ANCSE DAR Project_Utiity Agreement_WG.pdf

PDF 179 KB Posted

Attached to
Arlington National Cemetery - Realignment of Columbia Pike
Solicitation number
693C73-21-R-000018
Issued by

About this file

This project utility agreement outlines the terms for relocating Washington Gas facilities as part of the Arlington National Cemetery Southern Expansion Defense Access Road project in Virginia. The federal government will assume costs for constructing permanent relocation infrastructure using utility company materials and standards, as well as temporary relocations. The utility company will provide final connections for approximately 3,375 linear feet of relocated gas conduit and appurtenances by a specified date. The federal highway administration seeks proposals for the Arlington National Cemetery Columbia Pike Realignment project involving roadwork, utilities, structures and mass grading. The solicitation is expected to exceed $10 million and include a base schedule and optional work. Proposals are due on May 20, 2021 as specified in solicitation 693C73-21-R-000018. Experience with similar projects is required.

View the file

Other files

File Type Posted
Amendment 0005 - VA ST ANC(1).pdf PDF
Amendment 0004 - VA ST ANC(1).pdf PDF
Amendment 0003 - VA ST ANC(1).pdf PDF
Amendment 0002 - VA ST ANC(1).pdf PDF
Amendment 0001 - VA ST ANC(1).pdf PDF
Arlington County Traffic Signal Specifications - 2019.pdf PDF
Final EFLHD ANC FONSI_LTL1.pdf PDF
Plans_lighting.pdf PDF
Plans_roadway and drainage-part 3.pdf PDF
ANCSE SIREPORT_DEQ_letter.pdf PDF
Final ANCSE Env Report.pdf PDF
Plans_signals.pdf PDF
Asbestos Related Info.pdf PDF
ANCSE DAR Project - Utilities Matrix 2021-04-23.pdf PDF
ADV_Offerors Qualifications Form.doc DOC document
FP14_Eng.pdf PDF
Plans_roadway and drainage-part 4.pdf PDF
Arlington County Construction Standards and Specifications - 2020.pdf PDF
MOA for the Southern Expansion project at ANC (2014-1094).pdf PDF
Plans_traffic control-part 1.pdf PDF
Plans_roadway and drainage-part 1.pdf PDF
ANCSE_Env_Memo 021920.pdf PDF
ANCSE DAR Project_Utiity Agreement_Verizon_Signedv1.pdf PDF
Final_EA_Appendices_ANC_Southern_Expansion.pdf PDF
VDOT 2020 Road and Bridge Specifications.pdf PDF
VETS-4212 Form.pdf PDF
Plans_x-sections.pdf PDF
ANCSE DAR Project_Utility Agreement_Comcast.pdf PDF
Arlington County Lighting Specifications - 2020.pdf PDF
Plans_dry utilities.pdf PDF
ANCSE_Settlement_Agreement (FBL Signed - 01.11.20).pdf PDF
Plans_traffic control-part 2.pdf PDF
Executed LAND_ACQUISITION-224949-v2.pdf PDF
Plans_walls and tunnel.pdf PDF
ADV_Subcontracting Plan - VA ST ANC(1).doc DOC document
Plans_signing and markings.pdf PDF
Plans_wet utilities.pdf PDF
RFP Solicitation - VA ST ANC(1).pdf PDF
ANCSE DAR Project_Utility Agreement_Dominion.pdf PDF
Plans_roadway and drainage-part 2.pdf PDF
Final_EA_ANC_Southern_Expansion.pdf PDF
Plans_landscape.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EASTERN FEDERAL LANDS HIGHWAY DIVISION

22001 Loudoun County Parkway, BLDG E-2, Suite 200

ASHBURN, VA. 20147

PROJECT UTILITY AGREEMENT

Arlington National Cemetery (ANC) Southern Expansion (SE), Defense Access Road (DAR) Project Project VA ST ANC(1)

Temporary and/or Permanent Relocation of Facilities

THIS AGREEMENT, by and between the U.S. Department of Transportation, Federal Highway Administration, hereinafter called the Government, and Washington gas, hereinafter called the "Utility Company," is authorized by Title 23 CFR 645.

