This Statement of Work (SOW) details a roofing replacement project for the Lower Admin Building at the Federal Correctional Institution (FCI) Texarkana in Texas. The project involves completely removing the existing roof system, including gypsum decking, and replacing it with new plywood decking, insulation, vapor barrier, and a 50-mil PVC single-ply membrane. The scope of work includes installing new sheet metal flashings, wood nailers, raising exhaust vents, and resealing control joints, with an approximate roof area of 5,730 square feet.
Key project requirements include a 30-calendar day completion timeline from Notice to Proceed, working five days per week, and strict security protocols for contractor access. The contractor must provide all necessary labor, materials, tools, and equipment, comply with safety standards, and adhere to institution security guidelines. The project will be completed with a 2-year contractor guarantee and a 20-year manufacturing warranty. The Federal Bureau of Prisons will provide minimal utilities, and the contractor is responsible for all cleanup, material disposal, and maintaining a clean work site in accordance with federal, state, and local regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Replace Roofing-Lower Admin Building
FCI TEXARKANA
I. SPECIFICATIONS
A. INTRODUCTION
The Federal Bureau of Prisons (FBOP), Federal Corrections Institution (FCI) Texarkana intends to award to a responsible entity for the provision of the repair and modernization of the Lower Admin Building roof, at FCI Texarkana, 4001 Leopard Drive, Texarkana, Tx 75501.
Awarded contractor will be required to provide all labor, materials, tools, permits, insurance, and equipment, necessary to accomplish the following scope of work.
Lower Admin building roof Location: Building #1
SQFT: Approximately 5,730
B. SCOPE OF WORK
Furnish all required engineering, permits, material, and labor.
Upon completion of contract, the roof will be a complete, fully functional, and working system.
Service will comply with all Local, State, and Federal codes, and meet all safety requirements.
Awarded Contractor shall be a reputable roofing provider with proven, experience in industrial roofing. The Contractor shall provide the Institution’s Contracting Officer and his Representative (COR) with such proof.
Work shall include but not limited to the following base-bid items.
• Contractor will stage proper laydown areas for material and personnel prior to work daily.
• Contractor will provide and utilize a Crane for loading materials, removing and replacing current HVAC equipment.
• Contractor will verify the function of the existing roof drains before construction has started and after construction is completed.
• Contractor will tear off the existing roof system down to the existing deck.
• Upon removal of the existing roof system, contractor will remove the existing gypsum decking down to the
Structural Framing.
• Contractor will replace existing gypsum decking with all newly installed ¾” plywood decking to existing structural framing per manufacturers standards.
• Contractor will account for capping curbs after old RTU is removed.
• Install Manufacturer standard Self-Adhering Vapor Barrier over the new deck.
• Install 1 layer of 2” Polyisocyanurate Insulation.
• Install 50-Mil PVC single-ply membrane.
• Provide new Sheet Metal Flashings at all Curbs, Walls, Coping, and Expansion Joints.
• Provide new Wood Nailers at Perimeter Edge, Coping, and Expansion Joint.
• Contractor will account for raising 1 Exhaust Vents to a minimum 8-inch flashing height.
• Contractor will Rake and Reseal 9 Control Joints.
• Clean up and haul off all waste into an on-site dumpster provided by the contractor.
• Will provide a contractor’s 2-year guarantee.
• Will provide a 20-year manufacturing warranty.
• While the crane is on site, FCI Texarkana will utilize it to replace HVAC equipment on the lower roof.
C.INSTLLATION REQUIRMENTS/QUALITY INSURANCE
1. Services and materials provided by the contractor will adhere to and shall be consistent with the most current industry standards, the Underwriters Laboratories (UL) and the General and the National Electric Code (NEC).
2. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractor’s employees. Damage will be corrected and restored to previous condition at no cost to the Government.
3. It shall be the Contractor’s responsibility for obtaining all measurements and data requirements to comply with manufacturer’s installation recommendations. All installations must be in accordance with product manufacture’s recommendations.
D. UTILITIES
The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.
E. TESTING AND ACCEPTANCE
The Contractor shall notify the Contracting Officers Representative (COR) (2) working days prior to the final system testing and certification so that arrangements can be made to have BOP required staff available to observe inspection. A complete plan detailing test procedures must be submitted to the Contracting Officers Representative (COR) in advance for final check out and testing of the complete system.
F. HOUSEKEEPING AND MATERIAL DISPOSAL
The contractor awarded the contract will be responsible to ensure the premises are always kept clean and free from accumulations of waste materials and rubbish. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work. The Contractor shall be responsible to remove all debris and waste materials from the job site at FCI Texarkana upon conclusion and acceptance of the project. These items must be disposed of in accordance with all Federal, State, and local laws.
