this file

This document is a Section 01 32 00 Construction Documentation file detailing requirements for contractors working on Veterans Health Administration (VHA) VISN 2 facilities. Contractors are mandated to utilize the Autodesk Construction Cloud (ACC) platform for project management and collaboration, with access and training provided at no cost by the VA. Key requirements include: requesting platform access within 14 days of contract award, completing mandatory online training within 12 calendar days, submitting staff information, and using ACC for all official project communications including RFIs, submittals, schedules, and site documentation.

The associated federal contract opportunity is a Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside solicitation for upgrading operating room and pharmacy dumbwaiters at the James J. Peters VA Medical Center in Bronx, NY. The project is classified under NAICS Code 236220 with a construction magnitude between $1-2 million, has a 270-calendar day completion timeline, and requires all bidders to be registered in SAM.gov and verified as SDVOSB. The scope involves replacing dumbwaiters in Building 100, with all work to be completed according to applicable federal, state, and local codes and VA directives.

View the file

Other files

File Type Posted
S06 SF30 36C24226B0003 0009.docx DOCX document
S05 RFI Questions and Answers 1-20-2026.docx DOCX document
S06 SF30 36C24226B0003 0008.docx DOCX document
S05 RFI Question and Answer 1-16-2026.docx DOCX document
S06 SF30 36C24226B0003 0007.docx DOCX document
S05 RFI Questions and Answers 1-12-2026.docx DOCX document
S06 Revised SOW Upgrade Dumbwaiters 12-17-2025.docx DOCX document
S05 RFI Questions and Answers 12-17-2025.docx DOCX document
S06 SF30 36C24226B0003 0006.docx DOCX document
S06 SF30 36C24226B0003 0005.docx DOCX document
S06 SF30 36C24226B0003 0004.docx DOCX document
SF30 36C24226B0003 0003.docx DOCX document
S05 Revised RFI Answers 11-18.docx DOCX document
SF30 36C24226B0003 0002.docx DOCX document
S06 Revised SOW - Upgrade OR and Pharmacy Dumbwaiters 11-5-2025.docx DOCX document
S04 IFB 36C24226B0003 UPGRADE DUMBWAITER PRE-BID SITE VISIT SIGN-IN SHEET.pdf PDF
S05 RFI Questions and Answers.pdf PDF
SF30 36C24226B0003 0001.docx DOCX document
S02 526-22-115 Drawings Upgrade SPD OR Dumbwaiters.pdf PDF
S02 Soliciation 36C24226B0003 10-24-2025.docx DOCX document
S02 526-22-115 VHA Specifications Upgrade SPD OR Dumbwaiters.pdf PDF
S02 Buy American Certificate blank.pdf PDF
S02 852.219-75 Limitation on Subcontracting Jan 2023- Blank.docx DOCX document
S02 WAGE DETERMINATION BRONX COUNTY.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

09-01-23

SECTION 01 32 00

CONSTRUCTION DOCUMENTATION

PART 1- GENERAL

1.1 DESCRIPTION:

A. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.

1.2 REQUIREMENTS:

A.Contractor shall accomplish and complete the following tasks upon award of contract:
1.Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award.
2.Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc.

3. The access request shall be in writing and include a list of staff. The list shall include the following information:

•Full Name
•Company Name
•Email Address
•Role/Position on the project (i.e., Project manager, site super)
4.Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days.
5.Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 Business days.
B.Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period.
C.Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above.
D.The contractor shall only use the ACC platform for all contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys.
E.Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform.
F.Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training.

‑ ‑ ‑ E N D ‑ ‑ ‑ 01 32 00 - 1