Amendment No. 3 to RFP 376508-CD
This is Amendment No. 3 to a Request for Proposal issued by Fermi Forward Discovery Group, LLC for the Central Utility Building Addition and Renovation Construction project (UIP Subproject 1-CUB). The amendment was issued October 29, 2026, and extends key deadlines for the procurement. The new questions due date is 5:00 p.m. CT on December 1, 2026 (extended from November 3, 2026), and the new proposal due date is 4:00 p.m. CT on December 17, 2026 (extended from November 17, 2026). The amendment provides reference documents including CUB original as-built drawings, electrical upgrade as-built drawings, DHP-CU-1 catalog submittal, and existing transformer photos. Offerors must acknowledge receipt of this amendment through email to the Procurement Specialist, return of a signed copy, or inclusion of acknowledgment in the proposal letter.
The amendment includes responses to 19 questions from prospective offerors addressing electrical design and construction scope clarifications. Key topics include cable bus support system responsibilities, temporary power requirements and coordination, project responsibility matrix for furnished and installed equipment, shutdown windows for various systems, conductor specification discrepancies, existing switchboard manufacturer information, interior conduit material specifications (EMT vs. galvanized rigid conduit restrictions based on location and environment), existing equipment demolition and removal procedures, transformer handling and storage procedures, and feeder length verification requirements. Notable responses clarify that equipment returned to the Owner will be stored onsite at FFDG-designated locations, existing conduit/conductors may be abandoned in place where approved by FFDG and non-interfering with new work, and contractors must conduct site surveys to verify field conditions where contract documents lack sufficient detail.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT TO SOLICITATION
AMENDMENT NO.
DATE OF AMENDMENT:
October 29, 2026
SOLICITATION (REQUEST FOR PROPOSAL) NO.
376508-CD
DATE RFP ISSUED:
September 17, 2026
PROJECT NO.
N/A
PROPOSAL CLOSE (DUE) DATE:
4:00pm CT on December 17, 2026
TITLE OF PROJECT:
Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB
Offerors must acknowledge this Amendment prior to the hour and date set forth in the solicitation by one of the following methods:
1. Immediately upon receipt of the amendment via email to the Procurement Specialist.
2. Return of the amendment with a signature on the acknowledgment signature line; or
3. In the Subcontractor's Proposal Letter that accompanies a Subcontractor's proposal.
If by virtue of this Amendment you desire to change an offer already submitted, such change may be made by email making reference to the Solicitation and this Amendment, and it is received prior to the due date and time set for proposals.
The above referenced Solicitation is amended as follows:
- This Amendment 03 to the RFP is being issued to provide responses to questions received from prospective offerors; and
- This Amenement 03 provides the following as-builts, shop drawings, catalog submittals and photos for reference only:
o CUB original As-built Drawings o Electrical upgrade As-Built drawings o DHP-CU-1 catalog submittal o Existing transformer photos
- This Amendment 03 also extends the questions due date and proposal due date as outlined below:
o Current questions due date: Close of business (5:00pm CT) on November 3, 2026 o New questions due date: Close of business (5:00pm CT) on December 1, 2026 o Current proposal due date: 4:00 pm CT on November 17, 2026 o NEW proposal due date: 4:00 pm CT on December 17, 2026
All other terms and conditions as referenced under the subject RFP remain unchanged.
Kindly acknowledge receipt by signing and returning one (1) copy of this Amendment with your proposal.
Company Name
Signature & Date
Name & Title of Individual
Fermi Forward Discovery Group, LLC Kirk Road & Wilson St.
P.O. Box 500, MS 312
Batavia, Illinois 60510-0500 USA
Chris Daleyo Procurement Specialist IV
(630) 840-4256 cdaley@fnal.gov mailto:cdaley@fnal.gov
REQUEST FOR PROPOSAL (RFP) No. 376508-CD- AMENDMENT NO. 3
Responses to Prospective Offerors’ Questions
Question 1: Please clarify responsibility for exterior cable bus support systems. Confirm whether the Electrical Contractor is to furnish and install all cable bus support steel and anchor hardware, etc.
