RFP 283-22-0568
Attachment 1b
DELIVERABLE SCHEDULE
2023 NSDUH:
| No. |
| Deliverable |
| Due Dates |
| Required Formats |
| Number of copies |
| 1 |
| Monthly Progress Report |
(Task 1, section 1) 15th business day of each month through date of contract expiration E
| 2 |
| Monthly Cost to Complete Report |
| 15th business day of each |
month through date of
E
| 3 |
| Monthly Earned Value Management Data |
| 20th business day of each |
month through date of
E
| 4 |
| Expert Consultants Reports |
(Task 1, section 3)
participant
| 5 |
| Advisory Consultants Reports |
(Task 1, section 3)
participant
| 6 |
| Survey Instruments (CAI specifications in English and Spanish, and screening specifications) |
(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/122 OMB CAI & Screener 3/30/22
Draft CAI & Screener Programming Specs (English only) 8/15/22
Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/22 H, C, E
H, C, E
H, C,E
H, C, F, E 5, 2
5, 2
1,5, 5
(Task 2, section 1) Draft 09/1/22 Final 10/15/22 H, E H, E
| 8 |
| NSDUH OMB 60-Day Notice |
(Task 2, section 2) Draft 2/1/22 Final 3/1/22 H, E H, E
| 9 |
| NSDUH OMB Clearance Package |
(Task 2, section 2) Draft 3/30/22 Final 04/30/22 H, E H, E
(Task 2, section 3) Final 7/1/22 or 7 months prior to implementation
| 11 |
| Field Test OMB Package |
(Task 2, section 3) Final 04/15/22 or 7 months prior to implementation
| 12 |
| Field Test Analytic Data File |
and Codebook (Task 2, section 3) Final 9 months after end of field test data collection
(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E
H, E
| 14 |
| 6-Month Context Effects Report (Task 2, section 4) |
| Draft 8/30/23 |
Final 10/15/23 H,E H,E
| 15 |
| 12-Month Context Effects Report (Task 2, section 4) |
| Draft 05/15/24 |
Final 06/30/24 H,E H,E
(Task 3, section 5) Draft 5/15/22 Final 6/30/22 H, E H, E
| 17 |
| Sample Design Report including sampling frame and samples and SAS programs |
(Task 3, section 5) Draft 12/15/23 Final 1/31/24 H, E H, E
| 18 |
| Sample Experience Report |
(Task 3, section 8) Draft 6/1/24 Final 7/15/24 H, E H, E
| 19 |
| Interviewer Recruitment, Training |
and Field Mgmt Plan (Task 4, section 3) Draft 03/1/22 Final 04/15/22 H, E H, E
| 20 |
| Data Collection Quality Control |
Plan (Task 5, section 1) Draft 7/1/22 Final 8/15/22 H, E H,E
| 21 |
| Field and Web Status Report |
(Task 5, section 5)
| Monthly beginning 1/31/23 |
| E |
| 22 |
| Half-Year Field Observation Report |
(Task 5, section 6g) Draft 08/15/23 Final 09/30/23 H, E H, E
| 23 |
| Full-Year Field Observation Report |
(Task 5, section 6g) Draft 02/15/24 Final 04/1/24 H, E H, E
| 24 |
| Field Observation Summary |
(Task 5, section 6g) Weekly beginning 02/15/23 E
| 25 |
| Data Management and Processing Plan |
(Task 6, section 1) Draft 2/1/22 Final 3/15/22 H, E H, E
| 26 |
| 6-Month Detailed Tables (Task 7, section 1) |
| Shells 5/30/23 |
First 60 tables 8/30/23 Remaining tables 10/15/23 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2
| 27 |
| 12-Month Detailed Tables (Task 7, section 2) including SAS programs |
| Shells 4/15/24 |
Final 7/15/24 H, C, E H, C, E 2, 2
TBD
| 28 |
| Editing, Imputation and Evaluation Report |
(Task 7, section 3) including SAS programs Draft 7/1/24 Final 8/15/24 H, E H, E
| 29 |
| First Findings Reports (Task 7, section 4) |
| Draft 7/15/24 |
Final 8/1/24 PDF-P files 8/15/24 H, E H, E H, C, E 3, 3
| 30 |
| Methodological Summary and Definition Report (Task 7, section 5) |
| Draft 5/1/24 |
Final 6/15/24 H, E H, C, E 3, 3
| 31 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 32 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 33 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 34 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 35 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 36 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 37 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 38 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 39 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 40 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 41 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 42 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 43 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 44 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 45 |
| State Data Tables (Task 8, section 1) including SAS programs |
| Draft 9/1/24 |
