RFQ Number - 72066924Q00002- Medical Depots_23APR2024.pdf
PDF 2 MB Posted
- Attached to
- Rehabilitation of Two (2) Pharmaceutical Depots/Warehouses in Grand Gedeh and River Gee Counties
- Solicitation number
- 72066924Q00002-Rehabilitation-HealthDepots
About this file
This document is a Request for Quotations (RFQ) for the Rehabilitation of Two (2) Pharmaceutical Depots/Warehouses in Grand Gedeh and River Gee Counties, Liberia. The United States Agency for International Development (USAID) is seeking quotations from local construction firms to rehabilitate these two medical depot facilities.
The scope of work includes completely replacing damaged ceiling systems, tiling floors and walls, addressing mechanical/electrical/plumbing systems, replacing or rehabilitating windows and doors, supplying and installing air-conditioning, repairing wall cracks and floors, repainting, installing shelving/racking, and replacing or repairing the roofing system. USAID anticipates awarding one Firm-Fixed-Price contract with a 12-month period of performance, including 9 months of construction and a 3-month defects liability period. The estimated cost range for the required construction is between $100,000 and $250,000. Quotations are due by June 10, 2024 at 11:00 am Monrovia time. A mandatory site visit is scheduled for May 15, 2024 at 10:00 am Monrovia time.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Issuance Date: April 23, 2024
Site Visit: May 15, 2024, 10:00am, Monrovia Time
Questions Due Date/Time: May 23, 2024, 11:00 am, Monrovia Time
Anticipated Date of Response to Questions: May 28, 2024
Quotation Due/Closing Date/Time: June 10, 2024, 11:00 am, Monrovia Time
Subject: Rehabilitation of Two (2) Pharmaceutical Depots/Warehouses in Grand Gedeh and
River Gee Counties
Dear Prospective Offerors:
The United States Government, represented by the U.S. Agency for International Development
(USAID), is requesting quotations for a project to Rehabilitate two (2) Pharmaceutical
Depots/Warehouses in Grand Gedeh and River Gee Counties, Liberia, for a twelve (12) month period.
USAID anticipates awarding one (1) Firm-Fixed-Price (FFP) contract as a result of this RFQ.
The contract will cover a period of twelve (12) months (nine (9) months of construction and three
(3) months of defect Liability period) subject to satisfactory performance. USAID estimates that the cost range for the required construction is between $ 100,000.00 and $ 250,000.00. The offeror must propose prices that are realistic and reasonable for the work described herein.
Site Visit: The Site Visit is mandatory and will be held on the date specified above. Offerors are required to visit the sites to fully understand current conditions of the existing project sites and to understand potential risks, challenges, and intricacies of the project that may impact the bid or quotation costs.
Offerors must submit quotations in accordance with Section L of this RFQ. The Offeror must also carefully review Section M – Evaluation Factors for Award. Sections B through I of the RFQ will become a substantive part of the anticipated contract with blanks to be completed by the
Contracting Officer upon award.
Questions and comments related to this RFQ must be submitted electronically no later than the question(s) due date/time stated above, to Ruth D. Caesar-Hne, Senior Contracts
Specialist/Administrative Contracting Officer at rcaesar-hne@usaid.gov with a copy to Karen
Cox, Senior Acquisition & Assistance Specialist at kcox@usaid.gov. No questions will be accepted after this date.
It is the responsibility of the recipient of this RFQ document to ensure that it has been received in its entirety, including subsequent RFQ amendments, if any. USAID bears no responsibility for data errors resulting from transmission or conversion processes.
Request for Quotation (RFQ) Number: 72066924Q00002
Rehabilitation of Two (2) Pharmaceutical Depots/Warehouses in
Grand Gedeh and River Gee Counties
Issuance of this RFQ does not obligate the United States Government to award a contract, nor does it commit the U.S. Government to pay for any costs incurred during the preparation or submission of quotations. Furthermore, the U.S. Government reserves the right to reject any and all offers, if such action is considered to be in the best interest of the U.S. Government.
The U.S. Government reserves the right to award this contract without discussions.
Should discussions be determined necessary, discussions will be held in accordance with FAR
15.306.
