About this file
This is Solicitation Addendum #1 to Oregon Department of Veterans Affairs RFP S-DASOBO-00016770 for the Roseburg Veterans Home Construction Manager/General Contractor project. The addendum modifies three key sections of the original RFP documents: (1) Similar Construction Project Experience requirements, reducing the required number of comparable projects from five to three projects of $50 million or more completed within the last seven years, with expanded requirements for detailed experience management narratives and correlation of proposed team members to project examples; (2) Qualifications of Proposed Personnel, requiring comprehensive organizational charts, two-page maximum resumes for all professional staff across project oversight, management, engineering, estimating, and onsite supervision, specified workload percentages during preconstruction and construction phases, and a guarantee that personnel with 50 percent or greater work commitment will maintain primary office locations within 60 miles of the project or satisfy proximity requirements through an approved staffing and on-site availability plan; and (3) Prevailing Wage Rates in the Early Work Amendment, confirming compliance with Oregon Revised Statutes 279C.800 through 279C.870 and Bureau of Labor and Industries wage rates for BOLI Region 2 (Clackamas/Douglas County), along with apprenticeship and outreach requirements. All modifications are indicated through bold and underlined new language and strikethrough deleted language. Proposers must acknowledge receipt of this material addendum by inserting its number in Attachment A, line item C.12, and provide all required signatures prior to the closing date; failure to do so may result in proposal rejection. Requests for clarification or protests regarding the addendum provisions must be submitted by 5:00 PM PT on November 6, 2026.
The addendum does not introduce new pricing structures or financial terms, as these remain governed by the original RFP documents establishing an Owner's Target GMP range of $69 million to $99 million to be negotiated during the preconstruction phase. No set-asides are established or modified by this addendum. The project is funded through $35 million in State appropriation with federal match funding (65% federal) through grant and appropriations, as outlined in the original opportunity. The addendum reinforces existing compliance obligations regarding prevailing wage rates, public works bonds, apprenticeship requirements, and Oregon COBID certification for subcontractor participation, with all requirements remaining the responsibility of the CM/GC. The proposal closing date remains November 19, 2026, as specified in the original RFP.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OregonBuys RFP # S-DASOBO-00016770 Page 1 of 2
RFP # S-DASOBO-00016770
SOLICITATION ADDENDUM # 1
This Solicitation Addendum modifies the RFP Documents only to the extent indicated herein. All other areas not specifically mentioned or affected by this Solicitation Addendum shall remain in full force. This Solicitation Addendum shall be added as a part of the Original Solicitation Document.
This Solicitation Addendum must be acknowledged by inserting its number on the appropriate blank lines in Attachment A, line-item C.12, and by providing all required signatures prior to Closing. Failure to do so may result in rejection of Proposal.
Requests for clarification, requests for change, and protests of Solicitation Addendum provisions addressed in this Solicitation Addendum must be received by DAS SPS by 5:00 PM (PT) on November 6, 2026, or they will not be considered. DAS SPS will not consider requests or protests of matters not added to or modified by this Solicitation Addendum.
The RFP Documents are modified as described below. New language is indicated by bold print and underlined.
Deleted language is indicated by strikethrough.
1. Amend RFP, Article IV – Proposal Information, Submission Procedures and Requirements, Section I – Proposal
Submission and Content Requirements, Sub-section 2.f.ii as follows:
(ii) Similar Construction Project Experience
• Provide a listing, in chronological order and in chart format, of the Proposer’s most recent similar projects of $50 million or more completed in the last seven (7) years (provide a list of five (5) three (3) or more). Information on these projects must include the following:
o Name of the owner, contact person, and current phone number;
o The architect, contact person, and current phone number;
o Location of the project and completion date;
o A brief description of the Project;
o Amount of initial contract award or negotiated GMP (if applicable);
o Final contract amount and total dollar amount of change orders; and o Description of any claims or pending claims relating to any of the listed Projects that resulted in litigation or arbitration and the disposition of such claims against Proposer.
o Correlation of team proposed and relation to project experience examples.
• Provide detailed experience in managing construction of the listed projects.