Final 9/30/24 H, C, E H, C, E 2, 2 2, 2
| 46 |
| State Analytical Report (Task 8, section 1) |
| Draft 11/30/24 |
Final 2/1/25 H, C, E H, C, E 2, 2 2, 2
| 49 | |
| Raw Data File | (Task 9, section 1) |
| Draft 3/30/24 | |
Final 4/30/19 C, E C, E
| 50 |
| Raw Data File Codebook |
(Task 9, section 1) and SAS programs
| Draft 3/30/24Final 4/30/24 |
| H, C, E |
H, C, E 2, 2 2, 2
| 51 |
| Preliminary Analytic Data File |
(Task 9, section 2) Draft 5/15/24 Final 6/15/24 C, E C, E
| 52 |
| Preliminary Analytic Data File |
Codebook (Task 9, section 2) Draft 5/15/24 Final 6/15/24 H, C, E H, C, E 2, 2 2, 2
| 53 |
| Final Analytical Data File |
(Task 9, section 3) Draft 8/30/24 Final 9/30/24 C, E C, E
Final Analytic File Codebook (Task 9, section 3) and SAS programs Draft 8/30/24 Final 9/30/24 H, C, E H, C, E 3, 3 3, 3
(Task 9, section 4) Draft 10/30/24 Final 11/30/24 C, E C, E
| 56 |
| Public Use File Codebook |
(Task 9, section 4) Draft 10/30/24 Final 11/30/24 H, C, E H, C, E 3, 3 3, 3
| 57 |
| Variable Tracking Spreadsheet |
| Draft 10/30/24 |
Final 11/30/24 E E
| 58 |
| Methodological Resource Book |
(Task 10) Draft 3/1/25 Final 4/15/25 C, E H, C, E 1, 2
| 59 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 60 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 61 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 62 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 63 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 64 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 65 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 66 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 67 |
| Report or Journal Article |
(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2
| 68 |
| Report or Journal Article |
(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2
| 69 |
| Report or Journal Article |
(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2
| 70 |
| Questionnaire Development Plan |
| Draft- As required |
Final – As required H, E H, C, E 2, 2
| 71 |
| Questionnaire Development OMB Generic Clearance Package |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 72 |
| Questionnaire Development Activity Summary Report |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 73 |
| Questionnaire Development Results Summary Report |
| Draft – As required |
Final – As required H, E H, C, E
| 75 |
| Other Methodological Redesign Research Plan |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 76 |
| Other Methodological Redesign Summary Report |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 77 |
| Field Interviewer Equipment Refresh Testing Plan |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 78 |
| Field Interviewer Equipment Refresh OMB Generic Clearance Package |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 79 |
| Field Interviewer Equipment Refresh Evaluation Report |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 80 |
| Annual CIPSEA Training Documentation |
| Prior to start of data collection |
| E |
| 81 |
| Records Management Training Documentation |
| Prior to start of data collection |
| E |
| 83 |
| IT Plan |
| Final – 60 days Contract Effective Date (CED) |
| H, E |
| 3 |
| 84 |
| IT Security Plan |
| 4 weeks Contract Effective Date |
| H, E |
| 3 |
| 85 |
| Electronic Systems Questionnaire |
| 4 weeks Contract Effective Date |
| E |
2024 NSDUH:
| No. |
| Deliverable |
| Due Dates |
| Required Formats |
| Number of copies |
| 1 |
| Monthly Progress Report |
(Task 1, section 1) 15th business day of each month through date of
E
| 2 |
| Monthly Cost to Complete Report |
| 15th business day of each |
month through date of
E
| 3 |
| Monthly Earned Value Management Data |
| 20th business day of each |
month through date of
E
| 4 |
| Expert Consultants Reports |
(Task 1, section 3)
participant
| 5 |
| Advisory Consultants Reports |
(Task 1, section 3)
participant
| 6 |
| Survey Instruments (CAI specifications in English and Spanish, and screening specifications) |
(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/23
OMB CAI & Screener 3/30/18
Draft CAI & Screener Programming Specs (English only) 8/15/23
Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/23 H, C, E
5, 2
(Task 2, section 1) Draft 09/1/23 Final 10/15/23 H, E H, E
| 8 |
| NSDUH OMB 60-Day Notice |
(Task 2, section 2) Draft 2/1/23 Final 3/1/23 H, E H, E
| 9 |
| NSDUH OMB Clearance Package |
