- Imperial County, Los Angeles County, Riverside County, San Diego County, Imperial City, East Los Angeles CDP, Glendale City, Lake Los Angeles CDP, Los Angeles City, Lake Riverside CDP, Riverside City, Imperial Beach City, Rancho San Diego CDP, San Diego City, San Diego Country Estates CDP, California
About this file
This document is an Addendum to Contract Number 9TSC0105 for the Rincon Fire Station Replacement project, issued by the California Department of Forestry and Fire Protection (CAL FIRE). The addendum replaces the Specification Section 329200-Turf and Grasses and Plan Page GC101 in their entirety. The project involves the demolition of an existing fire station and the design and construction of a new two-engine, 12-bed barracks/mess hall fire station, along with supporting buildings and site improvements, located in Pauma Valley, California. The Prime Bidder must be a licensed B - General Building Contractor and self-perform a minimum of 30% of the work. Bidders must access the Invitation for Bid (IFB) document through the State of California's online marketplace portal, Cal eProcure.
The contract is funded by the State of California and the project is located within San Diego County. The Prime Bidder must utilize applicable subcontracting if not licensed for all disciplines required to complete the service, and confirm licensing is current and active throughout the duration of the service. There are no specific set-aside requirements mentioned, and no information provided on incumbents or the current contracting environment.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF CALIFORNIA THE NATURE RESOURCES AGENCY Gavin Newsom, Governor
DEPARTMENT OF FORESTRY AND FIRE PROTECTION
P.O. Box 944246
SACRAMENTO, CA 94244-2460
Website: www.fire.ca.gov
(916) 653-7772
ADDENDUM 2 TO:
Contract Number 9TSC0105
Rincon Fire Station Replacement
September 23, 2024
Please review the following Addendum 2 to Contract Number 9TSC0105.
The contact person for this Addendum is:
California Department of Forestry and Fire Protection Dennis Schrader
1131 S Street Sacramento, CA 95811
Dennis.Scrhader@fire.ca.gov
Please note that no verbal information given will be binding upon the State unless such information is issued in writing as an official addendum.
Dennis Schrader Contracts Analyst
Please note the following changes to Contract Number 9TSC0105
A. Spec Section 329200-Turf and Grasses has been replaced in its entirety with Spec Section 329200-Turf and Grasses. See Attached Spec Section 329200-Turf and Grasses.
B. Plan Page, GC101 has been replaced in its entirety with Plan Page, GC101. See Attached Plan Page, GC101.
SECTION 329200 - TURF AND GRASSES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Hydroseeding.
2. Sodding.
3. Erosion -control materials.
B. Related Sections:
1. Section 311000 "Site Clearing" for topsoil stripping and stockpiling.
2. Section 312000 "Earth Moving" for excavation, filling and backfilling, and rough grading.
3. Section 328400 "Plant Irrigation Systems" for turf irrigation.
4. Section 329300 "Exterior Plants and Soils" for border edgings.
1.3 DEFINITIONS
A. Duff layer: The surface layer of native topsoil that is composed of mostly decayed leaves, twigs, and detritus.
B. Finish grade: Elevation of finished surface of planting soil.
C. Manufactured topsoil: Soil produced off-site by homogeneously blending mineral soils or sand with stabilized organic soil amendments to produce topsoil or planting soil.
D. Pesticide: A substance or mixture intended for preventing, destroying, repelling, or mitigating a pest. This includes insecticides, miticides, herbicides, fungicides, rodenticides, and molluscicides. It also includes substances or mixtures intended for use as a plant regulator, defoliant, or desiccant.
E. Pests: Living organisms that occur where they are not desired or that cause damage to plants, animals, or people. These include insects, mites, grubs, mollusks (snails and slugs), rodents (gophers, moles, and mice), unwanted plants (weeds), fungi, bacteria, and viruses.
F. Planting soil: Standardized topsoil; existing, native surface topsoil; existing, in-place surface soil; imported topsoil; or manufactured topsoil that is modified with soil amendments and perhaps fertilizers to produce a soil mixture best for plant growth.
G. Subgrade: Surface or elevation of subsoil remaining after excavation is complete, or top surface of a fill or backfill before planting soil is placed.
H. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.
I. Surface soil: Soil that is present at the top layer of the existing soil profile at the Project site. In undisturbed areas, the surface soil is typically topsoil, but in disturbed areas such as urban environments, the surface soil can be subsoil.
1.4 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.5 INFORMATION SUBMITTALS
A. General: Submit each submittal to the State in quantity, format, and type, as specified herein and as directed by the State. See Division 01330, “Submittal Procedures.”
B. Qualification Data: For landscape Installer.
C. Certification of Grass Seed: From seed vendor for each grass-seed monostand or mixture, stating the botanical and common name, percentage by weight of each species and variety, and percentage of purity, germination, and weed seed. Include the year of production and date of packaging.
D. Product data: For each type of product indicated.
1. Pesticides and Herbicides: Include product label and manufacturer's application instructions specific to this Project.
1.6 CLOSEOUT SUBMITTAL
A. Maintenance instructions: Recommended procedures to be established by the State for maintenance of turf during a calendar year. Submit before expiration of required initial maintenance periods.
1.7 QUALITY ASSURANCE
A. Installer qualifications: A qualified landscape Installer whose work has resulted in successful turf establishment.
1. Professional membership: Installer shall be a member in good standing of either the Professional Landcare Network or the American Nursery and Landscape Association.
Experience: Five years' experience in turf installation
2. Pesticide applicator: State licensed, commercial.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Seed and Other Packaged Materials: Deliver packaged materials in original, unopened containers showing weight, certified analysis, name and address of manufacturer, and indication of conformance with State and Federal laws, as applicable.
B. Sod: Harvest, deliver, store, and handle sod according to requirements in "Specifications for Turfgrass Sod Materials" and "Specifications for Turfgrass Sod Transplanting and Installation" in TPI's "Guideline Specifications to Turfgrass Sodding." Deliver sod in time for planting within 24 hours of harvesting. Protect sod from breakage and drying.
C. Bulk materials:
1. Do not dump or store bulk materials near structures, utilities, walkways and pavements, or on existing turf areas or plants.
2. Provide erosion-control measures to prevent erosion or displacement of bulk materials, discharge of soil-bearing water runoff, and airborne dust reaching adjacent properties, water conveyance systems, or walkways.
3. Accompany each delivery of bulk fertilizers and soil amendments with appropriate certificates.
1.9 FIELD CONDITIONS
A. Planting restrictions: Plant during one of the following periods. Coordinate planting periods with initial maintenance periods to provide required maintenance from date of planting completion.
B. Weather limitations: Proceed with planting only when existing and forecasted weather conditions permit planting to be performed when beneficial and optimum results may be obtained. Apply products during favorable weather conditions according to manufacturer's written instructions.