Sincerely, Garth Patterson
Contracting Officer
TABLE OF CONTENTS
B.1 PURPOSE
B.2 CONTRACT TYPE
B.3 FIXED PRICE CONSTRUCTION SERVICES SCHEDULE
B.4 METHOD OF PAYMENT AND SCHEDULE OF VALUES
C.1 PURPOSE
C.2 BACKGROUND
C.3 OBJECTIVES
C.4 SCOPE OF WORK (SOW)
C.5 QUALITY CONTROL SYSTEM
C.6 REMEDIAL WORK
C.7 WORK PLAN
C.8 POST AWARD MEETING
C.9 DATA RIGHTS
C.10 CONSTRUCTION MEETINGS
C.11 SOURCE OF SUPPLY AND QUALITY OF SOURCE MATERIALS
C.12 SAFETY PROGRAM AND SAFETY PLAN
C.13 GENERAL SAFE WORK PRACTICES
C.14 PRIVATE SECTOR AND STAKEHOLDER ENGAGEMENT
C.15 ENVIRONMENTAL MITIGATION AND MONITORING
C.16 GENDER CONSIDERATIONS
C.17 CLIMATE RISK MANAGEMENT
C.18 SUSTAINABLE CONSTRUCTION
D.1 AIDAR 752.7009 MARKING (JAN 1993)
D.2 BRANDING
D.3 BRANDING STRATEGY, IMPLEMENTATION PLAN AND MARKING PLAN
E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE ..18
E.2 INSPECTION AND ACCEPTANCE/RESPONSIBLE OFFICIAL
F.1 PLACE OF PERFORMANCE
F.2 PERIOD OF PERFORMANCE
F.3 SCHEDULE OF DELIVERABLES AND REPORTS
F.4 REPORTS AND DELIVERABLES OR OUTPUTS
F.5 INSPECTION, SURVEYS OR TESTING
F.6 52.246-12 - INSPECTION OF CONSTRUCTION (AUG 1996)
F.7 SUBSTANTIAL COMPLETION
F.8 CONSTRUCTION WARRANTY (DEFECTS LIABILITY)
F.9 FINAL CONSTRUCTION ACCEPTANCE
F.10 SUBMITTAL AND REVIEW PROCESS
F.11 CONSTRUCTION PHOTOGRAPH
F.12 KEY PERSONNEL
F.13 RETAINAGE - FAR 52.232-5 (e)
F.14 LIQUIDATED DAMAGES - CONSTRUCTION - FAR 52.211-12
F.15 SCHEDULES FOR CONSTRUCTION CONTRACTS - FAR 52.236-15
F.16 SUSPENSION OF WORK - FAR 52.242-14
G.1 ADMINISTRATIVE CONTRACTING OFFICE
G.2 CONTRACTING OFFICER’S REPRESENTATIVE
G.3 CONTRACTOR’S GENERAL POINT OF CONTACT
G.4 PAYING OFFICE
G.5 ACCOUNTING AND APPROPRIATION DATA
G.6 CONTRACTOR'S PAYMENT ADDRESS
G.7 TECHNICAL DIRECTIONS/RELATIONSHIP WITH USAID
G.8 MODIFICATION AUTHORITY
H.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE..35
H.3 LANGUAGE REQUIREMENTS
H.4 EXECUTIVE ORDER ON TERRORISM FINANCING (FEB 2002)
H.5 GENDER REPORTING
H.7 RIGHT TO PROCURE FROM OTHER SOURCES
H.8 MAXIMIZING USE OF LOCAL ENTITIES
H.9 AIDAR 752.225-70 SOURCE AND NATIONALITY REQUIREMENTS (FEB 2012) .37
H.10 ADS 302.3.5.9 NONDISCRIMINATION (June 2012)
H.11 CORRESPONDENCE IDENTIFICATION
H.12 ADS 302.3.5.14 STANDARDS FOR ACCESSIBILITY FOR THE DISABLED IN
USAID CONSTRUCTION CONTRACTS (July 2007)
H.13 DISCLOSURE OF INFORMATION
H.15 PROHIBITION ON THE USE OF FEDERAL FUNDS TO PROMOTE, SUPPORT,
OR ADVOCATE THE LEGALIZATION OR PRACTICE OF PROSTITUTION–
TIP ACQUISITION (MAY 2007)
H.16 VOLUNTARY POPULATION PLANNING ACTIVITIES (JUNE 2008)
H.17 ORDER OF PRECEDENCE
H.18 ADS 302.3.5.17 LIMITATION ON SUBCONTRACTING TO NON-LOCAL
ENTITY
I.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE ...43
I.2 COMBATING TRAFFICKING IN PERSONS (Nov 2021)
I.3 52.204-13 – SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
I.4 FAR 52.236-2 - DIFFERING SITE CONDITIONS (APR 1984)
I.5 52.236-3 - SITE INVESTIGATION AND CONDITIONS AFFECTING THE
WORK (APR 1984)
I.6 FAR 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
I.7 FAR 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
I.8 FAR 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
I.9 FAR 52.236-8 OTHER CONTRACTS (APR 1984)
I.10 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,
EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)
I.11 FAR 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
I.12 FAR 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
I.13 FAR 52.236-12 CLEANING UP (APR 1984)
I.14 FAR 52.236-13 ACCIDENT PREVENTION (NOV 1991)
I.15 FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984) ...62
I.16 FAR 52.236-16 QUANTITY SURVEYS (APR 1984)
I.17 FAR 52.236-17 LAYOUT OF WORK (APR 1984)
I.18 FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(FEB 1997) ALTERNATE II (FEB 1997)
I.19 FAR 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
I.20 AIDAR 752.202-1 DEFINITIONS ALT 70 JAN 1990
I.21 AIDAR 752.236-70 STANDARDS FOR ACCESSIBILITY FOR THE DISABLED IN
USAID CONSTRUCTION CONTRACTS (JULY 2007)
I.22 AIDAR 752.242-70 PERIODIC PROGRESS REPORTS (OCT 2007)
I.23 AIDAR 752.245-70 GOVERNMENT PROPERTY—USAID REPORTING
REQUIREMENTS (JULY 1997)
I.24 AIDAR 752.245-71 TITLE TO AND CARE OF PROPERTY (APR 1984)
I.25 AIDAR 752.7013 CONTRACTOR-MISSION RELATIONSHIPS (OCT 1989)
I.26 AIDAR 752.7025 APPROVALS (APR 1984)
I.27 AIDAR 752.7027 PERSONNEL (DEC 1990)
SECTION J – ATTACHMENTS
SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER
STATEMENTS OF OFFERORS OR RESPONDENTS
L.1 GENERAL
L.2 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED
BY REFERENCE
L.3. 52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
L.4 52.216-1 TYPE OF CONTRACT (APR 1984)
L.5. FAR 52.236-27 - SITE VISIT ALT I (CONSTRUCTION) (FEB 1995)
L.6. QUESTIONS AND CLARIFICATIONS:
L.7. GENERAL INSTRUCTIONS TO OFFERORS
L.7.9. DELIVERY INSTRUCTIONS
L.8. TECHNICAL QUOTATIONS
L.9 PRICE QUOTATION
M.4 EVALUATION OF PRICE QUOTATIONS
SECTION B - SERVICES PRICES
B.1 PURPOSE
The purpose of this contract is to procure the services of a local construction firm to provide construction services for the rehabilitation works at the Ministry of Health (MOH) County Depots in Grand Gedeh and River Gee Counties as specified in Section C of this Request for Quotations
(RFQ).