The Government in partnership with Arlington National Cemetery, Virginia Department of Transportation (VDOT), and Arlington County, are working to expand the area of the cemetery south of the cemetery’s current limits for future interments, by using the Old Navy Annex site, and Right-of-Way (ROW) from Southgate Road and VDOT’s interchange with Columbia Pike (Route 244) and Washington Boulevard (Route 27) areas. To that end, the ANCSE DAR Project will realign Columbia Pike with a new intersection with S. Joyce Street;

reconfigure the west side off and on ramps of the Washington Boulevard and Columbia Pike Interchange to a tight diamond interchange; replace Southgate Road with a new segment of S. Nash Street; construct new widened pedestrian sidewalks along Columbia Pike, including a separate cycle track on the north side; an underpass access tunnel between the north side and south side of Columbia Pike for providing access between the cemetery expansion site and a new location for the Cemetery Operations Complex (Ops Complex); retaining walls in a parcel of land south of relocated Columbia Pike for the new Ops Complex; traffic signals at three intersections; streetlighting and landscaping; mass grading of the Ops Complex and cemetery expansion site; and relocation of all utilities from the cemetery expansion site to the Columbia Pike corridor and other identified corridors, as required.

The Utility Company agrees to the following for all Utility Company owned facilities:

ASSUMING FULL OR A PERCENTAGE OF COMPENSABLE PROPERTY RIGHTS:

1.) For those Utility Companies having a full or a percentage of a compensable property interest (or “prior rights”), the United States will cover 100%, or a calculated percentage of the reasonable cost of constructing new facilities and moving the existing facilities (as it relates to the property interest). Please provide evidence of your compensable property interest, to include deeds and plats.

ASSUMING NO COMPENSABLE PROPERTY RIGHTS:

1.) For temporary relocations of facilities, the Utility Company will provide these services either prior to, or during construction, with the Utility Company’s own personnel and resources.

For this work, the Government will reimburse the Utility Company for all reasonable costs, including design, related to the temporary relocation of facilities.

2.) For constructing permanent new facilities and moving the existing facilities:

• The Government will construct the utility owner’s infrastructure using materials provided by the Utility Company. The Government will construct these facilities using the Utility Company’s standards and specifications.

• To construct the utility owner’s infrastructure, the Utility Company, at its option, may provide to the Government a list of contractors to be used by the Government’s construction contractor. The Government’s contractor will be responsible for entering appropriate subcontracts with the contractors provided by the Utility Company.

• During construction, the Government will permit periodic inspections of the infrastructure and coordinate through the Government’s Construction Operations Engineer assigned to the project.

• The Government’s Final Approved Construction Documents will indicate the location of the new facilities.

• The Utility Company will have the opportunity to review and comment upon the location and design of the new facilities.

• Upon completion of the Utility Company’s infrastructure, the Utility Company, in coordination with the Government’s construction contractor, will make final connections, so that the Utility Company’s existing utilities can be removed from the Cemetery Expansion Site.

• Removal of temporary facilities will be at Government expense. Temporary facilities will be removed by the Government’s contractor, unless the Utility Company expresses the desire to remove the utility for salvaging materials, etc.

The Government will assume the cost of constructing the permanent infrastructure; however, all materials will be provided by the Utility Company at the Utility Company’s sole cost. In addition to covering the cost of materials, the Utility Company will be responsible for all other costs, such as design costs and labor associated with making connections, related to the permanent moving of facilities.

