This Request for Quote (RFQ26006658) is issued by the Rhode Island Army National Guard for the installation of a cooling-dominant HVAC system at the Bristol Armory facility. The project involves furnishing and installing inverter-driven, air-source heat pump equipment to provide cooling to designated spaces and supplemental heating during shoulder seasons while maintaining the existing gas-fired hydronic boiler as the primary heat source. The system includes seven outdoor condenser units ranging from 0.5 to 6 tons (specifically: one 6-ton, one 4-ton, two 3-ton, three 2.5-ton, one 1-ton, and one 0.5-ton unit), matched indoor units selected based on room-by-room cooling loads, and independent zone controls with wireless and wall-mounted controllers. All work must be completed in an occupied building with coordination among ongoing operations and other trades. A non-mandatory pre-bid conference is scheduled for Friday, May 29, 2026, at 10:00 a.m. at 470 Metacom Avenue, Bristol, Rhode Island.
All HVAC equipment must operate on 208/230V single-phase power and comply with Build America, Buy America (BABA) requirements with a minimum of 65% domestic content, with documentation required upon submittal. The contractor is responsible for final system design, verification of field conditions, cooling load calculations, shop drawings, control information, equipment cut sheets, and complete system installation, testing, and commissioning. All materials and equipment must utilize R-410A refrigerant or an approved equivalent, meet manufacturer requirements and local codes, and coordinate with the existing hydronic heating system and solar systems. Equivalent equipment from approved manufacturers may be submitted for review. The contractor shall provide all labor, materials, equipment, supervision, supports, dunnage, vibration isolation, electrical disconnects, breakers, and whip connections necessary for a complete and operational system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VendorChangeDetailsReport_RFQ26006658_v4_Jul_22_26.pdf | ||
| RFQ26006658 Questions and Answers - final 07-22-2026.xlsx | XLSX spreadsheet | |
| RFQ26006658 Amendment 4 dated 07-22-2026.docx | DOCX document | |
| RFQ26006658_May_22_26_solicitation_doc.pdf | ||
| RFQ26006658_Aug_3_26_solicitation_doc.pdf | ||
| RFQ26006658 Amendment 2 dated 06-17-2026.docx | DOCX document | |
| Screenshot 2026-07-17_BristolArmory_480_277_MSB1.png | PNG image | |
| RFQ26006658_May_29_26_solicitation_doc.pdf | ||
| RFQ26006658 Amendment 3 dated 07-03-2026.docx | DOCX document | |
| RFQ26006658 Amendment 1 dated 05-29-2026.docx | DOCX document | |
| Bristol_HVAC_LayOut.pdf | ||
| RFQ26006658_Jul_20_26_solicitation_doc.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2021-1.A Page 1 of 4 Revised 01/17/2023
AGENCY SOLICITATION SPECIFICATIONS
RFQ – REQUEST FOR QUOTE PUBLIC WORKS
HEADER RHODE ISLAND ARMY NATIONAL GUARD
TITLE: RFQ26006658 BRISTOL ARMORY HVAC
SECTION A. BACKGROUND
The Rhode Island Army National Guard is undertaking improvements to upgrade the facility’s cooling capabilities and provide limited supplemental heating.
The building is currently heated by a gas-fired hydronic (hot water) boiler system, which shall remain the primary heat source.
This project introduces new ductless/multi-zone systems to provide:
• Cooling to all designated spaces
• Supplemental heat during shoulder seasons or as needed
Work will be accomplished in an occupied building. All work shall be coordinated with ongoing operations and other trades.
SECTION B: SCOPE OF WORK AND REQUIREMENTS
The contractor shall provide all labor, materials, equipment, and supervision necessary to install a complete and operational HVAC system.
1. Outdoor Units (Condensers)
Provide and install the following Mitsubishi Electric equipment: or equal
• (1) – 6 Ton Heat Pump Condenser o Model: PUZ-A72NKA7
• (1) – 4 Ton Heat Pump Condenser o Model: PUZ-A48NKA7
2021-1.A Page 2 of 4 Revised 01/17/2023
• (2) – 3 Ton Heat Pump Condensers o Model: PUZ-A36NKA7
• (3) – 2.5 Ton Heat Pump Condensers o Model: PUZ-A30NKA7
• (1) – 1 Ton Heat Pump System o Model: MUZ-GL12NA
• (1) – 0.5 Ton Heat Pump System o Model: MUZ-GL06NA
General Notes
• All systems shall be standard heat pump (non-hyper heat).
• Equipment shall be used for supplemental heating only.
• Contractor shall provide matching indoor units, controls, and all required accessories for a complete and operational system.
• Equivalent equipment by approved manufacturers may be submitted for review.
Installation Requirements
• Condensing units shall be installed on the low roof where applicable, unless otherwise approved.
• Provide all supports, dunnage, and vibration isolation.
• Maintain manufacturer-required clearances and service access.
2. Indoor Units
Provide indoor units to match system requirements.
Acceptable Types
• Wall-mounted units: MSZ-GS Series
• Ceiling cassette units:
o MLZ-KP (1-way) o SLZ-KA (4-way) Requirements
• Capacities shall be selected based on room-by-room cooling loads.
• Systems shall be designed primarily for cooling performance.
• Each unit shall provide:
o Independent temperature control.
o Proper air distribution for space.
2021-1.A Page 3 of 4 Revised 01/17/2023
3. Controls
• Provide manufacturer standard controls for all systems.
• Each zone shall have independent control.
• Provide wireless controllers for each indoor unit.
• Provide wall-mounted wired controllers in common and shared spaces.
4. Electrical
All HVAC equipment shall operate on 208/230V, single-phase power.
Contractor shall:
• Verify existing electrical capacity.
• Provide all disconnects, breakers, and whip connections.
• Coordinate with other trades and solar systems.
5. System Requirements
All systems shall:
• Be inverter-driven
• Utilize R-410A refrigerant (or approved equivalent).
• Be standard efficiency (non–Hyper Heat) systems.
• Be suitable for cooling-first operation with supplemental heating only.
• Be installed per manufacturer requirements and local codes.
6. Buy America / BABA Compliance
All materials and equipment shall comply with Build America, Buy America (BABA) requirements:
• Minimum 65% domestic content.
• Contractor shall provide documentation upon submittal submission.
7. General Requirements
• Contractor responsible for final system design and coordination.
• Verify all field conditions prior to installation.
• Coordinate with existing hydronic heating system.
• System shall be installed complete, tested, and operational.
8. Submittals
• Equipment cut sheets.
• Cooling load calculations.
• Shop drawings and layout.
2021-1.A Page 4 of 4 Revised 01/17/2023
• Control information.
9. Coordination
• Coordinate with Owner and all trades.
• Minimize disruption to building operations.
• Ensure proper startup and commissioning system.