(Task 2, section 2) Draft 3/30/23 Final 04/30/23 H, E H, E
(Task 2, section 3) Final 7/1/23 or 7 months prior to implementation
| 11 |
| Field Test OMB Package |
(Task 2, section 3) Final 04/15/23 or 7 months prior to implementation
| 12 |
| Field Test Analytic Data File |
and Codebook (Task 2, section 3) Final 9 months after end of field test data collection
(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E
H, E
| 14 |
| 6-Month Context Effects Report (Task 2, section 4) |
| Draft 8/30/24 |
Final 10/15/24 H,E H,E
| 15 |
| 12-Month Context Effects Report (Task 2, section 4) |
| Draft 05/15/25 |
Final 06/30/25 H,E H,E
(Task 3, section 5) Draft 5/15/23 Final 6/30/23 H, E H, E
(Task 3, section 5) Draft 12/15/24 Final 1/31/25 H, E H, E
| 18 |
| Sample Experience Report including frame and samples |
(Task 3, section 8) Draft 6/1/25 Final 7/15/25 H, E H, E
| 19 |
| Interviewer Recruitment, Training |
and Field Mgmt Plan (Task 4, section 3) Draft 03/1/23 Final 04/15/23 H, E H, E
| 20 |
| Data Collection Quality Control |
Plan (Task 5, section 1) Draft 7/1/23 Final 8/15/23 H, E H,E
| 21 |
| Field and Web Status Report |
(Task 5, section 5)
| Monthly beginning 1/31/24 |
| E |
| 22 |
| Half-Year Field Observation Report |
(Task 5, section 6g) Draft 08/15/24 Final 09/30/24 H, E H, E
| 23 |
| Full-Year Field Observation Report |
(Task 5, section 6g) Draft 02/15/25 Final 04/1/25 H, E H, E
| 24 |
| Field Observation Summary |
(Task 5, section 6g) Weekly beginning 02/15/24 E
| 25 |
| Data Management and Processing Plan |
(Task 6, section 1) Draft 2/1/23 Final 3/15/23 H, E H, E
| 26 |
| 6-Month Detailed Tables (Task 7, section 1) |
| Shells 5/30/24 |
First 60 tables 8/30/24 Remaining tables 10/15/24 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2
| 27 |
| 12-Month Detailed Tables (Task 7, section 2) including programs |
| Shells 4/15/25 |
Final 7/15/25 H, C, E H, C, E 2, 2
TBD
| 28 |
| Editing, Imputation and Evaluation Report |
(Task 7, section 3) including programs Draft 7/1/25 Final 8/15/25 H, E H, E
| 29 |
| First Findings Reports (Task 7, section 4) |
| Draft 7/15/25 |
Final 8/1/25 PDF-P files 8/15/25 H, E H, E H, C, E 3, 3
| 30 |
| Methodological Summary and Definition Report (Task 7, section 5) |
| Draft 5/1/25 |
Final 6/15/25 H, E H, C, E 3, 3
| 31 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 32 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 33 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 34 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 35 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 36 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 37 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 38 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 39 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 40 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 41 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 42 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 43 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 44 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 45 |
| State Data Tables (Task 8, section 1) including programs |
| Draft 9/1/25 |
Final 9/30/25 H, C, E H, C, E 2, 2 2, 2
| 46 |
| State Analytical Report (Task 8, section 1) |
| Draft 11/30/25 |
Final 2/1/26 H, C, E H, C, E 2, 2 2, 2
| 47 | |
| Sub-state Data Tables | (Task 8, section 2) |
| Summary tables 2/15/26 | |
All tables 6/1/26 C, E C, E
| 48 |
| Sub-state Analytical Report |
(Task 8, section 2) Draft 3/30/26 Final 6/1/26 C, E C, E
| 49 | |
| Raw Data File | (Task 9, section 1) |
| Draft 3/30/25 | |
Final 4/30/25 C, E C, E
| 50 |
| Raw Data File Codebook |
(Task 9, section 1) Draft 3/30/25 Final 4/30/25 H, C, E H, C, E 2, 2 2, 2
| 51 |
| Preliminary Analytic Data File |
(Task 9, section 2) Draft 5/15/25 Final 6/15/25 C, E C, E
| 52 |
| Preliminary Analytic Data File |
Codebook (Task 9, section 2) Draft 5/15/25 Final 6/15/25 H, C, E H, C, E 2, 2 2, 2
| 53 |
| Final Analytical Data File |
(Task 9, section 3) Draft 8/30/25 Final 9/30/25 C, E C, E
| 54 |
| Final Analytic File Codebook |
(Task 9, section 3) Draft 8/30/25 Final 9/30/25 H, C, E H, C, E 3, 3 3, 3
(Task 9, section 4) Draft 10/30/25 Final 11/30/25 C, E C, E
| 56 |
| Public Use File Codebook |
(Task 9, section 4) Draft 10/30/25 Final 11/30/25 H, C, E H, C, E 3, 3 3, 3
| 57 |
| Variable Tracking Spreadsheet |
| Draft 10/30/25 |
Final 11/30/25 E