B.2 CONTRACT TYPE
This award will be a Firm-Fixed-Price Contract. Firm-Fixed-Price Contracts provide for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. For the consideration set forth in the contract, the contractor must provide the deliverables described in Section C and Section F.
B.3 FIXED PRICE CONSTRUCTION SERVICES SCHEDULE
The contractor is responsible to provide all the resources necessary to complete the requirements as described below at the Firm Fixed Price.
B.3.1
NO DESCRIPTION
OF WORKS
QTY UNIT TOTAL
FIXED
PRICE
01 Mobilization & demobilization
(20% of the total price of Items No.
02 – 03 below)
1 JOB
02 Rehabilitation of
River Gee County
Medical Depot
1 JOB
03 Rehabilitation of
Grand Gedeh
County Medical
Depot
1 JOB
TOTAL FIXED
PRICE
B.4 METHOD OF PAYMENT AND SCHEDULE OF VALUES
Payment will be made in accordance with Section G.5, FAR Clauses 52.232-5, Payments under
Fixed-Price Construction Contracts (MAY 2014) and FAR 52.232-27, Prompt Payment for Construction Contracts (JAN 2017).
[END OF SECTION B]
SECTION C – DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK
STATEMENT OF WORK
C.1 PURPOSE
The purpose of this mechanism is to procure the services of a local construction firm to rehabilitate two (2) Pharmaceutical Depots/Warehouses in Grand Gedeh and River Gee Counties.
USAID/Liberia is utilizing the Mission A&E Services Task Order (TO2), Green Power
Technology (GPT), to provide engineering designs and construction oversight services.
C.2 BACKGROUND
USAID/Liberia, through its Health Office, is procuring malaria, family planning, and other vital medicines and supplies via the Global Health Supply Chain Program - Procurement and Supply
Management (GHSC-PSM) activity. These items are stored at the Central Medical Stores and subsequently distributed to county depots, public health facilities, and community health programs.
The structures at the county depot have deteriorated and require immediate renovation. Repairing wall cracks and addressing infrastructure defects at these facilities will demonstrate USAID’s commitment to improving health facility infrastructure and ensuring proper storage of pharmaceutical supplies. The efficacy of drugs and bed nets is currently jeopardized by potential exposure to excessive heat or water due to the poor condition of the infrastructure.
To tackle these issues, USAID will fund the rehabilitation of two (2) medical depots in Grand
Gedeh and River Gee Counties.
C.3 OBJECTIVES
The objective of this award is to procure the services of a local construction firm to provide construction services at two (2) Ministry of Health County Depots/Warehouses located in Grand
Gedeh and River Gee Counties as specified in the Statement of Work (SOW), Specifications and
Drawings attached to this RFQ.
C.4 SCOPE OF WORK (SOW)
The contractor must provide all supervision, labor, materials, camps, equipment and all other provisions, whether of a temporary or permanent nature, required to execute and complete the works in accordance with the design. This will include, but not be limited to, the rehabilitation of two (2) medical depots in two (2) counties (Grand Gedeh and River Gee) in Liberia. The contractor must implement the works in accordance with the following requirements, but not limited to:
1. The contractor must provide all services required for all construction activities, construction means and methods, coordination, logistics, testing, and surveys.
2. The contractor must provide experienced managers, engineers, foremen, surveyors, material technicians, and other technical staff, together with all transport, instruments, and equipment, to always ensure adequate supervision and execution of the works.
3. Upon issuance of the Notice to Proceed (NTP), the contractor must provide the following services during the construction period specified in Section F: REPORTS AND
DELIVERABLES OR OUTPUTS:
The construction project will involve renovating and expanding drug depots for the Ministry of
Health. This encompasses completely replacing damaged ceiling systems, including ceiling tiles, strips, and ceiling noggins. Tiling works will be carried out, involving installing floor and wall tiles in necessary areas and rehabilitating any demolished or cracked tiles. Mechanical, electrical, and plumbing (MEP) systems will be addressed, along with replacing or rehabilitating windows
(jalousie, wooden, or sliding) and doors, including frames, locks, and hinges.
Additionally, the project will include supplying and installing an air-conditioning system, repairing wall cracks, rehabilitating concrete floors with cracks, or sinking, repainting the building internally and externally (including applying anti-rust treatment to metal doors and security bars), installing shelving and racking, and replacing or repairing the damaged roofing system, among other necessary tasks.
