S05 RFI Questions and Answers.pdf

PDF 61 KB Posted

Attached to
Y1DZ--NRM-CONST 526-22-115 - UPGRADE OR & PHARMACY DUMBWAITERS
Solicitation number
36C24226B0003
Issued by

About this file

This document is a Request for Information (RFI) Questions and Answers for Project No. 526-22-115, which involves upgrading dumbwaiters in the Operating Room (OR) and Pharmacy at a VA facility. The document addresses four key contractor questions regarding project details, including potential asbestos abatement, rail replacement feasibility, material procurement lead times, and work scheduling requirements.

Key details include a 270-day Period of Performance (POP) that does not include potential material lead times, contractor responsibility for asbestos testing and abatement up to 400 square feet, and work timing restrictions. While most non-disruptive work can be performed during the day, sensitive areas like the pharmacy, Sterile Processing Service (SPS), and OR require after-hours and weekend work. The project involves replacing dumbwaiter rails in a small shaft, potentially requiring selective wall demolition, with any wall damage to be patched and painted to match existing conditions.

View the file

Other files

File Type Posted
S05 RFI Questions and Answers 1-20-2026.docx DOCX document
S06 SF30 36C24226B0003 0009.docx DOCX document
S05 RFI Question and Answer 1-16-2026.docx DOCX document
S06 SF30 36C24226B0003 0008.docx DOCX document
S06 SF30 36C24226B0003 0007.docx DOCX document
S05 RFI Questions and Answers 1-12-2026.docx DOCX document
S06 SF30 36C24226B0003 0006.docx DOCX document
S05 RFI Questions and Answers 12-17-2025.docx DOCX document
S06 Revised SOW Upgrade Dumbwaiters 12-17-2025.docx DOCX document
S06 SF30 36C24226B0003 0005.docx DOCX document
S06 SF30 36C24226B0003 0004.docx DOCX document
SF30 36C24226B0003 0003.docx DOCX document
SF30 36C24226B0003 0002.docx DOCX document
S05 Revised RFI Answers 11-18.docx DOCX document
SF30 36C24226B0003 0001.docx DOCX document
S06 Revised SOW - Upgrade OR and Pharmacy Dumbwaiters 11-5-2025.docx DOCX document
S04 IFB 36C24226B0003 UPGRADE DUMBWAITER PRE-BID SITE VISIT SIGN-IN SHEET.pdf PDF
S02 Soliciation 36C24226B0003 10-24-2025.docx DOCX document
S02 526-22-115 VHA Specifications Upgrade SPD OR Dumbwaiters.pdf PDF
S02 526-22-115 Drawings Upgrade SPD OR Dumbwaiters.pdf PDF
S02 WAGE DETERMINATION BRONX COUNTY.pdf PDF
S02 Buy American Certificate blank.pdf PDF
S02 852.219-75 Limitation on Subcontracting Jan 2023- Blank.docx DOCX document
S02 013200 Construction Documentation.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 526-22-115 Upgrade OR & Pharmacy dumbwaiters

RFI - Questions and Answers

Question#1 Is there any asbestos abatement on this project?

Answer: Please see drawing # GI-001, Note #19:

“ASBESTOS AND LEAD PAINT SURVEYS HAVE NOT BEEN INITIATED BY THE VA, SPECS ARE

INCLUDED FOR BOTH ITEMS IN CASE THEY ARE NEEDED IF ASBESTOS OR LEAD PAINT IS

DETECTED DURING THE DEMOLTIION OR CONSTRUCTION PHASES OF THE PROJECT.

COR TO BE NOTIFIED OF ANY SUSPICIOUS MATERIALS THAT MAY CONATAIN ASBESTOS

OR LEAD PAINT AND THE VA COR TO APPROVE ANY TESTING OR REMOVAL.”

The only concern is the CMU blocked removed for access panels. It’s highly doubtful that CMU would contain asbestos, but it’s not sampled on our O&M plan so it’s best to sample it prior to this project. The only potential concern is whether there is any sprayed-on fireproofing inside the shaft, which is also doubtful.

Contractor to proceed with testing during the demolition phase. If any hazardous material is found the contractor is responsible for the abatement up to 400 square feet. The contractor must include the abatement and testing line items cost detailed in their bid.

Question#2 Can you confirm the rails are to be removed and replaced? This is highly irregular and may be impossible given the dimensions of the existing hoistway.

Answer: It isn't impossible, the shaft is quite small and working in new track will require it to be installed in smaller sections and welded. The contractor can demolish some walls on the floors that the dumbwaiter passes by to get the rails inside the shaft but ANY DAMAGE

TO WALLS DURING DEMO/CONSTRUCTION SHALL BE PATCHED AND PAINTED TO MATCH

EXISTING TEXTURE AND PAINT COLORS

Question#3 Current lead times to obtain equipment from dumbwaiter manufacturers is often greater than one year. The entire POP for this project is 270 days, which would be impossible to meet if materials can’t be procured, which is entirely outside of the contractors’ control. Will the VA consider a POP extension once the material lead times are known?

Answer: The POP, which is 270 days, does not include the potential lead time to receive the dumbwaiters/materials.

Question#4 Is the entire job required to be performed after hours? This will dramatically increase pricing, and the majority of this work will not be disruptive to the facility. Can you confirm whether or not we can work during the day for non-disruptive work?

Answer: The work can be performed during the day as long as it is not disruptive to the facility but in sensitive areas like the pharmacy, SPS, and OR, the work must be done after hours and weekend. Please read the phasing notes drawing # GI-002 for more information.