S-DASOBO-00016770-Addendum_2.pdf

PDF 466 KB Posted

Attached to
ODVA Roseburg Veterans Home CM/GC
Solicitation number
S-DASOBO-00016770
Issued by
Douglas County, Oregon

About this file

This Solicitation Addendum #2 modifies RFP S-DASOBO-00016770 for the Oregon Department of Veterans Affairs' Roseburg Veterans Home Construction Manager/General Contractor (CM/GC) procurement. The addendum makes material changes to proposal submission requirements and cost proposal documentation, specifically amending the Preconstruction Phase Services section to clarify that services are estimated at a 5–9 month duration and replacing Attachment C (Cost Proposal Form) entirely with revised versions that eliminate the Schedule of Values requirement for General Conditions Work Monthly Cost and add column titles to the Direct or Reimbursable Costs table. Proposers must acknowledge receipt of this addendum by inserting its number in Attachment A, line item C.12, and must sign and return the addendum with their proposal by the closing date of November 19, 2026. All requests for clarification, change requests, and protests regarding this addendum must be received by the Department of Administrative Services (DAS) State Procurement Services by 5:00 PM PT on Tuesday, November 17, 2026, or they will not be considered.

The revised cost proposal structure requires proposers to submit: (A) a not-to-exceed Preconstruction Cost with hourly rates for CM/GC team and key personnel performing preconstruction services and other direct or reimbursable costs using Attachment C-1; (B) Construction Costs including the CM/GC Fee as a percentage of cost of work and Insurance and Bonding Costs with itemized Builder's Risk insurance breakouts; and (C) a proposed monthly cost for reimbursable General Conditions Work over an estimated 24-month duration with a detailed cost breakdown using Attachment C-2. The addendum specifies that General Conditions Work includes on-site project office expenses, personnel wages stationed at the project site, and approved travel and subsistence expenses, while excluding salaries of personnel at the CM/GC's principal office. The Owner reserves the right to procure Builder's Risk insurance at its sole discretion, and any Owner-provided coverage must be deducted from the contractor's insurance and bonding costs to prevent duplication, with subcontractors required to comply with this provision.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OregonBuys RFP # S-DASOBO-00016770 Page 1 of 1

RFP # S-DASOBO-00016770

SOLICITATION ADDENDUM # 2

This Solicitation Addendum modifies the RFP Documents only to the extent indicated herein. All other areas not specifically mentioned or affected by this Solicitation Addendum shall remain in full force. This Solicitation Addendum shall be added as a part of the Original Solicitation Document.

This Solicitation Addendum must be acknowledged by inserting its number on the appropriate blank lines in Attachment A, line-item C.12, and by providing all required signatures prior to Closing. Failure to do so may result in rejection of Proposal.

Requests for clarification, requests for change, and protests of Solicitation Addendum provisions addressed in this Solicitation Addendum must be received by DAS SPS by 5:00 PM (PT) on Tuesday, November 17, 2026, or they will not be considered. DAS SPS will not consider requests or protests of matters not added to or modified by this Solicitation Addendum.

The RFP Documents are modified as described below. New language is indicated by bold print and underlined.

Deleted language is indicated by strikethrough.

1. Amend RFP, Article IV – Proposal Information, Submission Procedures and Requirements, Section I – Proposal Submission and Content Requirements, Sub-section 2.c.i as follows:

(i) Preconstruction Phase Services: State the not-to-exceed Preconstruction Fee, including hourly rates for personnel who will be performing Preconstruction Phase Services and any other direct or reimbursable costs that will be included in Preconstruction Fee. Preconstruction Phase Services are estimated to be a 5- 9- month duration.

2. DELETE RFP Attachment C – Cost Proposal Form in its entirety and REPLACE with the following Attachment C – Cost Proposal Form, Addendum 2 attached to this Addendum.

Attachment C has been revised to remove the requirement to submit a Schedule of Values for Section C – Cost for General Conditions Work Monthly Cost and Attachment C-1 has been revised to add column titles to the Direct or Reimbursable Costs table, headers were updated.

