This document is a Request for Information (RFI) from the California Department of Forestry and Fire Protection (CAL FIRE) for the replacement of an existing fire station located in Pauma Valley, San Diego County, California. The project involves the demolition of the existing facility and the design and construction of a new two-engine, 12-bed barracks/mess hall, single-building fire station with associated support structures and site improvements. The Prime Bidder must be a licensed B - General Building Contractor and self-perform a minimum of 30% of the work. Responses to the RFI are due by September 27, 2024.

The RFI document provides clarification on several contractor inquiries, including the state's budget for the project, responsibility for certain fees, pre-selected subcontractors, and specifications for the wash building and storm drainage. The state indicates that there are Small Business/Disabled Veteran Business Enterprise (SB/DVBE) participation incentives, but a 20% self-perform requirement in lieu of 30% will not be accepted. The state has not provided the engineer's estimate or budget for the project.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request For Information (RFI) #1

Contract Number 9TSC0105, Rincon FS Replacement

Questions Due 09/18//2024

Program Response Due 09/27/2024

Contractor- What is the State’s budget for this project?

Program Response – Not Provided

Contractor- Will the project still be awarded if all bids come back over the designated budget?

Program Response – Potentially

Contractor- Please confirm TACPA is optional in proposal response.

Program Response – The work is not in a TACPA zone so there is no TACPA incentive.

Contractor- Please confirm that the General contractor will not be responsible for the Egress Fees

Program Response – GC is responsible

Contractor- Please confirm that the General contractor will not be responsible for the Traffic Control Permit Fees

Program Response – GC is responsible

Contractor- Please verify if any subcontractors or vendors are pre-selected.

Program Response – No preselected subs

Contractor- Please confirm that the wash building will not have CMU walls of any height.

Program Response – There will be no CMU walls in Wash Building

Contractor- Please Confirm 4” water connection to be accomplished by water district.

Contractor will take responsibility past the meter.

Program Response – GC to coordinate with all utility providers

Contractor- Please verify if any species are required for slope retention during construction, and please provide hydro seeding requirements.

Program Response – No species required during construction, See Spec Section 329200 for hyrdro seeding requirements.

Contractor- Please confirm that no work is to be done to the existing 3 bay apparatus building that is to remain.

Program Response – Correct.

Contractor- On CG101 there is a section of Storm Drain with a size call out of 21” x 15”.

This is not a typical pipe size and we are unable to purchase. Please provide an updated pipe size for this section please see attached clouded plan page.

Program Response – This is a 21x15 Arch pipe this is available to purchase, but a substitution could be requested for multiple smaller diameter circular pipes (3 – 12” DIA pipes would be required, or 2 – 15” DIA).

Contractor- Please provide a detail for the “Flared end section” with an IE of 971.45’.

Please confirm this is the only outlet that will require a flared end section.

Program Response- 12” and smaller DIA pipe do not require a flared end. Per Spec Section 334200 3.4 B: Install outlets that spill onto grade, with flared end sections that match pipe, where indicated. Based on pipe selection a flared end from that manufacturer will be provided.

Contractor- Are there any SB/DVBE participation incentives?

Program Response-Yes

Contractor- Will you accept at least 20% self-perform requirement instead of 30%?

Program Response-No

Contractor- What is the engineer’s estimate or budget for this project?

Program Response-Not provided

Contractor- We would like to request an RFI deadline extension. Many subcontractors are too busy bidding projects within the next 2 weeks that they haven’t had time to thoroughly look at this project. Please advise.

Program Response- I’m ok with RFI’s until 9/27 @ 2 PM.