This request for proposals solicits construction services for the Arlington National Cemetery - Columbia Pike Realignment Project in Arlington County, Virginia. The project involves realigning Columbia Pike and S. Joyce Street, replacing Southgate Road with a new S. Nash Street segment, expanding Foxcroft Heights Park, and modifying the Columbia Pike/Washington Boulevard interchange. Additional work includes constructing pedestrian and bicycle facilities, installing street lighting, and extensively relocating utilities. The project will prepare the site for a second contractor to construct five retaining walls, one tunnel, and perform mass grading. The estimated cost is over $10 million.

Proposals are due on the date specified in block 13a of the SF1442 solicitation form. Offerors must submit qualifications demonstrating experience with similarly complex and high-magnitude work. The solicitation will evaluate proposals using a best value determination considering technical merit and price. The contract will be awarded as a base schedule with an option for additional work. The performance period to complete all work is 1,433 calendar days if both schedules are awarded together. The Department of Transportation Federal Highway Administration issued the solicitation.

View the file

Other files

File Type Posted
Amendment 0005 - VA ST ANC(1).pdf PDF
Amendment 0004 - VA ST ANC(1).pdf PDF
Amendment 0003 - VA ST ANC(1).pdf PDF
Amendment 0002 - VA ST ANC(1).pdf PDF
Amendment 0001 - VA ST ANC(1).pdf PDF
Arlington County Traffic Signal Specifications - 2019.pdf PDF
ANCSE DAR Project_Utiity Agreement_WG.pdf PDF
Final EFLHD ANC FONSI_LTL1.pdf PDF
Plans_lighting.pdf PDF
Plans_roadway and drainage-part 3.pdf PDF
ANCSE SIREPORT_DEQ_letter.pdf PDF
Final ANCSE Env Report.pdf PDF
Plans_signals.pdf PDF
Asbestos Related Info.pdf PDF
ANCSE DAR Project - Utilities Matrix 2021-04-23.pdf PDF
ADV_Offerors Qualifications Form.doc DOC document
FP14_Eng.pdf PDF
Plans_roadway and drainage-part 4.pdf PDF
Arlington County Construction Standards and Specifications - 2020.pdf PDF
MOA for the Southern Expansion project at ANC (2014-1094).pdf PDF
Plans_traffic control-part 1.pdf PDF
Plans_roadway and drainage-part 1.pdf PDF
ANCSE_Env_Memo 021920.pdf PDF
ANCSE DAR Project_Utiity Agreement_Verizon_Signedv1.pdf PDF
Final_EA_Appendices_ANC_Southern_Expansion.pdf PDF
VDOT 2020 Road and Bridge Specifications.pdf PDF
VETS-4212 Form.pdf PDF
Plans_x-sections.pdf PDF
ANCSE DAR Project_Utility Agreement_Comcast.pdf PDF
Arlington County Lighting Specifications - 2020.pdf PDF
Plans_dry utilities.pdf PDF
ANCSE_Settlement_Agreement (FBL Signed - 01.11.20).pdf PDF
Plans_traffic control-part 2.pdf PDF
Executed LAND_ACQUISITION-224949-v2.pdf PDF
Plans_walls and tunnel.pdf PDF
ADV_Subcontracting Plan - VA ST ANC(1).doc DOC document
Plans_signing and markings.pdf PDF
Plans_wet utilities.pdf PDF
ANCSE DAR Project_Utility Agreement_Dominion.pdf PDF
Plans_roadway and drainage-part 2.pdf PDF
Final_EA_ANC_Southern_Expansion.pdf PDF
Plans_landscape.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract No.

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

VAST ANC(l)

ARLINGTON NATIONAL CEMETERY

REALIGNMENT OF COLUMBIA PIKE FROM WASHINGTON BLVD TO OAK ST.

CONTRACTOR:

ADDRESS:

REQUEST FOR PROPOSAL

RFPNo. 693C73-21-R-000018

This Contract Cites

STANDARD SPECIFICATIONS (FP-14)

STATE Virginia

COUNTY ARLINGTON

AGENCY Virginia Department of Transportation

TYPE OF IMPROVEMENT

Realignment of Columbia Pike from Washington Blvd to S. Oak St, reconfiguration of interchange with Washington Blvd and Columbia Pike, removal of Southgate Rd, construction of S. Nash Street and shortening S.

Joyce Street. Relocation of utilities from existing locations to new road alignments and consolidated utility corridors, retaining walls in various locations, tunnel under Columbia Pike, mass grading and other miscellaneous work.