| 58 |
| Methodological Resource Book |
(Task 10) Draft 3/1/26 Final 4/15/26 C, E H, C, E 1, 2
| 59 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 60 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 61 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 62 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 63 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 64 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 65 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 66 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 67 |
| Report or Journal Article |
(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2
| 68 |
| Report or Journal Article |
(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2
| 69 |
| Report or Journal Article |
(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2
| 70 |
| Redesign Field Test Plan |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 71 |
| Redesign Field Test OMB Clearance Package |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 72 |
| Redesign Field Test Report |
| Draft – 3 months after data collection |
Final – 6 months after data collection H, E
H, C, E
5, 3
| 73 |
| Redesign Field Test Data File and Codebook |
| Draft – 8 months after data collection |
Final – 9 months after data collection H, C, E
H, C, E 3, 3
3, 3
| 80 |
| Annual CIPSEA Training Documentation |
| Prior to start of data collection |
| E |
| 81 |
| Records Management Training Documentation |
| Prior to start of data collection |
| E |
| 82 |
| IT Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
| 83 |
| IT Security Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
2025 NSDUH:
| No. |
| Deliverable |
| Due Dates |
| Required Formats |
| Number of copies |
| 1 |
| Monthly Progress Report |
(Task 1, section 1) 15th business day of each month through date of
E
| 2 |
| Monthly Cost to Complete Report |
| 15th business day of each |
month through date of
E
| 3 |
| Monthly Earned Value Management Data |
| 20th business day of each |
month through date of
E
| 4 |
| Expert Consultants Reports |
(Task 1, section 3)
participant
| 5 |
| Advisory Consultants Reports |
(Task 1, section 3)
participant
| 6 |
| Survey Instruments (CAI specifications in English and Spanish, and screening specifications) |
(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/19
OMB CAI & Screener 3/30/19
Draft CAI & Screener Programming Specs (English only) 8/15/19
Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/24 H, C, E
5, 2
(Task 2, section 1) Draft 09/1/24 Final 10/15/24 H, E H, E
| 8 |
| NSDUH OMB 60-Day Notice |
(Task 2, section 2) Draft 2/1/24 Final 3/1/24 H, E H, E
| 9 |
| NSDUH OMB Clearance Package |
(Task 2, section 2) Draft 3/30/24 Final 04/30/24 H, E H, E
(Task 2, section 3) Final 7/1/24 or 7 months prior to implementation
| 11 |
| Field Test OMB Package |
(Task 2, section 3) Final 04/15/24 or 7 months prior to implementation
| 12 |
| Field Test Analytic Data File |
and Codebook (Task 2, section 3) Final 9 months after end of field test data collection
(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E
H, E
| 14 |
| 6-Month Context Effects Report (Task 2, section 4) |
| Draft 8/30/25 |
Final 10/15/25 H,E H,E
| 15 |
| 12-Month Context Effects Report (Task 2, section 4) |
| Draft 05/15/26 |
Final 06/30/26 H,E H,E
(Task 3, section 5) Draft 5/15/24 Final 6/30/24 H, E H, E
| 17 |
| Sample Design Report including frame and samples |
(Task 3, section 5) Draft 12/15/25 Final 1/31/26 H, E H, E
| 18 |
| Sample Experience Report |
(Task 3, section 8) Draft 6/1/26 Final 7/15/26 H, E H, E
| 19 |
| Interviewer Recruitment, Training |
and Field Mgmt Plan (Task 4, section 3) Draft 03/1/24 Final 04/15/24 H, E H, E
| 20 |
| Data Collection Quality Control |
Plan (Task 5, section 1) Draft 7/1/24 Final 8/15/24 H, E H,E
| 21 |
| Field and Web Status Report |
(Task 5, section 5)
| Monthly beginning 1/31/25 |
| E |
| 22 |
| Half-Year Field Observation Report |
(Task 5, section 6g) Draft 08/15/25 Final 09/30/25 H, E H, E
| 23 |
| Full-Year Field Observation Report |
(Task 5, section 6g) Draft 02/15/26 Final 04/1/26 H, E H, E
| 24 |
| Field Observation Summary |
(Task 5, section 6g) Weekly beginning 02/15/25 E
| 25 |
| Data Management and Processing Plan |
(Task 6, section 1) Draft 2/1/24 Final 3/15/24 H, E H, E
| 26 |
| 6-Month Detailed Tables (Task 7, section 1) |
| Shells 5/30/25 |