Scope of Permanent Work

In order to construct the permanent infrastructure for the Utility Company, the Utility Company agrees to provide all materials to the Government’s contractor for permanent relocation of approximately 3,375 LF of 12-inch gas conduits including appurtenances (valves, etc.) in a bundle as indicated in the Government’s Final Approved Construction Documents. This agreement will be modified once the Government’s Construction Documents are finalized, to specify the exact quantity of conduit to be constructed by the Government’s contractor.

In order to construct the permanent infrastructure for the Utility Company, the Government will construct trenches to the appropriate width and depth to install the conduit runs between connection tie-ins to existing valves and proposed valves, as shown in the Government’s Final Approved Construction Documents. All work will be performed to the Utility Company’s standards and specifications.

Upon completion of the Government’s work, and at a day and time coordinated and planned between the Government’s contractor and the Utility Company, the Utility Company agrees to do the final connections to transfer and restore the Utility Company’s service to the new permanent relocation to allow removal of the existing Utility Company’s facilities from the Cemetery Expansion Site.

Preliminary Engineering activities for making final connections are to be performed by the Utility Company.

The Government will have project on-site inspectors for inspecting the contractor’s work, but encourages the Utility Company to arrange inspection of the work through the Government’s Construction Operations Engineer (COE). Through such arrangement, with Utility Company points of contacts (POCs) and other information such as POC phone numbers and email provided to the Government’s COE, the Government’s COE will provide advance, notice for inspection of the Government’s work. Note that the Utility Company is prohibited from directing the Government’s contractor’s work. Any issues or punch list items identified by the Utility Company’s inspector should be coordinated with the Government’s COE for addressing any issues and punch list items. The Utility Company will be allowed a follow up inspection to ensure issues and punch list items brought to the COE’s attention has been addressed.

Scope of Temporary Work

The scope of the temporary relocation of the Utility Company’s facilities will be shown in the Government’s Final Approved Construction Documents. There will be approximately 2,355 LF of 8-12-inch temporary conduits to be installed.

Scheduling and Coordination

The Utility Company shall collaborate with the Government’s COE and contractor to complete the work herein described, and will collaborate and plan with the COE and contractor a schedule to perform the work to avoid unnecessary delay or conflict to the progress of other work related to the Government’s Project VA ST ANC(1).

Authorization to Proceed

In accordance with the schedule negotiated with the Government’s COE and contractor, the Utility Company will complete the work herein described as soon as practicable after written notice to proceed by the Government and will schedule the performance of the work to avoid unnecessary delay or conflict to the progress of work by the Government’s contractor. The Government will provide written notice to proceed to the Utility Company. This notification shall be provided when the infrastructure constructed by the Government’s contractor is complete. The Utility Company will not commence work until receipt of notice in writing from the Government to begin work.

The Utility Company will afford the Government the opportunity of inspecting the work by furnishing notice of the date the work will start to Mr. Sean O. Brien, COE, Eastern Federal Lands Highway Division, Federal Highway Administration, 22001 Loudoun County Parkway, Building E-2, Suite 200, Ashburn, VA 20147.

Extra Work

If conditions require a change or update in the scope of the work, the performance of extra work, or major changes in the planned work as herein described, this agreement shall be modified by a written amendment covering the required changes which, when executed by both parties hereto, shall become a part of this agreement.

This agreement and cost responsibility will be amended should the Utility Company provide evidence of compensable property interest prior to the commencement of work.

Permits The Utility Company shall make application to appropriate authorities to obtain all necessary permits required to perform work herein described, if required.

The Utility Company will be required to obtain a Land Use Permit or Permit to be in VDOT and County Right of Way (ROW) following completion of the relocated facilities if within public

ROW.

IN WITNESS WHEREOF, the parties hereto have executed this Utility Project Agreement No. ________ as of the date of signature of the Company.

Company:

BY: ______________________________________________

TITLE:

DATE: ___________________________________________

FED TAX I.D.: ____________________________________

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

BY: _____________________________________________

Leo R. Dario

TITLE: Project Support Engineer

DATE: __________________________________________