Project Length Totals

1.20 0.00

For Parking Areas, Lane Miles is calculated as SQFT/1 lft (nominal) lane

Parking Roadway / Parking Area / Other Stations / SQFT Linear Route Lane

Sthedule Area Feet Miles Miles

A □ Columbia Pike 2876 To 5767 2,891 0.55 0.00

A □ S. Joyce Street 11150 To 11456 306 0.06 0.00

A □ S. Nash Street 10000 To 10873 873 0.17 0.00

A □ Washington Blvd Off Ramp 204 To 1203 999 0.19 0.00

A □ Washington Blvd On Ramp 000 To 750 750 0.14 0.00

A □ Southgate Road 1000 To 1361 361 O.Q7 0.00

A □ Oak Street 10662 To 10754 92 0.02 0.00

B □ Tunnel and Retaining Walls RW 1-5 NA To NA 0 0.00 0.00

TABLE OF CONTENTS

Page

Notice to Offerors 1 through 2

Checklist for Offer Submission 1 through 2

*SF-1442 Solicitation, Offer, and Award 1 through 6

Proposal Schedule Instructions 1 through 8

*Proposal Schedule B-1 through B-33

*SF-24 Bid Bond C-1 through C-2

FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION

REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES

Index to Federal and Transportation Acquisition Regulations 1 through 6

Representations and Certifications (SAMs online) D-1 through D-2

Instructions to Offerors E-1

*Socioeconomic Program Requirements F-1 through F-9

Minimum Wage Schedule F-10 through F-16

*General Contract Requirements G-1 through G-9

Construction Contract Requirements H-1 through H-5

Special Contract Requirements J-1 through J-214

Section K K-1 through K-3

Permits Obtained for this Project pending

SPECIFICATIONS On CD/beta.SAM.gov

Plans_dry utilities see CD/beta.SAM.gov Plans_landscape see CD/beta.SAM.gov Plans_lighting see CD/beta.SAM.gov Plans_roadway and drainage see CD/beta.SAM.gov Plans_signals see CD/beta.SAM.gov Plans_signing and markings see CD/beta.SAM.gov Plans_traffic control see CD/beta.SAM.gov Plans_walls and tunnel see CD/beta.SAM.gov Plans_wet utilities see CD/beta.SAM.gov Plans_x-sections see CD/beta.SAM.gov

TABLE OF CONTENTS

Page

ANCSE SIREPORT_DEQ_letter 1 page ANCSE_Env_Memo 021920 1 through 2 Asbestos Related Info 1 through 18 Final ANCSE Env Report 1 through 240 Final EFLHD ANC FONSI_LTL1 1 through 11 Final_EA_ANC_Southern_Expansion 1 through 165 Final_EA_Appendices_ANC_Southern_Expansion 1 through 395 MOA for the Southern Expansion project at ANC (2014-1094) 1 through 20 ANCSE DAR Project - Utilities Matrix 2021-04-23 1 through 3 ANCSE DAR Project_Utiity Agreement_Verizon_Signedv1 1 through 6 ANCSE DAR Project_Utiity Agreement_WG 1 through 5 ANCSE DAR Project_Utility Agreement_Comcast 1 through 5 ANCSE DAR Project_Utility Agreement_Dominion 1 through 5 ANCSE_Settlement_Agreement (FBL Signed - 01.11.20) 1 through 5 ExecutedLAND_ACQUISITION-#224949-v2 1 through 25 *Offeror’s Qualifications Form 1 through 7

* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5

*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE PROPOSAL SUBMITTAL

PACKAGE

NOTICE TO OFFERORS

CONTRACT FORMAT:

Offerors should note that the format of this contract is in accordance with Federal Acquisition Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-pages in this booklet.

FAR provisions and clauses incorporated by reference can be accessed on the Internet website at https://www.acquisition.gov/. Offerors are encouraged to review the documents thoroughly before submitting a proposal.

PROPOSAL BOOKLET AND OFFER SUBMITTAL:

It is the responsibility of the Offeror to verify that this proposal is complete as listed in the Table of Contents. The Offeror is responsible for submitting all required forms and documents with the offer.

Offerors should use the Checklist for Offer Submission included in this booklet to check that their proposals are complete.

CONSTRUCTION CONTRACTS:

As stated in FAR Clause 52.236-1, the Contractor shall perform on the site, and with its own organization, work equivalent to at least 50%. Additional guidance is given in FAR Subpart

35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e. proprietary Cintec arch strengthening) There are exceptions and they will be reviewed on a case-by-case basis.

HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:

As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Offeror must submit prior to award a Material Safety Data Sheet (MSDSs) for all hazardous materials that the Offeror identifies in paragraph (b) of this clause in Section G of this booklet. Failure to submit MSDSs may render the Offeror ineligible for award of contract. The apparent low Offeror should submit their MSDSs within two weeks after bid opening.

ATTENTION LARGE BUSINESSES - UTILIZATION OF SMALL BUSINESS CONCERNS:

All offerors that are large businesses should note their responsibilities in the awarding of subcontracts in accordance with FAR Clause 52.219-8, Utilization of Small Business Concerns. An awardee, if a large business concern, should note its responsibility to establish and conduct a subcontracting plan in accordance with FAR Clause 52.219-9, Alternate I, Small Business Subcontracting Plan. If the apparently successful offeror selected for award is a LARGE BUSINESS, then that offeror is required to submit a subcontracting plan prior to contract award. If the apparently successful offeror fails to submit a subcontracting plan within the time limit prescribed by the Contracting Officer, the offeror will be ineligible for award. PLEASE NOTE: A blank subcontracting plan is included in this solicitation package as a separate document for your use.

