RFP 283-22-0568_Attachment 1b Deliverable Schedule.docx

DOCX document 99 KB Posted

Attached to
2023-2027 National Surveys on Drug Use and Health (NSDUH)
Solicitation number
283-22-0568
Issued by

About this file

This document outlines deliverables and due dates for the 2023-2027 National Surveys on Drug Use and Health contract. The contractor will be required to design and conduct annual substance use and mental health surveys of approximately 152,000 US households to support prevalence estimates for the nation, 50 states, DC, Puerto Rico and other territories. Key deliverables include monthly progress reports; expert and advisory consultant reports; survey instruments in English and Spanish; interviewer materials; OMB submissions; sample design plans and reports; data collection, processing and analysis plans and reports; detailed tables; findings reports; and raw, preliminary and public use data files. Due dates range from monthly through the contract period to final reports up to 9 months post data collection. Formats include written documents, data files and codebooks. The number of copies varies by deliverable. The Substance Abuse and Mental Health Services Administration within the Department of Health and Human Services is the contracting agency.

View the file

Other files

File Type Posted
UPDATED RFP 283-22-0568 NSDUH RFP_11.05.2021.docx DOCX document
UPDATED_RFP_283-22-0568 Attachment 1a PWS_11.05.2021.docx DOCX document
SAMHSA-Technology-Standards-2019.pdf PDF
UPDATED_RFP 283-22-0568_Attachment 9 Packaging and Delivery of Proposals via eCPS_11.05.2021.docx DOCX document
283-22-0568 Amendment 1 SF-30.pdf PDF
NSDUH Questions and Answers for RFP 283-22-0568 _Amendment 1.docx DOCX document
RFP 283-22-0568_Attachment 16 Summary of Cost and Hours Spreadsheet.xls XLS spreadsheet
RFP 283-22-0568_Attachment 1c PWS TOA.docx DOCX document
RFP 283-22-0568_Attachment 13 Contractor_Perf_Form.docx DOCX document
RFP 283-22-0568_Attachment 4 Voucher Review Sheet.docx DOCX document
RFP 283-22-0568_Attachment 12 Client Letter.docx DOCX document
RFP 283-22-0568_Attachment 11 Contact Points.docx DOCX document
RFP 283-22-0568 NSDUH RFP.docx DOCX document
RFP 283-22-0568_Attach19b Credit Release Form.pdf PDF
RFP 283-22-0568_Attachment 2 QASP.docx DOCX document
RFP 283-22-0568_Attachment 14 Breakdown_Estimated_Costs rev.docx DOCX document
RFP 283-22-0568_Attachment 21_Sealed Proposal Cover Page and Instructions.docx DOCX document
RFP 283-22-0568_Attachment 17 HHS Section 508 Evaluation Template.docx DOCX document
RFP 283-22-0568_Attachment 6a Privacy Act - System Notice 09-30-0036.pdf PDF
RFP 283-22-0568_Attachment 20 NSDUH Reference Materials.pdf PDF
RFP 283-22-0568_Attachment 9 Packaging and Delivery of Proposals via eCPS.docx DOCX document
RFP 283-22-0568_Attachment 18 Subcontracting Plan.pdf PDF
RFP 283-22-0568_Attachment 7 Disclosure of Lobbying Activities.docx DOCX document
RFP 283-22-0568_Attachment 15 IT Total Estimated Cost Sheet.xls XLS spreadsheet
RFP 283-22-0568_Attach19a e-QIP Forms.pdf PDF
283-22-0568 RFP Cover Letter.pdf PDF
RFP 283-22-0568_Attachment 1d General Requirements.docx DOCX document
RFP 283-22-0568_Attachment 3 Wage Determinations.pdf PDF
RFP 283-22-0568_Attachment 5 Billing Instructions.docx DOCX document
RFP 283-22-0568_Attachment 1a PWS.docx DOCX document
RFP 283-22-0568_Attachment 6b Privacy Act - System Notice 09-90-1601.pdf PDF
RFP 283-22-0568_Attachment 10 Government Notice for Handling Proposals.docx DOCX document
RFP 283-22-0568_Attachment 8 Proposal Intent Response Form.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 283-22-0568

Attachment 1b

DELIVERABLE SCHEDULE

2023 NSDUH:

No.
Deliverable
Due Dates
Required Formats
Number of copies
1
Monthly Progress Report

(Task 1, section 1) 15th business day of each month through date of contract expiration E

2
Monthly Cost to Complete Report
15th business day of each

month through date of

E

3
Monthly Earned Value Management Data
20th business day of each

month through date of

E

4
Expert Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

5
Advisory Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

6
Survey Instruments (CAI specifications in English and Spanish, and screening specifications)

(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/122 OMB CAI & Screener 3/30/22