This Solicitation Addendum constitutes a MATERIAL CHANGE to the Proposal; and it MUST BE SIGNED AND RETURNED WITH THE PROPOSAL ON THE CLOSING DATE AND TIME. ITS RECEIPT MUST ALSO BE

ACKNOWLEDGED BY INSERTING ITS NUMBER ON THE APPROPRIATE BLANK LINES IN

ATTACHMENT A, LINE ITEM C.12 OF THE PROPOSAL DOCUMENT.

Signature: ___________________________________________ Date: ____________________

Proposer Name: _________________________________________________________________ (Please Print)

RFP S-DASOBO-00016770 - Addendum 2

ATTACHMENT C

COST PROPOSAL FORM

Addendum 2

A. PRECONSTRUCTION COST

State the Not-to-Exceed Preconstruction Cost. Include hourly rates for personnel who will be performing Preconstruction Phase Services. Also include other direct or reimbursable costs that are used to calculate the Preconstruction Cost (Preconstruction Phase Services are estimated to be nine (9) month duration). Proposer must attach a rate schedule for CM/GC’s Team and Key Personnel responsible for performing Preconstruction Phase Services using the chart found in Attachment C-1 below.

Not-to-Exceed Preconstruction Cost $

B. CONSTRUCTION COSTS

• CM/GC FEE (as per Attachment D, Sample CM/GC Contract, Article 6, Section 6.3)

Percentage of the cost of the work %

• INSURANCE AND BONDING COST (as per Attachment D, Sample CM/GC Contract, Article 6, Section 6.3)

Total Cost of the work %

Provide breakout of all separate insurance and bonding costs that comprise the total percentage, above, including Builder’s Risk.

The Owner reserves the right to procure and maintain, at its sole discretion, a Builder’s Risk insurance policy for the Project. Proposers must itemize Builder’s Risk insurance costs separately in their proposal, including premiums, endorsements, and applicable deductibles. Coverage shall include, without limitation, insurance against the perils of fire (with extended coverage) and physical loss or damage including, without duplication of coverage, theft, vandalism, rigging and hoisting, terrorism, malicious mischief, collapse, earthquake, flood, windstorm, falsework, testing and startup, temporary buildings and debris removal including demolition occasioned by enforcement of any Legal Requirements, and shall cover reasonable compensation for Architect’s and Contractor’s services and expenses required as a result of such insured loss. Should the Owner exercise its right to provide such coverage, the awarded Contractor shall deduct the amount originally attributed to Builder’s Risk insurance from its insurance and bonding costs as set forth in this Cost Proposal. If Owner‑provided insurance covers any portion of the Contractor’s risk, the Contractor shall neither procure additional Builder’s Risk insurance for the same coverage nor include it in the proposal. Duplication of coverage is prohibited.

This provision supersedes any conflicting Builder’s Risk requirements in the Sample Contract Documents. In the event of Owner’s implementation, the awarded Contractor shall cooperate in transitioning to Owner‑provided insurance without revision to the work scope or schedule, except as expressly allowed by contract. The Contractor shall require all Subcontractors to comply with this provision. Any Subcontractor cost impacts resulting from the removal of Builder’s Risk must be deducted by the Contractor.

C. COST FOR GENERAL CONDITIONS WORK MONTHLY COST

State the proposed monthly cost for reimbursable General Conditions Work – see Attachment D, Sample CM/GC Contract, Article 8, Section 8.8). (General Conditions Work estimated to be a twenty-four (24) month duration).

General Conditions Work Monthly Cost: $

Proposer must attach a completed Cost for General Conditions Work Breakdown to show a breakout of the GC items included in its monthly cost (above) using the following chart in Attachment C-2 below.

