About this file
This is a Price Schedule for a repair and furnishing project at Goodfellow Air Force Base, Texas. The contract covers the repair of kitchen flooring in Building B334 with a total performance period of 164 calendar days.
The solicitation includes two Contract Line Items (CLINs). CLIN 0001 encompasses all costs associated with kitchen flooring repair and replacement, including demolition, floor preparation, temporary partition construction and deconstruction, application of new flooring, site cleanup, and demobilization. CLIN 0002 covers kitchen flooring furnishing costs, including inventory, removal, storage, sanitization, cleaning, and reinstallation of all kitchen equipment, as well as costs for temporary storage units and equipment cleaning and sanitization upon successful hookup and installation. Both CLINs are priced as fixed-price jobs in U.S. dollars, with pricing lines left blank for contractor submission. Contractors must provide all labor, equipment, materials, and incidentals necessary to complete both CLINs in accordance with specifications and photos referenced in the complete contract.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
REPAIR Kitchen Flooring B334
GOODFELLOW AIR FORCE BASE, TEXAS
SCHEDULE OF ITEMS
Provide all labor, equipment, materials, and incidentals necessary to accomplish CLIN 0001 and CLIN 0002 in accordance with the specifications and photos subject to the terms and conditions of the complete contract. Total performance period of the project shall be ONE HUNDRED and SIXTY-FOUR (164) calendar days.
CLIN DESCRIPTION QTY UNIT PRICE AMOUNT
CLIN 0001 PRICE: Repair Kitchen Flooring: All costs associated with the demolition, repair, and replacement of the kitchen flooring in B334. This includes all time and costs associated with constructing/deconstructing temporary partitions, floor demolition and preparation, application of new flooring, site cleanup, and demobilization. This CLIN does not include any of the following CLINs within it.
1 Job $ USD
CLIN 0002 PRICE: Repair Kitchen Flooring Furnishing: All costs associated with inventory, removal, storage, sanitization, cleaning, and reinstallation of all kitchen equipment. This includes costs of temporary storage units such as storage containers along with costs to clean and sanitize equipment upon successful hookup and installation.
1 Job $ USD