Draft CAI & Screener Programming Specs (English only) 8/15/22

Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/22 H, C, E

H, C, E

H, C,E

H, C, F, E 5, 2

5, 2

1,5, 5

7
Interviewer Materials

(Task 2, section 1) Draft 09/1/22 Final 10/15/22 H, E H, E

8
NSDUH OMB 60-Day Notice

(Task 2, section 2) Draft 2/1/22 Final 3/1/22 H, E H, E

9
NSDUH OMB Clearance Package

(Task 2, section 2) Draft 3/30/22 Final 04/30/22 H, E H, E

10
Field Test Protocol

(Task 2, section 3) Final 7/1/22 or 7 months prior to implementation

H, E
3
11
Field Test OMB Package

(Task 2, section 3) Final 04/15/22 or 7 months prior to implementation

H, E
5
12
Field Test Analytic Data File

and Codebook (Task 2, section 3) Final 9 months after end of field test data collection

H, E
2
13
Field Test Report

(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E

H, E

14
6-Month Context Effects Report (Task 2, section 4)
Draft 8/30/23

Final 10/15/23 H,E H,E

15
12-Month Context Effects Report (Task 2, section 4)
Draft 05/15/24

Final 06/30/24 H,E H,E

16
Sample Design Plan

(Task 3, section 5) Draft 5/15/22 Final 6/30/22 H, E H, E

17
Sample Design Report including sampling frame and samples and SAS programs

(Task 3, section 5) Draft 12/15/23 Final 1/31/24 H, E H, E

18
Sample Experience Report

(Task 3, section 8) Draft 6/1/24 Final 7/15/24 H, E H, E

19
Interviewer Recruitment, Training

and Field Mgmt Plan (Task 4, section 3) Draft 03/1/22 Final 04/15/22 H, E H, E

20
Data Collection Quality Control

Plan (Task 5, section 1) Draft 7/1/22 Final 8/15/22 H, E H,E

21
Field and Web Status Report

(Task 5, section 5)

Monthly beginning 1/31/23
E
22
Half-Year Field Observation Report

(Task 5, section 6g) Draft 08/15/23 Final 09/30/23 H, E H, E

23
Full-Year Field Observation Report

(Task 5, section 6g) Draft 02/15/24 Final 04/1/24 H, E H, E

24
Field Observation Summary

(Task 5, section 6g) Weekly beginning 02/15/23 E

25
Data Management and Processing Plan

(Task 6, section 1) Draft 2/1/22 Final 3/15/22 H, E H, E

26
6-Month Detailed Tables (Task 7, section 1)
Shells 5/30/23

First 60 tables 8/30/23 Remaining tables 10/15/23 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2

27
12-Month Detailed Tables (Task 7, section 2) including SAS programs
Shells 4/15/24

Final 7/15/24 H, C, E H, C, E 2, 2

TBD

28
Editing, Imputation and Evaluation Report

(Task 7, section 3) including SAS programs Draft 7/1/24 Final 8/15/24 H, E H, E

29
First Findings Reports (Task 7, section 4)
Draft 7/15/24

Final 8/1/24 PDF-P files 8/15/24 H, E H, E H, C, E 3, 3

30
Methodological Summary and Definition Report (Task 7, section 5)
Draft 5/1/24

Final 6/15/24 H, E H, C, E 3, 3

31
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

32
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

33
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

34
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

35
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

36
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

37
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

38
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

39
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

40
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

41
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

42
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

43
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

44
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

45
State Data Tables (Task 8, section 1) including SAS programs
Draft 9/1/24

Final 9/30/24 H, C, E H, C, E 2, 2 2, 2

46
State Analytical Report (Task 8, section 1)
Draft 11/30/24

Final 2/1/25 H, C, E H, C, E 2, 2 2, 2

49
Raw Data File(Task 9, section 1)
Draft 3/30/24

Final 4/30/19 C, E C, E

50
Raw Data File Codebook

(Task 9, section 1) and SAS programs

Draft 3/30/24Final 4/30/24
H, C, E

H, C, E 2, 2 2, 2

51
Preliminary Analytic Data File

(Task 9, section 2) Draft 5/15/24 Final 6/15/24 C, E C, E

52
Preliminary Analytic Data File

Codebook (Task 9, section 2) Draft 5/15/24 Final 6/15/24 H, C, E H, C, E 2, 2 2, 2

53
Final Analytical Data File

(Task 9, section 3) Draft 8/30/24 Final 9/30/24 C, E C, E

Final Analytic File Codebook (Task 9, section 3) and SAS programs Draft 8/30/24 Final 9/30/24 H, C, E H, C, E 3, 3 3, 3