1.10 MAINTENANCE SERVICE
A. Initial turf maintenance Service: Provide full maintenance by skilled employees of landscape Installer. Maintain as required in Part 3. Begin maintenance immediately after each area is planted and continue until acceptable turf is established but for not less than the following periods:
1. Sodded turf: 90 from date of planting completion.
B. Continuing maintenance proposal: From installer to the State, in the form of a standard yearly (or other period) maintenance agreement, starting on date initial maintenance service is concluded. State services, obligations, conditions, and terms for agreement period and for future renewal options.
PART 2 - PRODUCTS
2.1 TURFGRASS SOD
A. Turfgrass Sod: Number 1 Quality/Premium, including limitations on thatch, weeds, diseases, nematodes, and insects, complying with "Specifications for Turfgrass Sod Materials" in TPI's "Guideline Specifications to Turfgrass Sodding." Furnish viable sod of uniform density, color, and texture that is strongly rooted and capable of vigorous growth and development when planted.
B. Turfgrass Species, Warm-Season Grass: [Buffalo grass (Bouteloua dactyloides).
2.2 FERTILIZERS
A. Commercial Fertilizer: Commercial-grade complete fertilizer of neutral character, consisting of fast- and slow-release nitrogen, 50 percent derived from natural organic sources of urea formaldehyde, phosphorous, and potassium in the following composition:
1. Composition:
a. 1 lb/1000 sq. ft. (0.45 kg/92.9 sq. m) of actual nitrogen, 4 percent phosphorous, and 2 percent potassium, by weight.
b. Nitrogen, phosphorous, and potassium in amounts recommended in soil reports from a qualified soil-testing laboratory.
B. Slow-Release Fertilizer: Granular or pelleted fertilizer consisting of 50 percent water-insoluble nitrogen, phosphorus, and potassium in the following composition:
1. Composition:
a. 20 percent nitrogen, 10 percent phosphorous, and 10 percent potassium, by weight.
b. Nitrogen, phosphorous, and potassium in amounts recommended in soil reports from a qualified soil-testing laboratory.
2.3 MULCHES
A. Straw mulch: Provide air-dry, clean, mildew- and seed-free, salt hay or threshed straw of wheat, rye, oats, or barley.
B. Sphagnum peat mulch: Partially decomposed sphagnum peat moss, finely divided or of granular texture, and with a pH range of 3.4 to 4.8.
C. Muck peat mulch: Partially decomposed moss peat, native peat, or reed-sedge peat, finely divided or of granular texture, with a pH range of 6 to 7.5, and having a water-absorbing capacity of 1100 to 2000 percent.
D. Compost mulch: Well-composted, stable, and weed-free organic matter, pH range of 5.5 to 8;
moisture content 35 to 55 percent by weight; 100 percent passing through 1-inch sieve; soluble salt content of 2 to 5 decisiemens/m; not exceeding 0.5 percent inert contaminants and free of substances toxic to plantings; and as follows:
1. Organic matter content: 50 to 60 percent of dry weight.
2. Feedstock: Agricultural, food, or industrial residuals; biosolids; yard trimmings; or source-separated or compostable mixed solid waste.
E. Fiber mulch: Biodegradable, dyed-wood, cellulose-fiber mulch; nontoxic and free of plant-growth or germination inhibitors; with a maximum moisture content of 15 percent and a pH range of 4.5 to 6.5.
F. Nonasphaltic tackifier: Colloidal tackifier recommended by fiber-mulch manufacturer for slurry application; nontoxic and free of plant-growth or germination inhibitors.
G. Asphalt emulsion: ASTM D 977, Grade SS-1; nontoxic and free of plant-growth or germination inhibitors.
2.4 PESTICIDES
A. General: Pesticide, registered and approved by EPA, acceptable to authorities having jurisdiction, and of type recommended by manufacturer for each specific problem and as required for Project conditions and application. Do not use restricted pesticides unless authorized in writing by authorities having jurisdiction.
B. Pre-emergent herbicide (selective and non-selective): Effective for controlling the germination or growth of weeds within planted areas at the soil level directly below the mulch layer.
C. Post-emergent herbicide (selective and non-selective): Effective for controlling weed growth that has already germinated.
2.5 EROSION-CONTROL MATERIALS
A. Erosion-control blankets: Biodegradable wood excelsior, straw, or coconut-fiber mat enclosed in a photodegradable plastic mesh. Include manufacturer's recommended steel wire staples, 6 inches long.
B. Erosion-control fiber mesh: Biodegradable burlap or spun-coir mesh, a minimum of 0.92 lb/sq.
yd. with 50 to 65 percent open area. Include manufacturer's recommended steel wire staples, 6 inches long.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas to be planted for compliance with requirements and other conditions affecting performance.
1. Verify that no foreign or deleterious material or liquid such as paint, paint washout, concrete slurry, concrete layers or chunks, cement, plaster, oils, gasoline, diesel fuel, paint thinner, turpentine, tar, roofing compound, or acid has been deposited in soil within a planting area.
2. Do not mix or place soils and soil amendments in frozen, wet, or muddy conditions.
3. Suspend soil spreading, grading, and tilling operations during periods of excessive soil moisture until the moisture content reaches acceptable levels to attain the required results.
4. Uniformly moisten excessively dry soil that is not workable and which is too dusty.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
C. If contamination by foreign or deleterious material or liquid is present in soil within a planting area, remove the soil and contamination as directed by the State Representative and replace with new planting soil.
3.2 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities, trees, shrubs, and plantings from damage caused by planting operations.
1. Protect adjacent and adjoining areas from hydro seeding and hydro mulching overspray.
2. Protect grade stakes set by others until directed to remove them.
B. Install erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.
3.3 TURF AREA PREPARATION
A. General: Prepare planting area for soil placement and mix planting soil according to Section 329113 "Soil Preparation.".
B. Placing Planting Soil: Place and mix planting soil in place over exposed subgrade.
1. Reduce elevation of planting soil to allow for soil thickness of sod
C. Moisten prepared area before planting if soil is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil.
D. Before planting, restore planting areas if eroded or otherwise disturbed after finish grading.
3.4 PREPARATION FOR EROSION-CONTROL MATERIALS
A. Prepare area as specified in "Turf Area Preparation" Article.
B. For erosion-control mats, install planting soil in two lifts, with second lift equal to thickness of erosion-control mats. Install erosion-control mat and fasten as recommended by material manufacturer.
C. Fill cells of erosion-control mat with planting soil and compact before planting.
D. For erosion-control blanket or mesh, install from top of slope, working downward, and as recommended by material manufacturer for site conditions. Fasten as recommended by material manufacturer.
