This is Addendum No. 1 to the bidding requirements and contract documents for the Wildland Firefighting Helitanker Station Rebid project issued by the San Bernardino County Department of Public Works - Special Districts (Project No. 1378.0185). The addendum clarifies specifications for a permanent aerial refilling cistern installation with a 3,000-5,000 gallon minimum tank capacity, though contractors may provide larger capacities if desired. Key specifications addressed include an 8-foot tall, 3/8-inch chain link fabric perimeter fence (approximately 200 linear feet), a 12-inch Class 150 A-C water pipe connection into native soil with hard compacted dirt conditions, electrical conduit sizing to be determined by the contractor, and mandatory SCADA capabilities with cellular communication systems. Optional pre-bid meetings were held on June 24 and June 26, 2026, at 10:30 a.m. at the original project location, with sign-in sheets provided. The addendum incorporates responses to 17 questions raised during the initial question-and-answer period and requires each bidder to include a dated and signed copy of the addendum with their sealed bid proposal.

The addendum clarifies that no plans exist outside the provided standards, and contractors must develop plans adhering to the bid documents and standards provided. The County will not disclose its engineer's estimate and will conduct compaction testing at no cost to the contractor. Contractors are responsible for providing their own construction water, determining the appropriate data carrier for communications based on site coverage, and obtaining all necessary permits. The $10 million general liability insurance limit applies to both occurrence and aggregate limits. No Scope of Work, meter, or backflow prevention device currently exists on site; these must be installed by the contractor. The addendum confirms that a Stormwater Quality Management Plan (SWQMP) is not required for this project and that native soil in the project area is sufficient without the need for additional infill or compaction measures.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wildland Firefighting Helitanker Station Addendum No. 1 Page 1 of 2

SAN BERNARDINO COUNTY

DEPARTMENT OF PUBLIC WORKS

SPECIAL DISTRICTS

ADDENDUM NO. 1

TO THE BIDDING REQUIREMENTS, CONTRACT DOCUMENTS, GENERAL CONDITIONS,

SPECIAL CONDITIONS, AND TECHNICAL SPECIFICATIONS FOR THE

Wildland Firefighting Helitanker Station Rebid

PROJECT NO.: 1378.0185

July 01, 2026

The Contract Bid Documents for the above referenced project are hereby amended in the following manner and the following manner only:

I. All provisions of Addendum No. 1 are hereby incorporated into the Contract Documents, and

Bidders shall account for all provisions pursuant to Addendum No. 1 in submitting their bid proposals. Each Bidder shall include a dated and signed copy of this Addendum with their sealed bid proposal.

1. ITEM NO. 1: Prebid Sign in Sheet

An optional bid walk was conducted and sign in sheet is uploaded that was held on 6/24/2026 and 6/26/2026 at 10:30 am at original project location.

2. Item No. 2: Initial Question and Answer period

1. Are there any plans? Attachment 8.0 Section G Contract DrawingsV1 appears to be the standards

a. There are no plans outside the standards that need to be met. It is up to the contractor to develop plans that adhere to the bid documents and standards provided

2. The links to Epro in bid documents do not seem to work correctly

a. Links are operational check with your IT department

3. EPro is not allowing bid item dollar amounts to be entered

a. EPro is not to be used to submit bid values. Vendors must use the itemized bid schedule provided within the bid docs for bidding.

4. 1. 3/8” 11ga Chain Link Fabric? Or 9ga. 2” with redwood slats? 2. Height? 3. Total L.F.?

4. Do you know the digging conditions at this site?

a. 3/8th inch chain link fabric no slats required. Height is 8 feet tall. Hard compacted dirt, Native soil. Total linear feet are roughly 200LF

5. Does the $10M Limit for the General Liability applies to both the Occurrence and

Aggregate limits, or if a different limit is needed on the Aggregate.

a. It applies to both occurrence and aggregate

6. Can county disclose engineer's estimate?

a. No County estimate will be disclosed

7. Can you please share the sign in sheet from job walk?

Wildland Firefighting Helitanker Station Addendum No. 1 Page 2 of 2

a. Sign in sheet for optional pre-bid meeting uploaded as amendments

8. Please clarify the tank size the bid schedule says 3,000-5,000, however the specs say

5,000-10,000?

a. Minimum Tank size is 3000-5000, however contractors are free to provide higher tank size amount if desired.

9. What size and type of pipe are we tying into?

a. 12’ Class 150 A-C Pipe

10. Can you give me locations of the meter, backflow?

a. There is no meter or backflow it is called out in the bid documents to be installed by the contractor.

11. For the electrical conduit run, what size conduit? Are there boxes? What sizes boxes?

How many?

a. There is one box installed on the northwest side of Well 5 that electricity and conduit can start to be ran to the location of the water cistern. Size of the conduit is to be determined by the contractor to hold the appropriate wiring necessary to operate the ancillary safety and lighting equipment for the station.

12. Is there a location where we can get water for construction phase?

a. There are no water hook ups in the area, and the contractor is responsible for providing their own construction water.

13. Does soil need to be brought in for infill or compaction?

a. No, native soil in project area is sufficient for the project. If native soil is disturbed, no extra measures are needed to return the area to its original state as best a possible if infill is needed elsewhere.

14. Is the contractor responsible for compaction testing?

a. No, the County will conduct testing as needed.

15. What data provider is needed for communications

a. The County has no preference on over the air data carrier ie, Verizon, AT&T, and T-Mobile. Contractor to validate which carrier has best service coverage in the project site to assist in making final submission.

16. Will SCADA be a requirement?

a. Yes, SCADA capabilities is a mandatory requirement. SCADA information will be provided to winning contractor.

17. Will a WQMP be necessary for this project?

a. No, a SWQMP is not required at this time.

ISSUE DATE: 7/01/2026 Date Acknowledged by Bidder: ____________

By: ______________________________ By: ____________________________

Mauricio L. Rodriguez, Senior Project Manager Bidders Company Name

Department of Public Works - Special Districts

Project Management Division _____________________________

Bidders Signature

2026-07-01T08:15:29-0700
Mauricio Rodriguez
I am approving this document

File details come from the government source that posted it. Updated .