INTERNET BASED DATA BASES - REQUIRED INPUT:

According to FAR Subpart 4.1102 contractors are required to be registered in the System for Award Management (SAM) at the time an offer is submitted. Access the following web site to register: https://www.sam.gov/.

According to FAR Subpart 4.1201 contractors are required to complete electronic annual representations and certifications in SAM accessed via https://www.sam.gov/ as a part of required registration.

According to FAR Subpart 22.1302 (b) federal contractors and sub-contractors MUST complete the required annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch https://www.sam.gov/ https://www.sam.gov/ http://www.dol.gov/vets/vets4212.htm

NOTICE TO OFFERORS - (CONT'D.)

filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

PAYMENT:

Offerors are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.

PROGRESS PAYMENTS:

ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in SAM must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the SAM database. Offerors are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.

WELFARE-TO-WORK INITIATIVE:

The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.

INCREASING SEAT BELT USE IN THE UNITED STATES:

The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.

OBTAINING PROPOSAL DOCUMENTS:

Request For Proposal (RFP) documents will not be mailed. All solicitation documents are available for direct download from the Contract Opportunities website: https://beta.sam.gov/.

Contractors are encouraged to register on the website (for this specific project) in order to receive automatic notifications when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:

eflhd.contracts@dot.gov.

THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES

NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON

THOSE CHANGES.

https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm https://beta.sam.gov/ mailto:eflhd.contracts@dot.gov

CHECKLIST FOR OFFER SUBMISSION

The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the Offeror. Failure to submit a complete proposal may be cause to reject your proposal.

1. Proposal Envelope:

a. Addressed as shown in Block 7 of SF-1442

b. In the lower left corner, indicate the following: Solicitation No., Project Name & Number, and mail to Suite E2-3-300, ATTENTION: ACQUISITIONS. If proposals are hand-delivered, bring them to the main entrance of Quantum Park, and ask for the Federal Highway Administration (EFLHD) Receptionist to be contacted and an EFLHD representative will come to collect the proposal.

2. Standard Form 1442: Solicitation, Offer and Award

a. Block 14: Name and Address of Offeror.

b. Block 15: Telephone Number of Offeror.

c. Block 16: Remittance Address if different from Block 14.

d. Block 19: All Amendments Acknowledged, with dates of Amendments.

e. Block 20: Proposal is signed and dated.

3. Proposal Schedule - (Pages B-1 through B-33)

a. Unit proposal price and proposal amount provided for each pay item in numbers.

b. Corrections initialed.

c. Price Evaluation eligibility is indicated on the Proposal Summary page.

4. Standard Form 24, Bid Bond (Pages C-1 through C-2) (Required if bid guarantee is bid bond)

a. Date executed

b. Legal name and address of Offeror.

c. Type of organization.

d. State of incorporation (if applicable).

e. Name and business address of Treasury approved surety.

f. Penal sum of bond (not less than 20% of proposal total).

g. Proposal identification.

h. Signature of Offeror

i. Seal, if corporation

j. Signature of Surety

k. Seal, if corporation

PROPOSALS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.

5. Power of Attorney.

a. Dated on or before execution date of bond

b. Power has original signature of surety, or is embossed with surety's seal in the certification section

CHECKLIST FOR OFFER SUBMISSION

PROPOSALS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.

6. Fill-ins. The following full text Clauses and/or Provision numbers shall be checked or filled in and returned with the proposal package:

a. 52.219-4 – HubZone ONLY - See Section F, Clause 52-219-4, paragraph "C", check block if wavier is applicable.

7. Offeror's Qualifications form (provided separately as part of the proposal Documents Package). Form completed, signed and submitted with proposal

8. Subcontracting Plan - Large Businesses Only:

Submittal is mandatory per FAR 52.219-9 Alt II.

Legislated subcontracting goals: (15 USC 644 (g)(1))

• 45.25% - Small Businesses (SB)

• 5% - Small Disadvantaged Businesses (SDB)

• 3% - HUBZone

• 5% - Small Woman Owned Business Entities (SWBE)

• 3% - Service-Disabled Veteran-Owned Small Businesses (SDVOSB)

9. System for Award Management (SAM): The contractor is currently registered in the System For Award Management (SAM) database at https://www.sam.gov/ at the time the offer is submitted. If the contractor elects to not have its active SAM registration viewable by the public, then the contractor must submit a copy with the proposal.

10. Online Representations and Certifications Application: The contractor's Representations and Certifications have been input online via the electronic database at https://www.sam.gov/.

11. VETS – 4212 Reporting: The contractor has completed the annual reporting requirement online at http://www.dol.gov/vets/vets4212.htm.