II. CONTRACTOR SECURITY/WORKING REGULATIONS
A. Working Hours
1. The schedule for these services will be five (5) days a week, Monday through Friday, with the exception of Federal holidays. The schedule will continue weekly until the installation is completed, not to exceed thirty (30) calendar days from Notice to Proceed (NTP). The rear gate will open at 8:00 A.M. and close at 2:30 P.M.
Requests to extend hours or change workdays must be submitted in writing by the Contractor to the Contracting Officer (CO) for approval at least forty-eight (48) hours in advance.
B. Delivery of Materials
1. All construction materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the COR for temporary storage.
2. Construction related deliveries which are directly shipped to the institution can be received between the hours of 8:00 AM - 2:30 PM, Monday - Friday, excluding federal holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor, or his representative, is not present to verify and accept the delivery.
3. Under no circumstances will FCI Texarkana staff be responsible for the acceptance of any Contractor deliveries.
4. The Contractor shall be responsible to provide for its own means of loading and unloading Contractor material and equipment.
5. The Contractor will not be permitted to impede or block driveways for any extended period that would hinder the normal operations of the institution.
C. Storage of Equipment/Tools
1. If required, all construction equipment/tools shall be stored in a designated area mutually agreed upon between the COR and the Contractor. If required, the Contractor shall provide a securable, single point access storage container, such as a Job or Gang Box, that will be left in an agreed upon storage area for the duration of the project. Size of the storage container will be determined by the Contractor and the COR. The container will be secured using institution pad locks, for institution security purposes. All equipment/tools stored within the container will be maintained in a safe an orderly fashion. All equipment and tools will be inventoried periodically and at the end of each day.
2. The Contractor shall be responsible for loading and unloading contractor materials and equipment. At no time shall Contractor materials or equipment being staged in a fashion that would block, impede or otherwise hinder the typical operations of the institution.
4. All Contractor ladders, scaffolding, hoists, and related fixtures, needed for the job, may be stored on site with approval.
5. The Contractor shall be required to adhere to the institution’s tool inventory program as it pertains to their tools and equipment entering and exiting the institution. If a contactor owned storage container is to be used for tools, materials, and equipment for the duration of the project, the Contractor will be required to use an institution approved “Daily Inventory Check Sheet” for all items maintained in the container.
D. Security Clearance/Contractor Badges
1. The Contractor shall provide the COR with the necessary security clearance information on all Contractor Field Technicians assigned to work on the project. In the event a Field Technician does not clear the Institution’s security screening process the contractor may, if necessary, submit another Field Technician candidate. By law, the BOP cannot, and will not, release any information regarding the reason as to why a Contractor employee was not able to clear the institution’s security screening process.
2. All security clearance documentation shall be reviewed and institution approved five (5) working days prior to contractor institution access. Approved security clearances will be in effect for the duration of the project.
3. Contractors assigned to the project will access and depart the institution grounds via the main entrance or when necessary, the lower property perimeter road gate.
4. FCI Texarkana shall provide the necessary escorting staff members to the Contractor and their assigned Field Technicians carrying out the prescribed work and will allow access to project related institution areas as needed.
E. Safety and Personal Protective Equipment
1. The Contractor shall comply with all applicable Federal, State, and Local safety standards providing their field technicians with all necessary safety equipment to include, proper personal protective equipment, Lock-Out / Tag-Out equipment, and any “job-site specific” safety equipment deemed necessary to safely complete the project described in this Statement of Work.
2. All contractor employees shall have, and wear, required personal protective equipment prescribed by industry standards at all times while on the job site. It is the responsibility of the contractor to provide such equipment.
F. Other Considerations
1. Contractor technicians will NOT be allowed to bring cell phones, cameras or two-way pagers into the Institution. Use of such devices, however, may be used on institution exterior grounds. FCI Texarkana reserves the right to restrict their use at any time if deemed a security threat or risk.
2. The Facilities Department at FCI Texarkana maintains a digital camera that will be utilized by FCI Facility Staff to document the project work. The Contractor may request copies of the digital photos for their record keeping.
3. All deviations from this Statement of Work must be approved in writing by the Contracting Officer and COR.
4. In the event of an institution emergency the contractor may be instructed to secure from all work, secure all tools, equipment and materials, and if necessary escorted off institution grounds. Work will be suspended until the institution emergency passes.
5. In accordance with the Bureau of Prisons Acquisition Regulation (BPAP) 37.103 (e):
1. This service is a contractual arrangement and not a personnel appointment.
2. Payment is based on an end product or accomplishment of a specific result.
3. The service does not constitute an employer/employee relationship.
4. The contractor will not be subject to Government supervision, except for security related matters. However, contractor performance shall be monitored.