E. Moisten prepared area before planting if surface is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil.
3.5 SODDING
A. Lay sod within 24 hours of harvesting. Do not lay sod if dormant or if ground is frozen or muddy.
B. Lay sod to form a solid mass with tightly fitted joints. Butt ends and sides of sod; do not stretch or overlap. Stagger sod strips or pads to offset joints in adjacent courses. Avoid damage to subgrade or sod during installation. Tamp and roll lightly to ensure contact with subgrade, eliminate air pockets, and form a smooth surface. Work sifted soil or fine sand into minor cracks between pieces of sod; remove excess to avoid smothering sod and adjacent grass.
1. Lay sod across angle of slopes exceeding 1:3.
2. Anchor sod on slopes exceeding 1:6 with wood pegs spaced as recommended by sod manufacturer but not less than 2 anchors per sod strip to prevent slippage.
C. Saturate sod with fine water spray within two hours of planting. During first week after planting, water daily or more frequently as necessary to maintain moist soil to a minimum depth of 1-1/2 inches below sod.
D. Water newly planted areas and keep moist until new turf is established.
3.6 HYDROSEEDING
A. hydroseeding: Mix specified seed, commercial fertilizer, and fiber mulch in water, using equipment specifically designed for hydroseed application. Continue mixing until uniformly blended into homogeneous slurry suitable for hydraulic application.
1. Mix slurry with fiber-mulch manufacturer’s recommended tackifier.
2. Spray-apply slurry uniformly to all areas to be seeded in a two-step process. Apply first slurry coat at a rate so that mulch component is deposited at not less than 500-lb/acre (5.2-kg/92.9 sq. m) dry weight, and seed component is deposited at not less than the specified seed-sowing rate. Apply slurry cover coat of fiber mulch (hydromulching) at a rate of 1000 lb/acre (10.4 kg/92.9 sq. m).
3.7 TURF MAINTENANCE
A. Maintain and establish turf by watering, fertilizing, weeding, mowing, trimming, replanting, and performing other operations as required to establish healthy, viable turf. Roll, regrade, and replant bare or eroded areas and remulch to produce a uniformly smooth turf. Provide materials and installation the same as those used in the original installation.
1. Fill in as necessary soil subsidence that may occur because of settling or other processes.
Replace materials and turf damaged or lost in areas of subsidence.
2. In areas where mulch has been disturbed by wind or maintenance operations, add new mulch and anchor as required to prevent displacement.
3. Apply treatments as required to keep turf and soil free of pests and pathogens or disease.
Use integrated pest management practices whenever possible to minimize the use of pesticides and reduce hazards.
B. Watering: Install and maintain temporary piping, hoses, and turf-watering equipment to convey water from sources and to keep turf uniformly moist to a depth of 4 inches
1. Schedule watering to prevent wilting, puddling, erosion, and displacement of seed or mulch. Lay out temporary watering system to avoid walking over muddy or newly planted areas.
2. Water turf with fine spray at a minimum rate of 1 inch per week unless rainfall precipitation is adequate.
C. Mow turf as soon as top growth is tall enough to cut. Repeat mowing to maintain specified height without cutting more than 1/3 of grass height. Remove no more than 1/3 of grass-leaf growth in initial or subsequent mowings. Do not delay mowing until grass blades bend over and become matted. Do not mow when grass is wet.
3.8 SATISFACTORY TURF
A. Turf installations shall meet the following criteria as determined by the State:
1. Satisfactory seeded turf: At end of maintenance period, a healthy, uniform, close stand of grass has been established, free of weeds and surface irregularities, with coverage exceeding 90 percent over any 10 sq. ft.
2. Satisfactory sodded turf: At end of maintenance period, a healthy, well-rooted, even-colored, viable turf has been established, free of weeds, open joints, bare areas, and surface irregularities.
3. Satisfactory plugged turf: At end of maintenance period, the required number of plugs has been established as well-rooted, viable patches of grass, and areas between plugs are free of weeds and other undesirable vegetation.
4. Satisfactory sprigged turf: At end of maintenance period, the required number of sprigs has been established as well-rooted, viable plants, and areas between sprigs are free of weeds and other undesirable vegetation.
B. Use specified materials to reestablish turf that does not comply with requirements and continue maintenance until turf is satisfactory.
3.9 PESTICIDE APPLICATION
A. Apply pesticides and other chemical products and biological control agents in accordance with requirements of authorities having jurisdiction and manufacturer's written recommendations.
Coordinate applications with the State's operations and others in proximity to the Work. Notify the State before each application is performed.
B. Post-emergent herbicides (selective and non-selective): Apply only as necessary to treat already-germinated weeds and in accordance with manufacturer's written recommendations.
3.10 CLEANUP AND PROTECTION
A. Promptly remove soil and debris created by turf work from paved areas. Clean wheels of vehicles before leaving site to avoid tracking soil onto roads, walks, or other paved areas.
B. Erect temporary fencing or barricades and warning signs as required to protect newly planted areas from traffic. Maintain fencing and barricades throughout initial maintenance period and remove after plantings are established.
C. Remove no degradable erosion-control measures after grass establishment period.
3.11 MAINTENANCE SERVICE
A. Turf Maintenance Service: Provide full maintenance by skilled employees of landscape Installer. Maintain as required in "Turf Maintenance" Article. Begin maintenance immediately after each area is planted and continue until acceptable turf is established, but for not less than the following periods:
1. Sodded Turf: 30 days from date of planting completion.
END OF SECTION 02920
dc d p c 2 c 1 c 2 w o pm 18 pm 18 o o 3 o or or x3 or x3 av x2 av x2 av x2 o p p 20 p p p p p p s 2 p p p p s 2 x3 s 2 p p s 2 o o
3-BAY
APPARATUS
BUILDING
RAISED GARDEN,STONE WALL PERIMETER
IE=968.3'
C M P
SET ALUM
CAP ON 3/4"
PIPE SET ALUM
CAP ON 3/4"
PIPE
SET ALUM PIPE &
CAP WITH STONE
MOUND
#100
SET BRASS CAP
ON 3/4" PIPE
EL:989.25'
ORCHARD ROAD (DIRT SURFACE)
#3
ALUM CAP,
STAMPED:
'RINCON
CONTROL 3'
EL:975.58'
W V
S
TA
TE
R
O U
TE
TO
P
AL
A P
AU
M A
VA
LL
EY
TO
V
AL
LE
Y C
EN
TE
R R
O
AD
R
IG
H T O F W A Y
R
IG
H T O F W A Y
R
IG
H T O F W A Y
APN 133-010-009
DOC#2001-0897659
McCORMICK RANCH, LLC
APN 133-050-032
DOC #78-295762
JAY & RAMONA WARD
M
CITRUS ORCHARD
CITRUS ORCHARD
CITRUS ORCHARD CITRUS ORCHARD
SECTION 23
SECTION 22
FO
G L
IN
E
FO
G L
IN
E
FO
G L
IN
E
FO
G L
IN
E
DOUBLE
YELLOW
LANE
STRIPES
POST
TELE WIRE
ORCHARD ROAD (DIRT SURFACE)
FO
G L
IN
E
(E
"W C
M
LC
(E 6" W C
(E
"W C
M
LC
(E 6" W C
S S
S
CO
NO
PARKING
H
YD
S
S
CLEAN AIR/
VANPOOL/EV
S
CO
S D
FIRE STATION
GEN
BLDG
V
EH
IC
LE
W A S H
EQ
U
IP
M
EN
T B
LD
G
STORAGE BUILDING
8" SD
8" SD
" S
D
8" SD
8" SD
12" SD
21"x15
" SD
12" SD
12" SD
CO
S D
S
V
EH
IC
LE
W A S H
C A N O P Y
" S
D
8" SD
NO
PARKING
TOC 981.93'
TOC 982.15'
FW 980.02'
SW 980.01'
TOC 980.14'
TOC 977.70'
TOC 977.37'
TOC 975.06'
TOC 975.28'
PVMT 973.92'
PVMT 974.62'
PVMT 974.78'
PVMT 974.85'
PVMT 975.28'
PVMT 974.08'
PVMT 977.99'
PVMT 977.03'
PVMT 979.84'
PVMT 981.33'
PAD EL 985.75'
PAD EL 987.25'
FW 986.42'
FW 986.42'
FW 986.42'
EL 988.47'
EL 980.84'
EL 985.75'
EL 986.25'
EL 983.25'
FL 987.87'
FL 980.58'
FL 977.80'
PVMT 983.37'
PVMT 976.08'
PVMT 979.47'
PVMT 979.98'
PVMT 981.00'
PVMT 979.69'
FL 971.50'
PVMT 978.15'
-0.4%
-1.9%
-3.0%
-4 .2
-4.7%
-4.9%
-5.0%
-3 .0
-2 .5
-2 .1
-5.0% -3.4%
-4.5%
-3 .6
-3.2%
-4.3%
-6.1%
-6.3%
-2 .8
-5 .5
TOC 975.28'
BOW 975.37'
TOW 977.37'
BOW 976.87'
TOW 978.87'
SW 981.47' SW 980.08'
N0 20 4010 20
1" = 20'-0"
CG102
SITE GRADING PLAN CG101
SITE GRADING PLAN
A. ECCLESTON
A. ECCLESTON
G. VINCENT
C U s e rs
\A E c c le s t\ A p p D a ta
\L o c a l\ T e m p \A c P u b lis h \2
C G
.d w g
J u n
:3
A M
V2
GENERAL NOTES
LEGEND
GRATES SHALL BE SET FLUSH WITH ADJACENT CONCRETE IN PAVED
AREAS AND BE SET 2" ABOVE ADJACENT FINISH GRADE IN LANDSCAPE
AREAS, SEE 3/CG501.
1. 18" x 18" CONCRETE CB: GRATE EL=983.09', SEE 2/CG502
2. 18" x 18" CONCRETE CB: GRATE EL=979.89', IE OUT=978.89'
3. STORMWATER INFILTRATION BASIN: BOT EL=977.72', SEE 4/CG501,
POND INLET: IE OUT=978.78'
4. 18" x 18" CONCRETE CB: GRATE EL=979.13', IE OUT=977.63'
5. CALTRANS TYPE "G0" CI: GRATE EL=980.11', IE IN=977.29',
IE OUT=977.19'
6. 18" x 18" CONCRETE CB: GRATE EL=979.82', IE OUT=977.82'
7. STORMWATER INFILTRATION BASIN: BOT EL=976.43', SEE 4/CG501,
POND INLETS: IE OUT=976.93'
8. 18" x 18" CONCRETE CB: GRATE EL=976.93', IE OUT=975.43'
9. CALTRANS TYPE "G0" CI: GRATE EL=976.71', IE OUT=974.71'
10. CALTRANS TYPE "G0" CI: GRATE EL=974.62', IE IN=972.62',
IE OUT=972.37'
11. CALTRANS TYPE "G0" CI: GRATE EL=974.08', CB#8 IE IN=972.53',
CI#10 IE IN=972.53', IE OUT=972.33'
12. 12" x 12" CONCRETE CB, GRATE EL=982.49', SEE 2/CG502
13. 18" x 18" CONCRETE CB, GRATE EL=979.75', RETAINING WALL BACK
DRAIN: IE IN=978.45', IE OUT=978.25'
14. 18" x 18" CONCRETE CB, GRATE EL=979.95', IE OUT = 978.95'
15. 18" x 18" CONCRETE CB: GRATE EL=979.95', IE OUT=978.95'
16. 18" x 18" CONCRETE CB: GRATE EL=979.95', IE IN=978.85', IE OUT=978.75'
17. STORMWATER INFILTRATION BASIN, BOT EL=975.90', SEE 4/CG501,
POND INLETS: IE OUT=977.80'
18. 18" x 18" CONCRETE CB: GRATE EL=976.96', IE OUT=974.96'
19. STORMWATER INFILTRATION BASIN, BOT EL=969.82', SEE 4/CG501
1. ALL ELEVATIONS ARE IN FEET.
2. ALL CONCRETE SIDEWALKS AND LANDINGS IMMEDIATELY ADJACENT TO BUILDING DOORS
SHALL BE 0.02 FT LOWER THAN FINISH FLOOR ELEVATIONS, UNO.
3. ALL GUTTER FLOW LINES OR FINISH GRADES ARE 0.5 FT BELOW THE TOP OF CURB
ELEVATION, UNO.
4. ZERO HEIGHT CURBS ARE FLUSH WITH ADJACENT SURFACE. TOC ELEVATIONS LABELED
INDICATES THE POINT AT WHICH A VARIABLE HEIGHT CURB REACHES THE STANDARD 6
INCHES.
5. ALL PUBLIC IMPROVEMENTS WITHIN COUNTY R.O.W. SHALL BE CONSTRUCTED TO
APPROVED COUNTY OF SAN DIEGO STANDARDS.
6. LOCATION AND VERTICAL ELEVATION INFORMATION OF EXISTING UTILITIES IS NOT KNOWN
OR PROVIDED. THE CONTRACTOR HAS THE TOTAL RESPONSIBILITY TO VERITY THE
LOCATION OF EXISTING UNDERGROUND UTILITIES AND TO NOTIFY UTILITY COMPANIES
WHEN WORKING IN THEIR PROXIMITY. PRIOR TO CONSTRUCTION, THE CONTRACTOR
SHALL POTHOLE TO VERIFY EXISTING UTILITY ALIGNMENTS AND ELEVATIONS. THE
CONTRACTOR SHALL PROVIDE CLEARANCES BETWEEN UTILITIES ACCEPTABLE TO
APPROPRIATE UTILITY OWNER, AND ENGINEER OF RECORD. CONTRACTOR SHALL NOTIFY
THE ENGINEER OF RECORD IF EXISTING UTILITIES ARE EXPECTED TO CONFLICT WITH
PROPOSED CONSTRUCTION, UPON DISCOVERY, PRIOR TO CONTINUING WORK.