The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL

DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A PROPOSAL

PACKAGE IS SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE

YOUR DATA PRIOR TO OFFER SUBMISSION MAY CAUSE THE PROPOSAL

TO BE REJECTED.

https://www.sam.gov/ https://www.sam.gov/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

ARLINGTON NATIONAL CEMETERY

DEFENSE ACCESS ROAD

PROJECT VA-ST-ANC(1)

REALIGNMENT OF COLUMBIA PIKE

REQUEST FOR PROPOSALS

RFP No 693C73-21-R-000018

Project Description: The Arlington National Cemetery Defense Access Roads (DAR) project consists of the realignment of Columbia Pike and S. Joyce Street, replacement of Southgate Road with a new segment of S. Nash Street, the expansion of Foxcroft Heights Park, and the modification of the Columbia Pike/Washington Boulevard interchange. Construction of pedestrian and bicycle facilities will increase multimodal connectivity, and installation of street lighting will enhance safety. This project will also prepare the site for a second contract to be awarded prior to completion of the DAR project. The DAR project will construct five retaining walls, one tunnel, and complete mass grading to allow the completion of the Southern Expansion performed by a second contractor. The project is located in Arlington County, Virginia.

Other work will include maintenance of bus, vehicle, pedestrian and bicycle traffic during construction, preserving safe multimodal access to the Air Force Memorial (AFM) for most of construction, and Construction of driveway entrances for future Pentagon 9/11 Memorial Visitor Education Center (VEC). Utilities that exist within lands that will be transferred to Arlington National Cemetery will require permanent relocation within the future roadway alignment rights of way. All utilities remain active during construction, so temporary relocations within the project limits will be required where impacted by construction activities.

Construction will coordinate with the ANCSE Southern Expansion project, Arlington County Columbia Pike Segment A project, Arlington County, the Virginia Department of Transportation, and other nearby projects and stakeholders. Elements of work will be constructed in accordance with VDOT, Arlington County, and other standards depending on the facility owner

The construction cost for the project is estimated to be more than $10,000,000.00.

Scope of Work: The detailed scope of work to be undertaken by the successful Offeror under the contract for this project is outlined in the Request for Proposal (RFP) solicitation documents.

These include the Plans, Special Contract Requirements (J Pages), and supplemental Government Furnished Information.

Procurement Overview of the Project: In accordance with Federal Acquisition Regulation (FAR) Part 15.101-1, the Eastern Federal Lands Highway Division (EFLHD) is conducting a Best Value Trade-off Source Selection Process for this project. Under this Notice, the EFLHD (also referred to as “the Government”) is soliciting all eligible Contractor firms/teams (Offerors) to participate in a two-step RFP process. The two-step RFP will include the submittal of two proposal packages; a Technical Proposal and a Price Proposal. A description of these proposals and their requirements can be found in the RFP’s Proposal Instructions (B Pages).

During step one, a selection evaluation board will review and evaluate the technical proposals submitted by all interested, responsive Offerors. The selection committee will select qualified Offerors based on a confidence rating evaluation criteria as stated in the RFP’s Proposal Instructions - Evaluation of Proposal Documents (B Pages). Offerors should submit technical proposals that are acceptable without additional explanation or information. The Government may make a final determination regarding a technical proposal’s acceptability solely on the basis of the technical proposal as submitted. The Government will proceed with the second step (trade-off evaluation) without requesting further information from any Offeror; however, the Government may request additional information from any Offeror with a technical proposal considered reasonable and close to acceptable, and may discuss any technical proposal with any Offeror. Only one technical proposal may be submitted by each Offeror. The step one technical proposal shall not include any prices or pricing information.

During step two, the Government will select the offer that represents the best value to the Government by using the trade-off process described in FAR Part 15.101-1. This process permits tradeoffs between price and technical “noncost” factors and allows the Government to accept other than the lowest priced offer. The award decision will be based on a comparative analysis and an integrated assessment of proposals against all source selection criteria in the solicitation.

All evaluation factors other than cost or price, when combined, are approximately equal in their importance when compared to cost or price. The Government is concerned with striking the most advantageous balance between technical merit (“quality”) and cost to the Government (i.e., the price). The degree of importance of price could become greater depending upon the equality of the technical proposals. If competing technical proposals are determined to be essentially equal, price could become the controlling factor. Only one price proposal may be submitted by each Offeror and the price proposal must be based upon the Offeror’s own technical proposal.

As stated in FAR Clause 52.236-1, the Contractor shall perform on the site, and with its own organization, work equivalent to at least 50% of the total amount of work to be performed under the contract.

Contract award is anticipated to be no earlier than July 2021, with Notice to Proceed anticipated to be issued after the receipt of valid Performance and Payment Bonds (see Block 12a of the SF- 1412 and FAR Clause 52.228-15), but no earlier than August 2021. Construction activities required to substantially complete the work in the South Parcel are to be completed by February 13, 2023, as specified in Subsection 108.06 of the Special Contract Requirements (J Pages). See Subsection 108 for additional construction activity restrictions.

It is not the intent of EFLHD to receive project specific design or engineering recommendations as part of the step one technical proposal other than what is necessary to support the technical proposal. Offerors should limit their technical proposal to the information required by this Notice, and other information that may be relevant to the qualifications and experience of the Offeror. No reimbursement will be made for any expenses associated with the preparation of a step one technical proposal or a step two price proposal.

Obligation to Keep Team Intact: In connection with the services covered by this procurement process, any in-house personnel, subcontractors, and outside associates will be limited to the individuals or firms that are specifically identified during the step one technical proposal. The Contractor shall obtain the Contracting Officer’s written consent before making any substitution for these designated in-house personnel, subcontractors, or outside associates.