The contractor must provide all the resources necessary for the construction of all works. The
Period of Performance (POP) of the activity shall be executed over a twelve (12) month period sequentially. The construction period shall be nine (9) months and the defects liability period shall be three (3) months. The three (3) months defects liability period shall cover the repair of completed components of all works which are deemed to have fallen into disrepair because of construction related defects and not normal wear and tear or misuse because of occupancy during the defect liability period.
C.5 QUALITY CONTROL SYSTEM
The contractor is to establish and maintain an effective Quality Control (QC) system in compliance with contract FAR Clause 52.246-12, Inspection of Construction. The QC system must consist of plans, procedures, and organization necessary to produce a product which complies with the contract requirements. The QC system must cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence.
The contractor, in compliance with the contract documents, shall provide quality control to ensure that all work adheres to the applicable standards and specifications of this contract. The contractor must prepare a Quality Control Plan and submit it to the USAID Contracting Officer’s
Representative (COR) for approval.
C.6 REMEDIAL WORK
When any part of the works, or any equipment or material, is found upon examination by the COR to not be in conformity to the requirements, or is at any stage before final acceptance, damaged so that it no longer conforms to the requirements, the COR shall order its complete removal and replacement, at no additional cost to USAID.
C.7 WORK PLAN
The contractor shall submit a work schedule, in accordance with Section F: REPORTS AND
DELIVERABLES OR OUTPUTS. Deliveries or Performance, utilizing the Critical Path
Method (CPM), for COR approval. During progression of work, the contractor shall identify the work is completed and reflect the progress relative to the construction schedule. The contractor shall provide information on the following:
Should the schedule of any of the activities, services or deliverables provided in this contract deviate from the contractual timeframes, the contractor shall immediately submit to the COR, with a copy to the Contracting Officer (CO), a schedule recovery plan. The cause of the delay(s), disruption(s), or interruption(s) shall be identified in the narrative, and the narrative shall provide an explanation of the work affected and the proposed corrective action to meet the milestone dates involved or to mitigate potential delays or disruptions.
No revision to the accepted milestones in the approved work plan shall be made without prior written approval of the COR. The contractor shall submit all requests for project work plan revisions in writing to the COR, with a copy to the CO, with justification and such supporting evidence, as USAID deems necessary, for a CO determination.
C.8 POST AWARD MEETING
Within fifteen (15) days after award, USAID will conduct a post award meeting to discuss and develop a mutual understanding relative to the details of the administration and execution of the contract. Participants will include the COR, the Contracting Officer, the
Quality Assurance Contractor (QAC), the contractor, and representatives from the relevant Government of Liberia Agency/Ministry, if necessary. Following the post award meeting a subsequent site hand over meeting will be conducted at the site. Both the contractor and the USAID COR will nominate a date for the site handover meeting: however, it is within the purview of the USAID COR to decide on the date of the site handover meeting.
C.9 DATA RIGHTS
USAID shall have unlimited rights to all as-built design documents as part of this contract and all other works developed in the performance of this contract that allows USAID to use said documents on any other design or construction project anywhere in the world without approval from, or additional compensation paid, to the contractor.
C.10 CONSTRUCTION MEETINGS
A recurring meeting shall be held at the job site as determined by the COR. The typical timeframe will be monthly, and attendance will at a minimum, include the COR or the Alternate COR, QAC, representatives from the Government Agency/Ministry, the contractor and/or other USAID invited observers. The purpose of the meeting will be to evaluate work progress, detail work plans for the upcoming month, as well as discuss issues relative to the implementation of the
Quality Control Plan, Safety and Health Plan, and the Environmental Monitoring and Mitigation
Plan (EMMP) provided in the Inception Report. Other agenda will be added as appropriate.
C.11 SOURCE OF SUPPLY AND QUALITY OF SOURCE MATERIALS
The contractor must furnish only new materials for incorporation into the work, except as specifically otherwise permitted in the contract. Materials shall be manufactured, handled, and used in a competent manner to ensure that completed work complies with the terms of the contract. Materials to be used in the work shall be subject to inspection of the COR or the QAC.
The quality of all materials shall conform to that specified in the “Technical Specifications”.
Manufacturers' test reports may supplement the contractor inspections, sampling, testing, and certification provisions. Manufacturers’ warranties, guarantees, instruction sheets, parts lists, and other material that are furnished with certain articles or materials incorporated into the work shall be delivered to USAID prior to project acceptance.
The contractor must store the materials to be installed and incorporated into the work in such a manner as to ensure the preservation of their quality and fitness for the work, and to facilitate inspection. Storage shall comply with environmental requirements.
C.12 SAFETY PROGRAM AND SAFETY PLAN
The contractor must provide all safety gears, communications, and transportation of materials, personnel, and equipment to maintain the safety and security of its personnel, materials, and equipment.
The contractor must be prepared to take appropriate actions in order to provide for its own safety and security and that of its employees. The contractor must avail itself of authorized safety and security protections and services. The contractor must continuously monitor the safety and security situation and update its comprehensive safety and security plan by means of qualified and competent staff.
The contractor must implement safety measures to accomplish the work in the safest manner possible at the work site(s). The contractor’s safety program must define roles, responsibilities, programs, policies, and procedures to accomplish the goal of achieving superior safety performance during all phases of the project.
