This memorandum from an environmental consulting firm summarizes asbestos investigations conducted for the Arlington National Cemetery Southern Expansion project. The investigations found asbestos containing materials buried on site, primarily in the eastern portion of the South Parking parcel. Mitigation measures are required during excavation and utility installation and will be detailed in the plans and specifications. However, uncertainties exist. The Defense Access Road project, which is separate from the Southern Expansion, will also impact investigation areas but is not bound by the expansion project's mitigation plans. Additionally, the full quantity of asbestos-containing materials requiring off-site disposal cannot be accurately determined until focused sampling is conducted in proposed excavation and utility areas. These uncertainties could impact cost and schedule planning if not addressed. The memorandum recommends ensuring the Defense Access Road project implements similar asbestos mitigation measures and conducting additional sampling to identify asbestos-containing materials requiring disposal.
This federal contract opportunity is for the Arlington National Cemetery - Columbia Pike Realignment Project in Arlington County, Virginia. The project scope includes realigning Columbia Pike and surrounding streets, expanding a park, modifying an interchange, and installing pedestrian and bicycle facilities. It will also include site preparation work for a subsequent expansion contract. The project value is over $10 million and will be awarded as a base schedule and option. The solicitation number is 693C73-21-R-000018 and bids are due in May 2021. Offerors must demonstrate experience on similar projects. The solicitation and any addenda will be available on beta.sam.gov. Registration in the System for Award Management database is required for payment. Subcontracting plans are mandatory for non-small businesses. The contracting agency is the Department of Transportation Federal Highway Administration.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hana Engineers and Consultants, LLC. • 7501 Boulder View Drive • Suite 620 • Richmond, Virginia 23225 • hanaengineers.com
February 19, 2020
Gregg Schwieterman Project Manager HNTB Corporation 2900 South Quincy Street, Suite 600 Arlington, VA 22206
Subject: Uncertainties associated with Hazardous Materials aspects of the Arlington National
Cemetery Southern Expansion (ANCSE) and Defense Access Road (DAR) Project
Dear Mr. Schwieterman, The purpose of this memo is to summarize the status of the environmental (i.e., hazardous materials) investigations related to the Arlington National Cemetery Southern Expansion (ANCSE) project and highlight some uncertainties associated with the property. Due to the status of the FOB2 property on the Federal Facilities Docket, Hana prepared an Environmental Site Inspection (SI) Report for the property in accordance with Comprehensive Environmental Response Compensation and Liability Act (CERCLA) requirements. The SI Report concluded that no remedial action was required at the FOB2 property based on future land use as part of ANC. However, this conclusion was predicated on the implementation of appropriate mitigation measures for Asbestos Containing Material (ACM) during the ANCSE Construction phase. The Virginia Department of Environmental Quality (VDEQ) Federal Facilities Section concurred with the SI Report in a letter dated December 13, 2019, which reiterated the need for appropriate mitigation measures during any excavation, grading or utility work. Hana will be assisting HNTB with the preparation of plans and specifications to identify all appropriate mitigation measures for
ANCSE.
Although the plans and specifications for ANCSE will identify appropriate mitigation measures for ANCSE, there are some uncertainties that should clarified to the project stakeholders moving forward. These uncertainties are identified and discussed below:
1. Portions of the ANCSE investigation area will be impacted by the Defense Access Road (DAR) project, which will include excavation, grading and utility installation. Since this project is a separate federal project from the ANCSE project, the plans and specifications detailing ACM mitigation measures for ANCSE are not applicable to the DAR project. However, if the DAR project does not also implement and document similar mitigation measures, this would be in violation of the concurrence letter from VDEQ and present potential regulatory issues.
Therefore, we recommend that ANC and/or USACE ensure that the DAR project receives all necessary data and reports related to this issue so that they can implement appropriate mitigation measures.
2. The quantity of ACM-impacted material requiring disposal cannot be accurately determined with the data collected to date. As the SI Report indicates, ACM is known to be buried in certain areas
Hana Engineers and Consultants, LLC. • 7501 Boulder View Drive • Suite 620 • Richmond, Virginia 23225 • hanaengineers.com of the site, primarily the eastern portion of the South Parking parcel. However, at the time the SI Report was prepared, specific areas of excavation and utility installation had not been identified. Therefore, previous sampling did not attempt to characterize material in these areas for future disposal. We believe focused sampling in areas proposed for excavation or utilities may be warranted so that material requiring off-site disposal during construction could be identified and quantified. Therefore, material requiring special disposal will not be firmly identified until the construction phase. We want to make clear that this presents great uncertainty with respect to planning for cost and schedule, as ACM material must be packaged, transported and disposed in accordance with 40 CFR Part 61, Subpart M and 9VAC20-81-620. Please note that this uncertainty also applies to the DAR project.