Response 1: Electrical Contractor shall coordinate with chosen cable bus vendor to design and install required cable bus support structures in coordination with final coordinated cable bus route into building, including exterior and interior support structures and hardware. Contractor shall provide all concrete foundations and supports required for cable bus supports as required per Civil and Structural drawings.
Question 2: Temporary Power - we anticipate that temporary power will be required to maintain continuous facility operations during construction activities, outages, cutovers, and equipment replacements. Temporary power may also be required to support Contractor operations, including but not limited to construction trailers, testing, commissioning, and temporary construction loads. Please clarify the temporary power loads required to maintain facility operations during construction, available connection points and electrical characteristics, duration and sequencing requirements, permitted outage windows, operational limitations, responsibility for providing, installing, maintaining, monitoring, fueling, and removing temporary power equipment, and Contractor requirements for temporary construction power, trailers, and associated temporary facilities.
Response 2: Refer to General Requirements specification 010010 for outage requirements and minimum utility services required. This specification defines a 7-day maximum outage, with contractor maintaining a base level of Utility Services. Contractor shall provide FFDG notice of any planned shutdowns in accordance with requirements outlined within drawings and specifications. Contractor to coordinate temporary power. Contractor to coordinate construction trailer location and power needs with FFDG. FFDG will provide the nearest power source for the contractor’s trailer.
Question 3: Please provide a project responsibility matrix identifying Contractor Furnished/Contractor Installed (CFCI), Owner Furnished/Contractor Installed (OFCI), and Contractor Furnished by Others (FBO) equipment.
Response 3: Refer to electrical drawings and specifications for identification of OFCI equipment and associated requirements. A responsibility matrix can be provided for convenience as part of a future drawing issuance.
Question 4: Shutdown Windows - Please provide acceptable shutdown windows for normal power, standby power, BAS systems, and medium-voltage systems.
Response 4: Refer to General Requirements specification 010010 for outage requirements and minimum utility services required. This specification defines a 7-day maximum outage, with contractor maintaining a base level of Utility Services. Contractor shall provide FFDG notice of any planned shutdowns in accordance with requirements outlined within drawings and specifications.
Question 5: Please clarify the apparent discrepancy between the MV feeder schedule showing 3#4/0 AL conductors and the MV cable specification identifying 750 kcmil aluminum conductors.
Identify which governs.
Response 5: MV Feeder schedule on E-011 only applies where 3MV240A feeder tag is shown on single line diagram E-302. 750MCM conductors apply where labelled on ES-301, 13.8kV HV One-Line Diagram.
Question 6: The E-101 Electrical Site Conduit Schedule identifies conduit quantities and sizes but does not identify conductor quantities, conductor sizes, cable types, or feeder designations associated with MV01-MV10 and LV40-LV53. Please provide a corresponding cable/feeder schedule or confirm the contractor is to determine conductor requirements from the single-line diagrams.
Response 6: Conductor requirements shall be determined from single-line diagrams for MV cabling. LV cabling requirements shall be determined from branch circuit wiring schedules and control wiring diagram.
Question 7: E-101 references ES-306 for feeder MV09 and MV10. ES-306 does not exist. Please clarify.
Response 7: Reference should be to ES-303 in MV Electrical package.
Question 8: The E drawings indicate numerous new breakers are to be added to existing switchboards; however, the contract documents do not provide existing switchboard manufacturer information, FO numbers, breaker catalog numbers, or breaker types required to verify compatibility. Please provide (if available): Existing switchboard manufacturer(s) and FO numbers, Existing breaker catalog numbers, frame sizes, and trip unit information, Available switchboard shop drawings, record drawings, or nameplate photos. Confirmation of specified meter model numbers and acceptance of current equivalent replacements where specified products are obsolete. Without this information, breaker compatibility cannot be verified, and pricing may be subject to revision based on field verification.
