Price Proposal spreadsheet.xls

XLS spreadsheet 51 KB Posted

Attached to
Pinecastle HVAC replacement
Solicitation number
N6945020R0120
Issued by

About this file

This document contains a price proposal spreadsheet for the solicitation to replace HVAC systems and install a new CRAC unit at Building 149L for the Naval Facilities Engineering Command. The price proposal spreadsheet requires the contractor to provide unit pricing and totals for direct materials, labor, equipment rental and ownership costs for both prime contract and subcontract work. The contractor must also include overhead and profit markups on labor and materials. The solicitation number is N6945020R0120 and responses are due by August 5, 2020 to the Naval Facilities Engineering Command for the work to be performed at Pinecastle.

View the file

Other files

File Type Posted
AMD 02 RFP N6945020R0120.pdf PDF
AMD 01 RFP N6945020R0120.pdf PDF
PRE-PROPOSAL INQUIRY FORM.xlsx XLSX spreadsheet
Pinecastle B149 HVAC Repl SOW .docx DOCX document
SOW Pinecastle B149 HVAC Repl Sketch.pdf PDF
RFP N6945020R0120.pdf PDF
SOW Pinecastle B149-L HVAC Pics.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRIM&SUB

PRICE PROPOSALSOLICITATION NO:N69450-20-R-0120
PRICE PROPOSALDATE:5-Aug-16
NAVFAC 4330/43 (8/88)BREAKDOWN OF DIRECT COSTSDATE:5 Aug 16
W.A. TITLE:Pinecastle Building 149L HVAC ReplacementSOLICITATION NO:N69450-20-R-0120
ITEMS OF WORK FORQTYUNITMATERIALLABOROEQUIPMENT
OFFICE:PWD JACKSONVILLEPrime ContractorUnit CostTotal CostUnit CostTotal CostRQtyRateTotal
1.000
DESCRIPTION:2.000
3.00
PRIME CONTRACTOR'S WORKRevisions/Comments4.000
1.Direct Materials|0|5.000
2.Sales Tax on Materials0.00%of line 10.00%0|6.000
3.Direct Labor|0|7.000
4.Insurance, Taxes, and Fringe Benefits0.00%of line 30.00%0|8.00
5.Rental Equipment|0|9.000
6.Sales Tax on Rental Equipment0.00%of line 50.00%0|10.000
7.Equipment Ownership and Operating Expenses|0|11.000
8.Subtotal||||||||||||||||||||||||||||||||||||||||||||||||||||||012.000
9.Prime's Field Office Overhead0.00%of line 80.0%0|||||||||||||||||||||||||||||||||15.000
10.SUBTOTAL (add lines 8 and 9)||016.000
Prime's Remarks:17.000
18.000
19.000
SUBCONTRACTOR'S WORK20.000
11.Direct Materials|0|21.000
12.Sales Tax on Materials0.00%of line 110.00%0|22.000
13.Direct Labor|0|23.000
14.Insurance, Taxes, and Fringe Benefits0.00%of line 130.00%0|24.000
15.Rental Equipment|0|25.000
16.Sales Tax on Rental Equipment0.00%of line 150.00%0|DIRECT Prime Contractor's TOTALS00RTotal (Rental)0
17.Equip. Ownership and Operating Expns|0|OTotal (Owned)0
18.SUBTOTAL (add lines 11-17)||0
19.Field Overhead0.00%of line 180.00%0|ITEMS OF WORK FORQTYUNITMATERIALLABOROEQUIPMENT
20.SUBTOTAL (add lines 18&19)||0SubcontractorUnit CostTotal CostUnit CostTotal CostRQtyRateTotal
21.Home Office Overhead0.00%of line 180.00%0|1.000
22.Profit0.00%of line 200.00%0|2.000
23.SUBTOTAL (Add Lines 20-22)||03.000
Sub's Remarks:4.000
5.000
6.000
7.000
8.000
SUMMARY9.000
24.Prime Contractor's Work (from line 10)|0|10.000
25.Sub-contractor's Work (from line 23)|0|11.000
26.SUBTOTAL (add lines 24 and 25)||012.000
27.Prime's Field Office Overhead on sub.0.00%of line 250.00%0|13.000
28.Prime's Home Office Overhead0.00%of line 260.00%0|14.000
29.Prime's Profit0.00%of line 260.00%0|15.000
30.SUBTOTAL (add lines 26 - 29)||016.000
31.Prime Contractor's Bond Premium0.00%of line 300.00%0|17.000
32.TOTAL COST (Add Lines 30 and 31)||018.000
19.000
20.000
21.
22.00
23.000
Prime Contractor name:24.000
Subcontractor name:25.000
DIRECT Subcontractor's TOTALS00RTotal (Rental)0
Signature & Title of preparer:OTotal (Owned)0
Date:5 Aug 16
NAVFAC 4330/43 (Back) page 2

File details come from the government source that posted it. Updated .