C.13 GENERAL SAFE WORK PRACTICES
The contractor must establish standard operating procedures for the project to guide employees in safe work practices. These standard operating procedures shall be included in the Inception
Report, as described in Section F: REPORTS AND DELIVERABLES OR OUTPUTS. All employees, including managers and supervisors, must have training and instruction on general and job-specific safety and health practices. Workplace safety and health training practices shall, at a minimum, include the following:
1. Explanation of contractor's site safety and health and measures for reporting any unsafe conditions, work practices, and injuries.
2. Use of appropriate clothing, including gloves, footwear, and personal protective equipment.
3. Information about chemical hazards to which employees could be exposed and other hazard communication program information.
4. Availability of toilet, handwashing, and drinking water facilities.
5. Provisions for medical services and first aid, including emergency procedures.
In addition, the contractor must provide specific instructions to each employee regarding hazards unique to his or her job assignment, to the extent that such information was not already covered in other training. The contractor must establish written safe work practices covering all phases of the work. Safety, quality and all other project programs and requirements that are placed upon the prime contractor shall all be required of all subcontractors.
C.14 PRIVATE SECTOR AND STAKEHOLDER ENGAGEMENT
USAID's approach in Liberia prioritizes engaging the private sector and stakeholders to foster sustainable development. By leveraging existing models and innovative financing solutions, USAID aims to integrate the private sector into infrastructure projects, ensuring beneficial impacts for society. This engagement includes exploring collaboration opportunities with local businesses and institutions to accelerate development interventions. Through coordinated efforts with contractors, USAID seeks to identify and support initiatives that align with Liberia's development goals, ultimately driving progress and prosperity for the country.
C.15 ENVIRONMENTAL MITIGATION AND MONITORING
The contractor is solely responsible for the remedy or mitigation measure(s) required by the environment-related effects of any of the construction or construction-related activities as directed by the Initial Environmental Examination (IEE) (see Attachment J.2, Initial Environmental
Examination). In case of an environmental problem, the contractor shall immediately notify the
COR who will instruct him as to the next course of action to take. Among the situations which may require such steps, are complaints or legal actions by third parties on matters such as environmental damage to property and natural resources, ground subsidence, interruption of groundwater flow, and surface and groundwater contamination.
The contractor will provide construction services to ensure that the works are completed in a manner that:
a. avoids adverse environmental and social impacts wherever possible.
b. restores work sites to acceptable standards; and
c. abides by any environmental performance requirements governed by local laws.
Environmental safeguards shall include, but not be limited to, considerations for the following:
a) Minimizing the effect of dust on the surrounding environment resulting from earth moving equipment, vibrating equipment, temporary/permanent access roads, etc. to ensure safety, health and the protection of workers and communities living in the vicinity dust producing activities.
b) Ensuring that noise levels emanating from machinery, vehicles, and noisy construction activities (e.g., excavation, blasting) are kept at a minimum for the safety, health and protection of workers within the vicinity of high noise levels and nearby communities.
c) Ensuring that existing water flow regimes in rivers, streams and other natural or irrigation channels is maintained and/or re-established where they are disrupted due to works being carried out.
d) Preventing oils, lubricants and wastewater used or produced during the execution of works from entering rivers, streams, irrigation channels and other natural water bodies/reservoirs, and ensuring that stagnant water in uncovered borrow pits is treated in the best way to avoid creating possible breeding grounds for mosquitoes.
e) Preventing and minimizing the impacts of quarrying, earth borrowing, piling, and building of temporary construction camps and access roads on the biophysical environment including protected areas and arable lands, local communities, and their settlements. In as much as possible restore/rehabilitate all sites to acceptable standards.
f) Discouraging construction workers from engaging in the exploitation of natural resources such as hunting, fishing, and collection of forest products or any other activity that might have a negative impact on the social and economic welfare of the local communities.
g) Implementing soil erosion control measures to avoid surface runoff and prevents siltation, etc.
h) Ensuring that, as much as possible, local materials are used to avoid importation of foreign material and long-distance transportation.
i) Ensuring public and worker safety and meeting traffic safety requirements for the operation of work to avoid accidents.
C.16 GENDER CONSIDERATIONS
The contractor is required to incorporate gender as an important consideration in the overall implementation of this contract and to respect the critical role women play in accelerating progress in development and advancing global prosperity and security. The contractor’s support of USAID infrastructure projects should consider the need for adaptations or modifications specifically tailored to reducing gender inequality, reducing gender-based violence, and increasing the roles and capabilities of women. Specifically, when providing support during design, procurement, and construction, attention should be given to the specific needs of women and girls.
C.17 CLIMATE RISK MANAGEMENT
Liberia is vulnerable to the impacts of climate variability and change, such as warmer temperatures, increases in annual rainfall, and increases in the frequency of heavy rainfall events. These climate change impacts present challenges to the country’s socio-economic development. Liberia’s low adaptive capacity to respond to climate change is partially due to the detrimental effects of the 1989-2003 Civil War. Since the war, the government, along with various international and national institutions and organizations, has been taking actions to better understand and address climate change challenges throughout the country. Remaining needs include data on short and long-term climate change impacts and vulnerabilities within the country, as well as the financial, technological, and human resources to identify adaptation priorities and implement appropriate adaptation plans and strategies.