55
Public Use Data File

(Task 9, section 4) Draft 10/30/24 Final 11/30/24 C, E C, E

56
Public Use File Codebook

(Task 9, section 4) Draft 10/30/24 Final 11/30/24 H, C, E H, C, E 3, 3 3, 3

57
Variable Tracking Spreadsheet
Draft 10/30/24

Final 11/30/24 E E

58
Methodological Resource Book

(Task 10) Draft 3/1/25 Final 4/15/25 C, E H, C, E 1, 2

59
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

60
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

61
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

62
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

63
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

64
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

65
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

66
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

67
Report or Journal Article

(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2

68
Report or Journal Article

(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2

69
Report or Journal Article

(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2

70
Questionnaire Development Plan
Draft- As required

Final – As required H, E H, C, E 2, 2

71
Questionnaire Development OMB Generic Clearance Package
Draft – As required

Final – As required H, E H, C, E 2, 2

72
Questionnaire Development Activity Summary Report
Draft – As required

Final – As required H, E H, C, E 2, 2

73
Questionnaire Development Results Summary Report
Draft – As required

Final – As required H, E H, C, E

75
Other Methodological Redesign Research Plan
Draft – As required

Final – As required H, E H, C, E 2, 2

76
Other Methodological Redesign Summary Report
Draft – As required

Final – As required H, E H, C, E 2, 2

77
Field Interviewer Equipment Refresh Testing Plan
Draft – As required

Final – As required H, E H, C, E 2, 2

78
Field Interviewer Equipment Refresh OMB Generic Clearance Package
Draft – As required

Final – As required H, E H, C, E 2, 2

79
Field Interviewer Equipment Refresh Evaluation Report
Draft – As required

Final – As required H, E H, C, E 2, 2

80
Annual CIPSEA Training Documentation
Prior to start of data collection
E
81
Records Management Training Documentation
Prior to start of data collection
E
83
IT Plan
Final – 60 days Contract Effective Date (CED)
H, E
3
84
IT Security Plan
4 weeks Contract Effective Date
H, E
3
85
Electronic Systems Questionnaire
4 weeks Contract Effective Date
E

2024 NSDUH:

No.
Deliverable
Due Dates
Required Formats
Number of copies
1
Monthly Progress Report

(Task 1, section 1) 15th business day of each month through date of

E

2
Monthly Cost to Complete Report
15th business day of each

month through date of

E

3
Monthly Earned Value Management Data
20th business day of each

month through date of

E

4
Expert Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

5
Advisory Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

6
Survey Instruments (CAI specifications in English and Spanish, and screening specifications)

(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/23

OMB CAI & Screener 3/30/18

Draft CAI & Screener Programming Specs (English only) 8/15/23

Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/23 H, C, E

5, 2

7
Interviewer Materials

(Task 2, section 1) Draft 09/1/23 Final 10/15/23 H, E H, E

8
NSDUH OMB 60-Day Notice

(Task 2, section 2) Draft 2/1/23 Final 3/1/23 H, E H, E

9
NSDUH OMB Clearance Package

(Task 2, section 2) Draft 3/30/23 Final 04/30/23 H, E H, E

10
Field Test Protocol

(Task 2, section 3) Final 7/1/23 or 7 months prior to implementation

H, E
3
11
Field Test OMB Package

(Task 2, section 3) Final 04/15/23 or 7 months prior to implementation

H, E
5
12
Field Test Analytic Data File

and Codebook (Task 2, section 3) Final 9 months after end of field test data collection

H, E
2
13
Field Test Report

(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E

H, E

14
6-Month Context Effects Report (Task 2, section 4)
Draft 8/30/24

Final 10/15/24 H,E H,E

15
12-Month Context Effects Report (Task 2, section 4)
Draft 05/15/25

Final 06/30/25 H,E H,E

16
Sample Design Plan

(Task 3, section 5) Draft 5/15/23 Final 6/30/23 H, E H, E

17
Sample Design Report

(Task 3, section 5) Draft 12/15/24 Final 1/31/25 H, E H, E

18
Sample Experience Report including frame and samples

(Task 3, section 8) Draft 6/1/25 Final 7/15/25 H, E H, E

19
Interviewer Recruitment, Training

and Field Mgmt Plan (Task 4, section 3) Draft 03/1/23 Final 04/15/23 H, E H, E

20
Data Collection Quality Control

Plan (Task 5, section 1) Draft 7/1/23 Final 8/15/23 H, E H,E

21
Field and Web Status Report

(Task 5, section 5)

Monthly beginning 1/31/24
E
22
Half-Year Field Observation Report

(Task 5, section 6g) Draft 08/15/24 Final 09/30/24 H, E H, E

23
Full-Year Field Observation Report

(Task 5, section 6g) Draft 02/15/25 Final 04/1/25 H, E H, E

24
Field Observation Summary

(Task 5, section 6g) Weekly beginning 02/15/24 E

25
Data Management and Processing Plan

(Task 6, section 1) Draft 2/1/23 Final 3/15/23 H, E H, E

26
6-Month Detailed Tables (Task 7, section 1)
Shells 5/30/24

First 60 tables 8/30/24 Remaining tables 10/15/24 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2

27
12-Month Detailed Tables (Task 7, section 2) including programs
Shells 4/15/25

