ODVA Roseburg Veterans Home CM/GC
Solicitation number
S-DASOBO-00016770
Issued by
Douglas County, Oregon

About this file

Clarification 3 Summary

This file is a Clarification 3 document issued by the Oregon Department of Veterans Affairs (ODVA) for RFP #S-DASOBO-00016770 regarding the Roseburg Veteran's Home Construction Manager/General Contractor (CM/GC) procurement. Issued on November 13, 2026, this clarification addresses twelve substantive questions submitted by prospective proposers regarding contract terms, proposal submission requirements, project scope, scheduling, environmental permits, and responsibility allocations. Key clarifications include confirmation that the owner will not include a Mutual Waiver of Consequential Damages; supplemental pages to the COBID Outreach form are permitted and excluded from page limits, while cost proposal supplemental pages are not; the Schedule of Values requirement has been removed per Addendum 2; utilities will be designed by the architect's consultants unless the trade involves a typical design-build system; and the preconstruction duration has been updated in Addendum 2. The document confirms that an environmental assessment and geotechnical report have been completed with no hazardous materials or contaminated soils identified, and that a State Removal-Fill Permit from the Department of State Lands is required for impacts to wetlands and ditch areas, with permit authorization anticipated in Q2 2027.

The clarifications establish that ODVA/Owner retains responsibility for DSL and Corps wetland permits, DEQ certifications, land use approvals, and building permits, while the CM/GC is responsible for normal trade permitting and deferred submittals. Adjacent development work by others may occur during the project schedule, requiring coordination. The Joint Permit Application was submitted to DSL on October 6, 2026, with compensatory mitigation proposed through mitigation credit purchases. These clarifications provide essential guidance to proposers regarding scope boundaries, permitting timelines, and contractual responsibilities prior to the November 19, 2026 proposal deadline.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Clarification 3 Date: November 13, 2026

RFP # S-DASOBO-00016770

ODVA Roseburg Veteran’s Home

1) Question: Is the owner is willing to include a Mutual Waiver of Consequential Damages in the contract should we be awarded the project.

Answer: The Owner has reviewed this request and prefers to maintain the contract language as drafted.

2) Question: May proposer use a font other than Times New Roman if the size and spacing are equivalent to Times New Roman 12pt?

Answer: The RFP does not state a required font for Proposals, only that the font used should be no smaller than Times New Roman size 12.

3) Question: May proposer attach supplemental pages to Attachment B (COBID Outreach form) to answer long form questions or to include a COBID trade partner plan? If so, will those pages be excluded from the overall page limit?

Answer: Yes, supplemental pages can be used to respond to Attachment B questions. Those supplemental pages are considered part of Attachment B and will be excluded from the page count limit.

4) Question: May proposer attach supplemental pages to Attachment C (Cost Proposal form) to support values entered in Attachment C-1 and C-2? If so, will those pages be excluded from the overall page limit?

Answer: No, Proposer should not include any additional attachments aside from those required in Attachment C.

5) Question: Attachment C, Item C (Cost for General Conditions Work Monthly Cost) requests a

“Complete Schedule of Values,” what additional information and cost breakdown is required beyond the information provided in Attachment C-2?

Answer: Please see update in Addendum 2. The Schedule of Values requirement has been removed.

6) Question: Section II.A. Project goals lists utility design and construction. Is design work anticipated to be included in proposer's scope of work?

Answer: Utilities will be designed by the Architects consultants. Unless a scope is a typical trade design build system (such as fire sprinklers) then CBTWO will be designers.

7) Question: The preconstruction duration per IV.I.2(c)(i) estimates 5 months. Attachment C estimates 9 months. The schedule duration under I.E shows March-December 2027. Please confirm which duration should be used for proposers NTE preconstruction fee calculations.

Answer: Please see the update to RFP IV.I.2(c)(i) in Addendum 2.

8) Question: The Civil sheets show proposed developments by others adjacent to the project. Is there an anticipated start date for this work, or will this work begin during the project schedule?

Answer: The start dates for this other work is not known but the work could begin during the work of the ODVA development so contractor should be prepared for coordination of activities

Clarification 3 Date: November 13, 2026

RFP # S-DASOBO-00016770

ODVA Roseburg Veteran’s Home

9) Question: Has contaminated soils investigation work been performed on the existing site or is this planned for the preconstruction services? Can a report be provided, and if not, will this scope fall under the Proposer’s scope of work or DAS/ODVA?

Answer: An environmental assessment of the site has taken place as well as a geotechnical report.

There were no hazardous materials or known contaminated soils identified at this time. If additional soil work is required, it would be part ODVA's scope and not the proposer.

10) Question: A joint permit application through DSL and the Corps is described in the RFP, however Attachment F indicates the Corp found none jurisdictional and DSL determination was pending. Please confirm if permitting through DSL is all that is required.

Answer: PBS/Apex is ODVA's environmental consultant. USACE has determined that the onsite wetlands and waters are not federally jurisdictional; therefore, a Section 404 permit from the Corps is not required. DSL took jurisdiction over Wetland 1, Wetland 2, and Ditch 2, and a state Removal-Fill Permit is required for the proposed impacts. The Joint Permit Application (JPA) was submitted to DSL on October 6, 2026. The DSL permit is currently anticipated in Q2 2027, subject to agency review and any requests for additional information. In addition, an MAO request was submitted to DEQ on October 6, 2026 for state water quality review associated with the proposed impacts to waters of the state.

11) Question: Has the wetlands permit application been submitted or approved and has a mitigation method been determined at this time?

Answer: The JPA was submitted to DSL on October 6, 2026 and is currently under agency review.

Permit authorization is anticipated in Q2 2027, subject to agency review and any requests for additional information. Compensatory mitigation is proposed through the purchase of mitigation credits.

12) Question: Supplemental General Condition SGC-6 requires the contractor apply for and obtain “permits required by the Contract Documents.” Please confirm that the DSL and Corps wetland permits, any DEQ certification, land use approvals, and the building permit are the Owner’s responsibility, and which, if any, fall to the CM/GC.

Answer: Yes, those identified in the question are the responsibility of ODVA/Owner. The CM/GC will be responsible for normal and customary trade permitting and deferred submittals to jurisdictions.