Short-term climate variability is already affecting Liberia, including temperature increases and rainfall variability. As the Government of Liberia (GOL) notes in their new national climate policy, “the impacts of climate change in Liberia not only undermine development gains but also pose serious risk to food security and adaptive capacity,” requiring urgent and concerted national action.
As impacts become more pronounced, climate change may erode the progress that Liberia has made and limit gains in the future, including the government’s ability to address its development challenges.
The climate risk management results indicated that increased temperatures, changes in amount and duration of rainfall and sea level rise would be addressed through a range of integrated strategies.
Engineering analysis preceding design activities will include consideration of climate change and its potential impacts on the location (siting), functionality and sustainability of resulting infrastructure and infrastructure services. Such analysis will include identification of relevant data sets and gaps, review of local building standards and codes for adequacy; and determination of safety factors or other measures of uncertainty that will be carried through design. The results of this analysis, including risks identified and how they are addressed, shall be documented.
Furthermore, because infrastructure can be costly and is often built to last for decades, these assets are uniquely affected by climate change, though impacts will vary across different infrastructure types and locations. It is critical that the potential impacts of climate change be considered as part of overall program and project development to ensure resiliency and sustainability. This needs to begin at the planning phase and continue throughout the life of a project. An ongoing process of adaptive management can help decision-makers understand vulnerability, assess climate impacts, identify priorities, and take appropriate adaptation actions.
C.18 SUSTAINABLE CONSTRUCTION
Sustainable construction focuses more on the built environment and surrounding ecosystems, during the design phase, construction phase and during the operational life cycle of the infrastructure. The contractor will identify ways in which sustainable construction approaches can be used to improve both technical performance and appropriateness of USAID-funded infrastructure.
Technical performance includes interventions to improve energy efficiency, water consumption, and materials consumption. Appropriateness is how the project aligns with community goals and how the project supports responsible development that integrates with existing systems from a social, environmental, cultural, and economic perspective. The development of local ownership is an important part of community engagement.
Conflict sensitivity and do no harm are required: the contractor must ensure that project activities are maximizing positive and constructive dynamics in the context and communities in which they operate, and not exacerbating negative or destructive dynamics. A conflict sensitive approach reflects understanding of the context in which the project will operate, the interaction between the proposed intervention and that context, and innovative thinking to avoid negative impacts and maximize positive ones.
[END OF SECTION C]
D - PACKAGING AND MARKING
D.1 AIDAR 752.7009 MARKING (JAN 1993)
a) It is USAID policy that USAID-financed commodities and shipping containers, and project construction sites and other project locations be suitably marked with the USAID emblem. Shipping containers are also to be marked with the last five digits of the USAID financing document number. As a rule, marking is not required for raw materials shipped in bulk (such as coal, grain, etc.), or for semi-finished products which are not packaged.
b) Specific guidance on marking requirements should be obtained prior to procurement of commodities to be shipped, and as early as possible for project construction sites and other project locations. This guidance will be provided through the cognizant technical office indicated on the cover page of this contract, or by the Mission Director in the
Cooperating Country to which commodities are being shipped, or in which the project site is located.
c) Authority to waive marking requirements is vested with the Regional
Assistant Administrators, and with Mission Directors.
d) A copy of any specific marking instructions or waivers from marking requirements is to be sent to the Contracting Officer; the original should be retained by the Contractor.
D.2 BRANDING
Branding and Marking under this contract must comply with the USAID “Graphic Standards
Manual.”
D.3 BRANDING STRATEGY, IMPLEMENTATION PLAN AND MARKING PLAN
In accordance with ADS 320 “Branding and Marking” the Contract incorporates USAID’s policy directives and required procedures on branding and marking of USAID-funded programs, projects, activities, public communications, and commodities with the USAID identity. The contractor must provide a corresponding Branding Strategy, Implementation and
Marking Plan in accordance with the guidance available at https://www.usaid.gov/branding/acquisition-awards.
D.3.1 Branding Strategy
Program/Activity Name: Rehabilitate two (2) Pharmaceutical Depots/Warehouses in
Grand Gedeh and River Gee Counties
Positioning: All materials developed as a result of this activity will contain the following attribution statement:
“This project was made possible by the United States Agency for International Development and the generous support of the American People through USAID/Liberia.”
Level of Visibility: All publications developed through this project except for research articles published in academic journals, will also display currently approved USAID Identity graphics, and conform to other requirements of the USAID Graphic Standards Manual.
D.3.2 Marking
Description of public communications and program materials to be produced as part of the activity will visibly bear the following USAID Identity:
1. Standard USAID Identity
2. “This project was made possible by the United States Agency for International
Development and the generous support of the American People through
USAID/Liberia Rehabilitation Two (2) Pharmaceutical Depots/Warehouses in
Grand Gedeh and River Gee Counties with Contract No. TBD.”
[END OF SECTION D]
E - INSPECTION AND ACCEPTANCE
E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are hereby incorporated by reference
(by Citation Number, Title, and Date) in accordance with the clause at FAR 52.252-2
CLAUSES INCORPORATED BY REFERENCE" in Section I of this contract.
See http://acquisition.gov/far/index.html for electronic access to the full text of a FAR clause.
