This is a Questions and Responses document from the Florida Department of Transportation (FDOT) addressing inquiries submitted by proposers for Proposal ID DOT-RFP-26-3007-CS, a Geographic Information System (GIS) Mapping Services and Data Management contract. The procurement requires vendors to provide staff across all 12 personnel classifications to be considered responsive, with proposals due January 21, 2026, at 10:30 AM. The technical evaluation will assess proposals on a 100-point scale, with responsive proposers scoring 80 points or higher advancing to oral presentations on February 10, 2026. Price proposals will be opened on February 11, 2026, with the final selection and intended award meeting scheduled for February 23, 2026. The contract term is three years with potential renewal options for up to three additional years, contingent upon satisfactory performance and fund availability. Vendors must submit estimated staff hours for each position across Tasks A through D as defined in the scope of services, and while remote work is acceptable for routine tasks, on-site presence is required for occasional team meetings, emergency event support, and periodic needs assessment meetings. All proposals must be submitted electronically in PDF format to D3.Purch@dot.state.fl.us, with technical questions submitted by January 12, 2026, at 1:30 PM.
The total maximum budgetary allocation for this contract is $1.5 million, with price proposals scored on a 20-point scale using a formula comparing the proposer's price to the lowest submitted price. An SBE (Small Business Enterprise) is not required for this project. General liability insurance is mandatory with minimum coverage limits of $200,000 per person and $300,000 per occurrence for bodily injury, and $200,000 per occurrence for property damage. Additional mandatory submission requirements include a Vendor Certification Regarding Scrutinized Companies Lists, an E-Verify Form, and a Foreign Country of Concern Attestation. The Department reserves the right to conduct on-site facility reviews after the proposal due date to verify vendor qualifications and financial capability. Liquidated damages are established at $100 per calendar day for failure to complete services by the designated completion date. Qualifications that can be verified through state and federal databases will be verified by the Department, while experience, licenses, certifications, and relevant project experience should be addressed on staff resumes and in the technical plan section.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Transportation
RON DESANTIS
GOVERNOR
605 Suwannee Street
Tallahassee, FL 32399-0450
JARED W. PERDUE, P.E.
SECRETARY
www.fdot.gov
M E M O R A N D U M
Date: 1/20/2026 To: All Proposers RE: Questions and Answers 1 Proposal ID: DOT-RFP-26-3007-CS Description: GIS Mapping Services and Date Management
1. Could you please advise when responses to submitted questions will be made available?
Response: As soon as possible
2. Additionally, would FDOT consider extending the submission deadline to ensure adequate time for proposers to incorporate any changes to our proposal based on those answers?
Response: An addendum was issued to address.
3. The billing rates for onsite staff generally differ from those for personnel assigned to our facilities. The rates table provided in the Price Proposal Form does not reflect this distinction. Could you please advise on the preferred method for submitting the onsite rates?
Response: There are no provisions under this contract for onsite personnel.
4. Is the Vendor required to provide staff in all 12 personnel classifications to be considered for award?
Response: Yes, all 12 personnel classifications need to be provided to be considered responsive.
5. Section 2b of the Technical Proposal states, “The approximate percent of time to be devoted exclusively for this project and to the assigned tasks should also be indicated.” However, because Task Work Orders have not yet been defined, what guidance does FLDOT provide to help proposers estimate the percentage of time for the project? Also, should the percent of time be listed for each individual task outlined in the scope of services?
Response: The vendor should address in their proposal the percentage of time the proposed staff are available for use in this agreement.
6. In Section 4 of the Technical Proposal, could you please explain how proposers are expected to estimate staff hours when Task Work Orders have not been provided?
Response: Please provide estimated staffhours for each position on their team for each task and their associated subtasks defined in the scope (Tasks A – D).
7. The evaluation system assigns points for both Key Personnel Qualifications and Technical Personnel. Could you clarify how these two categories differ, and indicate where details about technical personnel, if they are distinct, should be placed within the proposal?
Response: Key personnel are those who meet the requirements in Section 8.2 of the RFP. Technical staff are those who will be utilized on an as-needed basis to perform technical functions and/or tasks required in the scope. There may be overlap between the two.
8. Section IX, Qualifications of Exhibit A Scope of Services, outlines additional requirements that must be addressed in the proposal. Given that Section 21, Proposal Format Instructions, stipulates adherence to the prescribed outline to avoid proposal rejection, where should these items be incorporated within the proposal document?
Response: The qualifications that can be verified through state and/or federal databases will be verified by the Department. Experience, licenses, certifications, and/or previous project experience should be addressed on staff resumes, and/or the prior relevant experience section of the technical plan. Copies of certificates for individual staff may be attached at the end of the proposal and will not be included in the page count.
9. Could you confirm whether an SBE is required for this project?
Response: An SBE is not required for this project.
10. There is mention of "Demonstrated ability of supplying staff for onsite services for a duration of 6 months or greater" in the RFP, can you clarify if the Department seeks staff to be present "onsite" for this engagement? Or if staff working remotely would be acceptable?
Response: On-site staffing is not a standard requirement; however, this language is included in the contract to allow for on-site presence should a specific project necessitate it. While routine work may be performed remotely, there will be instances where on-site participation is required, including occasional team meetings, emergency event support, and periodic needs assessment meetings for upcoming or potential projects.