Final 7/15/25 H, C, E H, C, E 2, 2

TBD

28
Editing, Imputation and Evaluation Report

(Task 7, section 3) including programs Draft 7/1/25 Final 8/15/25 H, E H, E

29
First Findings Reports (Task 7, section 4)
Draft 7/15/25

Final 8/1/25 PDF-P files 8/15/25 H, E H, E H, C, E 3, 3

30
Methodological Summary and Definition Report (Task 7, section 5)
Draft 5/1/25

Final 6/15/25 H, E H, C, E 3, 3

31
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

32
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

33
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

34
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

35
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

36
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

37
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

38
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

39
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

40
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

41
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

42
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

43
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

44
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

45
State Data Tables (Task 8, section 1) including programs
Draft 9/1/25

Final 9/30/25 H, C, E H, C, E 2, 2 2, 2

46
State Analytical Report (Task 8, section 1)
Draft 11/30/25

Final 2/1/26 H, C, E H, C, E 2, 2 2, 2

47
Sub-state Data Tables(Task 8, section 2)
Summary tables 2/15/26

All tables 6/1/26 C, E C, E

48
Sub-state Analytical Report

(Task 8, section 2) Draft 3/30/26 Final 6/1/26 C, E C, E

49
Raw Data File(Task 9, section 1)
Draft 3/30/25

Final 4/30/25 C, E C, E

50
Raw Data File Codebook

(Task 9, section 1) Draft 3/30/25 Final 4/30/25 H, C, E H, C, E 2, 2 2, 2

51
Preliminary Analytic Data File

(Task 9, section 2) Draft 5/15/25 Final 6/15/25 C, E C, E

52
Preliminary Analytic Data File

Codebook (Task 9, section 2) Draft 5/15/25 Final 6/15/25 H, C, E H, C, E 2, 2 2, 2

53
Final Analytical Data File

(Task 9, section 3) Draft 8/30/25 Final 9/30/25 C, E C, E

54
Final Analytic File Codebook

(Task 9, section 3) Draft 8/30/25 Final 9/30/25 H, C, E H, C, E 3, 3 3, 3

55
Public Use Data File

(Task 9, section 4) Draft 10/30/25 Final 11/30/25 C, E C, E

56
Public Use File Codebook

(Task 9, section 4) Draft 10/30/25 Final 11/30/25 H, C, E H, C, E 3, 3 3, 3

57
Variable Tracking Spreadsheet
Draft 10/30/25

Final 11/30/25 E

58
Methodological Resource Book

(Task 10) Draft 3/1/26 Final 4/15/26 C, E H, C, E 1, 2

59
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

60
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

61
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

62
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

63
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

64
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

65
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

66
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

67
Report or Journal Article

(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2

68
Report or Journal Article

(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2

69
Report or Journal Article

(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2

70
Redesign Field Test Plan
Draft – As required

Final – As required H, E H, C, E 2, 2

71
Redesign Field Test OMB Clearance Package
Draft – As required

Final – As required H, E H, C, E 2, 2

72
Redesign Field Test Report
Draft – 3 months after data collection

Final – 6 months after data collection H, E

H, C, E

5, 3

73
Redesign Field Test Data File and Codebook
Draft – 8 months after data collection

Final – 9 months after data collection H, C, E

H, C, E 3, 3

3, 3

78
INTENTIONALLY BLANK
79
INTENTIONALLY BLANK
80
Annual CIPSEA Training Documentation
Prior to start of data collection
E
81
Records Management Training Documentation
Prior to start of data collection
E
82
IT Plan
30 days prior to ATO anniversary review date
H, E
3
83
IT Security Plan
30 days prior to ATO anniversary review date
H, E
3

2025 NSDUH:

No.
Deliverable
Due Dates
Required Formats
Number of copies
1
Monthly Progress Report

(Task 1, section 1) 15th business day of each month through date of

E

2
Monthly Cost to Complete Report
15th business day of each

month through date of

E

3
Monthly Earned Value Management Data
20th business day of each

month through date of

E

4
Expert Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

5
Advisory Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

6
Survey Instruments (CAI specifications in English and Spanish, and screening specifications)

(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/19

OMB CAI & Screener 3/30/19

Draft CAI & Screener Programming Specs (English only) 8/15/19

Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/24 H, C, E

5, 2

7
Interviewer Materials

(Task 2, section 1) Draft 09/1/24 Final 10/15/24 H, E H, E

8
NSDUH OMB 60-Day Notice

(Task 2, section 2) Draft 2/1/24 Final 3/1/24 H, E H, E

9
NSDUH OMB Clearance Package

(Task 2, section 2) Draft 3/30/24 Final 04/30/24 H, E H, E

10
Field Test Protocol

(Task 2, section 3) Final 7/1/24 or 7 months prior to implementation

H, E
3
11
Field Test OMB Package

(Task 2, section 3) Final 04/15/24 or 7 months prior to implementation

H, E
5
12
Field Test Analytic Data File

and Codebook (Task 2, section 3) Final 9 months after end of field test data collection