We wished to bring these uncertainties to your attention so that you can inform USACE and other stakeholders. We are glad to discuss these further with you and the project team.
Please contact me at 757-470-8361 or jeff.zoeckler@hanaengineers.com if you have any questions.
Sincerely, Jeff R. Zoeckler Vice President mailto:jeff.zoeckler@hanaengineers.com
T-21
Parking Parcel
Navy Annex/FOB2 Parcel
Southgate Road Right of Way Parcel
NEX Service Station Parcel
Air Force Memorial Parcel
T-6
T-40
T-39
T-35
T-23
B-10
T-9
T-38
T-31
T-11
T-25
T-27 T-24
T-22
T-13 T-19
T-12
T-41
T-42
T-14
T-8
T-7
T-4
T-5
T-3
T-2
T-1
T-43
T-37T-36
T-34
T-33
T-30
T-32
T-10
T-20
T-28
T-29
T-26
T-18
T-16
T-17
T-15
Filename: C:\Users\Christina Anderson\Documents\HANA\GIS\ANCSE\MXD\Results\Figure 7 - Asbestos Sampling Results.mxd
Asbestos Sampling Results Project No: 64516 Date: December 2016
ARLINGTON NATIONAL CEMETERY
SOUTHERN EXPANSION
Figure: 7
0 210 420105 Feet
Legend Soil Sampling Results - Asbestos
Not Detected
<0.25%
0.25
0.84
2%
Not Sampled
Bulk Debris Sampling Results - Asbestos Not Detected
10%
15%
20%
Not Sampled
Site Boundary
Parcel Boundaries
2015 ACM Soil Removal Area (approximate)
Former FOB2 Footprint
MEMORANDUM
Hana Engineers and Consultants, LLC. • 7501 Boulder View Drive • Suite 620 • Richmond, Virginia 23225 • hanaengineers.com 1
Date: January 13, 2021
To: Gregg Schweiterman, HNTB
From: Jeff Zoeckler, Vice President
Subject: Summary of asbestos survey and sampling
Dear Mr. Schweiterman, This memorandum summarizes the investigation to identify potential asbestos containing material (ACM) associated with inactive steam pipe within utility vaults along Southgate Rd, Columbia Pike, and within the ANC complex. A photographic log is included in Attachment 1. Analytical results are included in Attachment 2.
An initial site visit was conducted on November 23, 2020 by Hana and its subcontractor (ECS). The purpose of the visit was to locate and identify any potential ACM. A total of 5 vaults were opened.
Approximate vault locations are presented on Figure 1. After opening Vault 1, it was found to be filled with water and no steam pipes were identified. Water depth was approximately 8 feet deep. Vault 2 was also filled with water, but the steam pipe was just visible under the water surface. Vault 3 was approximately 14.5 feet deep and had approximately 2 feet of standing water and the top of a steam pipe was exposed. Steam pipes were also partially exposed in Vaults 4 and 5, which also contained water.
None of the observed steam pipes appeared to be wrapped with insulation. A closer inspection of the pipe was not conducted. The vaults could not be entered as they are considered a confined space and would require appropriate safety precautions for entry.
On January 6, 2021, Hana and subcontractors ECS and ACE Environmental conducted an inspection of inside the vaults and sampling of potential ACM. The air withing the vaults were monitored for potentially hazardous conditions. A safety wench and tripod were set up above the vault and the inspector was harnessed to the wench. The indoor air was continuously monitored while the inspector was inside the vault. Water was not pumped out of the vaults prior to inspection. Vaults 3, 4, and 5 were inspected. Upon inspection, the steam pipe did not have any visible insulation. The inspector identified other materials that could have contained ACM. These materials included: residual pipe material, steam pipe gasket, rubberized pipe fitting, fiberboard pipe covering, textured wall coating, white powder around pipe fitting (Vault 4).
The samples were analyzed by Scientific Analytical Institute, Inc. The results are provided in Attachment
2. None of the samples collected contained any ACM.
Please contact me at 757-470-8361 or jeff.zoeckler@hanaengineers.com if you have any questions.