2. Amend RFP, Article IV – Proposal Information, Submission Procedures and Requirements, Section I – Proposal
Submission and Content Requirements, Sub-section 2.f.iv as follows:
(iv) Qualifications of Proposed Personnel
• Provide an organization chart showing your proposed staff for this Project, including all professional staff in the following areas: Project executive oversight; project management administration; engineering and estimating; and onsite construction supervision. Contractor shall ensure that all on-site team members are reflected on the organizational chart.
• Include resumes for all individuals listed in the chart, with a maximum length of two pages for each resume. Indicate the proposed percentage of each person’s total workload that will be allocated to this Project during Preconstruction Phase Services, and during Construction Phase Services. The resumes must include each person’s length of tenure with the firm, education, work history and prior work experience with similar projects, including similar public sector
OregonBuys RFP # S-DASOBO-00016770 Page 2 of 2
CM/GC projects.
• For those individuals who are not full-time assigned to this Project, describe in narrative form how and when they will work on the Project, as well as which other project responsibilities will fill their time. Additionally, describe the prior experience, if any, of the team members working with each other on projects of similar scope (please be specific) and the role that each team member will fill for this Project.
• By listing individuals in the Proposal and stating a percentage of each individual’s work time that will be allocated to the Project, the Proposer guarantees that these individuals will be available to work on the Project for the percentages shown. The Proposer also guarantees that any individuals listed in the Proposal as having a 50 percent or greater work commitment to the Project will have their primary office location within 60 miles of the Project or will satisfy the proximity requirement through a project-specific staffing and on-site availability plan. ODVA reserves the right to approve or reject any changes to the proposed personnel.
ODVA further reserves the right to request a substitution of personnel if ODVA determines that the substitution will be in the best interest of the State.
3. Amend RFP, Attachment D – Sample Construction Manager/General Contractor (“CM/GC”) Contract, Exhibit
D – Early Work Amendment to CM/GC Contract, Article 6 as follows:
6. Prevailing Wage Rates. The CM/GC and all subcontractors shall comply with the provisions of ORS 279C.800 through 279C.870, relative to Prevailing Wage Rates and the required public works bond, as outlined in Sections C.1, C.2 and G.2.3 of the General Conditions. The Bureau of Labor and Industries (“BOLI”) wage rates below (and any applicable amendments), which is incorporated herein by reference, apply to the Work authorized under this Early Work Amendment and to all future Work under the CM/GC Contract through the remainder of the Project:
____ _, 20__ Prevailing Wage Rates for Public Works Contracts in Oregon ____ _, 20__ Prevailing Wage Rate Amendments, This Project is subject to the Apprenticeship and Outreach, Recruitment and Retention Requirements set forth in ORS
279C.533. See in general: https://www.oregon.gov/boli/apprenticeship/pages/minimum-standards.aspx for the Apprenticeship and Outreach, Recruitment, and Retention Requirements
____ _, 20__ PWR Apprenticeship Rates, which can be downloaded at the following web address:
https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx
The Work will take place in Clackamas Douglas County, Oregon, BOLI Region 2 6 The CM/GC understands and agrees that the CM/GC remains responsible for meeting all State of Oregon BOLI requirements.
This Solicitation Addendum constitutes a MATERIAL CHANGE to the Proposal; and it MUST BE SIGNED AND RETURNED WITH THE PROPOSAL ON THE CLOSING DATE AND TIME. ITS RECEIPT MUST ALSO BE
ACKNOWLEDGED BY INSERTING ITS NUMBER ON THE APPROPRIATE BLANK LINES IN
ATTACHMENT A, LINE ITEM 12 OF THE PROPOSAL DOCUMENT.
Signature: ___________________________________________ Date: ____________________
Proposer Name: _________________________________________________________________ (Please Print) https://www.oregon.gov/boli/apprenticeship/pages/minimum-standards.aspx http://www.oregon.gov/boli/WHD/PWR/Pages/__________Index.aspx http://www.oregon.gov/boli/WHD/PWR/Pages/__________Index.aspx
6. Prevailing Wage Rates. The CM/GC and all subcontractors shall comply with the provisions of ORS 279C.800 through 279C.870, relative to Prevailing Wage Rates and the required public works bond, as outlined in Sections C.1, C.2 and G.2.3 of the Gener...