H, E
2
13
Field Test Report

(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E

H, E

14
6-Month Context Effects Report (Task 2, section 4)
Draft 8/30/25

Final 10/15/25 H,E H,E

15
12-Month Context Effects Report (Task 2, section 4)
Draft 05/15/26

Final 06/30/26 H,E H,E

16
Sample Design Plan

(Task 3, section 5) Draft 5/15/24 Final 6/30/24 H, E H, E

17
Sample Design Report including frame and samples

(Task 3, section 5) Draft 12/15/25 Final 1/31/26 H, E H, E

18
Sample Experience Report

(Task 3, section 8) Draft 6/1/26 Final 7/15/26 H, E H, E

19
Interviewer Recruitment, Training

and Field Mgmt Plan (Task 4, section 3) Draft 03/1/24 Final 04/15/24 H, E H, E

20
Data Collection Quality Control

Plan (Task 5, section 1) Draft 7/1/24 Final 8/15/24 H, E H,E

21
Field and Web Status Report

(Task 5, section 5)

Monthly beginning 1/31/25
E
22
Half-Year Field Observation Report

(Task 5, section 6g) Draft 08/15/25 Final 09/30/25 H, E H, E

23
Full-Year Field Observation Report

(Task 5, section 6g) Draft 02/15/26 Final 04/1/26 H, E H, E

24
Field Observation Summary

(Task 5, section 6g) Weekly beginning 02/15/25 E

25
Data Management and Processing Plan

(Task 6, section 1) Draft 2/1/24 Final 3/15/24 H, E H, E

26
6-Month Detailed Tables (Task 7, section 1)
Shells 5/30/25

First 60 tables 8/30/25 Remaining tables 10/15/25 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2

27
12-Month Detailed Tables (Task 7, section 2) including programs
Shells 4/15/26

Final 7/15/26 H, C, E H, C, E 2, 2

TBD

28
Editing, Imputation and Evaluation Report

(Task 7, section 3) including programs Draft 7/1/26 Final 8/15/26 H, E H, E

29
First Findings Reports (Task 7, section 4)
Draft 7/15/26

Final 8/1/26 PDF-P files 8/15/26 H, E H, E H, C, E 3, 3

30
Methodological Summary and Definition Report (Task 7, section 5)
Draft 5/1/26

Final 6/15/26 H, E H, C, E 3, 3

31
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

32
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

33
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

34
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

35
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

36
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

37
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

38
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

39
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

40
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

41
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

42
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

43
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

44
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

45
State Data Tables (Task 8, section 1) including programs
Draft 9/1/26

Final 9/30/26 H, C, E H, C, E 2, 2 2, 2

46
State Analytical Report (Task 8, section 1)
Draft 11/30/26

Final 2/1/27 H, C, E H, C, E 2, 2

49
Raw Data File(Task 9, section 1)
Draft 3/30/26

Final 4/30/26 C, E C, E

50
Raw Data File Codebook

(Task 9, section 1) Draft 3/30/26 Final 4/30/26 H, C, E H, C, E 2, 2 2, 2

51
Preliminary Analytic Data File

(Task 9, section 2) Draft 5/15/26 Final 6/15/26 C, E C, E

52
Preliminary Analytic Data File

Codebook (Task 9, section 2) Draft 5/15/26 Final 6/15/26 H, C, E H, C, E 2, 2 2, 2

53
Final Analytical Data File

(Task 9, section 3) Draft 8/30/26 Final 9/30/26 C, E C, E

54
Final Analytic File Codebook

(Task 9, section 3) Draft 8/30/26 Final 9/30/26 H, C, E H, C, E 3, 3 3, 3

55
Public Use Data File

(Task 9, section 4) Draft 10/30/26 Final 11/30/26 C, E C, E

56
Public Use File Codebook

(Task 9, section 4) Draft 10/30/26 Final 11/30/26 H, C, E H, C, E 3, 3 3, 3

57
Variable Tracking Spreadsheet
Draft 10/30/26

Final 11/30/26 E

58
Methodological Resource Book

(Task 10) Draft 3/1/27 Final 4/15/27 C, E H, C, E 1, 2

59
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

60
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

61
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

62
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

63
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

64
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

65
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

66
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

67
Report or Journal Article

(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2

68
Report or Journal Article

(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2

69
Report or Journal Article

(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2

70
Redesign Dress Rehearsal Field Test Plan
Draft – As required

Final – As required H, E H, C, E 2, 2

71
Redesign Dress Rehearsal Field Test OMB Clearance Package
Draft – As required

Final – As required H, E H, C, E 2, 2

72
Redesign Dress Rehearsal Field Test Report
Draft – 3 months post data collection

Final – 6 months post data collection H, E

H, C, E

5, 2

73
Redesign Dress Rehearsal Field Test Data File and Codebook
Draft – 7 months post data collection

Final – 9 months post data collection H, C, E

H, C, E 2, 2

2, 2

74
INTENTIONALLY BLANK
75
INTENTIONALLY BLANK
76
INTENTIONALLY BLANK
77
INTENTIONALLY BLANK
78
INTENTIONALLY BLANK
79
INTENTIONALLY BLANK
80
Annual CIPSEA Training Documentation
Prior to start of data collection
E
81
Records Management Training Documentation
Prior to start of data collection
E
82
IT Plan
30 days prior to ATO anniversary review date
H, E
3
83
IT Security Plan
30 days prior to ATO anniversary review date
H, E
3

