This is a Past Performance Questionnaire (PPQ) template for solicitation 36C10F24R0075, a VA design-build project to replace seismically deficient animal research buildings at the Sepulveda VA Medical Center. The PPQ requires contractors to provide details about previous contract performance, including contract information, pricing, and project descriptions.

The questionnaire includes evaluation criteria across seven key areas: quality, schedule/timeliness, communication, management/personnel/labor, cost/financial management, subcontract management, and an overall summary. Evaluators must rate performance using a scale from Outstanding to Unsatisfactory. The PPQ is not included in the page count for SF 330 submissions and must be returned to the offeror for incorporation into their SF 330 submission rather than being submitted directly to VA CFM. The related contract opportunity is for a $20-50 million design-build project for a new 7,500 GSF animal research facility, with RFQ responses due February 14, 2025, and a planned contract duration of 546 calendar days.

View the file

Other files

File Type Posted
36C10F24R0075 A0008.docx DOCX document
36C10F24R0075 A0007_1.docx DOCX document
36C10F24R0075 - A0007.docx DOCX document
CA20250022 10-03-2025.pdf PDF
Building 7 Retrofits 2.pdf PDF
Building 7 Retrofits 1.pdf PDF
Building 7 Retrofits 3.pdf PDF
Building 7 - 2000 Seismic Correction.pdf PDF
Building 7 - Canopy Structural Architectural.pdf PDF
36C10F24R0075 A0006.pdf PDF
Bldg 103 Drawings.pdf PDF
Building 7 1994 Consolidated Research.pdf PDF
36C10F24R0075 A0006_1.docx DOCX document
Combined Reports.pdf PDF
Building 7 -first floor.pdf PDF
Building 103 Animal Research 1985.pdf PDF
Building 47 Combined Files.pdf PDF
Building 7 -basement.pdf PDF
TemplateSubcontractingPlan.docx DOCX document
36C10F24R0075 P0005_1.docx DOCX document
VAAR Class Dev - 822_852 Compliance with E.O. 13899.pdf PDF
Wage Determination CA20250022.docx DOCX document
36C10F24R0075 A0004.docx DOCX document
36C10F24R0075 A0003.docx DOCX document
36C10F24R0075 A0003_1.docx DOCX document
36C10F24R0075 A0002.docx DOCX document
36C10F24R0075 A0001_1.docx DOCX document
36C10F24R0075_2.docx DOCX document
36C10F24R0075 PHASE I REQUEST FOR QUALIFICATION.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION & FACILITIES MANAGEMENT ● 400 MARE ISLAND WAY, SUITE 100 ● VALLEJO, CA 94589

PAST PERFORMANCE QUESTIONAIRE - 36C10F24R0075

PAST PERFORMANCE QUESTIONNAIRE (PPQ)

*All PPQs are NOT included in the page count for SF 330 submissions.

SECTION 1

CONTRACT INFORMATION – Contractor to complete #1-3

1. CONTRACTOR INFORMATION

NAME OF OFFEROR BEING EVALUATED: Click or tap here to enter text.

ADDRESS: Click or tap here to enter text.

POINT OF CONTACT: Click or tap here to enter text.

CONTACT PHONE NUMBER: Click or tap here to enter text.

CONTACT EMAIL ADDRESS: Click or tap here to enter text.

WORK PERFOMED AS: Click or tap here to enter text.

PERCENT OF PROJECT WORK PERFORMED: Click or tap here to enter text.

IF SUBCONTRACTOR, WHO WAS THE PRIME? Click or tap here to enter text.

2. CONTRACT INFORMATION

CONTRACT TITLE: Click or tap here to enter text.

CONTRACT NUMBER AND DO/TO NUMBER: Click or tap here to enter text.

CONTRACT TYPE: Click or tap here to enter text.

CONTRACT LOCATION: Click or tap here to enter text.

AWARD DATE: Click or tap to enter a date.

ORIGINAL CONTRACT ACCCEPTANCE (construction accepted) Date: Click or tap to enter a date.

ACTUAL CONTRACT ACCEPTANCE: Click or tap to enter a date.

EXPLAIN DIFFERENCES: Click or tap here to enter text.

ORIGINAL IMPLEMENTATION PRICE: Click or tap here to enter text.

ORIGINAL CONTRACT PRICE (all costs - design/installation/financing): Click or tap here to enter text.