First 60 tables 8/30/25 Remaining tables 10/15/25 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2
| 27 |
| 12-Month Detailed Tables (Task 7, section 2) including programs |
| Shells 4/15/26 |
Final 7/15/26 H, C, E H, C, E 2, 2
TBD
| 28 |
| Editing, Imputation and Evaluation Report |
(Task 7, section 3) including programs Draft 7/1/26 Final 8/15/26 H, E H, E
| 29 |
| First Findings Reports (Task 7, section 4) |
| Draft 7/15/26 |
Final 8/1/26 PDF-P files 8/15/26 H, E H, E H, C, E 3, 3
| 30 |
| Methodological Summary and Definition Report (Task 7, section 5) |
| Draft 5/1/26 |
Final 6/15/26 H, E H, C, E 3, 3
| 31 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 32 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 33 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 34 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 35 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 36 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 37 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 38 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 39 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 40 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 41 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 42 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 43 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 44 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 45 |
| State Data Tables (Task 8, section 1) including programs |
| Draft 9/1/26 |
Final 9/30/26 H, C, E H, C, E 2, 2 2, 2
| 46 |
| State Analytical Report (Task 8, section 1) |
| Draft 11/30/26 |
Final 2/1/27 H, C, E H, C, E 2, 2
| 49 | |
| Raw Data File | (Task 9, section 1) |
| Draft 3/30/26 | |
Final 4/30/26 C, E C, E
| 50 |
| Raw Data File Codebook |
(Task 9, section 1) Draft 3/30/26 Final 4/30/26 H, C, E H, C, E 2, 2 2, 2
| 51 |
| Preliminary Analytic Data File |
(Task 9, section 2) Draft 5/15/26 Final 6/15/26 C, E C, E
| 52 |
| Preliminary Analytic Data File |
Codebook (Task 9, section 2) Draft 5/15/26 Final 6/15/26 H, C, E H, C, E 2, 2 2, 2
| 53 |
| Final Analytical Data File |
(Task 9, section 3) Draft 8/30/26 Final 9/30/26 C, E C, E
| 54 |
| Final Analytic File Codebook |
(Task 9, section 3) Draft 8/30/26 Final 9/30/26 H, C, E H, C, E 3, 3 3, 3
(Task 9, section 4) Draft 10/30/26 Final 11/30/26 C, E C, E
| 56 |
| Public Use File Codebook |
(Task 9, section 4) Draft 10/30/26 Final 11/30/26 H, C, E H, C, E 3, 3 3, 3
| 57 |
| Variable Tracking Spreadsheet |
| Draft 10/30/26 |
Final 11/30/26 E
| 58 |
| Methodological Resource Book |
(Task 10) Draft 3/1/27 Final 4/15/27 C, E H, C, E 1, 2
| 59 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 60 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 61 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 62 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 63 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 64 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 65 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 66 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 67 |
| Report or Journal Article |
(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2
| 68 |
| Report or Journal Article |
(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2
| 69 |
| Report or Journal Article |
(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2
| 70 |
| Redesign Dress Rehearsal Field Test Plan |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 71 |
| Redesign Dress Rehearsal Field Test OMB Clearance Package |
| Draft – As required |
Final – As required H, E H, C, E 2, 2
| 72 |
| Redesign Dress Rehearsal Field Test Report |
| Draft – 3 months post data collection |
Final – 6 months post data collection H, E
H, C, E
5, 2
| 73 |
| Redesign Dress Rehearsal Field Test Data File and Codebook |
| Draft – 7 months post data collection |
Final – 9 months post data collection H, C, E
H, C, E 2, 2
2, 2
| 80 |
| Annual CIPSEA Training Documentation |
| Prior to start of data collection |
| E |
| 81 |
| Records Management Training Documentation |
| Prior to start of data collection |
| E |
| 82 |
| IT Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
| 83 |
| IT Security Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
2026 NSDUH:
| No. |
| Deliverable |
| Due Dates |
| Required Formats |
| Number of copies |
| 1 |
| Monthly Progress Report |
(Task 1, section 1) 15th business day of each month through date of