ATTACHMENT C-1

Preconstruction Rate Schedule for CM/GC’s Team and Key Personnel

Hourly Rates Name Position Title Hourly Rate

Direct or Reimbursable Costs Cost Item Actual Cost

ATTACHMENT C-2

COST FOR GENERAL CONDITIONS WORK BREAKDOWN

General Conditions Work means that portion of the Work required to support construction operations at the jobsite not otherwise included in nor excluded from the Cost of the Work in accordance with Attachment D, Sample CM/GC Contract, Article 8 and 9, including the cost of expenses of Contractor’s offices at the job site (e.g. job trailer), telephone calls, communication devices, computers, software, vehicle cost, postage and parcel delivery charges, telephone and internet service at the Project site and reasonable petty cash expenses of the CM/GC’s office at the Project site which are solely for the benefit of the Work, and wages or salary of personnel assigned to the Project stationed at the site, or working on the project remotely if approved by Agency, as listed in the table below.

General Conditions Work includes that portion of the travel and subsistence expenses of the CM/GC's personnel determined by the Owner to be reasonable and necessary, at the Owner approved rates, incurred while traveling in discharge of duties connected with the Work. Additionally, CM/GC personnel who are scheduled to work at the Project site for less than six months may receive a subsistence per diem approved by Owner in accordance with State Travel Rules if their place of residence is greater than 60 miles from the Project site, provided no such personnel shall be entitled to such per diem reimbursement beyond such six-month period.

Salaries and other compensation of the CM/GC’s personnel stationed at the CM/GC’s principal office or offices other than the CM/GC’s office at the project site and expenses of the CM/GC’s principal offices and offices other than the Project Site office are not included in General Conditions Work and are governed by the applicable sections of the CM/GC contract.

CM/GC shall bill approved personnel time against the hours listed in the table; and, in no event shall CM/GC exceed the Not to Exceed maximum price of the General Conditions Work. Additionally, main office staff travel shall not be reimbursed unless approved in advance by the Owner and only to the extent allowed under the State of Oregon travel reimbursement guidelines (“State Travel Rules”) applicable to the Owner and only at approved State of Oregon travel rates.

This list will be finalized based on the CM/GC’s Proposal and reflected in the negotiated contract.]

The reimbursable General Conditions Work Costs are limited to those included in the table below:

Job-site Reimbursable Cost Description / Rates Hourly Billable Rate NTE

Superintendent

General Superintendent Senior Superintendent Superintendent Project Engineer (Field Engineer)

Project Management

Project Director Senior Project Manager Project Manager Project Engineer Project Coordinator

Scheduling Scheduler

Quality Support Quality Manager

Safety Supervisor Safety Manager

Document Reproduction As Needed/Recurring N/A

Postage As Needed/Recurring N/A

Meals & Petty Cash As Needed/Recurring N/A

Temporary Site/Field Offices S l i l

As Needed/Recurring N/A Sanitary Facilities for Field Offi

As Needed/Recurring N/A Project Signs, Directional and T Si

As Needed/Recurring N/A Field Office Furniture, Supplies, and Equipment As Needed/Recurring N/A

General Safety Signage, Gear, & Maintenance As Needed/Recurring N/A

Field Office Drinking Water As Needed/Recurring N/A

Field Office Internet Services As Needed/Recurring N/A

Field Office Electricity Billings As Needed/Recurring N/A

General Small Equipment Rental As Needed/Recurring N/A Truck Equipment Fuel and L b i

As Needed/Recurring N/A Superintendent Trucks As Needed/Recurring N/A

NTE TOTAL $

ADPD14.tmp
Percentage of the cost of the work %
Total Cost of the work %
Provide breakout of all separate insurance and bonding costs that comprise the total percentage, above, including Builder’s Risk.
The Owner reserves the right to procure and maintain, at its sole discretion, a Builder’s Risk insurance policy for the Project. Proposers must itemize Builder’s Risk insurance costs separately in their proposal, including premiums, endorsements, and...
This provision supersedes any conflicting Builder’s Risk requirements in the Sample Contract Documents. In the event of Owner’s implementation, the awarded Contractor shall cooperate in transitioning to Owner‑provided insurance without revision to the...

File details come from the government source that posted it. Updated .