NUMBER TITLE DATE
FEDERAL ACQUISITION REGULATION
(48 CFR Chapter 1)
52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
52.246-21 WARRANTY OF CONSTRUCTION MAR 1994
E.2 INSPECTION AND ACCEPTANCE/RESPONSIBLE OFFICIAL
USAID inspection and acceptance of services, reports and other required deliverables or outputs shall take place at USAID/Liberia or at any other location where the services are performed and reports and deliverables or outputs are produced or submitted.
A CO may designate a COR for the contract. The COR identified in Section G has been delegated authority to inspect and accept all services, reports and required deliverables or outputs.
[END OF SECTION E]
SECTION F – DELIVERIES OR PERFORMANCE
The following contract clauses pertinent to this section are hereby incorporated by reference (by
Citation Number, Title, and Date) in accordance with the clause at FAR 52.252-2 CLAUSES
INCORPORATED BY REFERENCE" in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.
NUMBER TITLE DATE
FEDERAL ACQUISITION REGULATION (48 CFR Chapter 1)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK APR 1984
52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION SEPT 2000
52.211-13 TIME EXTENSIONS SEPT 2000
52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984
52.232-5 (e) PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (RETAINAGE) MAY
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984
52.242-14 SUSPENSION OF WORK APR 1984
F.1 PLACE OF PERFORMANCE
The place of performance for this contract shall be Grand Gedeh and River Gee Counties, Liberia, West Africa.
F.2 PERIOD OF PERFORMANCE
The period of performance is twelve (12) months. Construction is to be completed within nine
(9) months from the Notice to Proceed (NTP), followed by three (3) months for the Defects
Liability Period (DLP).
F.3 SCHEDULE OF DELIVERABLES AND REPORTS
General
The contractor will submit to the USAID Contracting Officer’s Representative (COR) all deliverables under this contract in draft form for comments. The COR will provide consolidated comments to the contractor. The contractor will submit the final form of all deliverables to the
COR, within fifteen (15) days following the COR receipt of the draft deliverable. Reporting requirements may be redefined by mutual agreement between the contractor and the COR. The contractor must submit all deliverables including reports, tender documents, and technical drawings, both in hard copies and electronic format. The contractor must submit all technical drawings related to project reports in hard copies and electronic format, or other relevant formats depending on the applicable software. The contractor must submit one (1) electronic copy and two (2) hard copies of the Final Report to the COR.
Deliverables Schedule
Deliverables Due Date
Performance Guarantee (5%) and Payment
Bond (5%)
Within 15 calendar days after signing of the award
Rehabilitation of Medical Depots in two (2) counties, Grand Gedeh and
River Gee
Within 9 calendar months after Notice to Proceed
(NTP)
Defect Liability Period Within 3 calendar months following substantial completion of all construction works
Detailed Work Plan (WP) Within 15 calendar days after NTP
Environmental Management and
Monitoring Plan (EMMP)
Within 15 calendar days after NTP
Reports Schedule
Reports Due Date
Inception Report; Schedule of Values; Health, Safety and Staff Welfare Plan; Quality Control
Plan
15 calendar days after NTP
Monthly Progress Reports 10 calendar days after the end of each calendar month
Weekly Site Reports and Visitors Log Made available for review by the COR when requested.
Substantial Completion Report, including Punch
List and Rectification Completion Work Plan
7 calendar days following inspection of works and before the issuance of substantial completion certificate.
Final Project Report 9 calendar months following Notice to Proceed
(NTP)
F.4 REPORTS AND DELIVERABLES OR OUTPUTS
In addition to the requirements set forth for submission of reports in Section I, and in accordance with AIDAR clause 752.242-70 on Periodic Progress Reports, the contractor must submit reports, deliverables, or outputs, as further described below, to the COR. All reports and other deliverables must be in the English language.
Reporting Requirements
The contractor will be required to provide USAID with several reports during the implementation of the project. These reporting mechanisms will be considered as major tools for the monitoring and reporting of the project’s progress against the project’s work plan. The contractor must submit to USAID, in electronic format, all the reports and documents listed below, and, if applicable, request USAID approval before proceeding to the next stage:
Performance Guarantee and Payment Bond: A performance guarantee and payment bond in the form of a bank guarantee from an international financial institution subject to the approval of USAID, covering all the construction works shall be submitted to USAID within fifteen (15) calendar days after signing the award.
The performance guarantee and payment bond are a prerequisite to the issuance of the Notice to Proceed (NTP). The value of the performance guarantee shall be equal to five percent (5%) of the total contract value. The performance guarantee secures performance and fulfillment of the contractor’s obligations under a patent provision. The value of the payment bond shall be equal to five percent (5%) of the total value of the contract.
The payment bond assures payments as required by law to all persons supplying labor or material in the prosecution of the work provided for in the contract.
The total Performance Guarantee and Payment Bond are equal to 10% of the total value of the contract. As noted above, the Performance Guarantee and Payment Bonds are a prerequisite to the issuance of the Notice to Proceed (NTP).
Inception Report; Schedule of Values; Health, Safety and Staff Welfare Plan; Quality
Control Plan, Environmental Monitoring and Mitigation Plan (EMMP); Detailed Work
Plan: The contractor shall prepare, for COR approval, an Inception Report, indicating a start-to-finish list of work items on the project (broken down into their component parts and with corresponding values) that, in total, represent the entire project from beginning to end and the entire contract price, a Health, Safety and Staff Welfare Plan for COR approval, an
Environmental Monitoring and Mitigation Plan (EMMP) for COR approval, a Detailed Work
Plan for COR approval, outlining the main components of the project, the sequence of construction, and the expected monthly volumes of work.