Response 8: Refer to as-built drawings for the CUB, for reference only that are provided with this Amendment 03. If additional information is needed, contact FFDG for additional site visit(s) to investigate site conditions and ascertain the information requested
Question 9: Drawing references for S-DHP-CUB-B1-1 indicate modifications to existing equipment, including: Note 1 - Existing equipment, Note 3 - New breakers, Note 4 - New power monitoring (PM), Note 7 - New PLC for load shedding. The contract documents do not provide sufficient information to identify the manufacturer, existing configuration, or equipment required to support the proposed modifications. Please provide: Manufacturer and model number of S- DHP-CUB-B1-1, Factory Order (FO) number and serial number, Original shop drawings and wiring diagrams (if available), Existing breaker catalog numbers and ratings (if available), Confirmation whether this equipment is paralleling gear, Details necessary to integrate the new power monitoring system and load-shedding PLC.
Response 9: Refer to as-built drawings for the CUB, for reference only, as well as the original catalog submittal for DHP-CU-1 that are provided with this Amendment 03. If additional information is needed, contact FFDG for additional site visit(s) to investigate site conditions and ascertain the information requested
Question 10: During the 10/13/26 site visit, it was observed that the existing interior conduit systems within the facility are predominantly Galvanized Rigid Conduit (GRC/RMC). However, our review of the contract drawings and specifications indicates EMT is generally permitted (with certain restrictions) for indoor installations and does not clearly require matching the existing GRC raceway system throughout. Please clarify whether new interior conduit associated with this project shall: Match the existing GRC/RMC raceway system throughout the facility or utilize EMT where permitted.
Response 10: Refer to Raceways specification section 260533 - 3.1 for permitted conduit uses. EMT is permitted in plant areas only where located above 12ft AFF (including above the Mezzanine) and not located near corrosive elements, including water treatment chemical dosing stations. EMT is permitted for finished interior spaces (e.g. conference room, control room) where not subject of physical damage, damp/wet locations, or corrosive chemicals.
Question 11: Given the uncertainty regarding general contractor participation and the number of outstanding RFIs, will additional time to receive and incorporate responses to outstanding RFIs and develop an accurate proposal be permitted? Providing additional time will help ensure that all bidders are pricing the same scope and will reduce the likelihood of assumptions, exclusions, or change orders resulting from unresolved design information. Please advise if a bid extension can be granted and provide the revised bid due date.
Response 11: The proposal due date has been extended to December 17, 2026 with this Amendment 03.
Question 12: Drawing E-100, Note 4 states that existing booster ring lighting is to be demolished and that all lighting fixtures and associated cabling are to be removed and returned to the Owner.
However, not all existing lighting fixtures, conduit, and associated raceways appear to be shown on the contract documents. Please confirm whether the demolition scope is limited to the lighting fixtures, conduit, and cabling indicated on the drawings. If demolition is intended to include additional existing lighting equipment not shown, please provide the locations, quantities, and any supplemental drawings or information necessary to define the full extent of the demolition work.
Response 12: Removal of lighting will include conduit and fixtures around the entire perimeter of the Booster Ring. See as-built drawings from the original construction provided with this Amendment 03, for reference only, specifically Sheet PE-9. If additional information is needed, contractor shall conduct a site survey to investigate extent of lighting fixtures that exist around booster ring and associated demolition scope required.
Question 13: Drawing E-100, Note 6 indicates removal of existing cabling within the conduit pathway between DSTR-42 and DSTR-42B; however, the size and quantity of the existing conductors could not be identified from the contract documents. Please provide the existing cable size, quantity, and configuration or clarify whether the contractor is to field verify.
