This is a Prime/Subcontractor Form for Volusia County's DeLand Courthouse Chiller Energy Plant (CEP) Upgrades and Efficiency Improvements project (Contract No. C-2014, ITB No. 25-B-##XX). The form requires all bidders to disclose all proposed subcontractors and their respective work scopes, with failure to complete and return the form resulting in a non-responsive bid. The project involves comprehensive replacement of the existing chiller plant infrastructure, including two 500-ton water-cooled chillers, primary and secondary chilled water pumps, and associated mechanical, electrical, and control system components at 101 N. Alabama Avenue in DeLand, Florida. A non-mandatory pre-bid meeting is scheduled for January 22, 2026, at 10:30 am at the courthouse loading dock, with question submissions due by February 5, 2026, at 11:59 pm. Electronic bids must be submitted through the County's eProcurement Portal by February 19, 2026, at 3:01 pm, and will be publicly opened via Microsoft Teams on the submission deadline. The contract term is 180 days upon award.

Bidders must complete the form by entering the total bid price in the designated green-shaded cells, including dollar values and percentage of work for both the prime contractor and all subcontractors, with total work percentages equaling 100%. The estimated project construction cost is $1,750,000.00. Bid bonds valued at 5% of the total bid price are required, and the County will evaluate bids based on conformance to requirements, bidder capability, subcontractor qualifications, proportional work performed, previous contract performance, and maintenance capabilities. Local business preference provisions apply, offering a 3% preference for prime contractors with a permanent location in specific Central Florida counties for at least six months, or a 2% preference if 51% or more of subcontracted work is performed by local businesses, with a maximum combined preference of 5%. The prime contractor is responsible for ensuring all subcontractors hold appropriate licenses, and any subcontractor changes during project completion require prior written approval from the County Project Manager.

View the file

Other files

File Type Posted
Deland_Courthouse_CEP_Upgrades_and_Efficiency_Improvements_(Addendum_#1_Revision).pdf PDF
Attachment_A_-_TRANE_Installation_Guide.pdf PDF
Attachment_B_-_HDW_-_HDW-1_-_Consolidated_Customer_Package.pdf PDF
Deland_Courthouse_CEP_Upgrades_and_Efficiency_Improvements.pdf PDF
Sales_Tax_Exemption_Procedure_26-B-24LL.pdf PDF
Sales_Tax_Exemption_Procedure_26-B-24LL.pdf PDF
PRIME-SUB_FORM_for_Contractors.xls XLS spreadsheet
PRIME-SUB_FORM_for_Contractors.xls XLS spreadsheet
Exhibit_E_-_Drawings_26-B-24LL.pdf PDF
Exhibit_F_-_Technical_Specifications_26-B-24LL.pdf PDF
MASTER_Construction_Contract_26-B-24LL.pdf PDF
Exhibit_E_-_Drawings_26-B-24LL.pdf PDF
Exhibit_F_-_Technical_Specifications_26-B-24LL.pdf PDF
MASTER_Construction_Contract_26-B-24LL.pdf PDF
Bid_Documents_26-B-24LL.pdf PDF
Bid_Documents_26-B-24LL.pdf PDF
Basic_Insurance_Requirements_26-B-24LL.pdf PDF
Basic_Insurance_Requirements_26-B-24LL.pdf PDF
Payment_and_Performance_Bond_26-B-24LL.pdf PDF
Payment_and_Performance_Bond_26-B-24LL.pdf PDF
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
VCG_-_Deland_Courthouse_-_CEP_Upgrades_100%_CD.pdf PDF
VCG_Deland_Courthouse_-CEP_upgrades_SPECIFICATIONS.pdf PDF
VCG_-_Deland_Courthouse_-_CEP_Upgrades_100%_CD.pdf PDF
VCG_Deland_Courthouse_-CEP_upgrades_SPECIFICATIONS.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Contract No. C-2014ITB No. 25-B-##XX
PRIME/SUBCONTRACTOR FORM
FAILURE TO COMPLETE AND RETURN THIS FORM MAY RESULT IN A NON-RESPONSIVE BID
Bidders are to list ALL Subcontractors that he/she proposed to perform scope of work for this project. The bidder hereby states that he/she proposes, if awarded the contract to hire the following Subcontractor(s) for this project. Prime Contractor is responsible for ensuring that all Subcontractors hold the appropriate license(s). Any change to the Subcontractors during the completion of this project shall receive prior approval from the County Project Manager. The County reserves the right to seek clarification regarding subcontractors but will not allow change to the total submitted base bid pricing.
TOTAL BID$ - 0This number should match the Total Bid Price

(inclusive of performance/payment bond, if applicable) as listed on Bid Form/Exhibit ?/Attachment ? - Bid Price Sheet

PRIME CONTRACTORCompany name and complete addressDollar Value performed by Prime Contractor% of Work performed by Contractor
$ - 00.00%
List appropriate sub contractors to be used for each displine listed below, if prime is self performing note self performing in the box under company name and address and submit $0.00 to equal 0 % as this should be included in the green box above. If additional subcontractors are required and their discipline is not listed below they may be added in the blank rows. This form will also be used to determine local preference in accordance with Section 2.8, D. Local Bid Preference in the solicitation.
Anticipated Subcontractor Disciplines required for this project.Company name and complete addressDollar Value performed by Subcontractor(s)% of Work performed by Subcontractor
(Examples: Electrical, HVAC, Plumbing,
Landscaping, etc. for your project)$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
$ - 00.00%
Bidders shall complete the areas shaded in GREEN, which shall be the dollar values assigned to each Contractor (Prime and Subs). All other cells shall be automatically calculated. The total listed in the GREY cell must equal 100%$ - 00%

Sheet2