Monthly Progress Reports: Submit ten (10) calendar days after the end of each calendar month, except at the end of each quarter, will detail achievements over the month, the status and approach to outstanding problems, and provide work plans for the coming month.
Weekly Site Reports and Visitors Log: This report shall be submitted weekly including weekly progress reports, report on weather, reports on quantities of construction material used during the week, quantities of works completed during the week, a log of official visitors to the project site, and a work plan for the following week. This weekly report must be jointly signed by the contractor’s project manager and the USAID COR and filed at the site offices.
Substantial Completion Report: Submit nine (9) months after Notice to Proceed (NTP). The substantial completion report shall give a broader perspective with a comprehensive discussion of the construction activities, including how the entire project is being performed and the plans for the implementation of the Defects Liability Period. The report should include a succinct description of the project purpose, including objectives, results achieved versus planned indicator targets. Implementation problems, lessons learned and issues requiring additional attention should be described in detail. This report should be no longer than thirty (30) pages.
Final Project Report: The Final Completion Report must include a) an executive summary; b) an overall description of the contractor’s activities during the life of the project; c) an assessment of progress made toward achieving overall objectives, results, expected outcomes and targets;
d) issues, problems and constraints that emerged during project implementation and actions taken to address them; e) lessons learned and recommendations; and f) a fiscal report describing how the contract’s funds were used. Annexes should include an index of all reports and information products produced under the project. This report should be no longer than forty (40) pages.
F.5 INSPECTION, SURVEYS OR TESTING
The contractor must provide notice to USAID when all of the following have occurred:
• Contractor has completed all the work required.
• Contractor has ensured that all such work has been performed in accordance with the requirements of the contract; and
• Contractor has furnished to USAID all the necessary reports, documentation, shop drawings and as-built designs.
USAID will then conduct such inspections, surveys and/or testing as it deems necessary. If such inspections, surveys and/or tests disclose that any of work does not meet the requirements of the contract, USAID will promptly advise the contractor as to any uncompleted work and/or errors in the work necessary to be corrected as a condition to project completion, which may be corrected as punch list items. Such notice shall be accompanied by a certification from contractor’s
Construction Quality Assurance Support Personnel in form and substance satisfactory to USAID, certifying conformity of the standards and specifications required in the contract. Upon completion of the uncorrected work, or correction of the errors identified as a prerequisite to project completion, the contractor shall provide written notification to USAID, and USAID will conduct additional inspections, surveys and/or testing, as it deems necessary. This procedure shall be repeated until USAID finds that all prerequisites to project completion have been met.
Final Section Clean-Up: As a prerequisite to project acceptance, the contractor must clean the entire site. The contractor must remove and dispose of all debris, excess materials, temporary structures, equipment, and return all parts of the project in a neat and presentable condition.
Conditions to Project Acceptance: Upon receipt of notification from the contractor that all conditions for project acceptance have been met, the COR in collaboration with the Contracting
Officer will conduct the final inspection and will issue a Certificate of Project Acceptance if all works has been completed and conform to the contract requirements. If work has not been completed or doesn’t conform to the contract requirements, the COR will notify the contractor regarding any work remaining to be performed. If USAID does not issue a Certificate of Project
Acceptance, the contractor shall promptly remedy the defective and/or uncompleted portions of the work. Thereafter, the contractor shall submit to USAID a revised Certification of Project
Completion with a new date based on when the defective and/or uncompleted portions of the work were corrected and completed. The foregoing process shall be repeated until the COR gives the contractor an executed Certificate of Project Acceptance.
F.6 52.246-12 - INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The contractor shall maintain complete inspection records and make them available to the Government.
All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not --
(1) Relieve the contractor of responsibility for providing adequate quality control measures;
(2) Relieve the contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e)The contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the contractor any additional cost of inspection or test when work is not ready at the time specified by the contractor for inspection or test, or when prior rejection makes reinspection or re test necessary. The
Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size and performance tests shall be performed as described in the contract.
(f) The contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The contractor shall promptly segregate and remove rejected material from the premises.
(g) If the contractor does not promptly replace or correct rejected work, the Government may
(1) By contract or otherwise, replace or correct the work and charge the cost to the contractor; or
(2) Terminate for default the contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the contractor or its subcontractors, the contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
.Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the
Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of Clause)
F.7 SUBSTANTIAL COMPLETION
Substantial completion shall be deemed to have occurred when the contractor has fully satisfied the construction requirement in accordance with the requirements of the contract, and at least 90% and the works and the contract requirements are completed and deemed fit for use by USAID.
F.8 CONSTRUCTION WARRANTY (DEFECTS LIABILITY)
The contractor guarantees all the work to be performed and all the materials to be furnished under this contract against defects in materials and workmanship for a period of three (3) months from the date of substantial completion.
The contractor shall, within a reasonable time, but in no case longer than thirty (30) calendar days after receipt of a written notice thereof, repair or replace any defects in materials or workmanship which may develop, or be identified, during the three (3) month defects liability period, and any damages resulting from repairing or replacing of such defects, at its own expense and without additional cost.