Supplemental Work: Offerors are expected to provide qualified and experienced staff to develop appropriate pre-construction or construction protocols as designated by Federal, state, and local regulations/guidelines, including but not limited to the following:

• Work Plan.

• Accident Prevention Plan.

• Health and Safety Plan.

• Environmental Management Plan.

• Waste Management Plan.

• Recycling Plan.

Submittals: Each Offeror must provide the required number of Technical and Price Proposals as described below to EFLHD in separate, sealed envelopes/boxes clearly addressed and identified for “Project No: VA-ST-ANC(1).”

Submit one (1) bound paper copy, one (1) unbound copy, and one (1) CD-ROM copy of the Technical Proposal. Submit the Technical Proposal copies separately from the Price Proposal in a sealed envelope/box and clearly labeled as the “Technical Proposal.”

Submit one (1) unbound paper copy and one (1) CD-ROM copy of the Price Proposal. Submit the Price Proposal separately from the Technical Proposal in a sealed envelope and clearly labeled as the “Price Proposal.”

Submit all proposal documents by the due date specified in Block 13 of the SF-1442 to the following address:

Federal Highway Administration Eastern Federal Lands Highway Division Quantum Park 22001 Loudoun County Parkway Suite E2-3-300 Ashburn, VA 20147 Attn: Mr. C. Shawn Long

It is the Offeror’s sole responsibility to see that its proposal documents are received. Proposal documents received after the time due will be rejected and returned without consideration or further evaluation.

Other Information: Questions concerning this solicitation may be directed to Mr. Long via e-mail to: EFLHD.Contracts@dot.gov. Please be sure to put the solicitation number and project title in the subject line of your email.

mailto:EFLHD.Contracts@dot.gov

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

SUITE E2-3-300

693C73

ATTN: ACQUISITIONS

ASHBURN VA 20147

See Block 7

a. NAME

C. Shawn Long

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

EFLHD.Contracts@dot.gov

VA ST ANC(1)

x 05/20/2021

693C7321R000018

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This Request For Proposals is for the Arlington National Cemetery - Columbia Pike Realignment Project No. VA ST ANC(1), located in Arlington County, Virginia in strict accordance with the Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Proposal Schedule, including all applicable Federal, State, and local taxes.

FP - Standard Specification for Construction of Roads & Bridges on Federal Highway Projects.

Proposal Schedule, Section B - pages B-1 through B-33.

Special Contract Requirements, Section J - pages J-1 through J-214.

Plans_dry utilities, see beta.SAM.gov.

Plans_landscape, see beta.SAM.gov.

Plans_lighting, see beta.SAM.gov.

Plans_roadway and drainage, see beta.SAM.gov.

Plans_signals, see beta.SAM.gov.

Plans_signing and markings, see beta.SAM.gov.

Plans_traffic control, see beta.SAM.gov.

Continued ...

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 1433 calendar days and complete it within ________________ ________________ calendar days after receiving

Continuation Sheet, Block 11

06/29/2021

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>

$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������

�%(��
�)��
�������
���
����� �������������������
���

�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�

0��#������ ��2�

������������
H������

������� �)4��

3�2���%����

�����"��� � ��������
�������������
��" ��������������
�������������"���

����������3 4��� '5 '6 �--����7��

3�2���%���

�����������������������
H������

������� )4������ �$���� �� �4������

���� 2 of ����6���������������������������

����2�� #��0 ��2�����

�)��������� )�&4'��������������� ������������ &4'���������������

�"������&��*���G��'����, Block 26

Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Branch Quantum Park 22001 Loudoun County Parkway Suite E2-2-200 Ashburn, VA 20147

Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL

9-AMC-AMZ-EFLINVOICES@FAA.GOV

Oklahoma City, OK 73125

EFLHD-CO

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

693C7321R000018

Plans_walls and tunnel, see beta.SAM.gov.

Plans_wet utilities, see beta.SAM.gov.

Plans_x-sections, see beta.SAM.gov.

ANCSE SIREPORT_DEQ_letter, 1 page.

ANCSE_Env_Memo 021920, pages 1 through 2.

Asbestos Related Info, pages 1 through 18.

Final ANCSE Env Report, pages 1 through 240.

Final EFLHD ANC FONSI_LTL1, pages 1 through 11.

Final_EA_ANC_Southern_Expansion, pages 1 through

165.

Final_EA_Appendices_ANC_Southern_Expansion, pages

1 through 395.

MOA for the Southern Expansion project at ANC

(2014-1094), pages 1 through 20.

ANCSE DAR Project - Utilities Matrix 2021-04-23, pages 1 through 3.

ANCSE DAR Project_Utiity

Agreement_Verizon_Signedv1, pages 1 through 6.

ANCSE DAR Project_Utiity Agreement_WG, pages 1 through 5.

ANCSE DAR Project_Utility Agreement_Comcast, pages 1 through 5.

ANCSE DAR Project_Utility Agreement_Dominion, pages 1 through 5.

ANCSE_Settlement_Agreement (FBL Signed -

01.11.20), pages 1 through 5.