Response 13: Contractor shall review the as-built drawings provided with this Amendment 03, for reference only, specifically the existing MV single line drawings. If additional information is required, Contractor shall conduct a full site survey to thoroughly investigate site conditions and ascertain the information requested.
Question 14: Drawing E100 indicates removal and return to Owner of the existing medium-voltage substation equipment. The contract documents do not identify the manufacturer, model numbers, or shipping/operating weights of the existing 5000 kVA transformers (Y-CU1A and Y- CU1B). Please provide the transformer nameplate information and associated shipping/operating weights or confirm the weights to be used for bidding purposes so that appropriate rigging, transportation, and return-to-owner requirements can be accurately included in the estimate.
Response 14: See photos of the existing transformers provided with this Amendment 03. If additional information is required, Contractor shall conduct a full site survey to thoroughly investigate site conditions and ascertain the information requested.
Question 15: The contract documents indicate that the existing medium-voltage transformers are to be removed and returned to the Owner. Please clarify whether the transformer insulating oil is to remain in the units during removal and transport, or if the oil is to be drained prior to removal.
If draining is required, please provide: Responsibility for oil removal and disposal/storage, Whether the oil contains any regulated materials requiring special handling or testing. Please confirm the intended procedure so that the required rigging, environmental controls, and transportation costs can be accurately included in the bid.
Response 15: There is no requirement in the contract documents to drain the oil. Leave the oil in the transformers when removing and transferring to the onsite storage location.
Question 16: The contract documents indicate that certain equipment is to be removed and returned to the Owner. Please clarify whether equipment designated for return to the Owner is to be stored onsite in a location designated by the Owner for later removal, or if the Electrical Contractor is responsible for transporting the equipment offsite. If offsite transportation is required, please provide the delivery location, unloading requirements, and identify the party responsible for transportation, rigging, and associated costs. Please clarify so that the proper labor, equipment, storage, and transportation costs can be accurately included in the bid.
Response 16: Equipment that is returned to the Owner will be stored onsite in a location designated by FFDG in accordance with specification 024119. Contractor shall set material aside for pick-up by FFDG personnel.
Question 17: Please provide existing feeder lengths or confirm contractor is to field verify all existing cable lengths for bidding purposes. The extent and condition of existing underground feeders, conduits, grounding systems, and associated equipment cannot be fully determined from the contract documents. Please confirm that concealed conditions differing from those reasonably observable during bidding will be addressed by change order.
Response 17: Contractor shall review the as-built drawings provided with this Amendment 03, for reference only, specifically the existing MV single line drawings. If additional information is required, Contractor shall conduct a full site survey to thoroughly investigate site conditions and ascertain the information requested.
Question 18: Existing mechanical equipment to be demolished are identified on Drawings E-201, E-202, E-203, and the Single-Line Diagram E-301. However, no conduit or cable schedules have been provided for the equipment indicated for removal. As a result, the sizes, quantities, routing, and extent of conduit and cable demolition cannot be accurately determined from the contract documents. In addition, several pieces of equipment appear on the single-line diagram but are not shown on the demolition plans, while other equipment shown on the demolition plans do not appear on the single-line diagram. This discrepancy makes it unclear which equipment and associated feeders, conduits, and conductors are required to be removed. Please clarify the complete demolition scope and provide conduit/cable schedules, feeder information, or additional drawings necessary to identify all associated conduits and conductors to be removed. Also, please confirm whether the demolition plans (E-201, E-202, E-203) or the single-line diagram (E-301) govern where discrepancies exist.
Response 18: Contractor shall review the as-built drawings provided with this Amendment 03, for reference only. Contractor should submit an RFI identifying and describing the referenced discrepancies for Engineer review.
Question 19: Please clarify whether existing conduit/conductors can be abandoned in place where complete removal is not feasible.
Response 19: Existing conduit/conductors may be abandoned in place where approved by FFDG and where existing conduit/cables will not interfere with new work required.
File details come from the government source that posted it. Updated .