7. CONTRACTOR IS RESPONSIBLE FOR CONTACTING "UNDERGROUND SERVICE ALERT" PRIOR
TO CONSTRUCTION.
8. UNIFORMLY SLOPE LANDSCAPE AREAS TOWARDS DRAINAGE INLETS.
EXISTING CONTOURS
PROPOSED CONTOURS
RETAINING WALL, SEE CG502
EARTHEN BERM
STORMWATER FLOW LINE
BOW BOTTOM OF WALL
CB CATCH BASIN
CI CURB INLET
EL ELEVATION
FFE FINISH FLOOR ELEVATION
FL FLOW LINE
FW BUILDING FLATWORK
IE PIPE INVERT ELEVATION
PVMT PAVEMENT
SD STORM DRAIN PIPE
TOC TOP OF CURB
1"
SHEET NUMBER
SHEET TITLE:
JOB NUMBER:
FILE DATE:
REVIEWED BY:
DRAWN BY:
DESIGNED BY:
RINCON
FIRE STATION
FACILITY
REPLACEMENT
16971 HIGHWAY 76
PAUMA VALLEY, CALIFORNIA 92061
SAN DIEGO COUNTY
DATENO. DESCRIPTION
P
LO
T D A
TE
P R O
JE
C T P A
TH
A
REVISIONS
V E R
B C D E F G H I J K L
A B C D E F G H I J K L
DSA Approval
OSFM Approval
TE
CHN
I CAL SERV I CES
Capital
Outlay
Rea l E state
Surveying Architecture& Engine erin g
Co ns tr uc t i on
Ma na ge me nt
To we rs Va ul ts
1131 S STREET, SACRAMENTO, CA 95811-2460
SHEET KEYNOTES
EARTHWORK NOTES
1. ALL GRADING SHALL BE PERFORMED IN CONFORMANCE WITH APPENDIX J OF THE 2019
CALIFORNIA BUILDING CODE.
2. EXISTING UNDOCUMENTED FILL
2.1. AS MUCH AS 8 FEET OF UNDOCUMENTED FILL WAS IDENTIFIED IN THE SOUTHEAST
CORNER OF THE SITE. APPROXIMATE LOCATION IS IDENTIFIED IN PROJECT
GEOTECHNICAL REPORT.
2.2. ALL UNDOCUMENTED FILL WITHIN FOOTPRINT OF PROPOSED IMPROVEMENTS
SHALL BE COMPLETELY REMOVED AND REPLACED WITH COMPACTED ENGINEERED
FILL.
2.3. UNDOCUMENTED FILL CANNOT BE USED AS ENGINEERED FILL.
3. ENGINEERED FILL
3.1. SOILS GENERATED ON SITE FROM CUT OPERATIONS ARE SUITABLE FOR USE AS
ENGINEERED FILL PROVIDED THE GEOTECHNICAL ENGINEER APPROVES THAT THE
SOILS WERE ADEQUATELY SAMPLED, TESTED, PROCESSED, STOCKPILED, AND
SELECTIVELY PLACED. SOILS SHALL NOT CONTAIN THE FOLLOWING:
3.1.1. DELETERIOUS MATERIAL.
3.1.2. OVERSIZED MATERIAL GREATER THAN 3 INCHES.
3.1.3. HIGHLY PLASTIC CLAYS.
3.2. IMPORT SOIL
3.2.1. SHALL BE WELL-GRADED MIXTURES OF GRAVEL, SAND, AND NON-PLASTIC
SILT, WITH LITTLE TO NO CLAY, WITH A LIQUID LIMIT OF LESS THAN 30 AND
PLASTICITY INDEX OF LESS THAN 12. IMPORT SHALL MEET REQUIREMENTS
3.1.1. - 3.1.3. ABOVE.
3.2.2. SHALL BE SAMPLED AND TESTED PRIOR TO TRANSPORTATION TO SITE.
3.2.3. SHALL BE NON-CORROSIVE.
4. GRADING
4.1. PRIOR TO GRADING OPERATIONS, A PRE-CONSTRUCTION MEETING SHALL BE
ARRANGED BY CONTRACTOR WITH PROJECT CIVIL ENGINEER, INSPECTOR OF
RECORD, REPRESENTATIVES OF THE GRADING CONTRACTOR AND GEOTECHINCAL
ENGINEER.
4.2. OVER-EXCAVATION BELOW FOUNDATIONS
4.2.1. BUILDING PADS SHALL BE OVER-EXCAVATED TO A DEPTH OF 3 FT BELOW
EXISTING GRADE OR TO A DEPTH OF 1 FT BELOW THE BOTTOM OF THE
FOOTINGS, WHICHEVER IS DEEPER. FOUNDATIONS SHALL BE BEARING
ENTIRELY UPON A UNIFORM THICKNESS OF ENGINEERED FILL.
4.2.2. EXPOSED OVER-EXCAVATED SURFACE SHALL BE SCARIFIED APPROXIMATELY
8 INCHES AND COMPACTED TO 90 PERCENT RELATIVE COMPACTION AT A
MOISTURE CONTENT WITHIN 3% OF OPTIMUM AND SUBSEQUENTLY PROOF
ROLLED WITH LOADED WATER TRUCK OR SIMILAR HEAVY EQUIPMENT.
UNSUITABLE AREAS THAT CANNOT REACH COMPACTION CRITERIA SHALL BE
OVER-EXCAVATED AND RE-COMPACTED WITH ENGINEERED FILL.
4.2.3. OVER-EXCAVATION AND ENGINEERED FILL REPLACEMENT OPERATIONS SHALL
EXTEND A MINIMUM DISTANCE OF AT LEAST 5 FEET OUTSIDE OF ALL
PROPOSED STRUCTURES.
4.3. ENGINEERED FILL SHALL BE COMPACTED IN HORIZONTAL LIFTS NOT EXCEEDING 8
INCHES (LOOSE THICKNESS). COMPACTION TESTING SHALL CONSIST OF ONE TEST
PER 500 CUBIC YARDS PLACED OR EVERY 1.5 FT OF ELEVATION GAIN, WHICHEVER
OCCURS FIRST.
5. CUT AND FILL SLOPES
5.1. ALL TEMPORARY EXCAVATION SLOPES SHALL MEET CAL-OSHA STANDARDS.
5.2. CONTRACTOR IS RESPONSIBLE TO PROVIDE SUFFICIENT AND SAFE EXCAVATION
SUPPORT AND PROTECT NEARBY UTILITIES, STRUCTURES, AND IMPROVEMENT.