E
| 2 |
| Monthly Cost to Complete Report |
| 15th business day of each |
month through date of
E
| 3 |
| Monthly Earned Value Management Data |
| 20th business day of each |
month through date of
E
| 4 |
| Expert Consultants Reports |
(Task 1, section 3)
participant
| 5 |
| Advisory Consultants Reports |
(Task 1, section 3)
participant
| 6 |
| Survey Instruments (CAI specifications in English and Spanish, and screening specifications) |
(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/25
OMB CAI & Screener 3/30/25
Draft CAI & Screener Programming Specs (English only) 8/15/25
Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/25 H, C, E
5, 2
(Task 2, section 1) Draft 09/1/25 Final 10/15/25 H, E H, E
| 8 |
| NSDUH OMB 60-Day Notice |
(Task 2, section 2) Draft 2/1/25 Final 3/1/25 H, E H, E
| 9 |
| NSDUH OMB Clearance Package |
(Task 2, section 2) Draft 3/30/25 Final 04/30/25 H, E H, E
(Task 2, section 3) Final 7/1/25 or 7 months prior to implementation
| 11 |
| Field Test OMB Package |
(Task 2, section 3) Final 04/15/25 or 7 months prior to implementation
| 12 |
| Field Test Analytic Data File |
and Codebook (Task 2, section 3) Final 9 months after end of field test data collection
(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E
H, E
| 14 |
| 6-Month Context Effects Report (Task 2, section 4) |
| Draft 8/30/26 |
Final 10/15/26 H,E H,E
| 15 |
| 12-Month Context Effects Report (Task 2, section 4) |
| Draft 05/15/27 |
Final 06/30/27 H,E H,E
(Task 3, section 5) Draft 5/15/25 Final 6/30/25 H, E H, E
| 17 |
| Sample Design Report including frame and samples |
(Task 3, section 5) Draft 12/15/26 Final 1/31/27 H, E H, E
| 18 |
| Sample Experience Report |
(Task 3, section 8) Draft 6/1/27 Final 7/15/27 H, E H, E
| 19 |
| Interviewer Recruitment, Training |
and Field Mgmt Plan (Task 4, section 3) Draft 03/1/25 Final 04/15/25 H, E H, E
| 20 |
| Data Collection Quality Control |
Plan (Task 5, section 1) Draft 7/1/25 Final 8/15/25 H, E H,E
| 21 |
| Field and Web Status Report |
(Task 5, section 5)
| Monthly beginning 1/31/26 |
| E |
| 22 |
| Half-Year Field Observation Report |
(Task 5, section 6g) Draft 08/15/26 Final 09/30/26 H, E H, E
| 23 |
| Full-Year Field Observation Report |
(Task 5, section 6g) Draft 02/15/27 Final 04/1/27 H, E H, E
| 24 |
| Field Observation Summary |
(Task 5, section 6g) Weekly beginning 02/15/26 E
| 25 |
| Data Management and Processing Plan |
(Task 6, section 1) Draft 2/1/25 Final 3/15/25 H, E H, E
| 26 |
| 6-Month Detailed Tables (Task 7, section 1) |
| Shells 5/30/26 |
First 60 tables 8/30/26 Remaining tables 10/15/26 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2
| 27 |
| 12-Month Detailed Tables (Task 7, section 2) including programs |
| Shells 4/15/27 |
Final 7/15/27 H, C, E H, C, E 2, 2
TBD
| 28 |
| Editing, Imputation and Evaluation Report |
(Task 7, section 3) including programs Draft 7/1/27 Final 8/15/27 H, E H, E
| 29 |
| First Findings Reports (Task 7, section 4) |
| Draft 7/15/27 |
Final 8/1/27 PDF-P files 8/15/27 H, E H, E H, C, E 3, 3
| 30 |
| Methodological Summary and Definition Report (Task 7, section 5) |
| Draft 5/1/27 |
Final 6/15/27 H, E H, C, E 3, 3
| 31 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 32 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 33 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 34 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 35 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 36 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 37 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 38 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 39 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 40 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 41 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 42 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 43 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 44 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 45 |
| Census Effects Evaluation: Impact on National Estimates Report |
| Draft 7/15/27 |
Final 8/1/27 H, E H, C, E 3, 3
| 46 | |
| State Data Tables (Task 8, section 1) | including programs |
| Draft 9/1/27 | |
Final 9/30/27 H, C, E H, C, E 2, 2 2, 2
| 47 |
| State Analytic Report (Task 8, section 1) |
| Draft 11/30/27 |
Final 2/1/28 H, C, E H, C, E, 2, 2 2, 2
| 48 | | |