ExecutedLAND_ACQUISITION-#224949-v2, pages 1 through 25.

Permits pending.

The project consists of the realignment of

Columbia Pike and S. Joyce Street, replacement of

Southgate Road with a new segment of S. Nash

Street, the expansion of Foxcroft Heights Park, and the modification of the Columbia

Pike/Washington Boulevard interchange. Other work includes construction of pedestrian and bicycle facilities to increase multimodal connectivity, installation of street lighting to enhance safety, and extensive utility relocation. Work will also include site preparation for a second contract to be awarded prior to completion of the

DAR project. This will include the construction of five retaining walls, one tunnel, and mass grading to allow the completion of the Southern

Expansion performed by a second contractor.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

CONTINUATION OF SF 1442

Block 2:

This project is UN-RESTRICTED - Proposals will be accepted from ALL eligible business concerns.

This procurement falls under North American Industry Classification System (NAICS) code 237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)

The award of this project is subject to a 10% price evaluation preference for eligible HubZone Small Business Concerns (must be on the SBA listing) (see FAR Clause 52.219-4).

Facsimile and electronic bids will not be accepted.

PHYSICAL DATA AVAILABLE FOR REVIEW

1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.

2. Environmental Documents (8)

3. Utility Documents (7)

4. Arlington County Construction Standards and Specifications - 2020

5. Arlington County Lighting Specifications – 2020

6. Arlington County Traffic Signal Specifications – 2019

7. VDOT 2020 Road and Bridge Specifications

8. Permits pending

Block 9:

In accordance with FAR Provision 52.236-27 Site Visit - Alternate I, an organized site visit has been scheduled for this project. See Section E of the solicitation for details and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.

∗Block 11:

Maximum Time Allowed for the Contract if Schedules A and B are Awarded at the Same Time:

If the Government awards the contract as Schedules A+B, then the performance period to complete all contract work will be 1,433 calendar days.

Maximum Time Allowed for Each Schedule of Work if Awarded Separately:

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 1,433 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 1,286 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

mailto:eflhd.contracts@dot.gov

See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above.

Work restrictions can be found in SCR Sections 108 and 156.

Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)

Block 12A:

Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.

Block 13:

A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision 52.228-1, Bid Guarantee.

Block 17:

Amounts should be completed as follows:

Schedule A - $ Schedule B (Option 1) - $

Other:

The estimated price is expected to be greater than $10,000,000.

Responsibility of bidders shall be evaluated in accordance with the information provided on the Offeror's Qualification Form, which can be downloaded from the Contract Opportunities website located at http://beta.SAM.gov. FP-14 versions can be downloaded at the FHWA web site located at http://flh.fhwa.dot.gov/resources/specs/.

Basis for Award:

EFLHD intends to award a fixed price contract without discussions with offerors (except clarifications as described in FAR 15.306(a)); therefore, the offeror's technical and price proposal should be clear and complete and contain the offeror's best terms. The Government reserves the right to conduct discussions if later deemed necessary. The Government further reserves the right to reject any or all offers if such action is in the Government's best interest.

The Government will select the offer that represents the best value to the Government by using the trade-off process described in FAR Part 15101-1. This process permits tradeoffs between price and technical “non-cost” factors and allows the Government to accept other than the lowest priced offer. The award decision will be based on a comparative analysis and an integrated assessment of proposals against all source selection criteria in the solicitation.

http://beta.sam.gov/ http://flh.fhwa.dot.gov/resources/specs/

Evaluation of Award:

All evaluation factors other than cost or price, when combined, are approximately equal in their importance when compared to cost or price. The Government is concerned with striking the most advantageous balance between technical merit (“quality”) and cost to the Government (i.e., the price). The degree of importance of price could become greater depending upon the equality of the technical proposals. If competing technical proposals are determined to be essentially equal, price could become the controlling factor. The Technical Proposal of the Offeror awarded the contract will be incorporated into the contract by reference and the Contractor shall be bound by its contents.

Please Note:

This solicitation is a Request for Proposal (RFP). Therefore, there will not be a public bid opening and proposals are not available for review.

Subcontracting Goals

Required from all other than Small business when the requirement is expected to exceed $750,000 ($1,500,000 for Construction) [FAR 19.702]. The Contracting Officer, along with review and advisory comments from the Office of Small Disadvantaged Business Utilization (OSDBU), is responsible for approving a reasonable and realistic plan [FAR 19.705-4] [TAM 1219.201(e)(6)]. The legislated subcontracting goals are as shown below. A copy of each subcontracting plan (or contractor statement that no subcontracts are to be awarded) must be provided to OSDBU prior to close of negotiations [TAM 1219.705-5 and - 6].

Legislated subcontracting goals: (15 USC 644 (g)(1)

• 45.25% - Small Businesses (SB)

• 5% - Small Disadvantaged Businesses (SDB)

• 3% - HUBZones

• 5% - Women-Owned Small Businesses (WOSB)

• 3% - Service-Disabled Veteran-Owned Small Businesses (SDVOSB)

PROPOSAL INSTRUCTIONS

PROJECT: VA-ST-ANC(1)

OFFERORS PLEASE NOTE: Before preparing the proposal, carefully read the Instructions to Offerors. While preparing the proposal, comply with the following:

Submit all required proposal information to EFLHD in sealed envelopes/boxes clearly addressed and identified for “Project No. VA-ST-ANC(1) - Solicitation No. 693C73-21-R-000018.”

