About this file

This document is a Questions & Answers (Q&A) file for Solicitation 072024-01 - Middle Mile Design & Engineering, issued by Newport Utilities. The solicitation involves selecting a consultant for a design and engineering project, with an anticipated consultant selection date scheduled for the first week of October 2024. The Q&A document contains a single question (Q6) from a potential bidder inquiring about the expected timeline for consultant selection.

The document provides a direct and concise response to the bidder's query, confirming the anticipated selection timeframe without additional details about the project's scope, budget, or specific engineering requirements. The question was logged on 09/05/2024, indicating this is part of an ongoing procurement process for a middle mile design and engineering project.

View the file

Other files

File Type Posted
Middle Mile Design Area Estimated Mileage.xlsx XLSX spreadsheet
Middle Mile Scope of Work Design.pdf PDF
Poles.cpg —
Poles.dbf DBF file
Poles.prj —
Poles.shx —
Q&A Document 3.pdf PDF
Zoom meeting Design _ Engineering.pdf PDF
Poles.sbn —
Poles.shp —
Q&A Document 1.pdf PDF
Q&A Document 2.pdf PDF
South_340.kmz KMZ file
Contract Certifications.pdf PDF
Liberty_Hill.kmz KMZ file
Q&A Document 5.pdf PDF
Q&A Document 8.pdf PDF
Wiley_Town.kmz KMZ file
Byrd Anti-Lobbying Certification.pdf PDF
Middle Mile Contract Design.pdf PDF
Poles.sbx —
Poles.shp.xml XML file
Q&A Document 6.pdf PDF
Q&A Document 7.pdf PDF
West_Parrottsville.kmz KMZ file
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers - 4

Solicitation 072024-01 - Middle Mile Design & Engineering

Buying Organization Newport Utilities

No Question/Answer Question Date

Q6 Question: Consultant Selection

Is there an anticipated date for selection on this project?

Answer: The 1st week of October.

09/05/2024

Questions & Answers - 4