| Sub-state Data Tables | (Task 8, section 2) | including programs |
| Summary tables 2/15/28 | | |
All tables 6/1/28 C, E C, E
| 49 |
| Sub-state Analytical Report |
(Task 8, section 2) Draft 3/30/28 Final 6/1/28 C, E C, E
| 50 |
| Raw Data File Codebook |
(Task 9, section 1) Draft 3/30/27 Final 4/30/27 H, C, E H, C, E 2, 2 2, 2
| 51 |
| Preliminary Analytic Data File |
(Task 9, section 2) Draft 5/15/27 Final 6/15/27 C, E C, E
| 52 |
| Preliminary Analytic Data File |
Codebook (Task 9, section 2) Draft 5/15/27 Final 6/15/27 H, C, E H, C, E 2, 2 2, 2
| 53 |
| Final Analytical Data File |
(Task 9, section 3) Draft 8/30/27 Final 9/30/27 C, E C, E
| 54 |
| Final Analytic File Codebook |
(Task 9, section 3) Draft 8/30/27 Final 9/30/27 H, C, E H, C, E 3, 3 3, 3
(Task 9, section 4) Draft 10/30/27 Final 11/30/27 C, E C, E
| 56 |
| Public Use File Codebook |
(Task 9, section 4) Draft 10/30/27 Final 11/30/27 H, C, E H, C, E 3, 3 3, 3
| 57 |
| Variable Tracking Spreadsheet |
| Draft 10/30/27 |
Final 11/30/27 E
| 58 |
| Methodological Resource Book |
(Task 10) Draft 3/1/28 Final 4/15/28 C, E H, C, E 1, 2
| 59 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 60 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 61 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 62 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 63 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 64 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 65 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 66 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 67 |
| Report or Journal Article |
(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2
| 68 |
| Report or Journal Article |
(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2
| 69 |
| Report or Journal Article |
(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2
| 80 |
| Annual CIPSEA Training Documentation |
| Prior to start of data collection |
| E |
| 81 |
| Records Management Training Documentation |
| Prior to start of data collection |
| E |
| 82 |
| IT Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
| 83 |
| IT Security Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
2027 NSDUH:
| No. |
| Deliverable |
| Due Dates |
| Required Formats |
| Number of copies |
| 1 |
| Monthly Progress Report |
(Task 1, section 1) 15th business day of each month through date of
E
| 2 |
| Monthly Cost to Complete Report |
| 15th business day of each |
month through date of
E
| 3 |
| Monthly Earned Value Management Data |
| 20th business day of each |
month through date of
E
| 4 |
| Expert Consultants Reports |
(Task 1, section 3)
participant
| 5 |
| Advisory Consultants Reports |
(Task 1, section 3)
participant
| 6 |
| Survey Instruments (CAI specifications in English and Spanish, and screening specifications) |
(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/26
OMB CAI & Screener 3/30/26
Draft CAI & Screener Programming Specs (English only) 8/15/26
Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/26 H, C, E
5, 2
(Task 2, section 1) Draft 09/1/26 Final 10/15/26 H, E H, E
| 8 |
| NSDUH OMB 60-Day Notice |
(Task 2, section 2) Draft 2/1/26 Final 3/1/26 H, E H, E
| 9 |
| NSDUH OMB Clearance Package |
(Task 2, section 2) Draft 3/30/26 Final 04/30/26 H, E H, E
(Task 2, section 3) Final 7/1/26 or 7 months prior to implementation
| 11 |
| Field Test OMB Package |
(Task 2, section 3) Final 04/15/26 or 7 months prior to implementation
| 12 |
| Field Test Analytic Data File |
and Codebook (Task 2, section 3) Final 9 months after end of field test data collection
(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E
H, E
| 14 |
| 6-Month Context Effects Report (Task 2, section 4) |
| Draft 8/30/27 |
Final 10/15/27 H,E H,E
| 15 |
| 12-Month Context Effects Report (Task 2, section 4) |
| Draft 05/15/28 |
Final 06/30/28 H,E H,E
(Task 3, section 5) Draft 5/15/26 Final 6/30/26 H, E H, E
| 17 |
| Sample Design Report including frame and samples |
(Task 3, section 5) Draft 12/15/27 Final 1/31/28 H, E H, E
| 18 |
| Sample Experience Report |
(Task 3, section 8) Draft 6/1/28 Final 7/15/28 H, E H, E
| 19 |
| Interviewer Recruitment, Training |
and Field Mgmt Plan (Task 4, section 3) Draft 03/1/26 Final 04/15/26 H, E H, E
| 20 |
| Data Collection Quality Control |
Plan (Task 5, section 1) Draft 7/1/26 Final 8/15/26 H, E H,E
| 21 |
| Field and Web Status Report |
(Task 5, section 5)
| Monthly beginning 1/31/27 |