2026 NSDUH:

No.
Deliverable
Due Dates
Required Formats
Number of copies
1
Monthly Progress Report

(Task 1, section 1) 15th business day of each month through date of

E

2
Monthly Cost to Complete Report
15th business day of each

month through date of

E

3
Monthly Earned Value Management Data
20th business day of each

month through date of

E

4
Expert Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

5
Advisory Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

6
Survey Instruments (CAI specifications in English and Spanish, and screening specifications)

(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/25

OMB CAI & Screener 3/30/25

Draft CAI & Screener Programming Specs (English only) 8/15/25

Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/25 H, C, E

5, 2

7
Interviewer Materials

(Task 2, section 1) Draft 09/1/25 Final 10/15/25 H, E H, E

8
NSDUH OMB 60-Day Notice

(Task 2, section 2) Draft 2/1/25 Final 3/1/25 H, E H, E

9
NSDUH OMB Clearance Package

(Task 2, section 2) Draft 3/30/25 Final 04/30/25 H, E H, E

10
Field Test Protocol

(Task 2, section 3) Final 7/1/25 or 7 months prior to implementation

H, E
3
11
Field Test OMB Package

(Task 2, section 3) Final 04/15/25 or 7 months prior to implementation

H, E
5
12
Field Test Analytic Data File

and Codebook (Task 2, section 3) Final 9 months after end of field test data collection

H, E
2
13
Field Test Report

(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E

H, E

14
6-Month Context Effects Report (Task 2, section 4)
Draft 8/30/26

Final 10/15/26 H,E H,E

15
12-Month Context Effects Report (Task 2, section 4)
Draft 05/15/27

Final 06/30/27 H,E H,E

16
Sample Design Plan

(Task 3, section 5) Draft 5/15/25 Final 6/30/25 H, E H, E

17
Sample Design Report including frame and samples

(Task 3, section 5) Draft 12/15/26 Final 1/31/27 H, E H, E

18
Sample Experience Report

(Task 3, section 8) Draft 6/1/27 Final 7/15/27 H, E H, E

19
Interviewer Recruitment, Training

and Field Mgmt Plan (Task 4, section 3) Draft 03/1/25 Final 04/15/25 H, E H, E

20
Data Collection Quality Control

Plan (Task 5, section 1) Draft 7/1/25 Final 8/15/25 H, E H,E

21
Field and Web Status Report

(Task 5, section 5)

Monthly beginning 1/31/26
E
22
Half-Year Field Observation Report

(Task 5, section 6g) Draft 08/15/26 Final 09/30/26 H, E H, E

23
Full-Year Field Observation Report

(Task 5, section 6g) Draft 02/15/27 Final 04/1/27 H, E H, E

24
Field Observation Summary

(Task 5, section 6g) Weekly beginning 02/15/26 E

25
Data Management and Processing Plan

(Task 6, section 1) Draft 2/1/25 Final 3/15/25 H, E H, E

26
6-Month Detailed Tables (Task 7, section 1)
Shells 5/30/26

First 60 tables 8/30/26 Remaining tables 10/15/26 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2

27
12-Month Detailed Tables (Task 7, section 2) including programs
Shells 4/15/27

Final 7/15/27 H, C, E H, C, E 2, 2

TBD

28
Editing, Imputation and Evaluation Report

(Task 7, section 3) including programs Draft 7/1/27 Final 8/15/27 H, E H, E

29
First Findings Reports (Task 7, section 4)
Draft 7/15/27

Final 8/1/27 PDF-P files 8/15/27 H, E H, E H, C, E 3, 3

30
Methodological Summary and Definition Report (Task 7, section 5)
Draft 5/1/27

Final 6/15/27 H, E H, C, E 3, 3

31
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

32
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

33
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

34
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

35
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

36
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

37
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

38
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

39
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

40
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

41
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

42
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

43
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

44
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

45
Census Effects Evaluation: Impact on National Estimates Report
Draft 7/15/27

Final 8/1/27 H, E H, C, E 3, 3

46
State Data Tables (Task 8, section 1)including programs
Draft 9/1/27

Final 9/30/27 H, C, E H, C, E 2, 2 2, 2

47
State Analytic Report (Task 8, section 1)
Draft 11/30/27

Final 2/1/28 H, C, E H, C, E, 2, 2 2, 2

48
Sub-state Data Tables(Task 8, section 2)including programs
Summary tables 2/15/28

All tables 6/1/28 C, E C, E

49
Sub-state Analytical Report

(Task 8, section 2) Draft 3/30/28 Final 6/1/28 C, E C, E

50
Raw Data File Codebook

(Task 9, section 1) Draft 3/30/27 Final 4/30/27 H, C, E H, C, E 2, 2 2, 2

51
Preliminary Analytic Data File

(Task 9, section 2) Draft 5/15/27 Final 6/15/27 C, E C, E

52
Preliminary Analytic Data File

Codebook (Task 9, section 2) Draft 5/15/27 Final 6/15/27 H, C, E H, C, E 2, 2 2, 2