Sincerely, Jeff R. Zoeckler, Vice President
Figure 1 Utility Vault Locations
Vault 1
Vault 2
Vault 3
Vault 4 Vault 5
Attachment 1 Photographic Log
PHOTOGRAPH LOG
Facility Name:
ANC
Site Location:
Along Southgate Dr and Columbia Pike
Project No.
64563
Photo No.
Date:
11/23/20
Description:
View North – Vault 1
Inside Vault 1
ANC
Site Location:
Along Southgate Dr and Columbia Pike
View East – Vault 2
View South – Vault 3
ANC
Site Location:
Along Southgate Dr and Columbia Pike
View Northeast – Vault 4
Inside Vault 4
ANC
Site Location:
Along Southgate Dr and Columbia Pike
View North – Vault 5
Inside Vault 5
ANC
Site Location:
Along Southgate Dr and Columbia Pike
01/6/21
Entry into Vault 5
Entry into Vault 5
ANC
Site Location:
Along Southgate Dr and Columbia Pike
Entry into Vault 4
Degrading Gasket in Vault
ANC
Site Location:
Along Southgate Dr and Columbia Pike
Textured wall inside Vault
View south - Vault 3
ANC
Site Location:
Along Southgate Dr and Columbia Pike
Inside Vault 3
Attachment 2 Analytical Results
Bulk Asbestos Analysis By Polarized Light Microscopy
EPA Method: 600/R-93/116 and 40 CFR, Part 763, Subpart E, App.E
11275/ ANCProject:
Sample ID
Lab Sample ID
Description
Lab Notes Asbestos Fibrous
Components Non-Fibrous Components
Attributes
Treatment
Michael HamillAttn:Customer: ECS Mid-Atlantic, LLC 14026 Thunderbolt Place Suite 100 Chantilly, VA 20151
Analysis ID: 71957320_PLM
Date Reported: 1/11/2021
Date Received: 1/7/2021
Lab Order ID: 71957320
None Detected
Residual Steam Pipe Material Brown, Black Non Fibrous Heterogeneous
Crushed71957320PLM_1
Other 100%
None Detected
Residual Steam Pipe Material Brown, Black Non Fibrous Heterogeneous
Crushed71957320PLM_2
Other 100%
None Detected
Black Steam Pipe Gasket Black Non Fibrous Heterogeneous
Dissolved71957320PLM_3
Fiber Glass Other 5% 95%
None Detected
Black Steam Pipe Gasket Black Non Fibrous Heterogeneous
Dissolved71957320PLM_4
Fiber Glass Other 5% 95%
None Detected
Black Rubberized Pipe Fitting Black Non Fibrous Homogeneous
Ashed71957320PLM_5
Other 100%
None Detected
Black Rubberized Pipe Fitting Black Non Fibrous Homogeneous
Ashed71957320PLM_6
Other 100%
None Detected
Brown Fiberboard Pipe Covering
Brown Non Fibrous Heterogeneous
Ashed71957320PLM_7
Fiber Glass Other 10% 90%
None Detected
Brown Fiberboard Pipe Covering
Brown Non Fibrous Heterogeneous
Ashed71957320PLM_8
Fiber Glass Other 10% 90%
Disclaimer: Due to the nature of the EPA 600 method, asbestos may not be detected in samples containing low levels of asbestos. We strongly recommend that analysis of floor tiles, vermiculite, and/or heterogeneous soil samples be conducted by TEM for confirmation of “None Detected” by PLM. This report relates only to the samples tested and may not be reproduced, except in full, without the written approval of SAI. This report may not be used by the client to claim product endorsement by NVLAP or any other agency of the U.S. government. Analytical uncertainty available upon request. Scientific Analytical Institute participates in the NVLAP Proficiency Testing program. Unless otherwise noted blank sample correction was not performed. Estimated MDL is 0.1%.