CONTRACTOR SHALL NOTIFY AND COORDINATE WITH NEIGHBORING PROPERTY
OWNERS WHEN EXCAVATIONS AND EARTHWORK OPERATIONS ENCROACH UPON OR
BEYOND THE PROPERTY LINE.
5.3. CUT SLOPES SHALL BE NO STEEPER THAN 2:1 (HORIZONTAL:VERTICAL).
5.4. FILL SLOPES SHALL BE NO STEEPER THAN 2.5:1.
FIRE STATIONFFE 980.50'
MATCH EXISTING GRADE
AT FOG LINE
5 FT WIDE ROCK-LINED
SWALE SLOPED TO
BASIN, SEE 6/CG501
4 FT WIDE ROCK-LINED
SWALE SLOPED TO
BASIN, SEE 6/CG501
MATCH EXISTING
GRADE AT FL
FLARED END SECTION,
IE OUT=971.45'
IE OUT=978.65'
IE OUT=973.25'
5 FT WIDE ROCK-LINED
OVERFLOW SPILLWAY,
SEE 6/CG501
VEGETATED SWALE
SEE 2/CG501 FOR
SD TRENCH, TYP
STORAGE BUILDING
FFE 981.50'
V
EH
IC
LE
W A S H
B
LD
G A
N D C
A N O P Y
FF
E
0.
GEN
BLDG
FFE
986.50'
MATCH EXISTING
GRADE AT CONCRETE
MATCH EXISTING GRADE
AT CONCRETE
MATCH EXISTING GRADE
AT CONCRETE
CG501
IE OUT=978.25'
CONNECT RETAINING
WALL BACK DRAINS
CONNECT AND DAYLIGHT
RETAINING WALL BACK
DRAINS
DAYLIGHT RETAINING
WALL BACK DRAIN
A . E
. E CC LES T O
N
C 90716
C IV I L
R E G
IS
T E R E D
PROFES S IO NA L
E N G
IN
E E R
S
T A T E OF CA L IFORNI
A
FFE 978.7'
FUEL VAULT
FFE 978.28'
TRASH ENCLOSURE
FFE 975.50'
OFFICE OF THE STATE FIRE MARSHAL
shall be available on the project site at all times.
06/22/21
APPROVED FIRE AND PANIC ONLY
Approval of this plan does not authorize or approve any omission or deviation from applicable regulations. Final approval is subject to field inspection. One set of approved plans
20-2611
3-BAY
APPARATUSBUILDING
S S
S
CO
8" SD
12" SD
" S
D
2"
SD
TOC 977.70'
TOC 977.37'
PVMT 978.15'
-4.7%
-4.9%
-5.0% -3.4%
-2 .8
-5 .5
BOW 975.37'
TOW 977.37'
BOW 976.87'
TOW 978.87'
MATCH EXISTING GRADE
AT CONCRETE
DAYLIGHT RETAINING
WALL BACK DRAIN
FFE 978.7'
FUEL VAULT
FFE 978.28'
TRASH ENCLOSURE
FFE 975.50'
DSA
D E P A R T M E N T O F G E N E R A L S E R V I C E S
DIVISION OF THE STATE ARCHITECT
DSA
DIVISION OF THE STATE ARCHITECT
DSA
DIVISION OF THE STATE ARCHITECT
DSA
DIVISION OF THE STATE ARCHITECT
IDENTIFICATION STAMP
DIV. OF THE STATE ARCHITECT
APP: INC:
REVIEWED FOR
SS FLS ACS
DATE:
04-119744
07/12/2021
#9TSC0105 Rincon Fire Station Replacement-General Contractor
Colton_Peltzer Cloud
Colton_Peltzer Cloud
| Please note the following changes to Contract Number 9TSC0105 |
| 329200 - TURF AND GRASSES_R1-BID QUESTION.pdf |
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section Includes: |
| 1. Hydroseeding. |
| 2. Sodding. |
| 3. Erosion -control materials. |
| B. Related Sections: |
| 1. Section 311000 "Site Clearing" for topsoil stripping and stockpiling. |
| 2. Section 312000 "Earth Moving" for excavation, filling and backfilling, and rough grading. |
| 3. Section 328400 "Plant Irrigation Systems" for turf irrigation. |
| 4. Section 329300 "Exterior Plants and Soils" for border edgings. |
| 1.3 DEFINITIONS |
| A. Duff layer: The surface layer of native topsoil that is composed of mostly decayed leaves, twigs, and detritus. |
| B. Finish grade: Elevation of finished surface of planting soil. |
| C. Manufactured topsoil: Soil produced off-site by homogeneously blending mineral soils or sand with stabilized organic soil amendments to produce topsoil or planting soil. |
| D. Pesticide: A substance or mixture intended for preventing, destroying, repelling, or mitigating a pest. This includes insecticides, miticides, herbicides, fungicides, rodenticides, and molluscicides. It also includes substances or mixtures inten... |
| E. Pests: Living organisms that occur where they are not desired or that cause damage to plants, animals, or people. These include insects, mites, grubs, mollusks (snails and slugs), rodents (gophers, moles, and mice), unwanted plants (weeds), fungi... |
| F. Planting soil: Standardized topsoil; existing, native surface topsoil; existing, in-place surface soil; imported topsoil; or manufactured topsoil that is modified with soil amendments and perhaps fertilizers to produce a soil mixture best for plan... |
| G. Subgrade: Surface or elevation of subsoil remaining after excavation is complete, or top surface of a fill or backfill before planting soil is placed. |
| H. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms. |
| I. Surface soil: Soil that is present at the top layer of the existing soil profile at the Project site. In undisturbed areas, the surface soil is typically topsoil, but in disturbed areas such as urban environments, the surface soil can be subsoil. |
| 1.4 PREINSTALLATION MEETINGS |
| A. Preinstallation Conference: Conduct conference at Project site. |
| 1.5 INFORMATION SUBMITTALS |
| A. General: Submit each submittal to the State in quantity, format, and type, as specified herein and as directed by the State. See Division 01330, “Submittal Procedures.” |
| B. Qualification Data: For landscape Installer. |
| C. Certification of Grass Seed: From seed vendor for each grass-seed monostand or mixture, stating the botanical and common name, percentage by weight of each species and variety, and percentage of purity, germination, and weed seed. Include the year ... |
| D. Product data: For each type of product indicated. |
| 1. Pesticides and Herbicides: Include product label and manufacturer's application instructions specific to this Project. |
| 1.6 CLOSEOUT SUBMITTAL |
| A. Maintenance instructions: Recommended procedures to be established by the State for maintenance of turf during a calendar year. Submit before expiration of required initial maintenance periods. |
| 1.7 QUALITY ASSURANCE |
| A. Installer qualifications: A qualified landscape Installer whose work has resulted in successful turf establishment. |
| 1. Professional membership: Installer shall be a member in good standing of either the Professional Landcare Network or the American Nursery and Landscape Association. |
| Experience: Five years' experience in turf installation |
| 2. Pesticide applicator: State licensed, commercial. |
| 1.8 DELIVERY, STORAGE, AND HANDLING |
| A. Seed and Other Packaged Materials: Deliver packaged materials in original, unopened containers showing weight, certified analysis, name and address of manufacturer, and indication of conformance with State and Federal laws, as applicable. |
| B. Sod: Harvest, deliver, store, and handle sod according to requirements in "Specifications for Turfgrass Sod Materials" and "Specifications for Turfgrass Sod Transplanting and Installation" in TPI's "Guideline Specifications to Turfgrass Sodding." ... |
| C. Bulk materials: |
| 1. Do not dump or store bulk materials near structures, utilities, walkways and pavements, or on existing turf areas or plants. |