53
Final Analytical Data File

(Task 9, section 3) Draft 8/30/27 Final 9/30/27 C, E C, E

54
Final Analytic File Codebook

(Task 9, section 3) Draft 8/30/27 Final 9/30/27 H, C, E H, C, E 3, 3 3, 3

55
Public Use Data File

(Task 9, section 4) Draft 10/30/27 Final 11/30/27 C, E C, E

56
Public Use File Codebook

(Task 9, section 4) Draft 10/30/27 Final 11/30/27 H, C, E H, C, E 3, 3 3, 3

57
Variable Tracking Spreadsheet
Draft 10/30/27

Final 11/30/27 E

58
Methodological Resource Book

(Task 10) Draft 3/1/28 Final 4/15/28 C, E H, C, E 1, 2

59
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

60
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

61
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

62
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

63
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

64
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

65
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

66
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

67
Report or Journal Article

(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2

68
Report or Journal Article

(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2

69
Report or Journal Article

(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2

70
INTENTIONALLY BLANK
71
INTENTIONALLY BLANK
72
INTENTIONALLY BLANK
73
INTENTIONALLY BLANK
74
INTENTONALLY BLANK
75
INTENTIONALLY BLANK
76
INTENTIONALLY BLANK
77
INTENTIONALLY BLANK
78
INTENTIONALLY BLANK
79
INTENTIONALLY BLANK
80
Annual CIPSEA Training Documentation
Prior to start of data collection
E
81
Records Management Training Documentation
Prior to start of data collection
E
82
IT Plan
30 days prior to ATO anniversary review date
H, E
3
83
IT Security Plan
30 days prior to ATO anniversary review date
H, E
3

2027 NSDUH:

No.
Deliverable
Due Dates
Required Formats
Number of copies
1
Monthly Progress Report

(Task 1, section 1) 15th business day of each month through date of

E

2
Monthly Cost to Complete Report
15th business day of each

month through date of

E

3
Monthly Earned Value Management Data
20th business day of each

month through date of

E

4
Expert Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

5
Advisory Consultants Reports

(Task 1, section 3)

As produced
H, E
1 per

participant

6
Survey Instruments (CAI specifications in English and Spanish, and screening specifications)

(Task 2, section 1) Draft 60-da7 CAI & Screener Specs #1 for 60-FRN submission (English only) 1/15/26

OMB CAI & Screener 3/30/26

Draft CAI & Screener Programming Specs (English only) 8/15/26

Final Electronic Instrument, Final CAI Specs(Spanish only) 11/1/26 H, C, E

5, 2

7
Interviewer Materials

(Task 2, section 1) Draft 09/1/26 Final 10/15/26 H, E H, E

8
NSDUH OMB 60-Day Notice

(Task 2, section 2) Draft 2/1/26 Final 3/1/26 H, E H, E

9
NSDUH OMB Clearance Package

(Task 2, section 2) Draft 3/30/26 Final 04/30/26 H, E H, E

10
Field Test Protocol

(Task 2, section 3) Final 7/1/26 or 7 months prior to implementation

H, E
3
11
Field Test OMB Package

(Task 2, section 3) Final 04/15/26 or 7 months prior to implementation

H, E
5
12
Field Test Analytic Data File

and Codebook (Task 2, section 3) Final 9 months after end of field test data collection

H, E
2
13
Field Test Report

(Task 2, section 3) Draft – 3 months after end of data collection Final – 9 months after end of field test data collection H, E

H, E

14
6-Month Context Effects Report (Task 2, section 4)
Draft 8/30/27

Final 10/15/27 H,E H,E

15
12-Month Context Effects Report (Task 2, section 4)
Draft 05/15/28

Final 06/30/28 H,E H,E

16
Sample Design Plan

(Task 3, section 5) Draft 5/15/26 Final 6/30/26 H, E H, E

17
Sample Design Report including frame and samples

(Task 3, section 5) Draft 12/15/27 Final 1/31/28 H, E H, E

18
Sample Experience Report

(Task 3, section 8) Draft 6/1/28 Final 7/15/28 H, E H, E

19
Interviewer Recruitment, Training

and Field Mgmt Plan (Task 4, section 3) Draft 03/1/26 Final 04/15/26 H, E H, E

20
Data Collection Quality Control

Plan (Task 5, section 1) Draft 7/1/26 Final 8/15/26 H, E H,E

21
Field and Web Status Report

(Task 5, section 5)