Submit all proposals so that they will arrive at the address shown in Block 7 of the SF-1442 on the due date specified in Block 13 of the SF-1442. Send proposals directly to the attention of the person listed in Block 9 of the SF-1442.

Submit one (1) bound paper copy, one (1) unbound copy, and one (1) CD-ROM copy of the Technical Proposal. Submit the Technical Proposal copies separately from the Price Proposal in a sealed envelope/box and clearly labeled as the “Technical Proposal.”

Submit one (1) unbound paper copy and one (1) CD-ROM copy of the Price Proposal. Submit the Price Proposal separately from the Technical Proposal in a sealed envelope and clearly labeled as the “Price Proposal.”

It is the Offeror’s sole responsibility to see that its proposal is received. Proposals received after the time due will be rejected without consideration or further evaluation. In addition, it is the Offeror’s responsibility to ensure all requirements of both the Technical Proposal and Price Proposal are included in their respective envelopes/boxes.

EVALUATION OF PROPOSAL DOCUMENTS

STEP 1 – TECNICAL PROPOSAL EVALUATION

The Technical Proposal is limited to 75 pages, 8.5” x 11” size paper, printed on one side only, pages numbered, and using Times New Roman font size 12. Gantt charts, site maps, or charts can be submitted on single sided sheets up to 11” x 17.” The Technical Proposal cover letter, outside covers, and section dividers do not count toward the 75-page limit.

An Evaluation Board will evaluate each Technical Proposal using the following evaluation criteria:

Factor 1 – Prior Experience, Past Performance, and Proposed Team

The Government will evaluate the qualifications of the Offeror by considering the Offeror’s example projects, past performance, and proposed project team, as described below. Offerors demonstrating a higher level of successful past performance in the evaluated areas will be more favorably rated.

(a) Example of Project and Past performance: Submit documentation that shows direct experience as a prime contractor that are of similar size and complexity to the subject solicitation. The projects should demonstrate the technical capabilities that are required for this solicitation. Submit documentation by providing at least three (3) but no more than five (5) completed projects in the past ten (10) years. Projects that include the following types of work will be given a more favorable rating: retaining wall construction, tunnel construction, multi-phased projects, projects that required maintenance of traffic throughout construction, and projects that required extensive utility relocations. Provide customer/owner point of contact, phone number, and email address for each relevant project.

(b) Example of Specialty or Subcontract Work Past Performance: For specialty work that may be subcontracted, submit documentation that lists the name of the subcontractor, and relevant project experience using the same guidance given in paragraph (a). Provide a statement indicating the subcontractor’s experience and technical competence relative to the nature of the work being performed.

(c) Proposed Team: Provide an organizational chart and submit resumes of key personnel to be involved in the project, indicating their specific experience within the past 5 years performing technically similar construction work, construction project management, and construction QC work for EFLHD and/or a similar DOT. At a minimum, include the Construction Superintendent and the QC Manager, each having a minimum of 2 years’ experience within the past 5 years performing technically the same or similar work. List any subcontractors whom the Offeror proposes to provide services and indicate their experience performing similar work.

FACTOR 1 - PRIOR EXPERIENCE, PAST PERFORMANCE AND PROPOSED

TEAM RATINGS

Color Rating

Adjectival Rating Description/Indicators

Blue Outstanding

Based on the offeror’s recent/relevant experience and performance record, the Government has a high expectation that the offeror will successfully perform the required effort in each of the 3 sub-factors mentioned above.

Purple Good

Based on the offeror’s recent/relevant experience and performance record, the Government has a reasonable expectation that the offeror will sufficiently perform the required effort in each of the 3 sub-factors mentioned above.

Green Acceptable

Based on the offeror’s recent/relevant experience and performance record, the Government has a reasonable expectation that the offeror will meet minimum expectations in performing the required effort in each of the 3 sub-factors mentioned above.

Yellow Marginal

Based on the offeror’s recent/relevant experience and performance record, the Government has a low expectation that the offeror will meet minimum expectations in performing the required effort for each of the 3 sub-factors mentioned above.

Red Unacceptable

Based on the offeror’s recent/relevant experience and performance record, the Government has no expectation that the offeror will be able to meet minimum expectations in performing the required effort for each of the 3 sub-factors mentioned above.

Factor 2 – Planned Approach to Construction and Project Understanding

The Government will review and evaluate each Offeror’s understanding of the contract work and overall approach to managing and constructing the project. Provide a general description of the Offeror’s methods and ability to complete the contract work on time and within the total bid amount, especially as it pertains to the interim milestone requirement for the South Parcel turnover that includes retaining wall construction, utilities relocation, mass grading and other work.