Approved SignatoryAnalyst
Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888
Yanelis Delgado (14)
P-F-002 r15 1/16/2021
Bulk Asbestos Analysis By Polarized Light Microscopy
EPA Method: 600/R-93/116 and 40 CFR, Part 763, Subpart E, App.E
11275/ ANCProject:
Sample ID
Lab Sample ID
Description
Lab Notes Asbestos Fibrous
Components Non-Fibrous Components
Attributes
Treatment
Michael HamillAttn:Customer: ECS Mid-Atlantic, LLC 14026 Thunderbolt Place Suite 100 Chantilly, VA 20151
Analysis ID: 71957320_PLM
Date Reported: 1/11/2021
Date Received: 1/7/2021
Lab Order ID: 71957320
None Detected
White Wall Texture Coating Cream Non Fibrous Homogeneous
Crushed71957320PLM_9
Other 100%
None Detected
White Wall Texture Coating Cream Non Fibrous Homogeneous
Crushed71957320PLM_10
Other 100%
None Detected
White Wall Texture Coating Cream Non Fibrous Homogeneous
Crushed71957320PLM_11
Other 100%
None Detected
White Power Steam Pipe Fitting
White Non Fibrous Homogeneous
Dissolved71957320PLM_12
Other 100%
None Detected
White Power Steam Pipe Fitting
White Non Fibrous Homogeneous
Dissolved71957320PLM_13
Other 100%
None Detected
White Power Steam Pipe Fitting
White Non Fibrous Homogeneous
Dissolved71957320PLM_14
Other 100%
Disclaimer: Due to the nature of the EPA 600 method, asbestos may not be detected in samples containing low levels of asbestos. We strongly recommend that analysis of floor tiles, vermiculite, and/or heterogeneous soil samples be conducted by TEM for confirmation of “None Detected” by PLM. This report relates only to the samples tested and may not be reproduced, except in full, without the written approval of SAI. This report may not be used by the client to claim product endorsement by NVLAP or any other agency of the U.S. government. Analytical uncertainty available upon request. Scientific Analytical Institute participates in the NVLAP Proficiency Testing program. Unless otherwise noted blank sample correction was not performed. Estimated MDL is 0.1%.
Approved SignatoryAnalyst
Scientific Analytical Institute, Inc. 4604 Dundas Dr. Greensboro, NC 27407 (336) 292-3888
Yanelis Delgado (14)
P-F-002 r15 1/16/2021
Client: ECS Mid-Atlantic, LLC Contact: Michael Hamill Address: 14026 Thunderbolt Place, Suite Phone: (703)-471 -8400 Fax:
Email: mhamill@ecslimited.com
Project: 11 2751AN C
Client Notes:
P.O.#. 112751ANC
Date Submitted: 1/6/2021 0:00
Analysis: PLM EPA 600/R-93/116 TumAroundTime: 3dav
!Samele Number Data1 B
1\0 6/ ·?;1D "Instructions:
Use Column •e• for your contact info
' To See an Example Click the ' bottom Exampla Tab.
Enter aamplea batween •cc• and ">>" o'• 7 Begin Samples with a •« "above Ille first sample Scientific and end with • •»• ba/ow Ille last sample. Analytical ,. Institute ,,.. !t-.J
Only Enter your data on the first sheet "Shee/1 •
Note: Data 1 and Data 2 are optional •· 4604 Dundas Drive
' fields that do not show up on the official Greensboro, NC 27407 report, however they wUI be Included Phone: 336.292,3888 in the electronic deta retumed to you Fax: 336.292.3313 to facilitate vour rein""'ration of the reoort data. Email: lab@sailab.com
Samele Descrlf!tlon
Data2
Residual Steam Pipe Material Facility Manhole Residual Steam Pipe Material Manhole 3 Access Black Steam Pipe Gasket Facility Manhole Black Steam Pipe Gasket Manhole 3 Access Black Rubberized Pipe Fitting Manhole 3 Access Black Rubberized Pipe Fitting Manhole 3 Access Brown Fiberboard Pipe Covering Manhole 3 Access Brown Fiberboard Pipe Covering Manhole 3 Access White Wall Texture Coating Manhole 3 Access White Wall Texture Coating Manhole 3 Access White Wall Texture Coating Manhole 4 Access White Power Steam Pipe Fitting Manhole 4 Access White Power Steam Pipe Fitting Manhole 4 Access White Power Steam Pipe Fitting Manhole 4 Access
1(1 I@~
A Ctfp ~ R·~ ft.;, v'>'l!-4 .,!'f
"M-:r. ,-c:: ,~~i~ E~ .. El
'"'"'"'~ Received By
I
| Asbestos_Sampling_Memo.pdf |
| Asbestos sampling |
| arlington national cemetEry southern expansion (ancse) |
| FROM: Jeff Zoeckler, Hana Project Manager |
| DATE: January 13, 2021 |
File details come from the government source that posted it. Updated .