Monthly beginning 1/31/27
E
22
Half-Year Field Observation Report

(Task 5, section 6g) Draft 08/15/27 Final 09/30/27 H, E H, E

23
Full-Year Field Observation Report

(Task 5, section 6g) Draft 02/15/28 Final 04/1/28 H, E H, E

24
Field Observation Summary

(Task 5, section 6g) Weekly beginning 02/15/27 E

25
Data Management and Processing Plan

(Task 6, section 1) Draft 2/1/26 Final 3/15/26 H, E H, E

26
6-Month Detailed Tables (Task 7, section 1)
Shells 5/30/27

First 60 tables 8/30/27 Remaining tables 10/15/27 H, C, E H, C, E H, C, E 2, 2 2, 2 2, 2

27
12-Month Detailed Tables (Task 7, section 2) including programs
Shells 4/15/28

Final 7/15/28 H, C, E H, C, E 2, 2

TBD

28
Editing, Imputation and Evaluation Report

(Task 7, section 3) including programs Draft 7/1/28 Final 8/15/28 H, E H, E

29
First Findings Reports (Task 7, section 4)
Draft 7/15/28

Final 8/1/28 PDF-P files 8/15/28 H, E H, E H, C, E 3, 3

30
Methodological Summary and Definition Report (Task 7, section 5)
Draft 5/1/28

Final 6/15/28 H, E H, C, E 3, 3

31
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

32
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

33
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

34
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

35
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

36
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

37
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

38
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

39
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

40
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

41
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

42
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

43
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

44
Ad hoc Research & Methodological Report (Task 7, section 6)
Draft -As required

Final-As required H, E H, C, E 2, 2

45
State Data Tables (Task 8, section 1) including programs
Draft 9/1/28

Final 9/30/28 H, C, E H, C, E 2, 2 2, 2

46
State Analytical Report (Task 8, section 1)
Draft 11/30/28

Final 2/1/29 H, C, E H, C, E 2, 2

Draft 11/30/28 Final 2/1/29 H, C, E H, C, E 2, 2 2, 2

50
Raw Data File(Task 9, section 1)
Draft 3/30/28

Final 4/30/28 C, E C, E

51
Raw Data File Codebook

(Task 9, section 1) Draft 3/30/28 Final 4/30/28 H, C, E H, C, E 2, 2 2, 2

52
Preliminary Analytic Data File

(Task 9, section 2) Draft 5/15/28 Final 6/15/28 C, E C, E

53
Preliminary Analytic Data File

Codebook (Task 9, section 2) Draft 5/15/28 Final 6/15/28 H, C, E H, C, E 2, 2 2, 2

54
Final Analytical Data File

(Task 9, section 3) Draft 8/30/28 Final 9/30/28 C, E C, E

55
Final Analytic File Codebook

(Task 9, section 3) Draft 8/30/28 Final 9/30/28 H, C, E H, C, E 3, 3 3, 3

56
Public Use Data File

(Task 9, section 4) Draft 10/30/28 Final 11/30/28 C, E C, E

57
Public Use File Codebook

(Task 9, section 4) Draft 10/30/28 Final 11/30/28 H, C, E H, C, E 3, 3 3, 3

58
Variable Tracking Spreadsheet
Draft 10/30/28

Final 11/30/28 E

59
Methodological Resource Book

(Task 10) Draft 3/1/29 Final 4/15/29 C, E H, C, E 1, 2

60
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

61
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

62
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

63
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

64
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

65
Mental Health Analytic Report

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

66
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

67
Mental Health Methodological Analysis

(Optional Task 1) Draft -As required Final-As required H, E H, C, E 2, 2

68
Report or Journal Article

(Optional Task 2, subtask 2.1) Draft -As required Final-As required H, E H, C, E 2, 2

69
Report or Journal Article

(Optional Task 2, subtask 2.2) Draft -As required Final-As required H, E H, C, E 2, 2

70
Report or Journal Article

(Optional Task 2, subtask 2.3) Draft -As required Final-As required H, E H, C, E 2, 2

71
INTENTIONALLY BLANK
72
INTENTIONALLY BLANK
73
INTENTIONALLY BLANK
74
INTENTONALLY BLANK
75
INTENTIONALLY BLANK
76
INTENTIONALLY BLANK
77
INTENTIONALLY BLANK
78
INTENTIONALLY BLANK
79
INTENTIONALLY BLANK
80
Annual CIPSEA Training Documentation
Prior to start of data collection
E
81
Records Management Training Documentation
Prior to start of data collection
E
82
IT Plan
30 days prior to ATO anniversary review date
H, E
3
83
IT Security Plan
30 days prior to ATO anniversary review date
H, E
3