(a) Provide a preliminary Construction Milestone schedule and outline the Offeror’s approach to meet the period of performance (calendar days) requirement for the project. Milestones for the schedule should correlate with the Transportation Management Plan sequencing. Include a narrative that describes the staging and sequencing needs as well as resources required to deliver.

(b) Provide a description of the sequencing and items of work needed to meet the South Parcel interim completion milestone date as described in Section 108.06 of the Special Contract Requirements (SCR).

(c) List any proposed value engineering or alternate technical concepts that may provide additional schedule advantages or allow an earlier completion date for either the South Parcel milestone or the final contract completion.

(d) Identify and list three (3) project risks, whether under the offeror’s control or not, that would result in adverse impacts to the schedule. For each risk, provide the offeror’s planned strategy to avoid or mitigate those risks in order to maintain the project’s schedule.

Proposals with South Parcel Turnover dates prior to February 13, 2023 will rank higher. Provide a description of the Offeror’s construction approach to complete the South Parcel turnover prior to February 13, 2023.

FACTOR 2 – PLANNED APPROACH TO CONSTRUCTION AND PROJECT

UNDERSTANDING

Color Rating

Adjectival Rating Description/Indicators

Blue Outstanding

Proposal meets requirements of the 4 sub-factors mentioned above and indicates an exceptional approach and understanding of the requirements to manage and construct the project. The proposal contains two or more strengths and no deficiencies. Proposal has a South Parcel Turnover date prior to February 13, 2023.

Purple Good

Proposal meets requirements of the 4 sub-factors mentioned above and indicates a thorough approach and understanding of the requirements to manage and construct the project. Proposal contains at least one strength and no deficiencies. Proposal has a South Parcel Turnover date prior to February 13, 2023.

Green Acceptable

Proposal meets requirements of the 4 sub-factors mentioned above and indicates an adequate approach and understanding of the requirements to manage and construct the project. Proposal has no strengths or deficiencies. Proposal includes a South Parcel Turnover date of February 13, 2023.

Yellow Marginal

Proposal does not clearly meet requirements, and has not demonstrated an adequate approach and understanding of the requirements to manage and construct the project. Proposal includes a South Parcel Turnover date of February 13, 2023.

Red Unacceptable Proposal does not meet requirements and contains one or more deficiencies and is unawardable. Proposal may or may not includes a South Parcel Turnover date of February 13, 2023.

Factor 3 – Project Management, Controls and Coordination

The Government will evaluate the Project Management and Controls of the Offeror by considering the Offeror’s approach to the project’s QC, schedule, and coordination as described below. Offerors demonstrating effective and efficient project management procedures will be more favorably rated.

(a) Quality Control: Provide a description of the planned approach to overall quality control, to deliver a quality construction project on-time. Include a summary of the proposed Quality Control Plan demonstrating soundness and reasonableness of the planned approach to QC for construction including materials sampling and testing.

Although not required, include information regarding any Document Control System (DCS) that the offeror proposes for the purposes of managing, tracking and controlling all transmittals, submittals, requests for information, meeting minutes, reports, correspondence and other pertinent project documents. Proposals that include the use of a DCS will rank higher.

(b) Utility Coordination: Provide a description of the offerors approach and understanding of the utility coordination description in Section 104.06 of the SCR and installation requirements of the project. If possible, reference successful strategies that have been implemented on other projects. Describe the means and methods by which the offeror will plan and control the scheduling of utility relocations to ensure the project is constructed on time or ahead of schedule.

(c) Coordination with other Contractors: Provide a description of the offeror’s planned approach to coordination with other contractors, and an understanding of the requirements of Section 104.07 of the SCR, with emphasis on the coordination required with the Arlington National Cemetery Southern Expansion project and contractor.

FACTOR 3 - PROJECT MANAGEMENT, CONTROLS AND COORDINATION

Color Rating

Adjectival Rating Description/Indicators

Blue Outstanding

The responses to the 3 sub factors show there is little potential to cause disruption of schedule or degradation of performance. With the proposed processes, normal contractor effort and normal Government monitoring will likely be able to overcome any difficulties.

Purple Good

The responses to the 3 sub factors show there is some potential to cause disruption of schedule or degradation of performance. With the proposed processes, special contractor emphasis and close Government monitoring will likely be able to overcome any difficulties.

Green Acceptable

The responses to the 3 sub factors show there is approximately 50% potential to cause disruption of schedule or degradation of performance. With the proposed processes, special contractor emphasis and close Government monitoring will likely be able to overcome any difficulties.

Yellow Marginal

The responses to the 3 sub factors show there is likely potential to cause disruption of schedule or degradation of performance. With the proposed processes, overcoming difficulties will be unlikely, even with special contractor emphasis and close Government monitoring.

Red Unacceptable Based on the responses, the Government has no expectations that schedule and performance requirements will be met.

STEP 2 – PRICE PROPOSAL EVALUATION

COMPLETING THE BID SCHEDULE

Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual Schedule of Work by adding the amounts of the listed items, and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.

To be eligible for award, Offerors must submit prices for each pay item.

Review Subsection 109.03 of the Special Contract Requirements regarding scope of payment for direct and indirect payment work.

Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Cost Proposal Summary page.