FINAL CONTRACT PRICE (including modifications, if applicable): Click or tap here to enter text.

EXPLAIN DIFFERENCES: Click or tap here to enter text.

3. PROJECT DESCRIPTION

SCOPE INCLUDED IN PROJECT: Click or tap here to enter text.

HOW IS THIS PROJECT RELEVANT TO PROJECT OF SUBMISSION? Click or tap here to enter text.

SECTION 2

EVALUATOR INFORMATION – Client to complete

Veterans Administration, Office of Constructions and Facilities Management, Western Region Office is considering the Offeror identified above for award of task order to provide professional design services in the development of Request for Proposals (RFP) for Project Number 691-903, Replace Seismically Deficient Animal Research Buildings 47 and 103 at VA Medical Center (VAMC), Sepulveda, California.

Your comments would be appreciated regarding this firm’s past performance. The intent of this form is to evaluate the company’s ability to perform the work as described in the solicitation. Please verify the accuracy of the information in Section 1 and complete the questionnaire as thoroughly as possible. VA CFM may contact you in order to obtain any additional information regarding a contract award.

Please return your completed questionnaire to the Offeror to be incorporated into the SF 330 submission. PPQs should not be submitted directly to VA CFM by the client. Refer to the solicitation for SF 330 submission due date.

EVALUATOR INFORMATION

NAME OF EVALUATOR: Click or tap here to enter text.

POSITION: Click or tap here to enter text.

ADDRESS: Click or tap here to enter text.

PHONE: Click or tap here to enter text.

EMAIL: Click or tap here to enter text.

DESCRIBE YOUR ROLE IN THE PROJECT: Click or tap here to enter text.

*Please see Page 4 for Adjectival Ratings for the following:

1. QUALITY

Ability to meet quality design and/or construction standards specified for technical performance
Choose an item.
Comments:

2. SCHEDULE/ TIMELINESS OF PERFORMANCE

Compliance with contract delivery/completion schedules including timely submission of data deliverables (If liquidated damages were assessed or the schedule was not met, please address below.)
Choose an item.
Comments:

3. COMMUNICATION

Contractor was reasonable and cooperative in dealing with client staff (including the ability to successfully resolve disagreements/disputes and responsiveness to client requests)
Choose an item.
Comments:

4. MANAGEMENT/ PERSONNEL/ LABOR

Effectiveness of management, including suppliers, materials, and/or labor force (including the ability to effectively lead, manage, and control the project)
Choose an item.
Continuity in the contractor’s personnel during execution of the contract (e.g., one person or team that stayed with the project throughout the contract)
Choose an item.
Comments:

5. COST/ FINANCIAL MANGEMENT

Ability to meet the terms and conditions within the contractually agreed price
Choose an item.
Comments:

6. SUBCONTRACT MANAGEMENT

Ability to manage subcontracting effort, including any subcontracting issues, and the contractor’s ability to resolve the problems without extensive customer guidance

Choose an item.

Comments:

7. SUMMARY

Would you hire or work with this firm again? If no, please explain below.
Choose an item.
Provide an overall rating for the work performed by this contractor.
Choose an item.

ADDITIONAL COMMENTS:

EVALUATOR SIGNATURE:
DATE:

ADJECTIVAL RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

*THIS PAGE WILL BE REMOVED FOR EVALUATION PURPOSES AND NOT BE COUNTED TOWARD THE SF 330 PAGE COUNT – IT IS FOR PPQ COMPLETION PURPOSES ONLY*

Rating
Definition
Outstanding
The Offeror’s performance met contractual requirements and exceeded many requirements to the Client’s benefit. The contractual performance was accomplished with few minor problems for which corrective actions taken by the Offeror were highly effective.
Above Average
The Offeror’s performance met contractual requirements and exceeded some requirements to the Client’s benefit. The contractual performance was accomplished with some minor problems for which corrective actions taken by the Offeror were effective.
Satisfactory
The Offeror’s performance met contractual requirements. The contractual performance contained some minor problems for which corrective actions taken by the Offeror were satisfactory.
Unsatisfactory
Performance did not meet contractual requirements. The contractual performance reflected a serious problem for which the Offeror has yet to identify corrective actions or the Offeror’s proposed actions appear only marginally effective or were not fully implemented.
Not Applicable
No information or did not apply to your contract.