| E |
| 22 |
| Half-Year Field Observation Report |
(Task 5, section 6g) Draft 08/15/27 Final 09/30/27 H, E H, E
| 23 |
| Full-Year Field Observation Report |
(Task 5, section 6g) Draft 02/15/28 Final 04/1/28 H, E H, E
| 24 |
| Field Observation Summary |
(Task 5, section 6g) Weekly beginning 02/15/27 E
| 25 |
| Data Management and Processing Plan |
(Task 6, section 1) Draft 2/1/26 Final 3/15/26 H, E H, E
| 26 |
| 6-Month Detailed Tables (Task 7, section 1) |
| Shells 5/30/27 |
First 60 tables 8/30/27 Remaining tables 10/15/27 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2
| 27 |
| 12-Month Detailed Tables (Task 7, section 2) including programs |
| Shells 4/15/28 |
Final 7/15/28 H, C, E H, C, E 2, 2
TBD
| 28 |
| Editing, Imputation and Evaluation Report |
(Task 7, section 3) including programs Draft 7/1/28 Final 8/15/28 H, E H, E
| 29 |
| First Findings Reports (Task 7, section 4) |
| Draft 7/15/28 |
Final 8/1/28 PDF-P files 8/15/28 H, E H, E H, C, E 3, 3
| 30 |
| Methodological Summary and Definition Report (Task 7, section 5) |
| Draft 5/1/28 |
Final 6/15/28 H, E H, C, E 3, 3
| 31 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 32 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 33 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 34 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 35 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 36 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 37 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 38 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 39 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 40 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 41 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 42 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 43 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 44 |
| Ad hoc Research & Methodological Report (Task 7, section 6) |
| Draft -As required |
Final-As required H, E H, C, E 2, 2
| 45 |
| State Data Tables (Task 8, section 1) including programs |
| Draft 9/1/28 |
Final 9/30/28 H, C, E H, C, E 2, 2 2, 2
| 46 |
| State Analytical Report (Task 8, section 1) |
| Draft 11/30/28 |
Final 2/1/29 H, C, E H, C, E 2, 2
Draft 11/30/28 Final 2/1/29 H, C, E H, C, E 2, 2 2, 2
| 50 | |
| Raw Data File | (Task 9, section 1) |
| Draft 3/30/28 | |
Final 4/30/28 C, E C, E
| 51 |
| Raw Data File Codebook |
(Task 9, section 1) Draft 3/30/28 Final 4/30/28 H, C, E H, C, E 2, 2 2, 2
| 52 |
| Preliminary Analytic Data File |
(Task 9, section 2) Draft 5/15/28 Final 6/15/28 C, E C, E
| 53 |
| Preliminary Analytic Data File |
Codebook (Task 9, section 2) Draft 5/15/28 Final 6/15/28 H, C, E H, C, E 2, 2 2, 2
| 54 |
| Final Analytical Data File |
(Task 9, section 3) Draft 8/30/28 Final 9/30/28 C, E C, E
| 55 |
| Final Analytic File Codebook |
(Task 9, section 3) Draft 8/30/28 Final 9/30/28 H, C, E H, C, E 3, 3 3, 3
(Task 9, section 4) Draft 10/30/28 Final 11/30/28 C, E C, E
| 57 |
| Public Use File Codebook |
(Task 9, section 4) Draft 10/30/28 Final 11/30/28 H, C, E H, C, E 3, 3 3, 3
| 58 |
| Variable Tracking Spreadsheet |
| Draft 10/30/28 |
Final 11/30/28 E
| 59 |
| Methodological Resource Book |
(Task 10) Draft 3/1/29 Final 4/15/29 C, E H, C, E 1, 2
| 60 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 61 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 62 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 63 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 64 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 65 |
| Mental Health Analytic Report |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 66 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 67 |
| Mental Health Methodological Analysis |
(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2
| 68 |
| Report or Journal Article |
(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2
| 69 |
| Report or Journal Article |
(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2
| 70 |
| Report or Journal Article |
(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2
| 80 |
| Annual CIPSEA Training Documentation |
| Prior to start of data collection |
| E |
| 81 |
| Records Management Training Documentation |
| Prior to start of data collection |
| E |
| 82 |
| IT Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |
| 83 |
| IT Security Plan |
| 30 days prior to ATO anniversary review date |
| H, E |
| 3 |