| 2. Provide erosion-control measures to prevent erosion or displacement of bulk materials, discharge of soil-bearing water runoff, and airborne dust reaching adjacent properties, water conveyance systems, or walkways. |
| 3. Accompany each delivery of bulk fertilizers and soil amendments with appropriate certificates. |
| 1.9 FIELD CONDITIONS |
| A. Planting restrictions: Plant during one of the following periods. Coordinate planting periods with initial maintenance periods to provide required maintenance from date of planting completion. |
| B. Weather limitations: Proceed with planting only when existing and forecasted weather conditions permit planting to be performed when beneficial and optimum results may be obtained. Apply products during favorable weather conditions according to m... |
| 1.10 MAINTENANCE SERVICE |
| A. Initial turf maintenance Service: Provide full maintenance by skilled employees of landscape Installer. Maintain as required in Part 3. Begin maintenance immediately after each area is planted and continue until acceptable turf is established bu... |
| 1. Sodded turf: 90 from date of planting completion. |
B. Continuing maintenance proposal: From installer to the State, in the form of a standard yearly (or other period) maintenance agreement, starting on date initial maintenance service is concluded. State services, obligations, conditions, and terms ...
| PART 2 - PRODUCTS |
| 2.1 TURFGRASS SOD |
| A. Turfgrass Sod: Number 1 Quality/Premium, including limitations on thatch, weeds, diseases, nematodes, and insects, complying with "Specifications for Turfgrass Sod Materials" in TPI's "Guideline Specifications to Turfgrass Sodding." Furnish viable ... |
| B. Turfgrass Species, Warm-Season Grass: [Buffalo grass (Bouteloua dactyloides). |
| 2.2 FERTILIZERS |
| A. Commercial Fertilizer: Commercial-grade complete fertilizer of neutral character, consisting of fast- and slow-release nitrogen, 50 percent derived from natural organic sources of urea formaldehyde, phosphorous, and potassium in the following compo... |
| 1. Composition: |
| a. 1 lb/1000 sq. ft. (0.45 kg/92.9 sq. m) of actual nitrogen, 4 percent phosphorous, and 2 percent potassium, by weight. |
| b. Nitrogen, phosphorous, and potassium in amounts recommended in soil reports from a qualified soil-testing laboratory. |
| B. Slow-Release Fertilizer: Granular or pelleted fertilizer consisting of 50 percent water-insoluble nitrogen, phosphorus, and potassium in the following composition: |
| 1. Composition: |
| a. 20 percent nitrogen, 10 percent phosphorous, and 10 percent potassium, by weight. |
| b. Nitrogen, phosphorous, and potassium in amounts recommended in soil reports from a qualified soil-testing laboratory. |
| 2.3 MULCHES |
| A. Straw mulch: Provide air-dry, clean, mildew- and seed-free, salt hay or threshed straw of wheat, rye, oats, or barley. |
| B. Sphagnum peat mulch: Partially decomposed sphagnum peat moss, finely divided or of granular texture, and with a pH range of 3.4 to 4.8. |
| C. Muck peat mulch: Partially decomposed moss peat, native peat, or reed-sedge peat, finely divided or of granular texture, with a pH range of 6 to 7.5, and having a water-absorbing capacity of 1100 to 2000 percent. |
| D. Compost mulch: Well-composted, stable, and weed-free organic matter, pH range of 5.5 to 8; moisture content 35 to 55 percent by weight; 100 percent passing through 1-inch sieve; soluble salt content of 2 to 5 decisiemens/m; not exceeding 0.5 perc... |
| 1. Organic matter content: 50 to 60 percent of dry weight. |
| 2. Feedstock: Agricultural, food, or industrial residuals; biosolids; yard trimmings; or source-separated or compostable mixed solid waste. |
| E. Fiber mulch: Biodegradable, dyed-wood, cellulose-fiber mulch; nontoxic and free of plant-growth or germination inhibitors; with a maximum moisture content of 15 percent and a pH range of 4.5 to 6.5. |
| F. Nonasphaltic tackifier: Colloidal tackifier recommended by fiber-mulch manufacturer for slurry application; nontoxic and free of plant-growth or germination inhibitors. |
| G. Asphalt emulsion: ASTM D 977, Grade SS-1; nontoxic and free of plant-growth or germination inhibitors. |
| 2.4 PESTICIDES |
| A. General: Pesticide, registered and approved by EPA, acceptable to authorities having jurisdiction, and of type recommended by manufacturer for each specific problem and as required for Project conditions and application. Do not use restricted pest... |
| B. Pre-emergent herbicide (selective and non-selective): Effective for controlling the germination or growth of weeds within planted areas at the soil level directly below the mulch layer. |
| C. Post-emergent herbicide (selective and non-selective): Effective for controlling weed growth that has already germinated. |
| 2.5 EROSION-CONTROL MATERIALS |
| A. Erosion-control blankets: Biodegradable wood excelsior, straw, or coconut-fiber mat enclosed in a photodegradable plastic mesh. Include manufacturer's recommended steel wire staples, 6 inches long. |
| B. Erosion-control fiber mesh: Biodegradable burlap or spun-coir mesh, a minimum of 0.92 lb/sq. yd. with 50 to 65 percent open area. Include manufacturer's recommended steel wire staples, 6 inches long. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Examine areas to be planted for compliance with requirements and other conditions affecting performance. |
| 1. Verify that no foreign or deleterious material or liquid such as paint, paint washout, concrete slurry, concrete layers or chunks, cement, plaster, oils, gasoline, diesel fuel, paint thinner, turpentine, tar, roofing compound, or acid has been depo... |
| 2. Do not mix or place soils and soil amendments in frozen, wet, or muddy conditions. |
| 3. Suspend soil spreading, grading, and tilling operations during periods of excessive soil moisture until the moisture content reaches acceptable levels to attain the required results. |
| 4. Uniformly moisten excessively dry soil that is not workable and which is too dusty. |
| B. Proceed with installation only after unsatisfactory conditions have been corrected. |
| C. If contamination by foreign or deleterious material or liquid is present in soil within a planting area, remove the soil and contamination as directed by the State Representative and replace with new planting soil. |
| 3.2 PREPARATION |
| A. Protect structures, utilities, sidewalks, pavements, and other facilities, trees, shrubs, and plantings from damage caused by planting operations. |
| 1. Protect adjacent and adjoining areas from hydro seeding and hydro mulching overspray. |
| 2. Protect grade stakes set by others until directed to remove them. |
B. Install erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.
| 3.3 TURF AREA PREPARATION |
| A. General: Prepare planting area for soil placement and mix planting soil according to Section 329113 "Soil Preparation.". |
| B. Placing Planting Soil: Place and mix planting soil in place over exposed subgrade. |
| 1. Reduce elevation of planting soil to allow for soil thickness of sod |
| C. Moisten prepared area before planting if soil is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil. |
| D. Before planting, restore planting areas if eroded or otherwise disturbed after finish grading. |
| 3.4 PREPARATION FOR EROSION-CONTROL MATERIALS |
| A. Prepare area as specified in "Turf Area Preparation" Article. |
| B. For erosion-control mats, install planting soil in two lifts, with second lift equal to thickness of erosion-control mats. Install erosion-control mat and fasten as recommended by material manufacturer. |
| C. Fill cells of erosion-control mat with planting soil and compact before planting. |
| D. For erosion-control blanket or mesh, install from top of slope, working downward, and as recommended by material manufacturer for site conditions. Fasten as recommended by material manufacturer. |
| E. Moisten prepared area before planting if surface is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil. |
| 3.5 SODDING |
| A. Lay sod within 24 hours of harvesting. Do not lay sod if dormant or if ground is frozen or muddy. |
| B. Lay sod to form a solid mass with tightly fitted joints. Butt ends and sides of sod; do not stretch or overlap. Stagger sod strips or pads to offset joints in adjacent courses. Avoid damage to subgrade or sod during installation. Tamp and roll ... |
| 1. Lay sod across angle of slopes exceeding 1:3. |
| 2. Anchor sod on slopes exceeding 1:6 with wood pegs spaced as recommended by sod manufacturer but not less than 2 anchors per sod strip to prevent slippage. |
| C. Saturate sod with fine water spray within two hours of planting. During first week after planting, water daily or more frequently as necessary to maintain moist soil to a minimum depth of 1-1/2 inches below sod. |
| D. Water newly planted areas and keep moist until new turf is established. |
| 3.6 HYDROSEEDING |
| A. hydroseeding: Mix specified seed, commercial fertilizer, and fiber mulch in water, using equipment specifically designed for hydroseed application. Continue mixing until uniformly blended into homogeneous slurry suitable for hydraulic application. |
| 1. Mix slurry with fiber-mulch manufacturer’s recommended tackifier. |
| 2. Spray-apply slurry uniformly to all areas to be seeded in a two-step process. Apply first slurry coat at a rate so that mulch component is deposited at not less than 500-lb/acre (5.2-kg/92.9 sq. m) dry weight, and seed component is deposited at not... |
| 3.7 TURF MAINTENANCE |
| A. Maintain and establish turf by watering, fertilizing, weeding, mowing, trimming, replanting, and performing other operations as required to establish healthy, viable turf. Roll, regrade, and replant bare or eroded areas and remulch to produce a un... |
| 1. Fill in as necessary soil subsidence that may occur because of settling or other processes. Replace materials and turf damaged or lost in areas of subsidence. |
| 2. In areas where mulch has been disturbed by wind or maintenance operations, add new mulch and anchor as required to prevent displacement. |
| 3. Apply treatments as required to keep turf and soil free of pests and pathogens or disease. Use integrated pest management practices whenever possible to minimize the use of pesticides and reduce hazards. |
| B. Watering: Install and maintain temporary piping, hoses, and turf-watering equipment to convey water from sources and to keep turf uniformly moist to a depth of 4 inches |
| 1. Schedule watering to prevent wilting, puddling, erosion, and displacement of seed or mulch. Lay out temporary watering system to avoid walking over muddy or newly planted areas. |
| 2. Water turf with fine spray at a minimum rate of 1 inch per week unless rainfall precipitation is adequate. |
C. Mow turf as soon as top growth is tall enough to cut. Repeat mowing to maintain specified height without cutting more than 1/3 of grass height. Remove no more than 1/3 of grass-leaf growth in initial or subsequent mowings. Do not delay mowing un...
| 3.8 SATISFACTORY TURF |
| A. Turf installations shall meet the following criteria as determined by the State: |
| 1. Satisfactory seeded turf: At end of maintenance period, a healthy, uniform, close stand of grass has been established, free of weeds and surface irregularities, with coverage exceeding 90 percent over any 10 sq. ft. |
| 2. Satisfactory sodded turf: At end of maintenance period, a healthy, well-rooted, even-colored, viable turf has been established, free of weeds, open joints, bare areas, and surface irregularities. |
| 3. Satisfactory plugged turf: At end of maintenance period, the required number of plugs has been established as well-rooted, viable patches of grass, and areas between plugs are free of weeds and other undesirable vegetation. |
| 4. Satisfactory sprigged turf: At end of maintenance period, the required number of sprigs has been established as well-rooted, viable plants, and areas between sprigs are free of weeds and other undesirable vegetation. |
B. Use specified materials to reestablish turf that does not comply with requirements and continue maintenance until turf is satisfactory.
| 3.9 PESTICIDE APPLICATION |
| A. Apply pesticides and other chemical products and biological control agents in accordance with requirements of authorities having jurisdiction and manufacturer's written recommendations. Coordinate applications with the State's operations and other... |
| B. Post-emergent herbicides (selective and non-selective): Apply only as necessary to treat already-germinated weeds and in accordance with manufacturer's written recommendations. |
| 3.10 CLEANUP AND PROTECTION |
| A. Promptly remove soil and debris created by turf work from paved areas. Clean wheels of vehicles before leaving site to avoid tracking soil onto roads, walks, or other paved areas. |
| B. Erect temporary fencing or barricades and warning signs as required to protect newly planted areas from traffic. Maintain fencing and barricades throughout initial maintenance period and remove after plantings are established. |
| C. Remove no degradable erosion-control measures after grass establishment period. |
| 3.11 MAINTENANCE SERVICE |
| A. Turf Maintenance Service: Provide full maintenance by skilled employees of landscape Installer. Maintain as required in "Turf Maintenance" Article. Begin maintenance immediately after each area is planted and continue until acceptable turf is estab... |